AECOM Technical Services, Inc. v. Flatiron AECOM, LLC

1:19-cv-02811CodAug 15, 2024

Full text

1
IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Judge William J. Martínez
Civil Action No. 19-cv-2811-WJM-KAS
AECOM TECHNICAL SERVICES, INC.,
Plaintiff-Counterclaim Defendant,
v.
FLATIRON | AECOM, LLC,
Defendant-Counterclaim Plaintiff.
ORDER AMENDING FINAL JUDGMENT
Before the Court are: (1) Defendant-Counterclaim Plaintiff Flatiron AECOM,
LLC’s (“JV” or “Flatiron”) Motion to Amend Final Judgment to Apply Correct Interest
Rates and Remove Imposition of Penalty Interest (“JV’s Motion”) (ECF No. 462); and (2)
Plaintiff-Counterclaim Defendant AECOM Technical Services, Inc.’s (“ATS”) Motion to
Alter and Amend the Judgment to Add Prejudgment Interest and Address Post-
judgment Interest (“ATS’s Motion”) (ECF No. 463). Both Motions are fully briefed. (ECF
Nos. 471, 472, 480, 481.) For the following reasons, the JV’s Motion is granted, and
ATS’s Motion is granted in part and denied in part.
I. LEGAL STANDARD
Federal Rule of Civil Procedure 59(e) permits a court to alter or amend a
judgment on timely motion by a party. “Rule [59(e)] was adopted to make clear that the
district court possesses the power to rectify its own mistakes in the period immediately
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 1 of 14
2
following the entry of judgment.” White v. N.H. Dep’t of Emp’t Sec., 455 U.S. 445, 450
(1982) (internal quotation marks and alterations omitted). The Tenth Circuit recognizes
that “the Court may amend the judgment in its discretion to correct clear error, including
a misapprehension of the controlling law, or to prevent manifest injustice.” Hayes
Family Tr. v. State Farm Fire & Cas. Co., 845 F.3d 997, 1004 (10th Cir. 2017).
II. ANALYSIS
On April 2, 2024, the Court entered Final Judgment in this case. (ECF No. 454.)
In relevant part, the Final Judgment reflected that ATS would recover: $5,259,105 from
the JV; penalty interest to be paid at the rate of 15% pursuant to Colorado Revised
Statutes § 24-91-103(2); prejudgment interest to be calculated pursuant to C.R.S. § 13-
21-101(1); and post-judgment interest to be calculated pursuant to C.R.S. §§ 13-21-
101(3) and (4). In the Motions, the parties challenge the awards of interest to ATS and
request that the Court amend the Final Judgment.
A. 	Prejudgment Interest
The Court awarded prejudgment interest pursuant to the statutory rate of 9% per
annum, compounded annually, as set forth in C.R.S. § 13-21-101. The parties agree
that this statutory rate does not apply here because that rate only applies to “actions
brought to recover damages for personal injuries.” § 13-21-101(1). The parties agree
that for a contract case with purely economic damages such as this one the proper
statute is C.R.S. § 5-12-102, which imposes prejudgment interest at 8% per annum.
See, e.g., USAA v. Parker, 200 P.3d 350, 357 (Colo. 2009) (C.R.S. § 5–12–102 controls
prejudgment interest in all cases except damages for personal injuries and where the
parties have otherwise agreed to a rate of interest); United Int’l Holdings, Inc. v. Wharf
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 2 of 14
3
(Holdings) Ltd., 210 F.3d 1207, 1233–34 (10th Cir. 2000) (“[O]ne who is damaged by a
breach of contract is entitled to recover prejudgment interest of eight percent annually
from the time of the breach”.), aff’d, 532 U.S. 588 (2001); In re Parker Excavating, Inc.,
2011 WL 5974666, at *6 (Bankr. D. Colo. Nov. 28, 2011) (applying 8% prejudgment
interest pursuant to Section 5-12-102 for subcontractor payments owed due to change
order requests).
