REDONDO CONSTRUCTION CORPORATION et al v. PUERTO RICO HIGHWAY AUTHORITY

3:02-ap-00113PrbAug 31, 2009

Full text

IN THE UNITED STATES BANKRUPTCY COURT
FOR THE DISTRICT OF PUERTO RICO
IN RE: 	:
:
REDONDO CONSTRUCTION 	: 	CASE NO. 02-02887 (GAC)
CORPORATION, CORP., 	:
:
Debtor 	: 	CHAPTER 11
___________________________________:
:
REDONDO CONSTRUCTION 	:
CORPORATION, CORP., 	:
:
Plaintiff 	:
:
v. 	: 	ADV. NO. 02-0113
:
PUERTO RICO HIGHWAY AND 	:
TRANSPORTATION AUTHORITY 	:
:
Defendant 	:
___________________________________:
DECISION AND ORDER
I. 	PROCEDURAL BACKGROUND
Pending before the Court is the complaint filed in the present
adversary 	procedure, 	by 	Redondo 	Construction, 	Corp. 	("Redondo"),
to 	determine 	if 	the 	Puerto 	Rico 	Highway 	and 	Transportation
Authority 	(“PRHTA”) 	is 	required 	to 	pay 	Redondo 	additional
compensation, 	including 	interests, 	for 	unpaid 	claims 	and 	damages
allegedly 	resulting 	from 	the 	work 	performed 	by 	Redondo 	under 	the
following 	contracts: 	Contract 	AC-019916 	(Las 	Cumbres 	Avenue, 	El
Capa); 	Contract 	AC-020303 	(Rio 	Grande 	de 	Loiza 	Bridge); 	Contract
AC-220095 	(Kennedy 	Avenue 	- 	Caparra 	Interchange); 	Contract 	AC-
100029 	(Ponce 	Adjuntas 	- 	PR-19) 	and 	Contract 	AC-800135 	(Third
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 1 of 59
2
Millennium Park).
Redondo 	is 	requesting 	additional 	compensation 	for 	extended
jobsite and home office overhead costs, additional compensation for
inefficiencies in the prosecution of the work due to the actions or
omissions 	of 	the 	PRHTA, 	reimbursement 	of 	additional 	patent 	and
excise taxes allegedly paid by Redondo due to the increase in the
value of the contracts, reimbursement of additional insurance and
bond 	costs 	allegedly 	paid 	by 	Redondo 	due 	also 	to 	the 	increase 	in
the 	value 	of 	the 	contracts, 	reimbursement 	of 	improperly 	assessed
liquidated damages, payment for additional work allegedly performed
by Redondo but not paid by the PRHTA, and a fifteen per cent (15%)
mark-up on all claim items as profit.
PRHTA contends that Redondo did not prove its entitlement to
most 	of 	the 	remedies 	sought, 	or 	demonstrated 	the 	indispensable
cause 	and 	effect 	relationship 	between 	the 	impacts 	and 	the
additional 	costs 	claimed. 	PRHTA 	also 	asserts 	that 	in 	the 	rare
instances that Redondo did prove its entitlement to said remedies,
he 	did 	not 	establish 	or 	substantiate 	the 	amount 	owed 	as
compensation.
The Court held the trial of the present adversary proceeding
on November 27-30, 2006; December 1, 2006; March 9, 2007; March 15,
2007; March 19-21, 2007; June 46 and 25-27, 2007; and November 5-7,
2008. Then on March 27, 2009, PRHTA filed the post trial brief with
proposed findings and conclusions of law (docket #364) and on the
same 	day, 	Redondo 	filed 	the 	post 	trial 	brief 	and 	the 	memorandum
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 2 of 59
3
with the finding of facts (dockets #365 and #366).
II. 	General Factual Background
Redondo 	has 	been 	engaged 	in 	the 	construction 	business 	for
thirty years, particularly in public or government projects, prior
to the filing for bankruptcy.
Prior 	to 	the 	filing 	of 	its 	petition 	for 	bankruptcy 	relief,
Redondo entered into various construction contracts with the PRHTA
and 	the 	Department 	of 	Transportation 	and 	Public 	Works 	of 	Puerto
Rico, with regard to the following projects: Contract AC-019916 -
Ave. Las Cumbres - El Capa (May 11, 1998); Contract AC-020303 - Rio
Grande de Loiza Bridge (April 11, 1996); Contract AC-220095 - Ave.
Kennedy-Caparra Interchange (October 31, 1997); Contract AC-100029
- Ponce -Adjuntas PR-10 (October 30, 1996); and, Contract AC-800135
- Parque del Tercer Milenio ("Third Millenium Park") (November 17,
1998).
The 	master 	contract 	for 	each 	project 	is 	contained 	in 	a
contract book that incorporates the award, the bid documents, the
plans and specifications. The master contract also incorporates the
Commonwealth 	of 	Puerto 	Rico, 	Department 	of 	Transportation 	and
Public Works and Highway Authority's "Standard Specifications for
Road and Bridge Construction of 1989" (The Blue Book).
On August 21, 2001 Redondo submitted to the PRHTA the claims
for time extensions, inefficiency, extended overhead, lost profits,
and/or 	other 	concepts 	for 	several 	projects, 	including 	the 	five
projects 	concerned 	herewith. 	At 	the 	time 	of 	the 	filing 	of 	the
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 3 of 59
4
complaint 	all 	five 	projects 	were 	completed 	and 	the 	PRHTA 	had 	not
informed 	Redondo 	of 	the 	results 	of 	any 	audit 	of 	the 	claims
presented.
By 	May 	of 	2003, 	after 	the 	filling 	of 	bankruptcy, 	Redondo
retained the firm of FPV & Co. to calculate its job site and main
office 	extended 	overhead 	for 	each 	project 	and 	issued 	a 	report
signed by CPA, Rafael Perez Villarini, with said calculations. The
reports 	prepared 	by 	Rafael 	Perez 	Villarini 	for 	each 	project 	were
styled 	"Independent 	Accountant's 	Report 	on 	Applying 	Agreed 	Upon
Procedures." 	Rafael 	Perez 	Villarini 	is 	a 	Certified 	Public
Accountant who is also certified as a Valuation Analyst.
Andrew Civitello (“Civitello”) testified as Redondo's expert
in 	construction 	management 	and 	Sid 	Scott 	(“Scott”) 	testified 	as
PRHTA's expert in construction claims.
III. 	Position 	of 	the 	Parties 	as 	to 	each 	claims 	in 	all 	of 	the
Projects
In 	the 	present 	case 	ten 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	Extended 	main 	office 	overhead 	and 	Extended 	job 	site
overhead, 	2. 	Inefficiency, 	3. 	Insurance 	and 	Bonds 	Premiums, 	4.
Patent 	and 	Excise 	Taxes, 	5. 	Profit 	(15%), 	6. 	Liquidated 	Damages,
7. Termination of contract, 8. Interest at 6%, 9. Overcharge, and
10. Unpaid Application for Certifications.
A. Redondo
1. Extended Main Office Overhead and Extended Job Site Overhead
Redondo asserts that the calculation of the job site overhead
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 4 of 59
5
was 	made 	from 	Redondo’s 	accounting 	records 	for 	each 	particular
project, 	taking 	in 	consideration 	overhead 	for 	each 	category
incurred 	during 	the 	period 	of 	the 	contract 	(when 	it 	commenced 	to
when it was substantially completed). The total job site overhead
was 	then 	divided 	by 	the 	number 	of 	days 	to 	obtain 	a 	per 	day 	(”per
diem”) expense, which was multiplied by the days for the extended
period 	(“the 	extensions 	of 	time”). 	The 	original 	information 	was
obtained from Redondo’s Accounting and Cost Departments. The home
office 	expenses 	come 	from 	the 	Accounting 	Department, 	and 	the 	job
site information comes from the project engineers who furnished the
same to the Cost Department.
To determine the proportion of home office overhead that could
be attributable to the extended period for a particular contract,
Perez Villarini used the Eichleay formula, which is the most widely
used for claims of extended overhead. Eichleay applies to partial
suspensions, 	and 	not 	necessarily 	to 	total 	suspensions. 	A 	partial
suspension means that some items are continuing, and some items are
not. That is what happened in Redondo’s claims.
2. Inefficiency
Redondo 	asserts 	that 	its 	computations 	were 	verified 	by
Civitello. A method for calculating the same is to understand the
way an activity or process is planned, and what that cost would be
for the planned method of completing that work; if the activity is
interrupted 	or 	affected, 	taking 	a 	longer 	or 	shorter 	time, 	the
characteristics 	of 	the 	work 	may 	change; 	if 	conditions 	on 	the
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 5 of 59
6
project 	occur, 	that 	differ 	from 	the 	conditions 	that 	were
anticipated when the cost for that activity was prepared, and those
conditions affect the performance of that work, that is a typical
inefficiency.
Inefficiency is a normal item to add, because of the character
of 	these 	projects, 	particularly 	the 	fact 	that 	work 	continued 	for
such 	a 	long 	time 	after 	substantial 	completion, 	and 	the 	nature 	of
the 	interruptions, 	are 	characteristic 	of 	inefficient 	work. 	These
impacts 	caused 	re-sequencing 	of 	work, 	in 	order 	to 	complete 	it,
according to whatever work areas were available. The inefficiencies
in these claims were caused because the planned scheme got changed
and broken up in multiple times by the Authority.
The 	problems 	encountered 	were: 	of 	design, 	conditions 	on 	the
site were different, sub-surface conditions under the ground were
different 	than 	anticipated 	on 	the 	bid, 	and 	the 	inability 	of 	the
Authority to make the areas within alignments available. Therefore,
Redondo was prevented from working through the project footprint,
in the sequence, as they should.
3. Insurance and Bonds Premiums
Redondo asserts that as per their contract with PRHTA and the
Blue 	Book, 	it 	is 	entitled 	to 	the 	additional 	insurance 	and 	bonds
premiums paid 	attributable to the Extra Work Order.
4. Patents and Excise Taxes
Redondo asserts that as per their contract with PRHTA and the
Blue 	Book, 	it 	is 	entitled 	to 	the 	additional 	patents 	and 	excise
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 6 of 59
7
taxes paid 	attributable to the Extra Work Order.
5. Profit
Civitello 	determined 	a 	profit 	margin 	of 	15% 	above 	all 	cost
items. Also, in some of the agreements with Redondo, the Authority
acknowledged a 15% profit, and in the industry the reasonable range
is 	between 	5% 	to 	20%. 	Civitello 	applied 	profit 	to 	the 	item 	of
overhead because profits are applied to direct costs like labor and
materials.
6. The Liquidated Damages
With regard to the imposition of liquidated damages, Civitello
concluded 	that 	it 	was 	improper. 	The 	provision 	for 	liquidated
damages states that they apply in cases where the contractor is in
default. Here, they were applied automatically without any notice
of default on Redondo’s part. The Authority withheld the liquidated
damages 	contemporaneously 	from 	current 	applications 	for 	payment.
There 	was 	no 	contractual 	procedure 	followed 	to 	make 	any 	previous
determination 	of 	contractor 	default 	first. 	This, 	without 	even
considering the basis for the delay (Id.).
7. Termination of Contract
Redondo 	asserts 	that 	Section 	108.11 	of 	the 	Blue 	Book 	allows
the 	contractor 	to 	claim 	for 	its 	damages 	and 	costs 	related 	to 	the
termination of a contract or to a portion thereof.
8. Interest
Redondo 	asserts 	that 	the 	Blue 	Book 	also 	provides 	for 	the
payments of interest at the legal rate and 31 LPRA § 3025 provides
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 7 of 59
8
that the legal interest, in cases of contractual delay, is 6% per
year. 	Civitello 	calculated 	interest 	from 	a 	very 	conservative
standpoint. He used as the starting point “the payment due”, which
he considered to be 30 days after the date of final inspection for
each project.
During 	his 	June 	25, 	2007, 	testimony, 	Civitello 	adjusted 	his
report 	to 	reflect 	Puerto 	Rico’s 	legal 	annual 	interest 	rate,
however, he used 6.5% instead of 6% (Ex. 2a-2c, Civitello 14th TR
6/25/07 pp 94-994).
