chapter-343•Hawaii Revised Statutes, Chapter 343 — Environmental Impact Statements
chapter-343Haw. Rev. Stat. ch. 343CodeJan 1, 1974
Division 1. Government — Title 19. Health
Hawaii Revised Statutes as published by the Hawaii State Legislature (files updated 1/5/2026 7:14 PM).
The legislature finds that the quality of humanity's environment is critical to humanity's well being, that humanity's activities have broad and profound effects upon the interrelations of all components of the environment, and that an environmental review process will integrate the review of environmental concerns with existing planning processes of the State and counties and alert decision makers to significant environmental effects which may result from the implementation of certain actions. The legislature further finds that the process of reviewing environmental effects is desirable because environmental consciousness is enhanced, cooperation and coordination are encouraged, and public participation during the review process benefits all parties involved and society as a whole.
It is the purpose of this chapter to establish a system of environmental review which will ensure that environmental concerns are given appropriate consideration in decision making along with economic and technical considerations.
[L 1979, c 197, §1(1); am L 1983, c 140, §4]
As used in this chapter unless the context otherwise requires:
"Acceptance" means a formal determination that the document required to be filed pursuant to section 343-5 fulfills the definition of an environmental impact statement, adequately describes identifiable environmental impacts, and satisfactorily responds to comments received during the review of the statement.
"Action" means any program or project to be initiated by any agency or applicant.
"Agency" means any department, office, board, or commission of the state or county government which is a part of the executive branch of that government.
"Applicant" means any person who, pursuant to statute, ordinance, or rule, officially requests approval for a proposed action.
"Approval" means a discretionary consent required from an agency prior to actual implementation of an action.
"Council" means the environmental advisory council.
"Director" means the director of the office of planning and sustainable development.
"Discretionary consent" means a consent, sanction, or recommendation from an agency for which judgment and free will may be exercised by the issuing agency, as distinguished from a ministerial consent.
"Environmental assessment" means a written evaluation to determine whether an action may have a significant effect.
"Environmental impact statement" or "statement" means an informational document prepared in compliance with the rules adopted under section 343-6 and which discloses the environmental effects of a proposed action, effects of a proposed action on the economic welfare, social welfare, and cultural practices of the community and State, effects of the economic activities arising out of the proposed action, measures proposed to minimize adverse effects, and alternatives to the action and their environmental effects.
The initial statement filed for public review shall be referred to as the draft statement and shall be distinguished from the final statement which is the document that has incorporated the public's comments and the responses to those comments. The final statement is the document that shall be evaluated for acceptability by the respective accepting authority.
"Finding of no significant impact" means a determination based on an environmental assessment that the subject action will not have a significant effect and, therefore, will not require the preparation of an environmental impact statement.
"Helicopter facility" means any area of land or water which is used, or intended for use for the landing or takeoff of helicopters; and any appurtenant areas which are used, or intended for use for helicopter related activities or rights-of-way.
"Office" means the office of planning and sustainable development.
"Person" includes any individual, partnership, firm, association, trust, estate, private corporation, or other legal entity other than an agency.
"Power-generating facility" means:
(1) A new, fossil-fueled, electricity-generating facility, where the electrical output rating of the new equipment exceeds 5.0 megawatts; or
(2) An expansion in generating capacity of an existing, fossil-fueled, electricity-generating facility, where the incremental electrical output rating of the new equipment exceeds 5.0 megawatts.
"Significant effect" means the sum of effects on the quality of the environment, including actions that irrevocably commit a natural resource, curtail the range of beneficial uses of the environment, are contrary to the State's environmental policies or long-term environmental goals as established by law, or adversely affect the economic welfare, social welfare, or cultural practices of the community and State.
"Wastewater treatment unit" means any plant or facility used in the treatment of wastewater.