Given the parties’ agreement, the Court grants those portions of the JV’s Motion
(ECF No. 462 at 3–4) and ATS’s Motion (ECF No. 463 at 8–9) requesting amendment
of the amount of prejudgment interest that the JV owes ATS. Accordingly, the Court
amends the prejudgment interest rate from 9% to 8% per annum pursuant to C.R.S. §
5-12-102. The proper amount of prejudgment interest that will be awarded to ATS is
$2,460,099.
B. 	Penalty Interest
1. 	Prompt Payment Statute
Colorado’s prompt payment statute provides:
Whenever a contractor receives payment pursuant to this
section, the contractor shall make payments to each of his
subcontractors of any amounts actually received which were
included in the contractor’s request for payment to the public
entity for such subcontracts . . . within seven calendar days
of receipt of payment from the public entity . . . If the
contractor fails to make timely payments to the subcontractor
as required by this section, the contractor shall pay the
subcontractor interest as specified by contract or at the rate
of fifteen percent per annum whichever is higher, on the
amount of the payment which was not made in a timely
manner. The interest shall accrue for the period from the
required payment date to the date on which payment is
made.
C.R.S. § 24-91-103(2).
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 3 of 14
4
The statute defines “subcontractor” as “any person, company, firm, or corporation
which is a party to a contract with a contractor to construct, erect, alter, install, or repair
any highway, . . . and which, in connection therewith, furnishes and performs on-site
labor with or without furnishing materials.” § 24-91-102(4).
2. 	Analysis
The JV argues that the judgment must be further amended because the Court
incorrectly awarded penalty interest as though ATS were a “subcontractor.” (ECF No.
462 at 2–3.) According to the JV, ATS does not qualify as such under C.R.S. § 24-91-
103(2), as no designer like ATS has ever been recognized as a “subcontractor” under
this statute. The JV argues that ATS did not perform any on-site labor; rather, ATS
designed the work that others performed on-site. And, even if ATS could qualify as a
“subcontractor,” the JV asserts that this interest rate could only apply to the sums that
the public entity Colorado Department of Transportation (“CDOT”) actually paid to the
JV for which ATS was owed payment—which is a fraction of the total damages award.
Accordingly, the JV requests that the Court amend the judgment and remove the
imposition of penalty interest under C.R.S. § 24-91-103(2).
ATS disagrees with the foregoing, arguing that it is a subcontractor under the
penalty interest statute and that the JV’s receipt of payment from CDOT triggered its
obligation to pay ATS for all remaining amounts owed under the Subcontract. (ECF No.
472 at 6–13.)
a. 	Whether ATS Qualifies as a Subcontractor
Despite the JV’s contention that ATS does not qualify as a subcontractor under
the statute, the Court concludes that sufficient evidence exists in the record to
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 4 of 14
5
determine that ATS is a subcontractor entitled to penalty interest. ATS performed work
for the JV under the Design Subcontract. (ECF Nos. 37-1, 37-2.) As ATS points out, it
is a “corporation” that was party to a “contract” (the Design Subcontract) with a
“contractor” (the JV) to “alter” a “highway” (the 12-mile portion of C-470). (ECF No. 472
at 6.) The main dispute hinges on whether ATS performed on-site labor.
ATS reminds the Court that “one of the reasons that ATS’s design necessarily
evolved the way it did was because the initial pre-bid design was based on high-level
surveying which Flatiron was required to supplement with more detailed surveying—a
process called ‘potholing’.” (ECF No. 472 at 6–7 (citing 1/29/2024 trial transcript at
189:2-190:11 (Mindy Steckmest testimony regarding how Flatiron’s delay in performing
required potholing delayed the final drainage design); 1/30/2024 trial transcript at
262:14-24 (same); 2/1/2024 trial transcript at 659:17- 660:15 (Will Carrier testimony
regarding potholing)).) ATS cites portions of Will Carrier’s trial testimony referring to
times when ATS “started getting out there and getting some of the potholes, we found
out through a field visit that this actually connects . . . to this manhole right around here.”