9. Overcharge
Redondo 	asserts 	that 	it 	was 	notified 	of 	the 	overcharge 	in
February of 2006, as part of the final liquidation of the project,
well 	after 	the 	litigation 	ensued, 	and 	over 	five 	years 	after
completion 	of 	the 	project. 	This 	even 	caused 	the 	splitting 	of 	the
case, 	to 	have 	separate 	hearings 	for 	this 	project. 	Said 	final
liquidation 	showed 	an 	alleged 	back 	charge 	against 	Redondo 	of
$1,447,079.71, mostly on the item of unclassified excavations. In
other 	words, 	the 	Authority 	claims 	that 	Redondo 	was 	overpaid 	in
regard 	to 	the 	volume 	of 	earth 	excavated 	in 	the 	project. 	It 	is
evident that the Authority fabricated this back charge in order to
offset Redondo’s claims, in view of the Authority’s lack of proof
and defenses in this case. The Authority simply could not prove the
overcharge. 	There 	was 	no 	evidence 	of 	its 	calculation 	and
Caraballo’s explanation of the same was, not only unintelligible,
but 	unsupported 	by 	independent 	documentary 	evidence, 	and 	not
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 8 of 59
9
credible (Stmnt. Fct. 457-463). Caraballo’s final liquidation and
testimony were disputed by the objective testimony of Eng. Campos
and 	his 	explanation 	of 	the 	difference 	in 	alignment 	of 	the 	Ponce-
Adjuntas 	Road’s 	Axis, 	due 	to 	the 	problem 	of 	the 	control 	points.
Caraballo’s determinations were also disputed by the overwhelming
documentary 	evidence 	about 	the 	increase 	in 	volume 	of 	earth
excavated due to the landslides, caused by the Authority’s defects
in the design of the inclination of the slopes.
Due 	to 	said 	factors, 	it 	is 	impossible 	to 	verify 	the
Authority’s position just based on the final liquidation, supplied
five 	years 	after 	substantial 	completion. 	Furthermore, 	these
calculations were performed by the Authority, based on drawings of
cross sections performed without Redondo’s participation. This was
done 	after 	the 	Authority 	and 	Caraballo 	approved 	Redondo’s
certifications for payments on a monthly basis, during five years
of construction, with a constant review an verification of the same
cross 	sections 	by 	Redondo’s 	and 	the 	Authority’s 	surveyors, 	this
without any claim of overpayments from the Authority during those
five 	years. 	Eng. 	Caraballo 	and 	Mr. 	Civitello 	explained 	that
Caraballo’s 	calculation 	were 	also 	incorrect 	because 	the 	item 	of
unclassified excavations was paid at two price levels, one portion
of 	the 	volume 	excavated 	at 	the 	original 	price 	of 	$4.80 	per 	cubic
meter, while another portion was paid at a price of $8.20 per cubic
meter. According to them, there was no way to correlate the volume
at 	the 	two 	different 	prices 	based 	solely 	on 	the 	information
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 9 of 59
10
provided 	by 	the 	final 	liquidations. 	This 	is 	why 	the 	Authority’s
expert required an ex-parte explanation from Caraballo, after the
conclusion of all testimonies, because he could not understand the
final 	liquidation 	based 	on 	the 	information 	provided 	by 	the
Authority 	during 	trial 	and 	tried 	to 	rehabilitate 	Caraballo’s
dubious testimony. Moreover, notwithstanding the fact that he could
not 	understand 	Caraballo’s 	final 	liquidation, 	Mr. 	Scott 	admitted
that 	he 	did 	not 	care 	to 	do 	an 	independent 	calculation 	of
Caraballo’s 	determination. 	The 	above 	is 	on 	top 	of 	the 	fact 	that
Caraballo’s computer was vandalized, and his data about the cross
section were lost and had to be reconstructed five years thereafter
by 	Surveyor 	Rivera 	Malave, 	which 	adds 	more 	doubts 	as 	to 	the
veracity 	of 	his 	calculations. 	Therefore, 	the 	overpayment 	was 	not
proved.
10. Certifications
Redondo 	asserts 	that 	the 	PRHTA’s 	bad 	faith 	is 	such, 	that 	it
has retained the payment of approved certifications for payments,
with the excuse that Redondo has not submitted information required
to process the final liquidations. Redondo argues that, first, it
has taken PRHTA all these years to process the final liquidations,
in violation of the Blue Book; second, it was the Authority who put
Redondo 	in 	the 	financial 	position 	of 	not 	being 	able 	to 	pay 	its
creditors, 	by 	delaying 	its 	claims; 	and 	third, 	that 	Redondo
presented evidence that it submitted all the information required
to process the final liquidations for each project (Ex. 35, 66, 98,
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 10 of 59
11
135a-e & 229), with the exception of the release from the sureties
regarding 	the 	performance 	bonds, 	and 	the 	evidence 	of 	payments 	to
the 	subcontractors. 	These 	last 	two 	items 	where 	not 	presented,
because 	Redondo 	was 	not 	able 	to 	pay 	its 	creditors 	due 	to 	its
bankruptcy, which was precisely due to the Authority’s delays and
lack of payment.
B. PRHTA
1. Extended Overhead and Extended Job Site Overhead
PRHTA asserts that it was stipulated by the parties that none
of the five (5) projects were completed at the original estimated
completion date. It is also clear that the PRHTA recognized that in
all 	these 	five 	(5) 	projects 	the 	owner 	introduced 	changes, 	due 	to
different reasons, and consequently reached agreements with Redondo
to compensate Redondo for such additional costs and time for those
changes under various extra work orders and agreements. Thus, while
it 	is 	undisputed 	that 	the 	Eichleay 	formula 	is 	the 	appropriate
method 	for 	measuring 	the 	amount 	of 	recovery 	of 	a 	claim 	for
unabsorbed overhead expenses, it is also undisputed that Redondo's
claim did not fully comply with Eichleay's prerequisites for such
recovery, 	when 	considering 	not 	the 	allegations 	but 	the 	actual
evidence presented at trial. 1 See, Stipulations No. 31, 65, 84, 99
and 118.
The Court of Appeals for the Federal Circuit has established
"two 	prerequisites 	to 	application 	of 	the 	Eichleay 	formula 	to
recover 	unabsorbed 	overhead 	... 	(1) 	that 	the 	contractor 	be 	on
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 11 of 59
12
standby 	and 	(2) 	that 	the 	contractor 	be 	unable 	to 	take 	on 	other
work." 	Interstate 	Gen. 	Gov't 	Contractors, 	Inc. 	v. 	West, 	12 	F.3d
1053, 1056 (Fed. Cir. 1993).
It asserts that the burden of proof lies squarely on Redondo's
shoulders. 	To 	be 	able 	to 	even 	apply 	the 	Eichleay 	formula 	to 	its
home 	office 	overhead 	claims, 	Redondo 	had 	to 	clearly 	and
convincingly establish that: a. the PRHTA constructively suspended
the Work and consequently made Redondo be on standby; and, b. that
Redondo was unable to take on other work at that time and because
of the PRHTA's actions. No such evidence was presented.
2. Inefficiencies
PRHTA argues that in proving lost productivity claims, it is
necessary to explain the nature of the injury because productivity
losses 	are 	by 	definition 	speculative. 	This 	involves 	focused 	and
straightforward 	evidence 	of 	how 	the 	disruptions 	caused 	the
productivity losses, the extent of these losses, and the monetary
damages 	associated 	with 	labor 	productivity 	losses. 	The 	proof
usually 	consists 	of 	job 	records, 	fact 	witnesses, 	and 	expert
testimony. 	See, 	Bramble, 	Barry 	B., 	Callahan, 	Michael 	T.,
Construction 	Delay 	Claims, 	Third 	Edition, 	Aspen 	Law 	&Business,
2000, p. 5-37.
It 	also 	argues 	that 	general 	unsupported 	statements 	that 	the
change 	orders 	impacted 	the 	work 	do 	not 	substitute 	for 	proof 	of
actual disruption. Rather, there must be evidence as to the effect
the changes had on the job. Bechtel Natl Inc., 90-1 B.C.A. (CCH) at
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 12 of 59
13
P22,549. See, e.g., Dravo Corp., ENGBCA No. 3800, 79-1 B.CA (CCH)
P13,575 	(1978) 	(loss 	of 	productivity 	not 	established 	where 	no
evidence 	crews 	were 	idle 	or 	underutilized). 	A 	claimant 	must 	show
not only that the disruption resulted solely from the defendant's
actions, but claimant must also show the extent of the disruption
and 	the 	harm 	it 	caused. 	No 	such 	showings 	were 	made 	by 	Redondo.
Under 	the 	case 	law, 	there 	must 	be 	contemporaneous 	documentary
evidence 	of 	disruptive 	effects. 	Claims 	of 	disruption 	must 	be
consistent with information in the Project files. The Project files
must show that the change orders were disrupting the Project, even
though the ultimate effect may not have been known until after the
job was complete. PRHTA concludes that Redondo is not entitled to
such claim.
3. Insurance and Bond Premiums
PRHTA 	asserts 	that 	Redondo 	is 	entitled 	to 	the 	insurance 	and
bonds 	premiums 	that 	it 	paid 	additionally 	but, 	no 	evidence 	was
presented.
4. Patents and Excise Taxes
PRHTA asserts that the revised Section 107.02 of the Blue Book
added 	a 	subsection 	"b" 	titled 	Municipal 	Taxes, 	which 	reads 	as
follows: "The Contractor shall pay all excise taxes Imposed by the
municipalities on construction projects no later than at the time
of the submittal of the first certification of partial payment as
per 	article 	109.06. 	Upon 	receipt 	of 	a 	certified 	Invoice 	or 	other
acceptable 	evidence 	of 	payment 	by 	the 	Contractor, 	the 	Authority
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 13 of 59
14
will reimburse the Contractor as provided below: 1) Form of payment
- Payment for the reimbursement of municipal excise taxes paid by
the 	Contractor 	will 	be 	made 	by 	an 	extra 	work 	order 	prepared 	for
this purpose. No payment will be made for mark-up, administrative
or 	incidental 	expense, 	profit, 	surcharges 	or 	any 	similar 	charge.
(2) Withholding of payments to the Contractor - If at the time of
the 	first 	certification 	for 	partial 	payment 	is 	submitted, 	the
Contractor has not paid the excise taxes, the Authority will retain
any monies due or that may become due to the Contractor up to the
full amount of the taxes. When the Contractor submits the evidence
of 	payment 	as 	per 	paragraph 	(1) 	above, 	the 	Authority 	will 	return
all retained monies.
PRHTA 	contends 	that 	the 	contracts 	clearly 	stated 	that
insurance 	premiums, 	bond 	costs, 	and 	municipal 	taxes 	are 	first
assessed using the original contract price as the base and paid by
the 	contractor 	BEFORE 	the 	Work 	actually 	begins. 	As 	also 	clearly
stated 	in 	the 	Blue 	Book, 	the 	contractor 	is 	fully 	responsible 	for
these costs which are not refundable, since they should have been
included in the contractor's bid. Notwithstanding the above, if the
final 	contract 	price 	exceeds 	the 	original 	contract 	estimate 	by
reason 	of 	changed 	or 	additional 	work, 	the 	contractor 	might 	be
entitled to a reimbursement for the additional insurance premiums,
bond 	costs, 	and 	municipal 	taxes 	paid, 	since 	those 	could 	not 	have
been 	included 	in 	the 	contractor's 	bid; 	although 	the 	contract
documents are silent in this regard. Nevertheless, to be entitled
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 14 of 59
15
to 	such 	reimbursement 	the 	contractor 	must, 	at 	the 	very 	least,
submit a certified invoice or other acceptable evidence of having
made those payments and no such evidence was provided by Redondo.
5. Profit
PRHTA 	asserts 	that 	if 	the 	extra 	work 	is 	paid 	for 	at 	unit
prices, 	then 	Section 	104.02 	of 	the 	Blue 	Book 	is 	controlling 	and
consequently, 	no 	additional 	profit 	could 	be 	assessed 	to 	those
items. 	Nevertheless, 	if 	the 	extra 	work 	is 	paid 	for 	on 	a 	Force
Account basis, since the payment is set unilaterally by the PRHTA,
Section 	109.04 	of 	the 	Blue 	Book 	includes 	an 	allowance 	of 	20% 	of
profit for labor costs, 15% of profit on the cost of materials and
10% of profit on insurance and taxes paid. It is important to note
that these additional payments constitute full compensation for all
items of expense not specifically designated.