[L 1974, c 246, pt of §1; am and ren L 1979, c 197, §1(2); am L 1983, c 140, §5; am L 1986, c 186, §1; am L 1987, c 187, §1 and c 325, §2; am L 1996, c 61, §1; am L 2000, c 50, §2; am L 2004, c 55, §2; am L 2005, c 130, §2; am L 2008, c 207, §3; am L 2016, c 27, §4; am L 2021, c 152, §12 and c 153, §9]
(a) All statements, environmental assessments, and other documents prepared under this chapter shall be made available for inspection by the public during established office hours.
(b) The office shall inform the public of notices filed by agencies of the availability of environmental assessments for review and comments, of determinations that statements are required or not required, of the availability of statements for review and comments, and of the acceptance or nonacceptance of statements.
(c) The office shall inform the public of:
(1) A public comment process or public hearing if a federal agency provides for the public comment process or public hearing to process a habitat conservation plan, safe harbor agreement, or incidental take license pursuant to the federal Endangered Species Act;
(2) A proposed habitat conservation plan or proposed safe harbor agreement, and availability for inspection of the proposed agreement, plan, and application to enter into a planning process for the preparation and implementation of the habitat conservation plan for public review and comment;
(3) A proposed incidental take license as part of a habitat conservation plan or safe harbor agreement; and
(4) An application for the registration of land by accretion pursuant to section 501-33 or 669-1(e) for any land accreted along the ocean.
(d) The office shall inform the public by the publication of a periodic bulletin to be available to persons requesting this information. The bulletin shall be available through the office and public libraries.
[L 1974, c 246, pt of §1; ren L 1979, c 197, §1(3); am L 1983, c 140, §6; am L 1992, c 241, §1; am L 1997, c 380, §8; am L 1998, c 237, §7; am L 2003, c 73, §3]
[Repealed]
[L 1983, c 140, §7]
(a) Except as otherwise provided, an environmental assessment shall be required for actions that:
(1) Propose the use of state or county lands or the use of state or county funds, other than funds to be used for feasibility or planning studies for possible future programs or projects that the agency has not approved, adopted, or funded, or funds to be used for the acquisition of unimproved real property; provided that the agency shall consider environmental factors and available alternatives in its feasibility or planning studies; provided further that an environmental assessment for proposed uses under section 205-2(d)(11) or 205-4.5(a)(13) shall only be required pursuant to section 205-5(b);
(2) Propose any use within any land classified as a conservation district by the state land use commission under chapter 205;
(3) Propose any use within a shoreline area as defined in section 205A-41;
(4) Propose any use within any historic site as designated in the National Register or Hawaii Register, as provided for in the Historic Preservation Act of 1966, Public Law 89-665, or chapter 6E;
(5) Propose any use within the Waikiki area of Oahu, the boundaries of which are delineated in the land use ordinance as amended, establishing the "Waikiki Special District";
(6) Propose any amendments to existing county general plans where the amendment would result in designations other than agriculture, conservation, or preservation, except actions proposing any new county general plan or amendments to any existing county general plan initiated by a county;
(7) Propose any reclassification of any land classified as a conservation district by the state land use commission under chapter 205;
(8) Propose the construction of new or the expansion or modification of existing helicopter facilities within the State, that by way of their activities, may affect:
(A) Any land classified as a conservation district by the state land use commission under chapter 205;
(B) A shoreline area as defined in section 205A-41; or
(C) Any historic site as designated in the National Register or Hawaii Register, as provided for in the Historic Preservation Act of 1966, Public Law 89-665, or chapter 6E; or until the statewide historic places inventory is completed, any historic site that is found by a field reconnaissance of the area affected by the helicopter facility and is under consideration for placement on the National Register or the Hawaii Register of Historic Places; and
(9) Propose any:
(A) Wastewater treatment unit, except an individual wastewater system or a wastewater treatment unit serving fewer than fifty single-family dwellings or the equivalent;
(B) Waste-to-energy facility;
(C) Landfill;
(D) Oil refinery; or
(E) Power-generating facility.
