Alex Molinaroli v. Stacy J. Miller

CourtListener 10109854WisctappFeb 16, 2021

Full text

COURT OF APPEALS
DECISION NOTICE
DATED AND FILED This opinion is subject to further editing. If
published, the official version will appear in
the bound volume of the Official Reports.
February 16, 2021
A party may file with the Supreme Court a
Sheila T. Reiff petition to review an adverse decision by the
Clerk of Court of Appeals Court of Appeals. See WIS. STAT. § 808.10
and RULE 809.62.

Appeal No. 2019AP1248 Cir. Ct. No. 2016CV5961

STATE OF WISCONSIN IN COURT OF APPEALS
DISTRICT I

ALEX MOLINAROLI,

PLAINTIFF-RESPONDENT-CROSS-APPELLANT,

V.

STACY J. MILLER A/K/A STACY AGOUDEMOS AND
KOSTANTINOS P. AGOUDEMOS,

DEFENDANTS-APPELLANTS-CROSS-RESPONDENTS.

APPEAL and CROSS-APPEAL from an order of the circuit court
for Milwaukee County: TIMOTHY M. WITKOWIAK, Judge. Affirmed in part;
reversed in part and cause remanded with directions.

Before Brash, P.J., Donald and White, JJ.

¶1 WHITE, J. Stacy J. Miller and Kostantinos P. Agoudemos (the
Millers) appeal the trial court order determining attorney fees under an
indemnification clause of an easement agreement. The Millers argue that the trial
No. 2019AP1248

court applied the incorrect legal standard to determine reasonable attorney fees
pursuant to WIS. STAT. § 814.045 (2017-18).1 Alex Molinaroli cross-appeals the
same trial court order arguing there was insufficient evidence to support the
damages awards against him. Upon review, we conclude that the trial court made
an erroneous exercise of discretion when it awarded damages for landscaping
costs and, accordingly, we reverse the part of the trial court order awarding those
damages. We affirm, however, the trial court order awarding damages for noise
and trespass.2 Because the attorney fees were based on the damage awards, we
reverse this part of the trial court order and remand for the new determination of
attorney fees.

BACKGROUND

¶2 This matter arises out of an easement agreement governing access to
condominium elements during construction. Molinaroli, residing in condominium
Unit 801, initiated the underlying action to this appeal against Park Terrace Bluff
Homes Condominium Association (the Association) and the Millers, neighbors
who reside in condominium Unit 815. Molinaroli wanted to add a swimming pool
within Unit 801; in April 2015, he entered into an easement agreement (the
Easement) with the Association to facilitate construction.

¶3 Under the Easement, the Association granted Molinaroli a temporary
construction easement over the common elements and limited common elements

1
All references to the Wisconsin Statutes are to the 2017-18 version unless otherwise
noted.
2
We note that neither party appeals the disposition of the Millers’ claims; therefore, we
affirm the parts of the trial court order not related to the damages awards and attorney fees.

2
No. 2019AP1248

reasonably necessary to construct the pool. Molinaroli was required to seek
express permission from other owners as necessary. The Easement contained an
indemnification clause that included reasonable attorney fees.

¶4 Over the following year, disputes arose between Molinaroli and the
Millers over access and modification of the side yard between the units. The side
yard was a limited common element appurtenant to Unit 815, over which the
Millers had exclusive rights under the Association’s governing documents.
Although the Millers and Molinaroli agreed that Molinaroli could set up
scaffolding in the side yard during construction, when the scaffolding was
removed the Millers found new HVAC pipes that vented into the side yard.
Molinaroli also installed security cameras, at least one of which faced the side
yard and Unit 815.

¶5 In July 2016, the Association notified Molinaroli that the installation
or planned installation of exhaust pipes, a boiler, air conditioning, and security
cameras were not in compliance with the Association governing documents and
the Easement. The Association set an August 5, 2016 deadline for Molinaroli to
bring the construction into compliance with the Agreement. In response, on
August 5, 2016, Molinaroli filed a complaint asking the trial court to reform the
condominium plat and governing documents, and to grant an implied easement,
relief from tortious interference by the Millers, and quiet title on ownership
claims.