6. Liquidated Damages
PRHTA 	asserts 	that 	liquidated 	damages 	was 	part 	of 	all 	the
contracts entered with Redondo. Furthermore, that pursuant to the
clear and unambiguous terms of Section 108.09(a) of the Blue Book,
if Redondo did not complete the Work in the time specified in the
contract, 	or 	as 	extended 	by 	mutual 	accord, 	then 	the 	PRHTA 	was
entitled to assess Liquidated Damages. Therefore, for Redondo to be
entitled 	to 	a 	disbursement 	of 	the 	withheld 	Liquidated 	Damages 	in
Projects AC-019916 and AC-800135, it bears the burden of proof of
establishing that: (a) Redondo timely requested extensions of time
in those two (2) projects; and (b) the PRHTA denied the extensions
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 15 of 59
16
of time, notwithstanding the fact that; (c) Redondo was entitled to
those extensions of time.
7. Termination of Contract
PRHTA argues that it can determine when in its best interests
it can eliminate parts of the work and that it compensated Redondo
according to Section 109.05 of the Blue Book, titled,"Payment for
Eliminated Items.”
On February 8, 2002, PRHTA issued Extra Work Order 12 in the
amount of $488,093.12 to compensate Redondo in full for the items
presented 	in 	the 	October 	25, 	1999 	c1aim. 	Neither 	Civitello 	nor
Redondo 	averted 	or 	submitted 	any 	documentation 	or 	analysis 	that
substantiated that Extra Work Order 12 did not fully compensate RCC
for the cost it incurred for the eliminated work. Redondo also did
not 	provide 	evidence 	to 	substantiate 	it's 	entitlement 	to 	an
additional 	$164,627.62 	for 	the 	eliminated 	work. 	Therefore, 	this
claim item must be denied.
8. Interest
PRHTA 	accept 	that 	under 	Rule 	44.3 	of 	the 	Rules 	of 	Civil
Procedure of Puerto Rico, 32, Redondo is entitled to interest.
9. Overcharge
PRHTA asserts that according to Certification Payment No. 57F,
dated 	April 	25, 	2005, 	the 	PRHTA 	overcompensated 	Redondo 	by
$1,098,845.94. This final certified payment included increases or
decreases 	in 	the 	final 	value 	of 	the 	work 	performed 	on 	the 	Ponce-
Adjuntas Project. Certification Payment No. 57F listed 20 contract
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 16 of 59
17
items 	regarding 	the 	"Work 	Performed" 	by 	Redondo. 	Of 	the 	20 	items
listed, 	18 	contract 	items 	were 	increased 	and 	two 	contract 	items
were decreased. Contract Items No. 020, Reinforcing Steel $2,741.13
and No. 102, Unclassified Excavation $772,425.49 were decreased by
a 	total 	value 	of 	$775,166.62. 	While 	the 	remaining 	increased
contract 	items 	had 	an 	aggregate 	value 	of 	$333,966.52. 	Therefore,
the 	net 	value 	of 	these 	items 	was 	($441,200.10). 	Certification
Payment 	No. 	57F 	showed 	that 	PRHTA 	further 	adjusted 	the 	final
certified 	payment 	for 	Material 	on 	Site, 	($265,540.86) 	and 	Extra
Retainage ($477,319). As previously stated, Certification Payment
No. 57F also showed that PRHTA compensated RCC $85,214.02 for fuel
increase 	in 	accordance 	with 	Special 	Provision 	Sections 	3.03 	and
7.0. 141.
10. Nonpayment of Certified Applications for Payment
PRHTA argues that Section 109.06 of the Blue Book states that
Partial payments will be made at least once each month as the work
progresses; the making of partial payments to the Contractor shall
not be construed as an acceptance on the part of the Authority of
any 	part 	of 	the 	work 	done 	or 	material 	furnished 	under 	this
contract, but only as payment on account; and that partial payments
may be suspended when in the judgment of the Engineer the work has
not 	proceeded 	according 	to 	the 	terms 	of 	the 	contract. 	It 	also
asserts that Section 109.09 of the Blue Book: that when the final
acceptance 	of 	the 	project 	has 	been 	made 	as 	provided 	in 	Article
105.16, 	the 	Engineer 	will 	prepare 	the 	final 	estimate 	of 	the 	work
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 17 of 59
18
performed; if the Contractor approves the final estimate or files
no claim or objection to the quantities therein, within 30 days of
receiving 	the 	final 	estimate, 	the 	Authority 	will 	process 	the
estimate 	for 	final 	payment; 	however, 	that 	the 	final 	payment 	will
not be made until the Contractor has filed with the Authority the
consent 	of 	the 	surety 	to 	payment 	of 	the 	final 	estimate 	and
satisfactory evidence by affidavit, or as otherwise required by the
Authority, that all his indebtedness by reason of the contract has
been 	fully 	paid 	or 	satisfactorily 	secured; 	and 	that 	upon 	final
adjudication of the claim, any additional payment determined to be
due 	the 	Contractor 	will 	be 	placed 	on 	a 	supplemental 	estimate 	and
processed for payment.
Finally, 	PRHTA 	assert 	that 	under 	section 	Section 	109.09, 	if
the Contractor has fulfilled all his obligations under the contract
but fails to approve the final estimate, the final payment will be
released 	after 	one 	year 	from 	the 	date 	of 	final 	acceptance 	of 	the
work by the Authority and such action shall operate as a release to
the Authority as if the Contractor had approved the final estimate.
It 	contends 	that 	Redondo 	had 	the 	burden 	of 	establishing 	its
full compliance with the clear and unambiguous language of Section
109.09 	of 	the 	Blue 	Book. 	If 	all 	closeout 	documents 	were 	provided
and 	submitted 	to 	the 	PRHTA, 	after 	the 	approval 	of 	the 	final
estimate by Redondo, payment was to be made for the sum found to be
due after deducting all previous partial payments and all amounts
to be retained or deducted under the provisions of the contract.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 18 of 59
19
IV. 	A. 	Stipulated 	facts 	by 	the 	parties 	as 	to 	each 	project 	and
Findings of Fact by the Court
A. Las Cumbres Avenue - El Capa
i. Stipulated facts by the parties
On May 11, 1998, Redondo entered into a $6,182,000.00 contract
with the PRHTA, for the construction of Road 199, known as "Avenida
Las Cumbres" ("Project AC-019916"). The Project AC-019916 was to be
completed in 360 days, i.e., on June 9, 1999.
As a condition to bid for the project, the contractor agreed
that 	it 	could 	not 	work 	during 	the 	first 	60 	days 	between 	stations
73+00 	to 	79+00 	because 	PRHTA 	had 	not 	acquired 	all 	the 	properties
and 	thus, 	the 	Contractor 	did 	not 	have 	full 	access 	to 	this 	area.
Sections 73+00 to 79+00 made up 34% of the project area.
Redondo started the project on June 15, 1998. By June 9, 1999,
the 	access 	problem 	had 	not 	been 	resolved 	and 	other 	acquisitions
were 	necessary 	to 	start 	working 	in 	sections 	79+00 	to 	81+20 	and
87+48 to 90+86.
There were changes in design to correct vehicular flow in the
residential area of Urbanizacion Colinas de Fairview; and changes
in site conditions in sections 83+00 to 85+00, where solid rock and
a portable water tank were encountered.
On 	December 	16, 	1999, 	RGG 	and 	PRHTA 	executed 	a 	first
settlement agreement that addressed a claim from RGG for delays on
the project. 	The 	PRHTA 	extended 	the 	date 	of 	substantial
completion 	of 	the 	original 	contract 	in 	365 	days, 	until 	May 	30,
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 19 of 59
20
2000. 	Additionally, 	PRHTA 	also 	agreed 	to 	pay 	Redondo 	$980,000.00
dollars 	for 	inefficiencies, 	inflation, 	Redondo's 	subcontractor
delays, and any other delay that may be known or unknown up to that
date.
Prior 	to 	the 	December 	16, 	1999 	agreement, 	the 	PRHTA 	had
submitted two change orders and five extra work orders and between
December 16, 1999 and September 13, 2000, the PRHTA had issued five
extra work orders and two change orders.
On June 26, 2000, Redondo submitted its second claim.
Between September 13, 2000 and September 19, 2000, the PRHTA
had issued one extra work order and one change order.
On September 19, 2000, PRHTA for the second time, extended the
date for substantial completion until October 15, 2000, except for
a tract across from the "Monte Atenas" development, which date was
extended until October 31, 2000.
According to the second extension agreement, the contract time
was 	extended 	because 	of 	the 	discovery 	of 	an 	existing 	20 	inch
potable water pipe in various locations and depths which affected
the 	construction 	of 	a 	MSE 	wall; 	and 	the 	redesign 	of 	the 	new
entrance and exit ramps to the Monte Atenas development because the
existing elevations shown on the drawings were different from the
actual 	elevation 	in 	the 	field. 	Also, 	in 	the 	second 	extension
agreement, the parties executed the following agreement: (a) that
Redondo 	would 	submit 	a 	schedule 	to 	substantially 	complete 	the
project on October 15, 2000. This completion date did not include
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 20 of 59
21
work 	in 	front 	of 	the 	Monte 	Atenas 	residential 	and 	commercial
complex; (b) that no additional time extension except for the items
specified in Article 2 of the agreement; (c) that the PRHTA could
assess liquidated damages if Redondo did not complete the Project
by 	October 	31, 	2000; 	(d) 	that 	the 	PRHTA 	agreed 	to 	pay 	Redondo
$1,500 per day for extended overhead on an interim basis until an
audit was performed at the completion of the project; (e) that by
October 15, 2000, the new substantial completion date, the public
could use the new Las Cumbres roadway; and (f) that the PRHTA would
return 	$180,000.00 	in 	liquidated 	damages 	it 	assessed 	on 	the
project.
Between 	September 	19, 	2000 	and 	April 	17,2001 	the 	PRHTA 	had
issued five extra work orders and five change orders.
On 	October 	18, 	2000, 	RGG 	submitted 	a 	further 	claim 	for 	time
extension and added costs from those discussed in its June 26, 2000
letter.
The PRHTA issued two (2) force account orders, which had added
supplements. Force Account Order No.1, contained in EWO NO.4 issued
on December 29,1998, paid RCC $50,000.00. On January 25,2001, the
PRHTA 	issued 	EWO 	No.7, 	a 	first 	supplement 	to 	EWO 	No.4, 	paid 	RCC
$75,000. 	On 	September 	20, 	2000, 	a 	second 	supplement 	to 	Force
Account 	NO.1 	was 	issued 	as 	EWO 	No. 	13, 	paid 	RCC 	$55,000. 	Force
Account Order No.2, contained in EWO No. 11, was issued on August
4,2000, paid RCC $220,000.
On 	January 	2, 	2001, 	PRHTA 	and 	RCC 	agreed 	to 	the 	92-day 	time
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 21 of 59
22
extension, which revised the completion date from October 31, 2000
to January 31, 2001 ("the third extension agreement").
Extra Work Order No. 15, issued on October 24, 2000, paid RCC
$154,061.00, 	for 	the 	difference 	in 	extended 	overhead 	costs 	after
the final audit was performed for the period from December 16, 1999
to May 30, 2000. Extra Work Order No. 16, paid RCC $229,500.00 for
extended overhead for the period May 30, 2000 to October 31,2000 at
$1,500 per day. EWO No. 17 (issued on October 24, 2000), paid RCC
$39,602 for additional work for temporary relocation of fiber optic
cables 	(PRTC) 	due 	to 	rock 	cutting. 	On 	December 	13, 	2000, 	PRHTA
issued EWO No. 18, a first supplement to Force Account Order No 2,
paid 	RCC 	$250,000 	for 	additional 	labor, 	material, 	and 	equipment
costs 	to 	complete 	added 	work. 	On 	April 	17,2001, 	PRHTA 	issued 	EWO
No. 20, a second supplement to Force Account Order No.2, paid RCC
$300,000. 	Change 	Order 	No.4 	(issued 	on 	July 	11, 	2000) 	and 	Change
Order 	No. 	7 	(issued 	on 	September 	14, 	2000), 	paid 	Redondo 	for
further unclassified excavation and rock excavation.