(b) Whenever an agency proposes an action in subsection (a), other than feasibility or planning studies for possible future programs or projects that the agency has not approved, adopted, or funded, or other than the use of state or county funds for the acquisition of unimproved real property that is not a specific type of action declared exempt under section 343-6, the agency shall prepare an environmental assessment for the action at the earliest practicable time to determine whether an environmental impact statement shall be required; provided that if the agency determines, through its judgment and experience, that an environmental impact statement is likely to be required, the agency may choose not to prepare an environmental assessment and instead shall prepare an environmental impact statement that begins with the preparation of an environmental impact statement preparation notice as provided by rules.
(c) For environmental assessments for which a finding of no significant impact is anticipated:
(1) A draft environmental assessment shall be made available for public review and comment for a period of thirty days;
(2) The office shall inform the public of the availability of the draft environmental assessment for public review and comment pursuant to section 343-3;
(3) The agency shall respond in writing to comments received during the review and prepare a final environmental assessment to determine whether an environmental impact statement shall be required;
(4) A statement shall be required if the agency finds that the proposed action may have a significant effect on the environment; and
(5) The agency shall file notice of the determination with the office. When a conflict of interest may exist because the proposing agency and the agency making the determination are the same, the office may review the agency's determination, consult the agency, and advise the agency of potential conflicts, to comply with this section. The office shall publish the final determination for the public's information pursuant to section 343-3.
The draft and final statements, if required, shall be prepared by the agency and submitted to the office. The draft statement shall be made available for public review and comment through the office for a period of forty-five days. The office shall inform the public of the availability of the draft statement for public review and comment pursuant to section 343-3. The agency shall respond in writing to comments received during the review and prepare a final statement.
The office, when requested by the agency, may make a recommendation as to the acceptability of the final statement.
(d) The final authority to accept a final statement shall rest with:
(1) The governor, or the governor's authorized representative, whenever an action proposes the use of state lands or the use of state funds, or whenever a state agency proposes an action within the categories in subsection (a); or
(2) The mayor, or the mayor's authorized representative, of the respective county whenever an action proposes only the use of county lands or county funds.
Acceptance of a required final statement shall be a condition precedent to implementation of the proposed action. Upon acceptance or nonacceptance of the final statement, the governor or mayor, or the governor's or mayor's authorized representative, shall file notice of such determination with the office. The office, in turn, shall publish the determination of acceptance or nonacceptance pursuant to section 343-3.
(e) Whenever an applicant proposes an action specified by subsection (a) that requires approval of an agency and that is not a specific type of action declared exempt under section 343-6, the agency initially receiving and agreeing to process the request for approval shall require the applicant to prepare an environmental assessment of the proposed action at the earliest practicable time to determine whether an environmental impact statement shall be required; provided that if the agency determines, through its judgment and experience, that an environmental impact statement is likely to be required, the agency may authorize the applicant to choose not to prepare an environmental assessment and instead prepare an environmental impact statement that begins with the preparation of an environmental impact statement preparation notice as provided by rules. The final approving agency for the request for approval is not required to be the accepting authority.
For environmental assessments for which a finding of no significant impact is anticipated:
(1) A draft environmental assessment shall be made available for public review and comment for a period of thirty days;
(2) The office shall inform the public of the availability of the draft environmental assessment for public review and comment pursuant to section 343-3; and
(3) The applicant shall respond in writing to comments received during the review and the applicant shall prepare a final environmental assessment to determine whether an environmental impact statement shall be required. A statement shall be required if the agency finds that the proposed action may have a significant effect on the environment. The agency shall file notice of the agency's determination with the office, which, in turn, shall publish the agency's determination for the public's information pursuant to section 343-3.
The draft and final statements, if required, shall be prepared by the applicant, who shall file these statements with the office.
The draft statement shall be made available for public review and comment through the office for a period of forty-five days. The office shall inform the public of the availability of the draft statement for public review and comment pursuant to section 343-3.
The applicant shall respond in writing to comments received during the review and prepare a final statement. The office, when requested by the applicant or agency, may make a recommendation as to the acceptability of the final statement.