(ECF No. 419 at 188–89.) Such testimony—de minimis though it may be—
demonstrates that ATS performed on-site labor when it visited the C-470 Project
(“Project”) site to alter the drainage design to reconcile potholing information with the
information collected by visiting the site. (ECF No. 472 at 7.)
Additionally, ATS cites numerous trial exhibits referring to field work and field
visits. (Id. at 7–8 (citing admitted trial exhibit P-190 at 1 (ATS’s proposed change order
(“PCO”) #D030-B2 for I-25 Interchange redesign, seeking payment for “the design and
associated field work” for Alternative 12); admitted trial exhibit P-192 at 1 (ATS’s PCO
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 5 of 14
6
#D030-A for I-25 Interchange redesign, seeking payment for “the design and associated
field work” for Alternative 10); admitted trial exhibit P-194 at 1 (ATS’s PCO #D030-B3A
for I-25 Interchange redesign, seeking payment for “the design and associated field
work” to complete Alternative 12); 2/16/2024 trial transcript at 2900:24-2901:15
(testimony of ATS’s standard of care expert Wayne Kalayjian describing all the types of
documents he reviewed, including documents relating to ATS’s field visits).
The JV replies that Carrier’s testimony “says nothing about any work ATS
actually did at the site,” and in fact, all his testimony shows is that “ATS found out
through a field visit that the water supply connects to a certain manhole.” (ECF No. 480
at 6 (internal quotations and alteration omitted).) According to the JV, Carrier’s
testimony fails to describe what work ATS did, who attended the visit, when the visit
occurred, or any other detail that suggests anything beyond the notion that ATS, once,
went to the job site and saw the work being performed by others. (Id.)
The JV also criticizes ATS’s citation to the three PCOs that refer to “field work,”
arguing that the language in the exhibits does not describe the field work conducted by
ATS nor states whether it was ATS or another party that performed the associated field
work (Id. at 7.) And the JV underscores that Wayne Kalayjian’s testimony offers no
information on the subject of field visits other than stating that he reviewed documents
which included “field visits.” (Id.) As such, the JV asserts that “the record is bereft of
any evidence of work done by ATS on-site” and that ATS could have made a record of
its on-site labor during trial—knowing it had requested penalty interest in its Complaint.
(Id.)
The Court considers this question a close call. However, based on the evidence
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 6 of 14
7
ATS identifies, the Court concludes that it performed some on-site labor such that it
qualifies as a subcontractor under the prompt payment law. The statute does not
require a certain number of times, or a minimum extent or scope, of on-site labor which
must be performed by a subcontractor. It does not require a particular type of
description or accounting of the manner of the on-site work done. Nor does the statute
require that the subcontractor perform “construction” work, as the JV suggests. (ECF
No. 471 at 5.)
All the statute requires is that the subcontractor performed on-site labor in
connection with its contract to alter a highway. The Court will not read into the statute
more requirements than were placed there by the legislature. While perhaps the JV is
correct that the Colorado legislature did not intend for an entity like ATS to fall within the
parameters of the prompt payment statute, that is for the legislature, not this Court, to
decide. Based on the language of the statute and the—admittedly scant—evidence
highlighted by ATS, the Court concludes that ATS is a subcontractor under the prompt
payment statute.
b. 	Whether to Apply Penalty Interest
The prompt payment statute provides that “the contractor shall make payments
to each of his subcontractors of any amounts actually received;” “[t]he contractor shall
make such payments within seven calendar days of receipt of payment from the public
entity;” and “interest shall accrue for the period from the required payment date to the
date on which payment is made.” C.R.S. § 24-91-103(2).
