PAVARINI MCGOVERN, LLC v. Waterscape Resort LLC et al

1:11-ap-02248NysbAug 15, 2014

Full text

UNITED STATES BANKRUPTCY COURT
SOUTHERN DISTRICT OF NEW YORK
---------------------------------------------------------------X
In re: 	:
:
WATERSCAPE RESORT LLC, 	: 	Chapter 11
: 	Case No. 11-11593 (SMB)
Debtor. 	:
---------------------------------------------------------------X
PAVARINI MCGOVERN, LLC, 	:
:
Plaintiff, 	: 	Adv. Proc. No. 11-02248 (SMB)
:
:
-against- 	:
:
WATERSCAPE RESORT LLC, et al. 	:
:
Defendants. 	:
---------------------------------------------------------------X
MEMORANDUM DECISION REGARDING WATERSCAPE’S
MOTION TO DISCHARGE LIENS OF CLASS 3 CREDITORS
A P P E A R A N C E S:
MEDINA LAW FIRM LLC
The Chrysler Building
405 Lexington Avenue, 7th Floor
New York, NY 10174
Eric S. Medina, Esq.
Of Counsel
– and –
RICHARD J. MIGLIACCIO, ESQ.
410 Park Avenue – 16th Floor
New York, NY 10022
Attorneys for Defendant Waterscape Resort LLC
BARTON LLP
420 Lexington Avenue
New York, NY 10170
Eric W. Sleeper, Esq.
Of Counsel
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 1 of 14
2
Attorneys for Plaintiff Pavarini McGovern, LLC
LAZARUS & LAZARUS, P.C.
240 Madison Avenue
New York, NY 10016
Harlan M. Lazarus, Esq.
Of Counsel
Attorneys for Defendants Salim Assa a/k/a Solly Assa and Ezak Assa.
TESSER & COHEN
946 Main Street
Hackensack, NJ 07601
Steven Cohen, Esq.
Of Counsel
Attorneys for Defendant John Civetta & Sons, Inc.
STUART M. BERNSTEIN
United States Bankruptcy Judge:
The debtor Waterscape Resort LLC (“Waterscape”) has moved to discharge certain
mechanics liens filed against its property and for related relief detailed below. The motion is
opposed by Pavarini McGovern, LLC (“Pavarini”), Waterscape’s general contractor, and one of
Pavarini’s subcontractors, John Civetta & Sons, Inc. For the reasons that follow, the motion to
discharge the liens as a matter of law is denied, but Pavarini is directed to specifically perform its
obligations under the parties’ contract.
BACKGROUND
The background to this dispute is discussed in In re Waterscape Resort LLC, Case No.
11-11593(SMB), 2014 WL 1389762 (Bankr. S.D.N.Y. Apr. 9, 2014). I assume familiarity with
that decision and discuss the facts required to explain this opinion.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 2 of 14
3
Waterscape owns property located in Manhattan. On June 28, 2007, it entered into a
Construction Management Agreement (“CMA”)1 with Pavarini as the Construction Manager to
build a 45-story hotel and condominium building on its property. Pavarini hired subcontractors
to do the actual work. The CMA provided that Pavarini would receive progress payments
through a requisition procedure based on the work performed by its subcontractors. Any
contract disputes were to be submitted to the Dispute Resolution Board (“DRB”), the specialized
ADR forum selected by the parties in the CMA. (See CMA Art. 19.5.) In September 2010,
when the Project was nearly complete, Waterscape discharged Pavarini as Construction Manager
and purported to terminate the CMA. Pavarini contended that Waterscape had wrongfully
withheld progress payments, owed Pavarini over $10 million, and the parties engaged in dispute
resolution before the DRB.
Waterscape commenced this chapter 11 case on April 5, 2011. On June 9, 2011, Pavarini
filed a proof of secured claim in the amount of $10,833,132.59, plus interest, which
corresponded to its filed mechanics lien. This sum included the amounts that Pavarini owed to
the subcontractors it had hired. Many of the subcontractors also filed their own mechanics liens.
As a result, approximately $20 million in mechanics liens were filed against Waterscape’s
property although roughly half that amount, at most, was actually owed.