The authority to accept a final statement shall rest with the agency initially receiving and agreeing to process the request for approval. The final decision-making body or approving agency for the request for approval is not required to be the accepting authority. The planning department for the county in which the proposed action will occur shall be a permissible accepting authority for the final statement.
Acceptance of a required final statement shall be a condition precedent to approval of the request and commencement of the proposed action. Upon acceptance or nonacceptance of the final statement, the agency shall file notice of the determination with the office. The office, in turn, shall publish the determination of acceptance or nonacceptance of the final statement pursuant to section 343-3.
The agency receiving the request, within thirty days of receipt of the final statement, shall notify the applicant and the office of the acceptance or nonacceptance of the final statement. The final statement shall be deemed to be accepted if the agency fails to accept or not accept the final statement within thirty days after receipt of the final statement; provided that the thirty-day period may be extended at the request of the applicant for a period not to exceed fifteen days.
In any acceptance or nonacceptance, the agency shall provide the applicant with the specific findings and reasons for its determination.
(f) Whenever an applicant requests approval for a proposed action and there is a question as to which of two or more state or county agencies with jurisdiction has the responsibility of determining whether an environmental assessment is required, the office, after consultation with and assistance from the affected state or county agencies, shall determine which agency has the responsibility for determining whether an environmental assessment by the applicant is required, except in situations involving secondary actions under section 343-5.5; provided that in no case shall the office be considered the approving agency.
(g) In preparing an environmental assessment, an agency may consider and, where applicable and appropriate, incorporate by reference, in whole or in part, previous determinations of whether a statement is required and previously accepted statements. The council, by rule, shall establish criteria and procedures for the use of previous determinations and statements.
(h) Whenever an action is subject to both the National Environmental Policy Act of 1969 (Public Law 91-190) and the requirements of this chapter, the office and agencies shall cooperate with federal agencies to the fullest extent possible to reduce duplication between federal and state requirements. Such cooperation, to the fullest extent possible, shall include joint environmental impact statements with concurrent public review and processing at both levels of government. Where federal law has environmental impact statement requirements in addition to but not in conflict with this chapter, the office and agencies shall cooperate in fulfilling these requirements so that one document shall comply with all applicable laws.
(i) A statement that is accepted with respect to a particular action shall satisfy the requirements of this chapter, and no other statement for the proposed action shall be required.
[L 1974, c 246, pt of §1; am and ren L 1979, c 197, §1(5), (6); am L 1980, c 22, §1; am L 1983, c 140, §8; gen ch 1985; am L 1987, c 187, §2, c 195, §1, c 283, §23, and c 325, §1; am L 1992, c 241, §2; am L 1996, c 61, §2; am L 2004, c 55, §3; am L 2005, c 130, §3; am L 2006, c 250, §4; am L 2008, c 110, §2 and c 207, §5; am L 2009, c 11, §4; am L 2012, c 172, §2 and c 312, §2; am L 2016, c 27, §5; am L 2021, c 152, §13]
(a) Notwithstanding any other law to the contrary, for any primary action that requires a permit or approval that is not subject to a discretionary consent and that involves a secondary action that is ancillary and limited to the installation, improvement, renovation, construction, or development of infrastructure within an existing public right-of-way or highway, that secondary action shall be exempt from this chapter; provided that the applicant for the primary action shall submit documentation from the appropriate agency confirming that no further discretionary approvals are required.
(b) As used in this section:
"Discretionary consent" means:
(1) An action as defined in section 343-2; or
(2) An approval from a decision-making authority in an agency, which approval is subject to a public hearing.
"Infrastructure" includes waterlines and water facilities, wastewater lines and wastewater facilities, gas lines and gas facilities, drainage facilities, electrical, communications, telephone, and cable television utilities, and highway, roadway, and driveway improvements.
"Primary action" means an action outside of the highway or public right-of-way that is on private property.
"Secondary action" means an action involving infrastructure within the highway or public right-of-way.