The JV argues that ATS is not entitled to any penalty interest. But to the extent
ATS is entitled to any penalty interest, the JV argues that ATS is only entitled to interest
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 7 of 14
8
on those sums that the JV requested and CDOT paid to the JV for ATS’s work and that
interest begins to run seven days after the date CDOT paid the JV such funds. (ECF
No. 462 at 6.) Specifically, the JV states that the only evidence in the record that
supports ATS’s claims for penalty interest is Jason Brada’s testimony that the JV
received payment from CDOT for PCOs D-030-A, D-030-B2, and D-030-B3B. (Id.
(citing ECF No. 452 at 29 (36:19-37:8)).) However, the JV states that neither Brada nor
any other witness or evidence established when CDOT paid the JV for any passed-
through PCOs, including the three listed above. (Id.) Thus, the JV argues that ATS has
failed to present sufficient evidence that it is entitled to penalty interest even if ATS
qualifies as a subcontractor. (Id. at 6–7.)
ATS takes the position that the JV was paid the $204 million contract price it bid
for the Project, and the statutory trigger for the JV’s obligation to pay ATS—its
subcontractor—is when the JV receives payment. (ECF No. 472 at 11.) According to
ATS, the JV’s receipt of payment for the Project triggered its obligation to pay its
subcontractors for all amounts that the JV owed them under their subcontracts. (Id.)
However, ATS explains that “[a]s Flatiron has not disclosed when CDOT made this
payment to Flatiron,” “ATS has calculated penalty interest based on the date each
amount was due and owing under the Subcontract.” (Id.)
Specifically, ATS’s damages expert, Trey Hoefer of Alvarez & Marsal Disputes &
Investigations, LLC, calculated 15% simple interest on each of the change order
amounts that constitute the jury’s verdict, starting from the date each amount was due
and owing under the Subcontract: 90 days after the PCO date for all PCOs not related
to the I-25 interchange; 10 days after the execution date of Change Order 18
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 8 of 14
9
(December 17, 2018) for PCOs related to the I-25 interchange; and 90 days after ATS’s
last pay application dated February 26, 2021 for any remaining unpaid subcontract
balance. (ECF No. 463 at 5; ECF No. 463-1.)
Here, the question is whether ATS presented sufficient evidence at trial to entitle
it to such interest. The Court concludes that it did not. As the JV emphasizes, the
statute requires timely payment only of those sums that the JV requested and that
CDOT paid to the JV for ATS’s work. C.R.S. § 24-91-103(2). Any applicable interest
begins to accrue seven days after the date CDOT paid the JV such funds. Id.
Therefore, in order to be entitled to an award of penalty interest, at trial ATS must
have established by a preponderance of the evidence both (1) that the JV was paid by
CDOT for some or all of the at-issue PCOs and (2) the timing of such payment.
The JV concedes that the evidence at trial confirmed that three of ATS’s 27
PCOs comprising its damages award were submitted by the JV and paid by CDOT
either in full or in part: PCOs D-030-A, D-030-B2, and D-030-B3B, constituting unpaid
change orders in the amount of $1,367,410.34. (ECF No. 471 at 9.) Nevertheless, the
JV argues, and the Court agrees, that ATS did not establish the timing of CDOT’s
payments to the JV. (Id. at 10.) The JV explains that
[w]hile the jury determined that the JV must pay ATS for
certain design work pursuant to change orders,[] that does
not mean, and the jury did not find, that the JV submitted any
of the change orders in question to CDOT (pursuant to the
parties’ agreed upon contractual mechanism) and then
CDOT paid these change orders, triggering this heightened
“penalty” interest. Again, payment coming due under the
Design Subcontract is not the same as being entitled to
penalty interest under the statute.
(Id.) Moreover, the JV underscores that ATS did not establish the timing of CDOT’s
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 9 of 14
10
payments to the JV and instead relied on Hoefer’s declaration and instructed him to
assume payment dates. (Id.) Without this evidence in the record, the Court cannot
determine the date on which penalty interest began to accrue and therefore cannot
properly calculate penalty interest under the statute.