¶6 The Association counterclaimed for breach of contract regarding the
Easement. The Millers filed compulsory counterclaims in their answer to
Molinaroli’s suit: under an overall theory of nuisance, their counterclaims
consisted of trespass, negligence in the installation of pipes in relation to the pool,

3
No. 2019AP1248

breach of the Easement with regard to the condition of the side yard, and a
declaratory judgment about their rights and control of the side yard.3 They also
requested attorney fees under the indemnification clause of the Easement.

¶7 The trial court granted partial summary judgment in favor of the
Millers and the Association on Molinaroli’s claims in January 2018. The trial
court entered an order dismissing on the merits with prejudice Molinaroli’s claims
for reformation, implied easement, tortious interference with contract, and quiet
title.

¶8 The trial court held a court trial on the Millers’ counterclaims on
February 28, 2019, and March 1 and 6, 2019, with a focus on the Millers’ alleged
damages. Relevant to the issue of damages, the court heard testimony from the
Millers and Molinaroli.

¶9 At the trial, Kostantinos4 testified that he accepted an offer from
Molinaroli to landscape the side yard in exchange for hosting scaffolding and
construction staging. Kostantinos testified that when the scaffolding was
removed, he found copper exhaust pipes for Molinaroli’s HVAC system and
security cameras in the yard, neither of which had been installed by permission.
He explained that the noise from the pipes interfered with watching TV, carrying
on conversations, and made it hard to use the side yard for outdoor leisure or
exercise. He also complained that there was a nasty exhaust smell, like gas. He

3
The counterclaim labeled four causes of action, but the Millers also satisfied notice
pleading requirements for a claim of nuisance. See Strid v. Converse, 111 Wis. 2d 418, 423, 331
N.W.2d 350 (1983). Because the trial court order addressed nuisance, we include it here.
4
We refer to Kostantinos Agoudemos as Kostantinos in his individual testimony.

4
No. 2019AP1248

testified that he felt he lost use of his property due to the security cameras pointed
at his bedroom and shower and the “noxious fume or noise or vibration” that he
experienced whenever he opened certain doors and windows. Kostantinos
testified that there was no physical or permanent damage to the grounds, wall, or
fence as a result of the pipes or construction, but that debris near the scaffolding
may require repair.

¶10 To establish the damages, Kostantinos testified that he believed that
Molinaroli stated in his deposition that the value of the promised landscaping of
the side yard was $20,000. Kostantinos testified that it costs approximately
$3,500 a month to live in their unit, but due to the pipes and cameras, the only
usable space in the unit was the basement. He concluded that the value of his
enjoyment of the property had diminished by 60% during this period of time.

¶11 Stacy5 testified that the construction process took over three years
and it was extremely loud. She testified that Molinaroli offered that “in exchange
for letting us have the scaffolding he would relandscape our yard once the
scaffolding was gone”—which she interpreted “to mean new grass, new
landscaping, edging because they cut the edging of the landscaping.” She also
testified that she believed Molinaroli said the planned landscaping cost an
estimated $20,000. She testified that their cost of living at the unit was about
$3,600 a month, and that due to the lack of privacy, the security cameras, the
pipes, the noise, fumes, and the lack of access to the yard, her use and enjoyment
of the property was diminished by 50% during construction. She testified that
although their counterclaim stated that they would need to add insulation to the

5
We refer to Stacy Miller as Stacy in her individual testimony.

5
No. 2019AP1248

unit for soundproofing, they had not installed anything—including window
treatments to block the cameras.

¶12 Molinaroli testified that he asked the Millers if he could put
scaffolding in the side yard, and they agreed but requested help with landscaping
and drainage issues in the side yard the following spring. Molinaroli disputed that
he had ever stated that the estimated cost of the landscaping was $20,000; he
reviewed his deposition testimony and found no mention of landscaping costs. 6 At
trial, he guessed based on his own life experience that landscaping a small side
yard would cost $3,000 to $5,000, but stated that he “just made [the price] up.”

¶13 The trial court entered a final order on June 21, 2019. 7 The trial
court dismissed the Millers’ nuisance claim because it concluded that the Millers
failed to meet the burden of proof to show that the operation of the boiler and the
security cameras unduly interfered with the use of the Millers’ unit or the side
yard. The trial court also dismissed the negligence claim because the Millers did
not offer a necessary expert opinion to support their claim. Additionally, the trial
court dismissed the declaratory relief claim because the issue was not pursued at
trial.