[L 2012, c 312, §1]
Except as otherwise provided in chapter 201H or under federal law, permanently affordable multi-family rental housing projects that are being redeveloped pursuant to a special management area use permit issued under section 205A-29.5 that are located on properties or districts on the Hawaii or national register of historic places shall be exempt from the requirements of this chapter.
[L 2025, c 313, §4]
(a) After consultation with the affected agencies and the environmental advisory council, the office of planning and sustainable development shall adopt, amend, or repeal necessary rules for the purposes of this chapter in accordance with chapter 91 including but not limited to rules that shall:
(1) Prescribe the procedures whereby a group of proposed actions may be treated by a single environmental assessment or statement;
(2) Establish procedures whereby specific types of actions, because they will probably have minimal or no significant effects on the environment, are declared exempt from the preparation of an environmental assessment;
(3) Prescribe procedures for the preparation of an environmental assessment;
(4) Prescribe the contents of an environmental assessment;
(5) Prescribe procedures for informing the public of determinations that a statement is either required or not required, for informing the public of the availability of draft environmental impact statements for review and comments, and for informing the public of the acceptance or nonacceptance of the final environmental statement;
(6) Prescribe the contents of an environmental impact statement;
(7) Prescribe procedures for the submission, distribution, review, acceptance or nonacceptance, and withdrawal of an environmental impact statement; and
(8) Establish criteria to determine whether an environmental impact statement is acceptable or not.
(b) At least one public hearing shall be held in each county prior to the final adoption, amendment, or repeal of any rule.
[L 1974, c 246, pt of §1; am and ren L 1979, c 197, §1(7); am L 1983, c 140, §9; am L 1986, c 186, §2; am L 1987, c 187, §3; am L 2008, c 110, §3; am L 2021, c 152, §14 and c 153, §9]
The purchase of the assets of the Waiahole water system shall be specifically exempt from the requirements of chapter 343.
[L 1998, c 111, §4]
(a) Any judicial proceeding, the subject of which is the lack of assessment required under section 343-5, shall be initiated within one hundred twenty days of the agency's decision to carry out or approve the action, or, if a proposed action is undertaken without a formal determination by the agency that a statement is or is not required, a judicial proceeding shall be instituted within one hundred twenty days after the proposed action is started. The office, any agency responsible for approval of the action, or the applicant shall be adjudged an aggrieved party for the purposes of bringing judicial action under this subsection. Others, by environmental court action, may be adjudged aggrieved.
(b) Any judicial proceeding, the subject of which is the determination that a statement is required for a proposed action, shall be initiated within sixty days after the public has been informed of such determination pursuant to section 343-3. Any judicial proceeding, the subject of which is the determination that a statement is not required for a proposed action, shall be initiated within thirty days after the public has been informed of such determination pursuant to section 343-3. The applicant shall be adjudged an aggrieved party for the purposes of bringing judicial action under this subsection. Others, by environmental court action, may be adjudged aggrieved.
(c) Any judicial proceeding, the subject of which is the acceptance or nonacceptance of an environmental impact statement required under section 343-5, shall be initiated within sixty days after the public has been informed pursuant to section 343-3 of the acceptance or nonacceptance of such statement. Affected agencies and persons who provided written comment to an accepted statement during the designated review period shall be adjudged aggrieved parties for the purpose of bringing judicial action under this subsection; provided that for aggrieved parties, the contestable issues shall be limited to issues identified and discussed in the written comment, and for applicants bringing judicial action under this section on the nonacceptance of a statement, the contestable issues shall be limited to those issues identified by the accepting authority as the basis for nonacceptance of the statement.
[L 1974, c 246, pt of §1; am and ren L 1979, c 197, §1(8); am L 1983, c 140, §10; am L 1992, c 241, §3; am L 2014, c 218, §8; am L 2021, c 152, §15]
If any provision of this chapter or the application thereof to any person or circumstance is held invalid, such invalidity shall not affect other provisions or applications of this chapter which can be given effect without the invalid provision or application; and to this end, the provisions of this chapter are declared to be severable.
[L 1974, c 246, pt of §1; ren L 1979, c 197, §1(9)]