Waterscape confirmed the Debtor’s Second Amended Plan of Reorganization (the
“Plan”) on July 21, 2011. (See Order Approving Disclosure Statement and Confirming Plan of
Reorganization, dated July 21, 2011 (ECF Main Doc. # 128).) The Plan placed the Pavarini and
1 	The CMA is annexed as Exhibit 2 to the Affidavit of William Frederick in Support of Pavarini McGovern,
LLC’s Motion for Partial Summary Judgment, filed June 25, 2012 (ECF Doc. # 35). “ECF Doc.” refers to the
docket in this adversary proceeding; “ECF Main Doc.” refers to the docket in the main bankruptcy case.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 3 of 14
4
subcontractors’ overlapping mechanics liens and trust fund claims under Article 3-A of the New
York Lien Law in Class 3, (Plan at § 4.3), and Waterscape and its secured lender agreed to carve
out $11 million from the hotel sale proceeds to fund an $11 million Trust Fund Account to pay
the Class 3 claims. (Id. §§ 4.1(b), 5.3.) Pavarini’s mechanics lien was deemed released and
discharged upon the funding of the Trust Fund Account, (id. at § 5.3), but the Plan did not affect
the subcontractors’ mechanics liens.
Each Class 3 claim was deemed to be disputed. Many actions involving Waterscape,
Pavarini and the subcontractors were already pending before the state court and the DRB, and the
intent of the Plan was to allow Pavarini and the subcontractors to continue to liquidate the
allowed amounts of their claims in the non-bankruptcy fora. Once a claim was liquidated
pursuant to a settlement or “Final Order,” the claim became an allowed claim subject to payment
from the Trust Fund Account or Waterscape’s own assets. The original definition of “Final
Order” was limited to an order rendered by a forum of competent jurisdiction as to which the
time to appeal had expired, no appeal was pending and the order had become conclusive and was
in full force and effect.
This definition did not suit Pavarini. The CMA provided that the amount of the Final
Payment as determined by the DRB was due prior to any appeal or review process. At Pavarini’s
insistence, the Plan was modified to state that “each alleged Class 3 Claim shall be determined
by settlement or Final Order in the ordinary course in a court, the Court, Dispute Resolution
Board (“DRB”) or other dispute resolution forum of competent jurisdiction pursuant to the
parties’ contracts and applicable laws and procedures.” (Plan § 4.3(b) (emphasis added).) As a
result of the change, Waterscape was obligated to satisfy Pavarini’s claim once the DRB
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 4 of 14
5
rendered its Final Accounting that reflected the disposition of all of the claims before it, and
prior to any appeal or review process.
On March 11, 2014, after years of litigation, the DRB issued its 97-page Final
Accounting in which it concluded that Waterscape owed Pavarini $8,093,655.92. On March 12,
2014, Pavarini moved to enforce the DRB’s Final Accounting and direct payment of Pavarini’s
Class 3 Claim. By Order dated April 24, 2014, the Court granted that motion and Pavarini has
been paid.
Following the payment, Waterscape made the pending motion. (Waterscape Resort
LLC’s Motion for the Entry of an Order: (I) Discharging Liens of Class 3 Creditors; (II)
Allowing Such Claims to the Extent of Payment to Pavarini McGovern LLC; (III) Deeming Such
Claims Satisfied; and (IV) Dismissing All Remaining Claims Asserted by Pavarini McGovern,
LLC, dated May 5, 2014 (“Motion”) (ECF Doc. # 173-1).) The Motion seeks an order
discharging all mechanics liens filed by Class 3 creditors and allowing their claims to the extent
of the payment to Pavarini. The Motion also seeks to compel Pavarini to discharge the
mechanics liens in accordance with the provisions of the CMA, or provide proof that they have
been satisfied. Finally, Waterscape seeks to dismiss a punitive damage claim that Pavarini has
moved for leave to assert by separate motion in this adversary proceeding against Waterscape
and its managing member, the defendant Salim Assa a/k/a Solly Assa.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 5 of 14
6
DISCUSSION
A. 	Discharge of Mechanics’ Liens Under New York Lien Law
Under New York Lien Law, a subcontractor may assert a lien against property regardless
of whether privity exists with the owner. N.Y. LIEN LAW § 32 ; accord Key Mech., Inc. v. BDC
56 LLC (In re BDC 56 LLC), 330 F.3d 111, 122 (2d Cir. 2003). The subcontractor’s lien “shall
not be for a sum greater than the sum earned and unpaid on the [prime] contract at the time of
filing the notice of lien, and any sum subsequently earned thereon.” N.Y. LIEN LAW § 4(1)3 ;
accord BDC 56 LLC, 330 F.3d at 122; SMI Bldg. Sys., LLC v. W. 4th St. Dev. Group, LLC, 83
A.D.3d 687, 688 (N.Y. App. Div. 2011). 	The right to recover from the owner is derivative of
the general contractor’s rights against the owner, and if the general contractor is not owed
anything more under its contract with the owner, the subcontractor cannot recover. Peri
Formwork Sys., Inc. v. Lumbermen’s Mut. Cas. Co., 975 N.Y.S.2d 422, 425-26 (N.Y. App. Div.