As both parties are aware, precious few cases cite the prompt payment statute,
much less analyze it. However, in New Design Construction Company v. Hamon
Contractors, Inc., the Colorado Court of Appeals touched on the issue. New Design
Constr. Co. v. Hamon Contractors, Inc., 215 P.3d 1172, 1184 (Colo. App. 2008). There,
the court explained that the trial court erred in calculating penalty interest from the date
certain projects were completed. Id. Instead, the court clarified that the contractor was
required to pay the subcontractor “within seven days of actually receiving each
installment payment from CDOT” and remanded the case with instructions for the trial
court to recalculate penalty interest. Id.
Based on New Design, which the Court finds highly persuasive, and, of course,
the clear language of the statute, the Court cannot overlook the fact that ATS failed to
elicit evidence at trial that would clarify if and when CDOT paid the JV for each PCO.
Were the Court to do so it would necessarily result in an improper penalty interest
calculation, and almost certainly constitute reversible error. As the JV rightly
emphasizes, “[p]roof of payment by CDOT to the JV of the change orders at issue
(except for the three change orders noted above) and the date of those payments are
simply not in the trial record.” (ECF No. 471 at 11.)
Given the foregoing, the Court finds that the JV has met its burden under Rule
59(e) to demonstrate that amendment of the judgment is in these circumstances
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 10 of 14
11
required. Accordingly, the Court grants that portion of the JV’s Motion which requests
that the Court amend the judgment to remove the award of penalty interest (ECF No.
462 at 7), and denies that portion of ATS’s Motion which requests that the Court alter
and amend its judgment to award penalty interest in the amount of $3,916,790 (ECF
No. 463 at 12). The Court amends the judgment to remove all penalty interest awarded
to ATS.
C. 	Post-judgment Interest1
The parties also agree that the Court should amend its final judgment to reflect
that post-judgment interest is governed by 28 U.S.C. § 1961, instead of the Colorado
personal injury interest statute, see C.R.S. §§ 13-21-101(3) and (4), which does not
apply. See, e.g., Youngs v. Am. Nutrition, Inc., 537 F.3d 1135, 1146 (10th Cir. 2008);
Moose Agricultural LLC v. Layn USA Inc., 639 F. Supp. 3d 1150, 1152 (D. Colo. 2022).
Section 1961(a) provides that post-judgment interest “shall be calculated from
the date of the entry of the judgment, at a rate equal to the weekly average 1-year
constant maturity Treasury yield, as published by the Board of Governors of the Federal
Reserve System, for the calendar week preceding [ ] the date of the judgment.” 28
U.S.C. § 1961. Section 1961(b) provides that the amount derived from the calculation
above “shall be compounded annually.”
Given the parties’ agreement, the Court grants those portions of the JV’s Motion
(ECF No. 462 at 7) and ATS’s Motion (ECF No. 463 at 12) requesting amendment of
1 The JV argues that if the Court applies penalty interest, it should run in place of post-
judgment interest. (ECF No. 480 at 9.) Because the Court has concluded that it cannot apply
penalty interest on this record, the parties’ dispute about penalty and post-judgment interest is
moot and the Court addresses it no further.
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 11 of 14
12
the amount of post-judgment interest that the JV owes ATS. Accordingly, the Court
amends the judgment to reflect that post-judgment interest is governed by 28 U.S.C. §
1961. However, it is not possible to calculate in advance a per diem amount of post-
judgment interest under this statute; rather, a judgment creditor calculates this post-
judgment interest in the course of collection and determining satisfaction of the
judgment.
D. 	Whether to Conduct an Evidentiary Hearing
The Court has considered whether it should conduct an evidentiary hearing on
the issues presented in the parties’ Motions and, in its discretion, determines that it will
not do so. As an initial matter, ATS only mentioned an evidentiary hearing in the
context of whether it qualifies as a subcontractor under the prompt payment statute.