The 	PRHTA 	conducted 	the 	final 	inspection 	of 	the 	project 	on
July, 10, 2001. 	The PRHTA imposed Redondo liquidated damages from
January 	31, 	2001 	until 	February 	24, 	2001, 	for 	a 	total 	amount 	of
$41,432.75.
By May 31, 2001 the PRHTA had requested Redondo to perform
additional work through force account.
An independent audit report was performed on May 20, 2003 by
Rafael Perez Villarini.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 22 of 59
23
The 	PRHTA 	concluded 	the 	final 	liquidation 	of 	the 	project 	on
October 19, 2005.
ii. Findings of Fact by the Court
The 	parties 	stipulated 	the 	amount 	to 	be 	calculated 	per 	diem
for both claims; for extended main office overhead $514.00 per diem
and 	for 	extended 	job 	site 	overhead 	$2,009.00 	per 	diem 	(docket
#363).
In the first settlement agreement (Plaintiff’s Exhibit #6 Id.
1) dated December 19, 1999, the parties accorded that Redondo was
to 	paid 	the 	amount 	of 	$30,000.00 	up 	to 	the 	total 	aggregate 	of
$300,000.00 for the 10 months for extended main office overhead and
for extended job site overhead. Then, an audit would be conducted
of the real cost incurred by the contractor and the payment would
be adjusted, and the difference if any would be paid.
In the second settlement agreement (Plaintiff’s Exhibit #6 Id.
2) 	dated 	September 	13, 	2000, 	the 	agreement 	was 	that 	the 	agency
would pay the contractor $1,500.00 per day from May 30, 2000, until
the completion of the project. Then, an audit would be conducted of
the real cost incurred by the contractor for said concept, and the
payment would be adjusted and the difference if any would be paid.
In the first settlement agreement, PRHTA paid $470,606.00 for
the inefficiency claim (Exhibit 6 Id. 1).
The first draft dated September 13, 2000 (Exhibit 6 Id. 2 and
Id. 3), stated that “the contractor will submit a work schedule to
substantially complete the project on October 31, 2000, no claims
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 23 of 59
24
for inefficiency will be made for this conceded period of time.”
The 	second 	draft 	of 	the 	settlement 	agreement 	the 	previous
sentence was edited to: “the contractor will submit a work schedule
to 	substantially 	complete 	the 	project 	on 	October 	31, 	2000, 	not
including 	the 	tract 	in 	front 	of 	the 	Monte 	Atenas 	residential 	and
Commercial development according to annex 1.”
Redondo used two different methods to calculate inefficiency
The 	first 	is 	the 	Direct 	Cost 	Comparison 	(Plaintiff’s 	Exhibit 	#6,
page 12) for a total amount of $2,957,405.00 and the second method
called the Direct Comparison Production Rates (Plaintiff’s Exhibit
#6, page 14) for a total amount of $2,667,904.80.
PRHTA’s letter indicates that the substantial completion was
on February 24, 2001 (Plaintiff’s Exhibit #24).
Civitello testified that he did not review any documents that
substantiate the amount paid nor does he know that Redondo actually
paid them (TR. 3/19/2007 p. 244).
The Joint Informative Motion in Regard to Stipulated Facts and
Table 	of 	Claims 	with 	Amounts 	Requested 	and 	Recognized 	(docket
#363), PRHTA calculated 15% profit in all the claims.
B. Rio Grande de Loiza Bridge
i. Stipulated fact by the parties
On 	April 	11, 	1996 	Redondo 	entered 	into 	a 	$12,250,000.00
contract with the PRHTA for the construction of a bridge over "Rio
Grande de Loiza" and an access to the Gurabo-San Lorenzo Road. The
project was to begin on April 22, 1996 and to be completed in 720
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 24 of 59
25
calendar days, i.e., on April 12, 1998.
On 	July 	17, 	1996 	the 	PRHTA 	approved 	a 	"Value 	Engineering"
proposal 	submitted 	by 	Redondo, 	in 	which 	the 	contractor, 	at 	the
PRHTA's request, submitted an alternative to build in less time and
with an economy or lower cost to the PRHTA.
Redondo's proposal advanced the date of substantial completion
to January 12, 1998.
Redondo substantially completed the project on April 15, 1998.
The PRHTA imposed liquidated damages to Redondo in the amount
of $185,069.00, from January 12,1998, to April 15, 1998.
On June 12, 1998, Redondo submitted a claim for an extension
of time for 134 days.
On June 16, 1998, PRHTA evaluated RCC's claim and found it was
due a time extension of 93 days.
As 	a 	result 	of 	the 	93-day 	time 	extension, 	the 	Substantial
Completion 	date 	was 	revised 	from 	January 	12, 	1998 	to 	April 	15,
1998.
Redondo submitted various claims for delays, extended overhead
for 	the 	time 	extension 	of 	93 	days 	and 	the 	reimbursement 	of 	the
liquidated damages.
The Independent Accountant's Report of May 20, 2003 calculated
a total of $180,513.00 for extended overhead for 93 days.
The total additional cost of the contract was $5,376,903.40.
ii. Findings of Fact by the Court
The 	parties 	stipulated 	the 	amount 	to 	be 	calculated 	per 	diem
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 25 of 59
26
for both claims; for extended main office overhead $464.00 per diem
and 	for 	extended 	job 	site 	overhead 	$1,477.00 	per 	diem 	(docket
#363).
PRHTA 	paid 	Redondo 	$132,000.00 	for 	what 	it 	was 	labeled
extended overhead (Plaintiff’s Exhibit #54).
Scott admitted that Extra Work Order 18, was not for overhead
(TR. 11/6/2008 pp. 374-376) design.
PRHTA 	recognizes 	the 	delays 	of 	the 	projects 	and 	accepts
responsibility 	(Plaintiff’s 	Exhibit 	#48). 	On 	the 	other 	hand,
Civitello, explains in detail how Redondo arrived at the figure and
that it was using the same method used to calculate the Las Cumbres
Avenue Project (Exhibit #2).
C. Kennedy Avenue - Caparra Interchange
i. Stipulated facts by the parties
On October 31, 1997, Redondo entered into a contract with the
PRHTA for the construction of an expansion of 1.10 Kms. of PR Road-
2, known as "Kennedy Ave.", between Kennedy and De Diego Ave. The
contract 	for 	$6,375,000 	included 	improvements 	to 	Caparra
Interchange, 	Phase1 	B, 	De 	Diego 	Expressway 	and 	Kennedy 	Avenue,
highways PR-22 and PR-2 Municipality of San Juan, Puerto Rico. The
project was to be completed in 365 calendar days, I.e., on November
16,1998.
On August 25, 1998, PRHTA notified Redondo of the elimination
of all work from progressive 23+39 (line 25B) to 25+40 (line 2SB)
and from progressive 5+40 (line 2) to progressive 29+75 (line 2).
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 26 of 59
27
On May 17, 1999, the PRHTA granted an extension of time of 163
calendar 	days 	to 	the 	original 	contract, 	moving 	the 	date 	of
substantial completion to April 28, 1999.
On 	October 	25, 	1999, 	Redondo 	submitted 	to 	the 	PRHTA 	a 	claim
for delays, extended main and job office overhead and damages and
expenses.
On 	October 	28, 	1999, 	PRHTA 	determined 	the 	project 	was
substantially completed on April 28, 1999.
On 	February 	8, 	2002, 	the 	Authority 	issued 	Extra 	Work 	Order
Num.12, for the payment of $488,093.12.
On August 5, 2002, the PRHTA issued and approved certification
No. 19 for the payment of EWO 12; and certification No. 20 F, for
some pending work and materials, both totaling, $515,229.04.
The settlement documents were completed on November of 2002.
Redondo noted an objection to the PRHTA's final determination
on certification 20 F.
Pursuant to a court order, the PRHTA deposited with the Clerk
of 	the 	Court 	the 	amount 	of 	$503,203.28 	for 	certifications 	for
payment No. 19 and No. 20F.
Redondo 	has 	not 	accepted 	the 	PRHTA's 	determinations 	on 	the
final liquidation.
ii. Findings of Fact by the Court
The 	parties 	stipulated 	the 	amount 	to 	be 	calculated 	per 	diem
for both claims; for extended main office overhead $500.00 per diem
and 	for 	extended 	job 	site 	overhead 	$1,989.00 	per 	diem 	(docket
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 27 of 59
28
$363).
PRHTA gave Redondo an extension of time in the letter dated
May 17, 1999 (Exhibit 73).
The final date was moved to April 28, 1999, 527 days (Exhibit
73).
Scott’s expert report for the PRHTA, asserted that although he
could not evaluate this claim due to the lack of sufficient project
documentation, at the end of his calculation of how much PRHTA owes
Redondo, 	it 	includes 	the 	amount 	claimed 	by 	Redondo 	due 	to 	the
termination of the contract (Defendant’s Exhibit E, Scott’s Expert
Report, page 57 - 58).
D. Ponce - Adjuntas - PR-19
i. Stipulated Facts by the Parties
On 	October 	30, 	1996, 	Redondo 	entered 	into 	a 	$21,820,00.00
contract 	with 	the 	PRHTA 	which 	included 	the 	construction 	of 	3.5
kilometers 	of 	paved 	highway, 	drainage 	improvements, 	pavement
markings, 	retaining 	walls, 	and 	the 	relocation 	of 	utilities 	and
sections of PR Road 10 and PR Road 515.
The 	project 	was 	to 	be 	completed 	on 	November 	2, 	1999, 	for 	a
total of 1,080 calendar days.
In 	this 	project 	PRHTA 	retained 	a 	Geological 	Technical
Consultant, 	Dr. 	Bernard, 	who 	made 	recommendations 	for 	the
redesigned the cross sections due to the problems of the landslides
and instability of the terrain.
During 	the 	prosecution 	of 	the 	Work, 	the 	PRHTA 	approved 	15
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 28 of 59
29
Change 	Orders 	totaling 	$8,038,568.58 	and 	20 	Extra 	Work 	Orders
totaling $12,061,028.79. As a result, the original contract value
increased from $21,820,000 to $41,919,597.37.
The 	PRHTA 	granted 	a 	first 	extension 	of 	time 	of 	253 	calendar
days, extending the completion date from November 2, 1999 to July
12, 2000. This extension was granted for all delays that could be
attributed to the PRHTA for the additional unclassified excavation
work 	to 	stabilize 	the 	slopes 	in 	the 	area 	where 	substantial 	cuts
were 	made. 	Then, 	PRHTA 	granted 	a 	third 	extension 	of 	time 	of 	19
calendar 	days, 	extending 	the 	completion 	date 	from 	September 	30,
2000 	to 	October 	19, 	2000. 	This 	time 	extension 	covered 	the 	19 	day
delay 	related 	to 	the 	construction 	of 	the 	Jersey 	Barrier 	between
Stations 	1497+80 	and 	1500+40. 	This 	construction 	of 	the 	Jersey
Barrier 	was 	performed 	by 	Redondo 	in 	accordance 	with 	the 	force
account contract provisions.
Redondo 	is 	claiming 	the 	extended 	overhead 	costs 	under 	the
second 	and 	third 	time 	extensions, 	but 	not 	under 	the 	first 	time
extension since the agreed price for the activity during the first
time extension included the extended overhead expense.
Redondo 	substantially 	completed 	the 	project 	on 	October 	19,
2000.
On 	March 	14 	and 	April 	22, 	2002, 	the 	PRHTA 	approved
certifications for payment no. 55 and no. 56 for a total amount of
$179,387.60.
In Certification for Payment No. 57F, PRHTA approved a final
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 29 of 59
30
fuel price adjustment of $85,214.02.
The 	Independent 	Accountant's 	Report 	issued 	on 	May 	20, 	2003
calculated 	a 	total 	of 	$486,684.00 	for 	extended 	overhead 	for 	99
days.
Regarding 	the 	payment 	of 	municipal 	taxes 	due 	for 	the 	Ponce-
Adjuntas Project, as awarded, on May 28, 1997, Redondo paid to the
Municipality of Ponce the amount of $200,000.00. From June 12, 1997
until March 12, 1998 RCC paid to the Municipality of Ponce ten (10)
payments of $49,355.80 each, for a total of $493,558.00. The total
amount 	paid 	by 	RCC 	for 	municipal 	taxes 	for 	the 	Ponce-Adjuntas
Project, as awarded, was $693,558.00.