2013). The purpose of the rule is to limit the owner’s liability to the amount it agreed to pay. Id.
at 426.
Despite the derivative nature of the subcontractor’s mechanics lien, the owner’s payment
in full of all amounts owed to the general contractor does not ipso facto discharge a
2 	N.Y. LIEN LAW § 3 (McKinney 2007) provides in relevant part:
A . . . subcontractor . . . who performs labor or furnishes materials for the improvement of real
property with the consent . . . of the owner thereof, or of his agent, contractor or subcontractor, . .
. shall have a lien for the principal and interest, of the value, or the agreed price, of such labor, . . .
or materials upon the real property improved or to be improved and upon such improvement, from
the time of filing a notice of such lien as prescribed in this chapter.
3 	N.Y. LIEN LAW § 4(1) (McKinney 2007) provides in relevant part:
If labor is performed for, or materials furnished to, a contractor or subcontractor for an
improvement, the lien shall not be for a sum greater than the sum earned and unpaid on the
contract at the time of filing the notice of lien, and any sum subsequently earned thereon. In no
case shall the owner be liable to pay by reason of all liens created pursuant to this article a sum
greater than the value or agreed price of the labor and materials remaining unpaid, at the time of
filing notices of such liens, except as hereinafter provided.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 6 of 14
7
subcontractor’s mechanics lien. 101 Park Ave. Assocs. v. Trane, 470 N.Y.S.2d 392, 393 (N.Y.
App. Div.), aff’d, 465 N.E.2d 359 (N.Y. 1984) is instructive. There, the owners withheld
payment, and the general contractor filed a mechanics lien for an amount that included the
unpaid charges submitted by a subcontractor (Trane). The owners posted a bond to discharge the
general contractor’s lien, and Trane filed its own mechanics lien. The Supreme Court granted
the owner’s application to discharge Trane’s mechanics lien, reasoning that the subcontractor
must satisfy its lien out of whatever the owner owes to the general contractor. Id. at 392.
The Appellate Division reversed. The majority concluded that the deposit did not affect
Trane’s mechanics lien, concluding that the Supreme Court had confused an unpaid
materialman’s right to a mechanics lien with the rules limiting the funds available to discharge
the lien. Id. at 393. The minority disagreed, stating that the result was unfair. In its view, the
mechanics lien against the owner’s real property should be discharged and attach to the bond
which secured the debt. Otherwise, “the owner is unjustifiably burdened with the cost of posting
successive undertakings to secure amounts for materials that were secured by previous
undertakings.” Id. at 394. The Court of Appeals nevertheless affirmed the Appellate Division,
noting that “Trane, as an unpaid subcontractor, has an unqualified right to a mechanic’s lien
upon the improved real property.” 101 Park Ave. Assocs. v. Trane, 465 N.E.2d 359, 359 (N.Y.
1984) (citing N.Y. LIEN LAW § 3).
Under the rule established in 101 Park Avenue Associates, the Final Payment to Pavarini
did not discharge the unpaid subcontractors’ mechanics liens, even if the effect of the payment
precludes the subcontractors from collecting anything more from Waterscape. Moreover, as
Pavarini points out, the DRB Final Accounting is still subject to review, and if Pavarini appeals,
Waterscape may ultimately owe it more. In that event, the subcontractors may still have
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 7 of 14
8
derivative rights against Waterscape that they can enforce through the foreclosure of their
mechanics liens against Waterscape’s real property.