¶14 The trial court concluded that the placement of the security cameras
was not within the express provisions of the Easement. The court concluded that
the security cameras, the pipes, and noise breached the Easement, constituting

6
Only a portion of Molinaroli’s deposition is in the record, but the submission does not
include a reference to $20,000. We defer to the trial court’s credibility determinations.
7
On June 12, 2019, the trial court accepted a stipulation of settlement between the
Association and Molinaroli that dismissed all claims with prejudice. The court entered the order
for dismissal the following day.

6
No. 2019AP1248

trespass. The court awarded nominal damages in the amount of $500 for the
trespass. The court noted that the Millers only anticipated curtains as a cost,
which they admitted at trial they did not incur. The court was not persuaded that
the Millers altered their use of their unit or the side yard based on the presence of
the security cameras.

¶15 On the Millers’ breach of the Easement claims, the trial court
concluded that the Millers offered no credible evidence of actual pecuniary loss as
a result of placement of the security cameras and, therefore, the Millers could not
recover damages on their breach of contract claim related to the cameras. The
court found that the Millers offered credible evidence that there was noise created
by the pipes and boiler that were not expressly allowed under the Easement and
therefore the presence of the pipes and the noise they generated constituted a
breach of the Easement. However, the court found that this breach was remedied
when the second boiler was turned off, the pipes were disconnected, and the
appropriate equipment was installed. The court awarded the Millers $5,000 for
this breach of the Easement.

¶16 The trial court concluded that the Millers and Molinaroli entered into
an agreement by which Molinaroli could put scaffolding in the side yard in return
for Molinaroli replacing the Millers’ “landscaping in the spring (2016) at [his]
cost.” The court awarded the Millers $5,000 in return for their allowance of the
scaffolding and damages caused by the scaffolding. Combined, the damages
totaled $10,500.

7
No. 2019AP1248

¶17 Finally, the court awarded the Millers attorney fees in the amount of
$31,500 dollars, which was three times the compensatory damages, pursuant to
WIS. STAT. 814.045(2)(a).8 The Millers appeal the award of attorney fees.
Molinaroli cross appeals arguing that the evidence was insufficient to support the
damages for the breach of the Easement, but he does not challenge the nominal
damages for trespass.

DISCUSSION

¶18 The Millers argue that the trial court erroneously exercised its
discretion to apply the statutory presumption under WIS. STAT. § 814.045(2)(a)
when it determined the amount of reasonable attorney fees payable by Molinaroli
under the indemnification clause. Molinaroli argues that the statutory presumption
was within the trial court’s discretion and supported by the paucity of billing
evidence to support the attorney fees. For reasons explained in more detail below,
we conclude it is premature to review the application of the reasonable attorney
fees statute to these facts.

¶19 Molinaroli argues that the compensatory damages award was not
supported by sufficient evidence; therefore, the damages award should be vacated.
The Millers argue that Molinaroli has waived a challenge to the sufficiency of the
evidence to support the damages awards by not raising it until this cross-appeal.
This argument fails. “In actions tried by the court without a jury, the question of

8
WISCONSIN STAT. § 814.045(2)(a) provides that “[i]n any action in which
compensatory damages are awarded, the court shall presume that reasonable attorney fees do not
exceed 3 times the amount of the compensatory damages awarded but this presumption may be
overcome if the court determines … that a greater amount is reasonable” under an analysis based
on fifteen factors contained within a subsection of the statute.

8
No. 2019AP1248

the sufficiency of the evidence to support the findings may be raised on appeal
whether or not the party raising the question has objected in the trial court to such
findings or moved for new trial.” WIS. STAT. § 805.17(4). Here, the trial court
conducted a trial without a jury. Molinaroli challenges the sufficiency of the
evidence to support the damages award. We conclude that Molinaroli did not
waive his right to raise this issue on appeal.9

¶20 Because the statutory presumption of attorney fees relies upon the
amount of compensatory damages awarded, our inquiry must begin with the cross-
appeal. We note that Molinaroli does not challenge the sufficiency of the evidence
to support the trial court’s conclusions that the Easement was breached by the
cameras, the pipes, and by the scaffolding and landscaping. Molinaroli only
argues that the trial court’s findings are insufficient to support the valuation of the
damages, specifically, as related to the awards for landscaping costs and noise-
related damages.

¶21 As a threshold matter, in his reply, Molinaroli argues that the
economic loss doctrine bars the Millers’ claims for damages outside of the
contract terms. This argument fails. The economic loss doctrine is inapplicable to
the Millers’ claims for breach of the Easement because there is no product or sales

9
Further, the record shows that the appeal and the cross-appeal were timely filed within
the statutory rules to initiate an appeal after the trial court issued its final order.