PRHTA 	issued 	Change 	Orders 	and 	Extra 	Work 	Orders 	that
increased 	the 	original 	contract 	estimate 	on 	the 	Ponce-Adjuntas
Project.
On February 22, 2001, regarding the payment of Municipal Taxes
(Arbitrios) due to an increase in the original contract estimate,
Redondo additionally paid to the Municipality of Ponce $124,744.91.
On 	December 	29, 	2005, 	the 	PRHTA 	deposited 	with 	the 	Clerk 	of
the Court the amount of $179,387.60 for certifications for payment
No. 55 and No. 56.
PRHTA acknowledged that RCC was entitled to $35/lm to install
12-gage guardrail material and $40/lm to install 10-gage material.
Thus, 	RCC 	would 	be 	entitled 	to 	the 	payment 	of 	$111,176.50, 	or
2,753.91m 	of 	12-gage 	material 	at 	$35/lm 	plus 	369.751m 	of 	10-gage
material at $40/lm.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 30 of 59
31
ii. Finding of Fact by the Court
In the letter dated November 28, 2001, Redondo has the right
to claim 99 days of extended overhead (Plaintiff’s Exhibit #123).
Redondo provided evidence of the insurance paid in the amount
of $106,190.00 (Plaintiff’s Exhibit 136e).
Redondo provided copy of all the checks made to the order of
Municipality 	of 	Ponce, 	for 	a 	total 	of 	19 	checks 	(Plaintiff’s
Exhibit 	#135e 	and 	135f), 	all 	with 	different 	check 	numbers 	and
dates.
The 	total 	amount 	of 	all 	the 	checks 	made 	by 	Redondo, 	made 	to
the order of Municipality of Ponce is $1,082,651.56, for the total
of the 19 checks (Plaintiff’s Exhibit 135e and 135f) and the check
made 	payable 	to 	the 	College 	of 	Engineers 	was 	for 	the 	total 	of
$21,823.00 (Plaintiffs Exhibit 135c and 135d).
Redondo and PRHTA stipulated that the amount that is owed to
Redondo is $85,214.02 (docket #363).
Redondo and PRHTA stipulated that the amount that is owed to
Redondo is $111,176.50 (docket #363).
E. Third Millennium Park
i. Stipulated facts by the Parties
On 	November 	17, 	1998, 	Redondo 	entered 	into 	a 	$21,696,000.00
contract 	with 	the 	PRHTA 	for 	the 	construction 	of 	a 	park 	along 	the
"Escambron" 	beach 	in 	San 	Juan, 	Puerto 	Rico; 	which 	included 	the
installation 	of 	retaining 	walls, 	pedestrian 	walkways, 	sidewalks,
and 	lifeguard 	towers, 	the 	demolition 	of 	existing 	structures,
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 31 of 59
32
electrical 	and 	mechanical 	work, 	landscaping, 	interior 	fit-out 	of
the restaurant and administration office, and other miscellaneous
work.
The 	project 	started 	on 	December 	7, 	1998, 	and 	the 	original
completion 	date 	was 	December 	2, 	1999, 	for 	a 	contract 	time 	of 	360
calendar days.
On 	August 	27, 	1999, 	PRHTA 	and 	Redondo 	executed 	a 	settlement
agreement that extended the contract time from December 2, 1999, to
December 	17, 	1999, 	15 	calendar 	days. 	Article 	number 	5 	of 	the
Settlement agreement stated: "The contractor will not work in the
project 	from 	December 	18, 	1999, 	up 	to 	and 	including 	January 	10,
2000." 	Article 	3 	of 	the 	Settlement 	Agreement 	of 	August 	27, 	1999
stated that PRHTA could assess liquidated damages in the amount of
$600 per day if Redondo did not complete the project by March 10,
2000.
Article 	8 	of 	the 	Settlement 	Agreement 	of 	August 	27, 	1999,
stated that PRHTA could assess contractual penalties in the amount
of $4,000 per day if RCC did not achieve substantial completion by
December 17, 1999.
During the project, five Change Orders ("C.O.") and seventeen
Extra Work Orders ("E.W.O.") were issued.
Extra Work Orders no. 9 through no. 16 issued after April 3,
2000 	paid 	RCC 	$2,041,007 	for 	the 	additional 	work 	requested 	by
PRHTA.
PRHTA determined that Redondo achieved substantial completion
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 32 of 59
33
on December 31, 1999.
The PRHTA applied Redondo liquidated damages in the amount of
$142,800.00, for the period between March 11, 2000 and November 3,
2000.
EWO no. 16 was approved on July 16, 2001.
On 	October 	10, 	2000 	Redondo 	claimed 	extended 	overhead 	from
March 10, 2000 to November 8, 2000, a total of 243 calendar days.
After 	a 	final 	inspection, 	the 	PRHTA 	determined 	that 	the
project completion date was November 3, 2000.
ii. Findings of Fact by the Court
The 	parties 	stipulated 	the 	amount 	to 	be 	calculated 	per 	diem
for both claims; for extended main office overhead $561.00 per diem
and 	for 	extended 	job 	site 	overhead 	$1,857.00 	per 	diem 	(docket
#363).
On the other hand, both Redondo’s expert witness and PRHTA’s
expert witness (Plaintiff’s Exhibit 2 and Defendant’s Exhibit E),
concluded 	that 	Redondo 	is 	entitled 	to 	607 	days 	for 	extended 	main
office overhead and for extended job site overhead.
On the other hand, in Plaintiff’s Exhibit 218, the settlement
agreement states that the $750,00.00 would be paid for the concept
of acceleration of work.
As per Plaintiff’s Exhibit #227 in the contract final report
PRHTA retained $162,500.00.
The evidence of the municipal taxes paid was for the amount of
$37,811.00 (Plaintiff’s Exhibit 228).
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 33 of 59
34
A check made payable to the College of Engineers was for the
total of $21,703.00 (Plaintiffs Exhibit 228).
V. 	DISCUSSION
A. Applicable Law
“Property 	and 	contract 	rights 	implicated 	in 	bankruptcy
disputes are determined in accordance with state law.” 	In re Ward,
194 B.R. 703, 711, fn 21 	(Bankr. D.Mass. 1996) (citing Butner v.
United States, 440 U.S. 48 (1979) and Ralar Distribution, Inc. v.
Rubbermaid, 	Inc. 	(In 	re 	Ralar 	Distrib., 	Inc.), 	4 	F.3d 	62, 	67-68
(1st 	Cir. 	1993)). 	Thus, 	the 	Laws 	of 	the 	Commonwealth 	of 	Puerto
Rico 	(“Civil 	Code 	of 	1930”) 	govern 	the 	breach 	of 	contract 	and
damages claims in the present case.
1. 	Contracts with the Government of Puerto Rico
In 	Fernandez & Gutierrez v. Mucicipio de San Juan, the Puerto
Rico Supreme Court indicated that when a contract involves the use
of 	public 	funds 	or 	goods, 	the 	rigorous 	application 	of 	all 	norms
regarding contracting and disbursement of those funds is essential,
in 	order 	to 	protect 	the 	public 	interest 	and 	funds. 	Fernandez 	&
Gutierrez v. Mucicipio de San Juan, 99 PRSC 26, 147 P.R. Dec. 824,
829 (1999).
The 	Puerto 	Rico 	Legislature 	in 	Art. 	1 	of 	Law 	Num. 	18 	of
October 30, 1975, supplies the basic limitation in appropriations
and contracting, reading as follows:
The departments, agencies, instrumentalities,
offices 	and 	all 	other 	bodies, 	and 	the
municipality 	of 	the 	Commonwealth 	of 	Puerto
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 34 of 59
35
Rico, with no exception whatsoever; shall keep
a 	registry 	of 	all 	contracts 	executed,
including amendments thereto, and shall remit
a 	copy 	thereto 	to 	the 	Office 	of 	the
Comptroller within fifteen (15) days following
the date of the execution or the amendment of
the contract.
P.R. Laws Ann. tit. 2, § 97 (2004). This presupposes that when
a government agency or municipality is a party to a contract or an
amendment 	thereto, 	the 	contract 	or 	amendment 	must 	be 	reduced 	to
writing, executed by both parties, and registered with the Office
of the Comptroller. 	Las Marias v. Municipio de San Juan, 2003 PRSC
121, 4. The Supreme Court of Puerto Rico alluded to the efficacy of
said statute in Fernandez & Gutierrez v. Municipio de San Juan, and
added 	that 	it 	“reflects 	the 	legislative 	intent 	of 	creating 	a
mechanism 	of 	checks 	and 	publicity 	of 	contracts 	executed 	by 	the
municipalities, 	which 	is 	of 	constitutive 	nature 	with 	respect 	to
efficacy.” 	Fernandez & Gutierrez v. Municipio de San Juan, 99 PRSC
26, 147 P.R. Dec. 824, 830 (1999).
On the other hand, it is well established in Puerto Rico that
the 	contracts 	between 	the 	government 	or 	its 	municipalities 	and 	a
private 	party, 	are 	subject 	to 	the 	same 	regulations 	and 	set 	of
doctrines 	as 	if 	the 	contract 	were 	between 	private 	parties.
Municipio de Mayaguez v. Lebron, 2006 PRSC 70, 2. See also, Campos
Ledesma v. Cia. Fom. Ind., 2001 PRSC 1.
2. 	Contracts in general
Contracts 	in 	Puerto 	Rico 	are 	governed 	by 	the 	Puerto 	Rico
Civil 	Code 	of 	1930. 	The 	Civil 	Code 	in 	article 	1044 	states 	that:
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 35 of 59
36
“[t]hose 	obligations 	arising 	from 	contracts 	have 	legal 	force
between 	the 	contracting 	parties, 	and 	must 	be 	fulfilled 	in
accordance 	with 	their 	stipulations.” 	Lopez 	Torres 	v. 	Gonzalez
Vazquez, 2004 PRSC 172, 2. See also P.R. Laws Ann. tit. 31, § 2994
(1990).
In 	Puerto 	Rico, 	the 	law 	recognizes 	that 	the 	contracting
parties 	may 	make 	any 	agreement 	and 	“establish 	the 	clauses 	and
conditions, which they may deem advisable, provided that they are
not in contravention of the law, morals, or public order.” 	Lopez
Torres 	v. 	Gonzalez 	Vazquez, 	2004 	PRSC 	172, 	2. 	See 	P.R. 	Laws 	Ann.
tit. 31, § 3372 (1990). Contracts are perfected by the mere consent
of the parties, and from that time they are binding, not only with
regard 	to 	the 	fulfillment 	of 	what 	has 	been 	expressly 	stipulated,
but 	also 	with 	regard 	to 	all 	the 	consequences 	which 	are 	in
accordance with good faith, use and law. 	Lopez Torres v. Gonzalez
Vazquez, 2004 PRSC 172, 2. See also P.R. Laws Ann. tit. 31, § 3375
(1990).
3. 	Interpretation of Contracts in Puerto Rico
The 	Puerto 	Rico 	Civil 	Code 	of 	1930, 	Articles 	1233 	through
1250, 	regulates 	contract 	interpretation. 	See 	P.R. 	Laws 	Ann. 	tit.
31, § 3471 through 3479 (1990). In Municipio de Mayaguez v. Lebron,
the Puerto Rico Supreme Court stated that the target in contractual
interpretation 	is 	to 	determine 	what 	are 	the 	real 	and 	common
intentions 	of 	the 	contracting 	parties. 	Municipio 	de 	Mayaguez 	v.
Lebron, 2006 PRSC 70, 4.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 36 of 59
37
In Marcial v. Tome, 144 P.R. Dec. 522 (1997), the leading case
in 	contracts 	interpretation, 	cited 	throughout 	the 	opinion 	of
Municipio de Mayaguez, 2006 PRSC 70, the Puerto Rico Supreme Court
held that:
[a]lthough 	the 	starting 	point 	of 	contract
interpretation 	must 	be 	the 	expressions
contained in the words, the trier cannot stop
at 	the 	literal 	sense, 	but 	must 	fundamentally
investigate the intent of the parties and the
spirit and purpose of the transaction, as they
are 	inferred 	from 	the 	overall 	conduct 	of 	the
interested 	parties 	and 	from 	the 	concurring
circumstances 	that 	may 	contribute 	to 	an
adequate 	investigation 	of 	the 	will 	of 	the
executing parties. Coop. La Sagrada Familia v.