Nor does the Final Payment discharge the mechanics liens under New York Lien Law §
20. A mechanics lien may be discharged under § 20 by the deposit of money “with the county
clerk, in whose office the notice of lien was filed.” 4 The payment discharges the lien as against
the real property and transfers it to the deposit. LaPointe v. J.T.T. Contractors, Inc., 545
N.Y.S.2d 388, 389 (N.Y. App. Div. 1989); Frank Salz and Sons, Inc. v. Lehr Constr. Corp., 477
N.Y.S.2d 559, 562 (N.Y. Sup. Ct. 1984). Waterscape did not deposit money with the county
clerk, and instead, paid Pavarini directly pursuant to the DRB decision. Accordingly, New York
Lien Law § 20 does not apply, and more generally, the Final Payment did not discharge the
subcontractors’ mechanics liens as a matter of law. 5
4 	N.Y. LIEN LAW § 20 (McKinney 2007) provides in relevant part:
A lien . . . may be discharged after the notice of lien is filed at any time before an action is
commenced to foreclose such lien, by depositing with the county clerk, in whose office the notice
of lien is filed, a sum of money equal to the amount claimed in such notice, with interest to the
time of such deposit . . . After action to foreclose the lien is commenced it may be discharged by a
payment into court of such sum of money, as, in the judgment of the court or a judge or justice
thereof . . . will be sufficient to pay any judgment which may be recovered in such action. Upon
any such payment, the county clerk shall forthwith enter upon the lien docket and against the lien
for the discharge of which such moneys were paid, the words “discharged by payment.”
5 	The authorities cited by Waterscape in its reply in support of the argument that the Final Payment
discharged the mechanics liens are distinguishable. They dealt with the effect under Lien Law of a payment into
court, Gen. Fire-Proof Door Corp. v. Citibank, N.A., 544 F. Supp. 191, 193 (S.D.N.Y. 1982) (payment into court
discharged liens pursuant to N.Y. LIEN LAW § 55), or to the clerk. Frank Salz and Sons, Inc. v. Lehr Constr. Corp.,
477 N.Y.S.2d 559, 562 (N.Y. Sup. Ct. 1984) (“I find, pursuant to Sections 19 and 20 of the Lien Law, that the shift
from a real property lien to a cash deposit lien did not modify the requirement that an action to foreclose a lien must
be commenced within one year of the filing of the notice of lien.”); Harlem Plumbing Supply Co. v. Handelsman,
337 N.Y.S.2d 329, 330 (N.Y. App. Div. 1972) (deposit pursuant to New York Lien Law § 20 discharged the
mechanics lien and shifted it to the fund). These statutory provisions do not apply to a payment by the owner to the
general contractor, and Waterscape has not pointed to a comparable provision of the Lien Law dealing with that type
of payment.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 8 of 14
9
B. 	Discharge of Mechanics Liens Under the Plan
Waterscape also contends that the Plan dealt with all of the claims asserted by Pavarini
and the subcontractors, and reasons that the payment to Pavarini satisfied the subcontractors’
mechanics liens. (Motion ¶¶ 24, 25.) The Plan expressly discharged Pavarini’s mechanics lien
but did not address the fate of the subcontractors’ mechanics liens should Waterscape pay
Pavarini. Instead, the Plan provided that Waterscape must pay the subcontractors’ mechanics
lien/trust fund claims once they were liquidated by a Final Order. Accordingly, the Plan does
not provide a basis to discharge the subcontractors’ mechanics liens as a result of the Final
Payment to Pavarini.
C. 	Discharge of Mechanics Liens Under the CMA
Finally, Waterscape seeks relief under the provisions of the CMA. CMA Article 4.24.1
requires Pavarini to take steps to discharge a mechanics lien under certain circumstances. It
states:
If, at any time, a lien of any kind is filed against the Project by Construction
Manager, a Trade Contractor or anyone claiming through Construction Manager
or a Trade Contractor for Work performed or for materials, equipment or supplies
furnished in connection with the Work for which: (1) Construction Manager
previously has been paid by Owner, or (2) Owner has not made payment because
of a bona fide dispute between the Owner and Trade Contractor, with
Construction Manager supporting Owner’s position, then Construction Manager,
within five (5) days after written notice from Owner, shall commence to cause
such lien to be cancelled and discharged of record by bonding or otherwise, and
thereafter diligently pursue such cancellation or discharge which must be
accomplished within thirty (30) days thereof. Costs arising out of bonding Trade
Contract liens as required under clause (2) of this section are a permissible
Contingency expense.