9
No. 2019AP1248

contract at issue.10 See Daanen & Janssen, Inc. v. Cedarapids, Inc., 216 Wis. 2d
395, 402, 573 N.W.2d 842 (1998). The Easement established rights and
responsibilities during Molinaroli’s pool construction. It is not a construction
contract. It was a temporary easement, which allowed Molinaroli to build the
pool.

¶22 The purpose of the Easement was to protect the Association and the
property rights of all owners of the condominium association affected by
Molinaroli’s construction. “An easement is a liberty, a privilege … distinct from
an ownership.” Grygiel v. Monches Fish & Game Club, Inc., 2010 WI 93, ¶13,
328 Wis. 2d 436, 787 N.W.2d 6 (citation omitted). “A written easement holder
has the right to use the easement in accordance with the express terms of the
easement grant.” Id., ¶19. When there “has been a breach of a contractual
obligation … the wronged party has a right to an appropriate remedy, which is
dependent upon the nature and extent of the wrong sustained.” Thorp Sales Corp.
v. Gyuro Grading Co., 111 Wis. 2d 431, 437-38, 331 N.W.2d 342 (1983).
“[W]hether a party has suffered a compensable economic loss and the dollar figure
to be attributed to that loss is a factual determination.” Fletcher v. Eagle River
Mem’l Hosp., Inc., 150 Wis. 2d 145, 155, 441 N.W.2d 297 (Ct. App. 1989), rev’d
on other grounds, 156 Wis. 2d 165, 456 N.W.2d 788 (1990).

10
“[T]he ‘economic loss doctrine’ is a judicially created doctrine providing that a
purchaser of a product cannot recover from a manufacturer damages that are solely economic in
nature under tort theories of negligence or strict liability.” Magestro v. North Star Env’t Constr.,
2002 WI App 182, ¶6, 256 Wis. 2d 744, 649 N.W.2d 722. The doctrine “limits recovery to only
economic losses” in contract actions. Id. “[E]conomic loss is damage to a product itself or
monetary loss caused by a defective product that does not cause personal injury or damage to
other property.” Biese v. Parker Coatings, Inc., 223 Wis. 2d 18, 23, 588 N.W.2d 312 (Ct. App.
1998).

10
No. 2019AP1248

¶23 The determination of damages for breach of an easement does not fit
neatly into other contract damages formulations. As a general rule “[f]or
obstruction of an easement, damages and injunctions requiring removal of the
obstruction, restoration of the easement, and prohibiting future obstruction are
normally appropriate.” RESTATEMENT (THIRD) OF PROPERTY (SERVITUDES) § 8.3
(2000). “A judgment for money damages ordinarily provides an adequate remedy
for a claim for maintenance, repair, or replacement expenses[.]” Id. Although an
easement governs an issue of property rights, it does not set forth the terms of a
property transaction, making it difficult to determine benefit of the bargain or
diminished value damages. Cf. Vandehey v. City of Appleton, 146 Wis. 2d 411,
415, 437 N.W.2d 550 (Ct. App. 1988); Champion Cos. of Wis., Inc. v. Stafford
Dev., LLC, 2011 WI App 8, ¶7, 331 Wis. 2d 208, 794 N.W.2d 916.11

¶24 Determining damages is within the trial court’s discretion. J.K. v.
Peters, 2011 WI App 149, ¶32, 337 Wis. 2d 504, 808 N.W.2d 141. We will not
disturb the trial court’s factual findings determining damages unless the findings
are “clearly erroneous.” WIS. STAT. § 805.17(2). When a trial court awards
damages, we will sustain that award “if there is any credible evidence that under
any reasonable view supports it and removes the issue from the realm of
conjecture.” Betterman v. Fleming Cos., 2004 WI App 44, ¶39, 271 Wis. 2d 193,
677 N.W.2d 673. A damages award must be “supported by credible evidence and

11
For example, “the benefit of the bargain is measured by the difference between the
value of the property as represented and its actual value as purchased.” Vandehey v. City of
Appleton, 146 Wis. 2d 411, 415, 437 N.W.2d 550 (Ct. App. 1988). “[A]n alternative measure of
recovery is … compensation based on the difference between real and represented value.”
Ollerman v. O’Rourke Co., 94 Wis. 2d 17, 53, 288 N.W.2d 95 (1980). “Evidence of a property’s
diminished value is one way to measure damages in a lawsuit over injury to property.”
Champion Cos. of Wis., Inc. v. Stafford Dev., LLC, 2011 WI App 8, ¶7, 331 Wis. 2d 208, 794
N.W.2d 916.