Castillo, 	107 	D.P.R. 	405, 	417 	[7 	P.R. 	Offic.
Trans. 	449, 	461] 	(1978). 	See: 	Marina 	Ind.,
Inc. v. Brown Boveri Corp., 114 D.P.R. 64, 69-
70 	[14 	P.R. 	Offic. 	Trans. 	86, 	94-95] 	(1983);
Merle 	v. 	West 	Bend 	Co., 	97 	D.R.R. 	392, 	399
(1969).
Marcial v. Tome, 144 P.R. Dec. at 537. “To judge the intention of
the contracting parties, all circumstances showing the will of the
parties must be examined.” Id. at 538. See also P.R. Laws Ann. tit.
31, § 3472 (1990). Specifically, special attention must be paid to
“their acts, previous to, contemporaneous with, and subsequent to
the execution of the contract.” Marcial v. Tome, 144 P.R. Dec. at
538. 	The 	Court 	also 	held 	that 	a 	Court 	should 	consider 	“the
occasion, 	the 	circumstances, 	the 	persons 	involved, 	and 	the
agreement they intended to negotiate.” Id.
A. Project Ave. Las Cumbres - Contract AC 019916
In 	the 	present 	case 	seven 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	extended 	main 	office 	overhead 	and 	extended 	job 	site
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 37 of 59
38
overhead, 2. inefficiency, 3. liquidated damages, 4. Insurance and
Bonds Premiums, 5. Profit (15%), 6. Unpaid application for payment
No. 35F and 7. Interest at 6%.
1. 	Extended 	main 	office 	overhead 	and 	extended 	job 	site
overhead
Redondo 	is 	claiming 	$375,734.00 	for 	extended 	main 	office
overhead 	and 	$1,468,579.00 	for 	extended 	job 	site 	overhead, 	for 	a
total of $1,844,313.00 for 731 days. PRHTA is accepting $79,156.00
for extended main office overhead and $309,386.00 extended job site
overhead, 	for 	a 	total 	of 	$388,542.00 	for 	154 	days. 	The 	parties
stipulated 	the 	amount 	to 	be 	calculated 	per 	diem 	for 	both 	claims;
for extended main office overhead $514.00 per diem and for extended
job 	site 	overhead 	$2,009.00 	per 	diem. 	The 	only 	difference 	is 	the
amount of days calculated by Redondo and by PRHTA.
PRHTA 	asserts 	that 	it 	only 	owes 	154 	additional 	days 	for
extended main office overhead and for extended job site overhead.
It 	contends 	that 	it 	paid 	for 	extended 	overhead 	in 	various 	checks
and 	what 	was 	pending 	was 	the 	additional 	days 	that 	corresponds 	to
the period of May 30, 2000 to October 31, 2000. On the other hand,
Redondo calculated 731 additional days, that corresponds from the
first 	extension 	of 	time 	given 	by 	PRHTA 	to 	the 	conclusion 	of 	the
project, from June 9, 1999 to May 31, 2001.
The project was started on June 15, 1998, it was suppose to be
finished 	on 	June 	9, 	1999, 	360 	days. 	In 	the 	first 	settlement
agreement the final date was moved to May 30, 2000. In the second
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 38 of 59
39
agreement the parties agreed that the final date was May 31, 2001.
In the first settlement agreement (Plaintiff’s Exhibit #6 Id.
1) dated December 19, 1999, the parties accorded that Redondo was
to 	paid 	the 	amount 	of 	$30,000.00 	up 	to 	the 	total 	aggregate 	of
$300,000.00 for the 10 months for extended main office overhead and
for extended job site overhead. Then, an audit would be conducted
of the real cost incurred by the contractor and the payment would
be adjusted, and the difference if any would be paid.
In the second settlement agreement (Plaintiff’s Exhibit #6 Id.
2) 	dated 	September 	13, 	2000, 	the 	agreement 	was 	that 	the 	agency
would pay the contractor $1,500.00 per day from May 30, 2000, until
the completion of the project. Then, an audit would be conducted of
the real cost incurred by the contractor for said concept, and the
payment would be adjusted and the difference if any would be paid.
In 	the 	present 	case, 	PRTHA 	asserts 	that 	it 	paid 	$229,000.00
for the extended overhead, on the other hand, Redondo asserts that
PRTHA 	paid 	$683,561.00 	for 	the 	extended 	overhead. 	Redondo
calculated 	731 	days, 	that 	was 	from 	the 	first 	extension 	of 	time
until the conclusion of the project. The audit was never conducted
as 	prescribed 	in 	the 	two 	settlement 	agreements. 	The 	parties
stipulated 	(Docket 	# 	363) 	that 	for 	the 	extended 	main 	office
overhead 	Redondo 	would 	be 	pay 	$514 	per 	day, 	and 	for 	the 	extended
job site overhead $2,009.00 per day.
The 	Court 	concludes 	that 	Redondo 	is 	entitled 	as 	per 	the 	two
settlement agreements to the extended main office overhead and the
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 39 of 59
40
extended job site overhead, from the first extension of time given
which 	was 	from 	June 	9, 	1999 	to 	May 	31, 	2001, 	for 	a 	total 	of 	731
days, 	minus 	the 	overhead 	already 	paid 	by 	PRHTA, 	which 	was
$683,561.00.
Extended Main Office Overhead 	$514 	x 731 = 	$375,734.00
Extended Job Site Overhead 	$2,009 	x 731 = 	$1,468,579.00
Paid to Redondo 	-$683,561.00
Total that PRHTA owes to Redondo 	$1,160,752.00
2. Inefficiency
PRHTA 	contends 	that 	in 	order 	for 	Redondo 	to 	be 	entitled 	to
inefficiency Redondo had to prove: 1. PRHTA breached the contract
or was directly responsible to Redondo for the alleged disruption
(liability), 	2. 	that 	the 	disruptions 	were 	the 	proximate 	cause 	of
the 	loss 	of 	productivity 	or 	inefficiency 	and 	that 	3. 	Redondo
suffered a quantifiable increase in its actual cost for the project
(damages) which was not compensated by PR in the change orders or
the Extra Work Orders issued. Redondo avers that he used the total
cost method to calculate inefficiency for this project because of
the extreme circumstances, which extended 300% the original time of
the 	project. 	He 	avers 	that 	this 	was 	the 	only 	method 	that 	could
really determine the damage to the company. Redondo avers that in
Tab 	9 	of 	Exhibit 	6, 	there 	is 	a 	drawing 	that 	explains 	the 	damages
produced 	on 	the 	project; 	it 	is 	a 	drawing 	of 	the 	whole 	highway,
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 40 of 59
41
showing 	the 	areas 	supposed 	to 	be 	available 	to 	be 	worked 	and 	the
areas that could not be worked, either because the right of way was
not 	acquired 	or 	because 	there 	were 	different 	situations 	that
prevented Redondo from working.
In the first settlement agreement, PRHTA paid $470,606.00 for
the 	inefficiency 	claim 	(Exhibit 	6 	Id. 	1). 	Then, 	Redondo 	offered
into 	evidence 	two 	drafts 	of 	the 	second 	settlement 	agreement. 	The
first draft dated September 13, 2000 (Exhibit 6 Id. 2 and Id. 3),
stated 	that 	“the 	contractor 	will 	submit 	a 	work 	schedule 	to
substantially complete the project on October 31, 2000, no claims
for inefficiency will be made for this conceded period of time.” On
the other hand, in the second draft of the settlement agreement the
previous sentence was edited to: “the contractor will submit a work
schedule to substantially complete the project on October 31, 2000,
not 	including 	the 	tract 	in 	front 	of 	the 	Monte 	Atenas 	residential
and Commercial development according to annex 1.”
The documentary evidence provided by Redondo demonstrates that
the 	inefficiency 	claim 	was 	from 	the 	beginning 	of 	the 	project, 	a
claims that was to be included and contemplated, all throughout the
project. In the first settlement agreement, PRHTA paid $470,606.00
for 	inefficiency 	and 	in 	the 	second, 	PRHTA 	did 	not 	include 	the
inefficiency 	because 	later 	Redondo 	could 	claim 	it. 	PRHTA 	can 	not
argue against its own acts, it paid inefficiency that was clearly
contemplated from the beginning.
Redondo used two different methods to calculate inefficiency
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 41 of 59
42
The 	first 	is 	the 	Direct 	Cost 	Comparison 	(Plaintiff’s 	Exhibit 	#6,
page 12) for a total amount of $2,957,405.00 and the second method
called the Direct Comparison Production Rates (Plaintiff’s Exhibit
#6, page 14) for a total amount of $2,667,904.80.
In the joint stipulated facts Redondo chose the first method.
The 	Court 	concludes 	that 	Redondo 	is 	entitled 	to 	the 	inefficiency
claim. 	The 	Court 	will 	concede 	the 	second 	amount 	the 	Direct
Comparison Production Rates (Plaintiff’s Exhibit #6, page 14) for
a total amount of $2,667,904.80.
3. Liquidated damages
PRHTA fixed the completion date of the project for January 31,
2001 and if the project was not completed by such date, then PRHTA
could retain liquidated damges. PRHTA determined that the project
was substantially completed on February 24, 2001. Redondo did not
demonstrate that it completed the project on January 31, 2001. On
the contrary, Redondo failed to achieve substantial completion by
January 	31, 	2001 	and 	was 	not 	granted 	an 	extension 	of 	time. 	PRTHA
retained $41,432.75 for the 23 days. PRHTA’s letter indicates that
the 	substantial 	completion 	was 	on 	February 	24, 	2001 	(Plaintiff’s
Exhibit #24). Thus, the Court concludes that PRHTA does not have to
refund any amount to Redondo for the concept of liquidated damages.
4. Insurance and Bonds Premiums
Redondo 	is 	claiming 	$126,736.06. 	Redondo 	did 	not 	present
evidence 	that 	demonstrates 	what 	amount 	it 	paid 	for 	insurance 	and
bonds. Furthermore, Civitello testified that he did not review any
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 42 of 59
43
documents that substantiate the amount paid nor does he know that
Redondo actually paid them (TR. 3/19/2007 p. 244). Thus, the Court
will not award an amount.
5. Profit (15%)
Redondo 	avers 	that 	it 	is 	entitled 	to 	15% 	because 	it 	is
reasonable and because it has been part of all the contracts that
it 	signed 	with 	PRHTA. 	Civitello 	agrees 	with 	Redondo, 	that 	15% 	is
reasonable within the construction industry. PRHTA argued that in
the Blue Book different percents apply to the different claims and
Scott asserted that for the claims presented by Redondo, no profit
should be applied, only for the cost of additional contract work,
which was not the case.
On the other hand, in the Joint Informative Motion in Regard
to Stipulated Facts and Table of Claims with Amounts Requested and
Recognized 	(docket 	#363), 	PRHTA 	calculated 	15% 	profit 	in 	all 	the
claims, therefore stipulating that a 15% profit could be granted to
Redondo.
The Court concludes that Redondo and PRHTA stipulated in the
Joint Informative Motion in Regard to Stipulated Facts and Table of
Claims 	with 	Amounts 	Requested 	and 	Recognized 	(docket 	#363), 	that
15% of profit could be granted to Redondo.
6. Unpaid Application for Payment no. 35F
Redondo 	had 	the 	burden 	of 	establishing 	its 	full 	compliance
with 	the 	clear 	and 	unambiguous 	language 	of 	Section 	109.09 	of 	the
Blue Book. If all closeout documents were provided and submitted to
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 43 of 59
44
the 	PRHTA, 	after 	the 	approval 	of 	the 	final 	estimate 	by 	Redondo,
payment was to be made for the sum found to be due after deducting
all 	previous 	partial 	payments 	and 	all 	amounts 	to 	be 	retained 	or
deducted under the provisions of the contract.