Waterscape has failed to satisfy either condition under CMA Article 4.24.1. First,
Waterscape did not “previously” pay Pavarini for the work and materials furnished by the
mechanics lienors at the time the liens were filed. Second, although Waterscape alleges that
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 9 of 14
10
Pavarini supported it through Pavarini’s assertion of millions of dollars of back charges against
its subcontractors for defective, non-conforming or incomplete work, Waterscape’s “proof” is
contained in an off-hand remark in its reply memorandum. (See Waterscape Resort LLC’s Reply
in Further Support of its Motion: (I) Discharging Liens of Class 3 Creditors; (II) Allowing Such
Claims to the Extent of Payment to Pavarini McGovern LLC; (III) Deeming Such Claims
Satisfied; and (IV) Dismissing All Remaining Claims Asserted, dated May 27, 2014
(“Waterscape Reply”), at ¶ 8 & n.5 (ECF Doc. # 179).) Waterscape did not supply any evidence
that it had a bona fide dispute with a subcontractor, or that Pavarini’s assertion of back charges
against subcontractors related to Waterscape’s disputes with the subcontractors as opposed to
Pavarini’s disputes with the subcontractors.6 In short, Waterscape failed to demonstrate that the
conditions precedent to Pavarini’s obligation to discharge liens under CMA Article 4.24.1
occurred.
In its reply memorandum, 7 Waterscape also invoked CMA Article 12.7.3. (Waterscape
Reply ¶ 7.) This provision is not limited to mechanics liens, and requires Pavarini to confirm that
all of the work-related obligations have been paid or otherwise satisfied “in exchange for Final
Payment”:
In exchange for Final Payment, Construction Manager shall turn over to Owner:
(1) an affidavit in form and substance satisfactory to Owner’s Lender, stating that
all payrolls, bills for materials and equipment, and other indebtedness connected
with the Work for which Owner or the property might in any way be responsible,
have been paid or otherwise satisfied; . . . (3) if required by the Owner, other data
establishing payment or satisfaction of all Construction Manager’s obligations,
including, but not limited to, receipts, Final Waivers and Releases of Liens in the
6 	This does not mean that Pavarini’s back charge claims against subcontractors equate to “supporting
Owner’s position” within the meaning of the CMA. The CMA is ambiguous on this point. Nevertheless, the
paucity of proof supplied by Waterscape makes it unnecessary to resolve the ambiguity.
7 	Although Waterscape mentioned CMA Article 12.7.3 first the first time in its reply memorandum, Pavarini
did object and addressed the applicability of the provision during oral argument.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 10 of 14
11
form set forth in Exhibit l from Construction Manager and all Trade Contractors
and major Vendors. . . .
Pavarini argues that it is not required to perform the obligations imposed under CMA
Article 12.7.3 (or CMA Article 4.24.1 which has already been addressed) because Waterscape
committed a material breach by wrongfully terminating the CMA, and the material breach
excused Pavarini from further performance. While Pavarini’s statement of the law is correct as
far as it goes, it is also the law that the non-breaching party cannot elect to continue to demand
the benefits under the breached contract while ignoring its corresponding obligations. See ARP
Films, Inc. v. Marvel Entm’t Group, Inc., 952 F.2d 643, 649 (2d Cir. 1991). Following
Waterscape’s breach, Pavarini invoked the contractual ADR procedures. Furthermore, it insisted
on changes to the Plan that equated a DRB resolution to a Final Order for purposes of allowance
and payment. It succeeded in arguing that the CMA required Waterscape to satisfy immediately
the $8 million obligation imposed under the Final Accounting, and successfully contended that
the CMA prohibited Waterscape from seeking review of or appealing from the Final Accounting
until it made the payment. Thus, Pavarini affirmed the ADR provisions of the CMA, and in
particular, the effect of the provisions relating to the Final Payment. 8 Having achieved the
bargained-for benefit, it is bound to perform the corresponding bargained-for obligation.
At oral argument, Pavarini also argued that any failure to comply with CMA Article
12.7.3 would constitute a breach of the CMA that Waterscape was required to submit to the
DRB. 9 (Transcript of May 29, 2014 Hearing (“5/29 Tr.”), at 13 (ECF Doc. # 181).) The
8 	It is also unreasonable to argue that the dispute resolution procedures did not survive the breach. They
were intended to resolve situations in which Waterscape failed to pay Pavarini, and any non-payment of a material
amount would constitute a material breach.
9 	Pavarini did not argue that CMA Article 12.7.3 was a condition to Final Payment but not a promise whose
nonperformance would give rise to a claim for breach of the CMA. In other words, Pavarini did not assert that a
failure to comply with CMA Article 12.7.3 might allow Waterscape to withhold the Final Payment, but did not
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 11 of 14
12
argument lacks merit. Pavarini never repudiated its obligations under CMA Article 12.7.3 prior
to the Final Payment, and any breach occurred simultaneously with or subsequent to the Final
Payment. The DRB lost its jurisdiction upon Final Payment. (CMA Art. 18.1.7 (“[T]he DRB
shall continue in existence for the duration of the construction of the Project and through final
payment.”)); accord Waterscape Resort, LLC v. Pavarini McGovern, LLC, N.Y. Cty. Index No.