(ECF No. 463 at 4 n.1.) A hearing on this issue is unnecessary, given the Court’s
findings above, see supra, Part II.B.2.a.
Relatedly, the Court sua sponte considered whether to conduct an evidentiary
hearing on the unanswered questions concerning penalty interest. The Court has
presided over this case since its inception in October 2019 and is of the view that both
parties have benefitted from exceptional legal representation throughout the litigation.
Nevertheless, in the Court’s view, all signs point to a conclusion that ATS’s counsel
simply overlooked the fact that ATS had pled a request for penalty interest under the
statute in its Complaint (ECF No. 1). As a consequence ATS failed to present the
requisite evidence at trial needed to meet the statutory requirements, and by doing
failed to provide the Court with the factual data it needed to properly calculate the
amount of penalty interest to which ATS might be entitled.
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 12 of 14
13
As the JV points out, Rule 59(e) is silent on whether a court must afford the
movant a further hearing. (ECF No. 471 at 5 n.2 (citing Echo Acceptance Corp. v.
Household Retail Servs., Inc., 267 F.3d 1068, 1094–95 (10th Cir. 2001) (holding district
court did not abuse its discretion when it decided a motion under Rule 59(e) without
granting an evidentiary hearing)).) Tenth Circuit case law shows that a trial court’s
decision to reopen the record is typically discretionary. See O’Toole v. Northrop
Grumman Corp., 364 F. App’x 472, 478 (10th Cir. 2010) (the district court did not abuse
its discretion in refusing to consider Mr. O’Toole’s new evidence and in denying his
request for a supplemental hearing); see also Mason v. Okla. Tpk. Auth., 182 F.3d
1212, 1215 (10th Cir. 1999) (concluding district court did not abuse its discretion in
rejecting defendant’s attempt to augment the evidentiary record on remand); Otero v.
Mesa County Valley Sch. Dist. No. 51, 628 F.2d 1271, 1272 (10th Cir. 1980) (holding
that district court did not err in refusing to reopen case and receive additional evidence
when the Tenth Circuit did not remand with directions to do so).
Here, the Court concludes that ATS pled a request for penalty interest under the
statute and knew—or at least should have known—that it would need to present
sufficient supporting evidence at trial to establish its entitlement to same by a
preponderance of the evidence. The Court notes in this regard that evidence of
CDOT’s payments to the JV for various PCOs directly relates to the work ATS
performed and was part of ATS’s breach of contract claim.
In its discretion, the Court concludes that ATS had a chance to present evidence
supporting its request for penalty interest at trial and failed to adequately do so.
Reopening the evidentiary record in a case that was tried to a jury after the jury has
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 13 of 14
14
issued its verdict in no small thing in American jurisprudence. It is a step that would
almost most certainly raise important Seventh Amendment issues. The Court will not
here engage in such an undertaking. The Court perceives no fundamental miscarriage
of justice to hold ATS to the evidence it adduced at trial, and no more. ATS will not
receive a second bite at the apple on the issue of penalty interest.
III. CONCLUSION
Accordingly, the Court ORDERS as follows:
1. 	The JV’s Motion (ECF No. 462) is GRANTED as set forth above;
2. 	ATS’s Motion (ECF No. 463) is GRANTED IN PART and DENIED IN
PART as set forth above; and
3. 	The Court will enter an Amended Final Judgment that will reflect:
a. 	Prejudgment interest at 8% pursuant to C.R.S. § 5-12-102(1)(b) in
the amount of $2,460,099;
b. 	Post-judgment interest at the federal rate pursuant to 28 U.S.C. §
1961, beginning on April 3, 2024; and
c. 	No penalty interest will be awarded pursuant to C.R.S. § 24-91-
103(2).
Dated this 15 th day of August, 2024.
BY THE COURT:
______________________
William J. Martínez
Senior United States District Judge
Case No. 1:19-cv-02811-WJM-KAS Document 492 filed 08/15/24 USDC Colorado
pg 14 of 14

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.