PRHTA 	does 	not 	discuss 	why 	it 	does 	not 	owe 	this 	amount 	to
Redondo, 	when 	all 	the 	project 	were 	completed 	years 	ago. 	Redondo
asserts that PRHTA retained the payment of approved certifications
for 	payments, 	with 	the 	excuse 	that 	Redondo 	has 	not 	submitted
information 	required 	to 	process 	the 	final 	liquidations. 	Redondo
contend that, it has taken the Authority all these years to process
the 	final 	liquidations, 	in 	violation 	of 	the 	Blue 	Book; 	secondly,
that the Authority was the one that placed Redondo in the financial
position 	of 	not 	being 	able 	to 	pay 	its 	creditors, 	by 	delaying 	its
claims; and thirdly, Redondo presented evidence that it submitted
all the information required to process the final liquidations for
each project (Ex. 35, 66, 98, 135a-e & 229), with the exception of
the release from the sureties regarding the performance bonds, and
the evidence of payments to the subcontractors because Redondo was
not 	able 	to 	pay 	its 	creditors 	due 	to 	its 	bankruptcy, 	which 	was
precisely due to the Authority’s delays and lack of payment (Stmnt.
Fct. 82 & Redondo 3 rd 176-177 & 4 th 62-63).
The 	Court 	concludes 	that 	Redondo 	is 	entitled 	to 	collect 	the
certifications 	that 	were 	not 	paid 	by 	the 	PRHTA 	because 	all 	the
projects were completed years ago.
7. Interest
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 44 of 59
45
Rule 44.3 of the Rules of Civil Procedure of Puerto Rico, 32
L.P.R.A. 	Ap. 	III 	R. 	44.3, 	states 	that 	when 	the 	defendant 	is 	the
Commonwealth 	of 	Puerto 	Rico, 	agencies, 	instrumentalities 	or
officers 	acting 	in 	their 	official 	capacity, 	the 	court 	will 	also
impose on the party that has acted rashly the payment of interest
at 	the 	rate 	fixed 	by 	the 	Finance 	Board 	of 	the 	Office 	of 	the
Commissioner 	of 	Financial 	Institutions 	which 	is 	in 	effect 	at 	the
moment 	the 	judgment 	is 	pronounced, 	from 	the 	time 	the 	cause 	of
action 	arises 	in 	every 	case 	of 	collection 	of 	money 	and 	from 	the
time 	the 	claim 	is 	filed 	in 	actions 	for 	damages 	until 	the 	date
judgment is pronounced. The current legal interest is 6%. The Court
concludes that Redondo is entitled to 6% interest.
Summary
1. Extended Main Office/ Job Site Overhead 	$1,160,752.00
2. Inefficiency 	$2,667,904.80
3. Liquidated Damages 	$ 	0.00
4. Insurance and Bonds Premiums 	$ 	0.00
5. Profit 	$ 	574,298.52
6. Unpaid Application for Payment No. 35F 	$ 	103,872.97
TOTAL 	$4,506,828.29
7. Plus Legal Interest 6%.
B. Contract AC 020303· Rio Grande de Loiza Bridge
In 	the 	present 	case 	six 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	Extended 	main 	office 	overhead 	and 	Extended 	job 	site
overhead, 	2. 	Inefficiency, 	3. 	Insurance 	and 	Bonds 	Premiums, 	4.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 45 of 59
46
Profit, 5. Unpaid Application for Payment No. 15F and 6. Interest.
1. Extended main office overhead and 1a. extended job site overhead
Redondo 	is 	claiming 	$43,152.00 	for 	extended 	main 	office
overhead 	and 	$137,361.00 	for 	extended 	job 	site 	overhead, 	for 	a
total 	of 	$180,513.00. 	PRHTA 	is 	accepting 	$48,513.00 	for 	both 	the
extended main office overhead and the extended job site overhead.
The 	parties 	stipulated 	the 	amount 	to 	be 	calculated 	per 	diem 	for
both claims; for extended main office overhead $464.00 per diem and
for 	extended 	job 	site 	overhead 	$1,477.00 	per 	diem. 	The 	only
difference is that PRHTA asserts that it paid Redondo $132,000.00
for the extended overhead and Redondo does not concede that PRHTA
paid that amount. The amount of days to be calculated is 93, same
days calculated by Redondo and PRHTA.
In 	the 	present 	case, 	PRHTA 	argues 	that 	according 	to
Plaintiff’s 	Exhibit 	#54, 	it 	paid 	Redondo 	$132,000.00 	for 	the
extended 	overhead. 	On 	the 	other 	hand, 	Scott 	admitted 	that 	Extra
Work Order 18 was not for overhead (TR. 11/6/2008 pp. 374-376). The
Court concludes that Redondo is entitled to extended overhead for
93 days and that the $132,000.00 of the Extra Work Order 18 was not
related to overhead.
Extended Main Office Overhead 	$464 	x 	93 = 	$ 	43,152.00
Extended Job Site Overhead 	$1,477 	x 	93 = 	$ 137,361.00
Total that PRHTA owes to Redondo 	$ 180,513.00
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 46 of 59
47
2. Inefficiency
Scott asserts that Redondo provided a basis for calculation of
its 	inefficiency 	costs. 	It 	states 	that 	the 	table 	was 	apparently
comparing 	budgeted 	versus 	actual 	material, 	equipment, 	and 	labor
production rates and that the approach was the same used by Redondo
for the Las Cumbres Avenue Project. Redondo did provide evidence as
to the delays attributable to PRHTA. PRHTA recognizes the delays of
the projects and accepts responsibility (Plaintiff’s Exhibit #48).
On 	the 	other 	hand, 	Redondo 	Civitello, 	explains 	in 	detail 	how
Redondo arrived at the figure and that it was using the same method
used to calculate the Las Cumbres Avenue Project. The Court gives
credibility to Redondo regarding this project because of the delays
caused by PRHTA.
The Court concludes that Redondo is entitled to inefficiency
claim 	using 	second 	amount 	Direct 	Comparison 	Production 	Rates
(plaintiff’s 	Exhibit 	#6, 	page 	14) 	for 	a 	total 	amount 	of
$900,401.19.
3. Insurance and Bonds Premiums
Redondo 	is 	claiming 	$146,042.69. 	Redondo 	did 	not 	present
evidence 	that 	demonstrates 	what 	amount 	it 	paid 	for 	insurance 	and
bonds. Thus, the Court will not award an amount.
4. Profit (15%)
Same as the section entitled: Profit, supra, discussed in the
Las Cumbres Avenue Project.
5. Unpaid Application for Payment no. 35F
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 47 of 59
48
Same as the section entitled: Unpaid Application for Payment,
supra, discussed in the Las Cumbres Avenue Project.
6. Interest
Same 	as 	the 	section 	entitled: 	Interest, 	supra, 	discussed 	in
the Las Cumbres Avenue Project.
Summary
1. Extended Main Office/ Job Site Overhead 	$ 	180,513.00
2. Inefficiency 	$ 	900,401.19
3. Insurance and Bonds Premiums 	$ 	0.00
4. Profit 	$ 	162,137.12
5. Unpaid Application for Payment No. 35F 	$ 	15,423.82
TOTAL 	$1,258,475.13
6. Plus Legal Interest 6%.
C. Contract AC 220095 • Kennedy Ave.
In 	the 	present 	case 	five 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	Extended 	main 	office 	overhead 	and 	Extended 	job 	site
overhead, 	2. 	Termination 	of 	contract, 	3. 	Profit, 	4. 	Interest 	5.
Interest for Application for Payment No. 19 and 20F.
1. 	Extended 	main 	office 	overhead 	and 	extended 	job 	site
overhead
Redondo 	is 	claiming 	$81,500.00 	for 	extended 	main 	office
overhead 	and 	$324,207.00 	for 	extended 	job 	site 	overhead, 	for 	a
total 	of 	$405,707.00. 	PRHTA 	is 	accepting 	$21,500.00 	for 	extended
main office overhead and $85,527.00 extended job site overhead, for
a 	total 	of 	$107,027.00. 	The 	parties 	stipulated 	the 	amount 	to 	be
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 48 of 59
49
calculated 	per 	diem 	for 	both 	claims; 	for 	extended 	main 	office
overhead 	$500.00 	per 	diem 	and 	for 	extended 	job 	site 	overhead
$1,989.00 	per 	diem. 	The 	only 	difference 	is 	the 	amount 	of 	days
calculated by Redondo and by PRHTA. PRHTA asserts that it only owes
43 	additional 	days 	for 	extended 	main 	office 	overhead 	and 	for
extended 	job 	site 	overhead, 	but 	it 	fails 	to 	explain 	why 	it 	only
conceded 	43 	days. 	It 	contends 	that 	it 	did 	not 	grant 	Redondo 	an
extension of time to finish the project. On the other hand, Redondo
calculated 163 additional days, because he contend that PRHTA did
grant him the extension of time.
On 	the 	other 	hand, 	Redondo 	explained 	that 	the 	project 	was
started 	on 	November 	17, 	1997, 	it 	was 	supposed 	to 	be 	finished 	on
November 	16, 	1998, 	for 	a 	total 	of 	364 	days. 	Then, 	PRHTA 	did 	give
Redondo 	an 	extension 	of 	time 	in 	the 	letter 	dated 	May 	17, 	1999
(Exhibit 73). The final date was moved to April 28, 1999, 527 days
(Exhibit 	73). 	Thus, 	527 	days 	minus 	(-) 	364 	days, 	for 	a 	total 	of
additional days of 163.
The Court concludes that Redondo is entitled as per the letter
dated 	May 	17, 	1999 	(Exhibit 	73) 	to 	the 	extended 	main 	office
overhead and the extended job site overhead for 163 days.
Extended Main Office Overhead 	$500 	x 163 = 	$ 81,500.00
Extended Job Site Overhead 	$1,989 	x 163 = 	$ 324,207.00
Total that PRHTA owes to Redondo 	$ 405,707.00
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 49 of 59
50
2. Termination of Contract
PRHTA contends that it did not terminate the contract of the
Kennedy 	Avenue, 	it 	only 	eliminated 	some 	of 	the 	contract 	work. 	It
asserts that this course of action 	was in their best interest and
that 	according 	to 	the 	Blue 	Book 	they 	can 	eliminate 	work 	without
meaning that the contract was terminated. The Blue Book also states
in section 109.5 d. that no allowance will be made for claims for
loss 	of 	anticipated 	profit 	or 	loss 	of 	expected 	reimbursement 	for
the elimination of any item. On the other hand, Scott asserted that
although 	he 	could 	not 	evaluate 	this 	claim 	due 	to 	the 	lack 	of
sufficient project documentation, at the end of his calculation of
the 	amount 	owed 	by 	PRHTA 	to 	Redondo, 	he 	did 	include 	the 	amount
claimed 	by 	Redondo 	due 	to 	the 	termination 	of 	the 	contract
(Defendant’s 	Exhibit 	E, 	Scott’s 	Expert 	Report, 	page 	57 	- 	58).
Redondo 	avers 	that 	PRHTA 	unilaterally 	terminated 	part 	of 	the
contract 	and 	that 	he 	is 	entitled 	to 	compensation 	for 	the
termination of the contract. Section 108.11 allows the contractor
to claim for its damages and costs related to the termination of a
contract or to a portion thereof.
The Court concludes that Redondo is entitled to compensation
for the termination of the contract in the amount of $164,627.62.
3. Profit (15%)
Same as the section entitled: Profit, supra, discussed in the
Las Cumbres Avenue Project.
4. Interest
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 50 of 59
51
Same 	as 	the 	section 	entitled: 	Interest, 	supra, 	discussed 	in
the Las Cumbres Avenue Project.
5. Interest for Application for Payment No. 19 and 20F
Application for Payment No. 19 and 20F were consigned in Court
after the debtor filed for bankruptcy, well after the project was
finished; 	thus, 	Redondo 	is 	entitled 	to 	collect 	interest 	from 	the
time 	the 	amounts 	were 	due, 	up 	to 	the 	date 	when 	it 	collected 	the
amounts 	due. 	Thus, 	Redondo 	is 	entitled 	to 	the 	amount 	of
$217,079.49.
Summary
1. Extended Main Office/ Job Site Overhead 	$ 405,707.00
2. Termination of Contract 	$ 164,627.62
3. Profit 	$ 	85,550.19
TOTAL 	$ 655,550.19
4. Plus Legal Interest 6%
5. Interest on Application for Payment No. 35F 	$ 217,079.49
D. Contract AC-100029- Road PR-10·Ponce·Adjuntas
In 	the 	present 	case 	nine 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	Extended 	main 	office 	overhead 	and 	Extended 	job 	site
overhead, 	2. 	Insurance 	and 	Bonds 	Premiums, 	3. 	Patent 	and 	Excise
Taxes, 4. Fuel Increase, 5. Guard Rail, 6. Profit, 7. Interest, 8.