652035/10, bench decision at 3-5 (N.Y. Sup. Ct. Dec. 20, 2011) (concluding that Waterscape
was required to submit claims to the DRB, and the DRB retained jurisdiction until final
payment). 10 Hence, Waterscape could not have raised the claim before the DRB.
Here, Waterscape made the Final Payment as required by the CMA, and “in exchange
for” the Final Payment, Pavarini must comply with CMA Article 12.7.3. How and when it will
do so must await further proceedings. This conclusion is not inconsistent with the earlier
determination that the Final Payment did not discharge the mechanics liens as a matter of New
York law or under the Plan. It simply enforces the bargain that the parties made under the CMA,
a bargain that leads to a different result than the law (or the Plan) might require.
D. 	Pavarini’s Punitive Damage Claim
Pending before the Court is a separate motion by Pavarini to amend its complaint to
assert a claim for punitive damages based upon Waterscape’s and Solly Assa’s alleged diversion
of trust funds. (See Memorandum of Law in Support of Motion for Leave to Amend Complaint to
Add a Demand for Punitive Damages, dated Mar. 12, 2014 (ECF Doc. # 150).) Waterscape
impose an affirmative duty on Pavarini that Waterscape could require Pavarini to specifically perform. Furthermore,
Pavarini did not maintain that Waterscape has an adequate remedy at law.
10 	A copy of the Supreme Court’s bench decision is annexed as Exhibit 1 to the Affidavit of Eric McGovern in
Support of Motion to Enforce the Dispute Resolution Board’s Final Decision and Direct Payment of Pavarini
McGovern, LLC's Class 3 Claim, dated Mar. 12, 2014 (ECF Main Case Doc. # 560).
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 12 of 14
13
opposed the motion. (See Waterscape Resort LLC’s: (I) Opposition to the Motion of Pavarini
McGovern, LLC to Amend its Complaint to Assert Punitive Damages; and (II) Cross-Motion in
Support of Motion to Amend Answer to Assert Counterclaim Against Pavarini McGovern, LLC
for Willful Overstatement of Lien Pursuant to N.Y. Lien Law § 39, dated Mar. 27, 2014 (ECF
Doc. # 161-1).) It argued that Pavarini had unduly delayed in asserting the claim, (id. ¶ 17), it
would suffer undue prejudice if the claim were asserted, (id. ¶ 18), and the amendment was
futile. (Id. ¶¶ 19-24.) The amendment was futile because the claim was asserted in a conclusory
manner, law of the case precluded its assertion and the mere diversion of funds did not satisfy the
standard for stating a claim for punitive damages. (Id. ¶¶ 23-24.)
Waterscape argued in the Motion that the punitive damage claim was also moot.
According to Waterscape, the Plan provided no mechanism to pay the claim. The “injunction
provisions provided under section 1141” expressly barred payment because Pavarini’s claims
have “indefeasibly been paid in full,” and the punitive damage claims do not fit within the
“Exclusions to Releases” set forth in Article 1.4 of the Plan, “since the operative facts,
concerning Waterscape’s alleged diversion were known to Pavarini at the time of the
confirmation of the Plan and were not included in the complaint in the above adversary
proceeding,.” (Motion ¶ 26.)
At oral argument, I raised the possibility that the Plan may have discharged the punitive
damage claim, and invited Waterscape to supplement its papers submitted in opposition to
Pavarini’s motion for leave to amend. (5/29 Tr. at 22.) Counsel for Waterscape never
supplemented the papers, and the Motion fails to explain why the Plan precludes payment if the
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 13 of 14
14
punitive damage claim was not discharged.11 The Court will consider the other arguments made
by Waterscape in opposition to Pavarini’s motion to amend its complaint in a separate decision.
The Court has considered the parties’ remaining contentions and concludes that they lack
merit. Settle order on notice.
Dated: New York, New York
August 15, 2014
/s/ Stuart M. Bernstein
STUART M. BERNSTEIN
United States Bankruptcy Judge
11 	The Plan pays 100% to all creditors, whether they are members of Class 3 or Class 5, the unsecured class.
Unless discharged, any punitive damage claim must be paid in full in accordance with the Plan.
11-02248-dsj Doc 183 Filed 08/15/14 Entered 08/15/14 10:20:27 Main Document
Pg 14 of 14

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.