11
No. 2019AP1248

[be] within reasonable limits.” Selmer Co. v. Rinn, 2010 WI App 106, ¶29, 328
Wis. 2d 263, 789 N.W.2d 621. Whether the trial court applied a proper legal
standard when it awarded damages is a question of law that we review de novo.
J.K., 337 Wis. 2d 504, ¶32,

¶25 From our review of the $5,000 damages award for scaffolding and
landscaping, we conclude there is no credible evidence in the record supporting
this amount; therefore, the trial court erroneously exercised its discretion to order
the same. There was no testimony as to the value of the proposed landscaping
work that was based on any proven costs to provide landscaping. Kostantinos and
Stacy each testified that Molinaroli’s deposition testimony set a $20,000 figure,
but Molinaroli denied this in his testimony. The Millers have not shown evidence
of Molinaroli stating a figure in negotiating the contract or in his deposition.
Molinaroli testified that he guessed that landscaping would cost $3,000-$5,000,
but he stated that the number was made up. There was no testimony to establish
the damages caused by the scaffolding or the cost of repair. The trial court’s order
does not explain its reasoning to award $5,000 in damages on this issue;
furthermore, our review of the record finds no credible evidence upon which to
affirm the order. Without any credible evidence, we cannot sustain the trial
court’s decision to order this damages award and we must reverse the order.
Betterman, 271 Wis. 2d 193, ¶39.

¶26 When we consider Molinaroli’s breach of the Easement by allowing
noisy pipes to disturb the Millers, Kostantinos and Stacy each testified that their
enjoyment in the property was diminished due to the noisy pipes and during the
time of construction. We sustain the trial court’s award of $5,000 in damages
because there is some credible evidence in the record. We are highly deferential
in our review of damage awards and we will affirm the award if there is any

12
No. 2019AP1248

credible evidence which under any reasonable view supports the finding. Selmer,
328 Wis. 2d 263, ¶28. The Millers’ diminished enjoyment was based on their
testimony and was not otherwise quantified in the record; however, we will not
allow the breaching party to “profit from that difficulty of proof” because
quantifying this issue is difficult to “definitely ascertain[] or determine[.]” See id.,
¶30 (citations omitted).

¶27 Molinaroli requests we vacate both damages awards for breach of
the Easement and remand for only nominal damages. We disagree. When “it is
certain that damage has resulted, mere uncertainty as to the amount will not
preclude the right of recovery.” Essock v. Mawhinney, 3 Wis. 2d 258, 270, 88
N.W.2d 659 (1958) (citation omitted). Molinaroli has not challenged the
sufficiency of the evidence underlying the court’s factual findings and legal
conclusions that Molinaroli breached the Easement. Because the Millers’ rights to
their property ownership has been injured by the breach of the Easement, “any
reasonable approximation of the amount of that injury must in justice be accepted
as a measure of the damages.” Thorp, 111 Wis. 2d at 437-38. Therefore, we
affirm the trial court award of $5,000 for the breach of the Easement for noisy
pipes.

¶28 Because the award of attorney fees were tied to the compensatory
damages, we remand the determination of attorney fees to the trial court. As
guidance to the trial court regarding attorney fees, we conclude that the plain
meaning of the text of WIS. STAT. § 814.045(2)(a) applies in all actions in which
compensatory damages are awarded. The determination of attorney fees remains
within the discretion of the trial court. See Village of Shorewood v. Steinberg,
174 Wis. 2d 191, 204, 496 N.W.2d 57 (1993). However, we note, when “the

13
No. 2019AP1248

reasonableness of attorney fees is disputed, record evidence is needed.” Peterson
v. Gauger, 148 Wis. 2d 231, 237, 434 N.W.2d 819 (Ct. App. 1988).

¶29 No WIS. STAT. RULE 809.25(1) costs shall be assessed to either
party.

By the Court.—Order affirmed in part; reversed in part and cause
remanded with directions.

Not recommended for publication in the official reports.

14

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.