Interest 	on 	Application 	for 	Payment 	No. 	55 	and 	No.56 	and
Certification 57F.
1. 	Extended 	main 	office 	overhead 	and 	extended 	job 	site
overhead
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 51 of 59
52
Redondo 	is 	claiming 	$121,671.00 	for 	extended 	main 	office
overhead 	and 	$365,013.00 	for 	extended 	job 	site 	overhead, 	for 	a
total 	of 	$486,684.00. 	PRHTA 	is 	contending 	that 	it 	does 	not 	owe
Redondo any amount, but instead it overpaid Redondo the amount of
$1,695,126.00 for both, the extended main office overhead and the
extended job site overhead.
In the Plaintiff’s Exhibit 129(a), Redondo and PRHTA accorded
that 	they 	would 	pay 	$1.00 	of 	the 	$8.20 	unit 	price 	of 	the
excavation, 	to 	cover 	the 	extended 	overhead 	for 	the 	extension 	of
time 	of 	253 	days 	granted. 	In 	the 	letter 	dated 	November 	28, 	2001,
Redondo was granted the right to claim 99 days of extended overhead
(Plaintiff’s 	Exhibit 	#123). 	PRHTA 	did 	not 	prove 	that 	Redondo 	was
overpaid. 	Redondo 	was 	paid 	for 	the 	extended 	overhead 	of 	253 	days
with 	the 	extra 	$1.00 	for 	excavation 	for 	a 	total 	of 	$1,243,748,
but, Redondo was still owed the extension of time of 99 days.
The 	Court 	concludes 	that 	Redondo 	is 	entitled 	as 	per 	the 	two
settlement agreements to the extended main office overhead and the
extended job site overhead, for the second extension of time given,
for the 99 days extension.
Extended Main Office Overhead 	$1,229 	x 99 = 	$ 121,671.00
Extended Job Site Overhead 	$3,687 	x 	99 = 	$ 365,013.00
Total that PRHTA owes to Redondo 	$ 486,684.00
2. Insurance and Bonds Premiums
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 52 of 59
53
Redondo provided evidence of the insurance paid (Plaintiff’s
Exhibit 136e). On the other hand, PRHTA did not present evidence as
to 	what 	payments 	if 	any, 	it 	refunded 	to 	Redondo. 	The 	evidence 	of
the 	insurance 	paid 	was 	the 	amount 	of 	$106,190.00 	(Plaintiff’s
Exhibit 136e). Thus, the Court concludes that Redondo is entitled
to the amount of $106,190.00.
3. Patents and Excise Taxes
Redondo 	provided 	evidence 	of 	a 	check 	made 	payable 	to 	the
College 	of 	Engineers 	paid 	(Plaintiffs 	Exhibit 	135c 	and 	135d) 	and
the 	documental 	evidence 	that 	proves 	how 	much 	it 	paid 	to 	the
Municipality 	of 	Ponce 	for 	municipal 	taxes. 	PRHTA 	did 	not 	present
evidence as to what payments if any, it refunded to Redondo.
Redondo provided copy of all the checks made to the order of
Municipality 	of 	Ponce, 	for 	a 	total 	of 	19 	checks 	(Plaintiff’s
Exhibit 	#135e 	and 	135f), 	all 	with 	different 	checks 	numbers 	and
dates. The total amount of all the checks made by Redondo, to the
order of Municipality of Ponce is $1,082,651.56, for the total of
the 19 checks (Plaintiff’s Exhibit 135e and 135f). The check made
payable to the College of Engineers was for the total of $21,823.00
(Plaintiffs Exhibit 135c and 135d).
4. Fuel Increase
Redondo and PRHTA stipulated that the amount that is owed to
Redondo is $85,214.02 (docket #363).
5. Guard Rail
Redondo and PRHTA stipulated that the amount that is owed to
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 53 of 59
54
Redondo is $111,176.50 (docket #363).
6. Profit (15%)
Same as the section entitled: Profit, supra, discussed in the
Las Cumbres Avenue Project.
7. Interest
Same 	as 	the 	section 	entitled: 	Interest, 	supra, 	discussed 	in
the Las Cumbres Avenue Project.
8. Interest for Application for Payment No. 55 and 56
The 	applications 	for 	Payment 	No. 	55 	and 	56 	were 	paid 	well
after 	the 	project 	was 	finished, 	thus, 	Redondo 	is 	entitled 	to
collect 	interest 	from 	the 	time 	when 	the 	amounts 	were 	due, 	up 	to
when it collected the amounts due. Thus, Redondo is entitled to the
amount of $32,078.18 and $14,572.42.
Summary
1. Extended Main Office/ Job Site Overhead 	$ 	486,684.00
2. Insurance and Bond Premiums 	$ 	106,190.00
3. Patents and Excise Taxes 	$1,082,654.56
$ 	21,823.00
4. Fuel Increase 	$ 	85,214.02
5. Guard Rail 	$ 	111,176.50
6. Profit 	$ 	284,060.86
TOTAL 	$2,177,799.94
7. Plus Legal Interest 6%
8. Interest Application No. 55 and No. 56 	$ 	32,078.18
$ 	14,572.42
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 54 of 59
55
E. Contract AC 800135 - Third Millennium Park
In 	the 	present 	case 	seven 	claims 	are 	still 	pending. 	Redondo
claims: 	1. 	extended 	main 	office 	overhead 	and 	extended 	job 	site
overhead, 	2. 	Additional 	Construction 	Overtime, 	3. 	Liquidated
damages, 	4. 	Insurance 	and 	Bonds 	Premiums, 	5. 	Profit 	(15%), 	6.
Unpaid Application for Payment No. 29 and 7. Interest.
1. 	Extended 	main 	office 	overhead 	and 	extended 	job 	site
overhead
Redondo 	is 	claiming 	$284,988.00 	for 	extended 	main 	office
overhead 	and 	$943,356.00 	for 	extended 	job 	site 	overhead, 	for 	a
total of $1,228,344.00. PRHTA is accepting $133,518.00 for extended
main 	office 	overhead 	and 	$441,966.00 	extended 	job 	site 	overhead,
for a total of $575,484.00. The parties stipulated the amount to be
calculated 	per 	diem 	for 	both 	claims; 	for 	extended 	main 	office
overhead 	$561.00 	per 	diem 	and 	for 	extended 	job 	site 	overhead
$1,857.00 	per 	diem. 	The 	only 	difference 	is 	the 	amount 	of 	days
calculated by Redondo and by PRHTA. PRHTA asserts that it only owes
238 	additional 	days 	for 	extended 	main 	office 	overhead 	and 	for
extended job site overhead. PRHTA’s expert witness concluded that
Redondo was paid $750,000.00 for extended main office overhead and
extended job site overhead. On the other hand, Redondo calculated
508 additional days.
Both 	Redondo’s 	expert 	witness 	and 	PRHTA’s 	expert 	witness
(Plaintiff’s Exhibit 2 and Defendant’s Exhibit E), concluded that
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 55 of 59
56
Redondo is entitled to 607 days for extended main office overhead
and for extended job site overhead. Redondo correctly admitted that
both expert witnesses miscalculated the days and the correct amount
is 	508 	days. 	On 	the 	other 	hand, 	in 	Plaintiff’s 	Exhibit 	218 	the
settlement agreement states that the $750,00.00 would be paid for
the 	concept 	of 	acceleration 	of 	work 	but 	not 	for 	the 	extended
overhead. Thus, the Court concludes that Redondo is entitled to 508
days of extended overhead.
Extended Main Office Overhead 	$ 	561 	x 508 = 	$ 284,988.00
Extended Job Site Overhead 	$1,857 	x 508 = 	$ 943,356.00
Total that PRHTA owes to Redondo 	$1,228,344.00
2. Additional Construction Overtime
No evidence was provided by Redondo to demonstrate Redondo was
entitled to additional construction overtime from March 10, 2000 to
May 31, 2001. The Court notices that overhead was paid from March
11, 	2000 	to 	July 	2001. 	The 	Court 	will 	not 	grant 	additional
overtime, when additional overhead is being paid.
3. Liquidated damages
On 	August 	27, 	1999, 	the 	parties 	agreed 	to 	extend 	the
completion date from December 2, 1999 to December 17, 1999 (docket
#366 stipulate facts), both parties also agree that the first part
of 	the 	project 	was 	not 	completed 	on 	December 	17, 	1999, 	but 	on
December 31, 1999. Thus, as per the agreement between the parties,
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 56 of 59
57
the 	liquidated 	damages 	that 	would 	be 	imposed 	by 	PRHTA 	would 	be
$4,000.00 per day after December 17, 1999 (docket #366, stipulated
facts). 	As 	per 	Plaintiff’s 	Exhibit 	#227 	in 	the 	contract 	final
report PRHTA retained $162,500.00. If the agreement for the final
completion was December 17, 1999, but Redondo finally completed the
first 	phase 	of 	the 	project 	on 	December 	31, 	1999, 	then 	PRTHA 	can
withhold the liquidated damages for 14 days.
Amount retained by PRHTA 	$162,500.00
Liquidated Damges 	$4,000 x 14 	$ 56,000.00
Amount to refund to Redondo 	$106,500.00
4. Patents and Excise Taxes
Redondo provided evidence of the municipal taxes (Plaintiff’s
Exhibit 228) and a check made payable to the College of Engineers
(Plaintiffs Exhibit 228). On the other hand, PRTHA did not present
evidence as to what payments if any, it refunded to Redondo.
The evidence of the municipal taxes paid was for the amount of
$37,811.00 (Plaintiff’s Exhibit 228) and the check made payable to
the 	College 	of 	Engineers 	was 	for 	the 	total 	of 	$21,703.00
(Plaintiffs Exhibit 228). Thus, the Court concludes that Redondo is
entitled to $59,514.00 for patents and excise taxes for the project
of the Third Millennium Park.
5. Profit (15%)
Same as the section entitled: Profit, supra, discussed in the
Las Cumbres Avenue Project.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 57 of 59
58
6.Unpaid Application for Payment No. 59
Same as the section entitled: Unpaid Application for Payment,
supra, discussed in the Las Cumbres Avenue Project.
7.Interest
Same as the section entitled: Interest, supra, discussed in the
Las Cumbres Avenue Project.
Summary
1. Extended Main Office/ Job Site Overhead 	$1,228,344.00
2. Additional Construction Overtime 	$ 	0.00
3. Liquidated Damages 	$ 	106,500.00
4. Patents and Excise Taxes 	$ 	59,514.00
5. Profit 	$ 	209,153.70
6. Unpaid Application for Payment No. 29 	$ 	41,363.33
TOTAL 	$1,644,875.03
7. Plus Legal Interest 6%
ORDER
IT IS ORDERED that PRHTA will compensate Redondo for the total
amount of $4,506,828.29, plus legal interest at 6% from August 10,
2001, for the Project Las Cumbres Avenue.
IT IS ORDERED that PRHTA will compensate Redondo for the total
amount 	$1,258,475.13, 	plus 	legal 	interest 	at 	6% 	from 	August 	10,
2001, for the Project Rio Grande de Loiza Bridge.
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 58 of 59
59
IT IS ORDERED that PRHTA will compensate Redondo for the total
amount 	$655,550.19, 	plus legal interest at 6% 	from July 18, 1999,
plus $ 217,079.49, for the Project Kennedy Avenue.
IT IS ORDERED that PRHTA will compensate Redondo for the 	total
amount 	$2,177,799.94, 	plus 	legal 	interest 	at 	6% 	from 	August 	10,
2001, plus $46,650.60 for the Project Ponce - Adjuntas.
IT IS ORDERED that PRHTA will compensate Redondo for the amount
of $11,644,875.33, plus legal interest at 6% from December 3, 2000,
for the Project The Third Millennium Park.
SO ORDERED.
In San Juan, Puerto Rico, this 31st day of August, 2009.
/s Gerardo A. Carlo-Altieri
____________________________
GERARDO A. CARLO-ALTIERI
Chief, U.S. Bankruptcy Judge
Case:02-00113-ESL Doc#:373 Filed:08/31/09 Entered:08/31/09 19:56:40 Desc: Main
Document Page 59 of 59