AECOM Technical Services, Inc. v. Flatiron AECOM, LLC

1:19-cv-02811CodSep 17, 2021

Full text

IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Judge William J. Martínez
Civil Action No. 19-cv-2811-WJM-KLM
AECOM TECHNICAL SERVICES, INC.,
Plaintiff-Counterclaim Defendant,
v.
FLATIRON | AECOM, LLC,
Defendant-Counterclaim Plaintiff.
ORDER DENYING AECOM TECHNICAL SERVICES, INC.’S
AMENDED EARLY MOTION FOR PARTIAL SUMMARY JUDGMENT
This contract dispute is before the Court on Plaintiff-Counterclaim Defendant
AECOM Technical Services, Inc.’s (“AECOM”) Amended Early Motion for Partial
Summary Judgment (“Motion”) (ECF No. 96). For the following reasons, the Motion is
denied.
I. STANDARD OF REVIEW
Summary judgment is warranted under Federal Rule of Civil Procedure 56 “if the
movant shows that there is no genuine dispute as to any material fact and the movant is
entitled to judgment as a matter of law.” Fed. R. Civ. P. 56(a); see also Anderson v.
Liberty Lobby, Inc., 477 U.S. 242, 248–50 (1986). A fact is “material” if, under the
relevant substantive law, it is essential to proper disposition of the claim. Wright v.
Abbott Labs., Inc., 259 F.3d 1226, 1231–32 (10th Cir. 2001). An issue is “genuine” if
the evidence is such that it might lead a reasonable trier of fact to return a verdict for the
nonmoving party. Allen v. Muskogee, 119 F.3d 837, 839 (10th Cir. 1997).
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 1 of 13
2
In analyzing a motion for summary judgment, a court must view the evidence and
all reasonable inferences therefrom in the light most favorable to the nonmoving party.
Adler v. Wal-Mart Stores, Inc., 144 F.3d 664, 670 (10th Cir. 1998) (citing Matsushita
Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986)). In addition, the
Court must resolve factual ambiguities against the moving party, thus favoring the right
to a trial. See Houston v. Nat’l Gen. Ins. Co., 817 F.2d 83, 85 (10th Cir. 1987).
II. BACKGROUND1
This case arises out of a contract dispute between AECOM and Defendant-
Counterclaim Plaintiff Flatiron | AECOM, LLC (“Flatiron”) over a highway construction
project, for which Flatiron was the lead design/build contractor, and AECOM was the
lead designer. (See ECF No. 37 ¶ 11.)
According to Flatiron, AECOM prepared a design under the Contractor/Designer
Teaming Agreement (“Teaming Agreement”) that failed to follow basic engineering and
Project requirements and affirmatively misled Flatiron about its conduct. (ECF No. 101
at 6 ¶ 15.) Flatiron provides examples of the alleged pre-bid problems, including an
outdated drainage design, 34,000 feet of missing drainage pipe, and missing concrete
barriers. (ECF No. 101 at 7 ¶¶ 22, 24–25.) Flatiron states that it has been injured by
AECOM’s breaches of the Teaming Agreement and the Subcontract, which have
required Flatiron to expend “at least $195 million dollars to address and correct
[AECOM’s] gross negligence.” (ECF No. 101 at 8 ¶ 29.)
1 The following factual summary is largely based on the parties’ briefs on the Motion and
documents submitted in support thereof. All citations to docketed materials are to the page
number in the CM/ECF header, which sometimes differs from a document’s internal pagination.
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 2 of 13
3
A. 	Teaming Agreement
On November 9, 2015, the parties entered into the Teaming Agreement (ECF
No. 37-1) to pursue the C-470 Express Lanes Project (“Project”) for the Colorado
Department of Transportation (“CDOT”). (ECF No. 96 at 1.) According to AECOM, the
Teaming Agreement governed how the parties’ relationship would then develop in the
event that CDOT awarded the parties the Project. (ECF No. 96 at 3 ¶ 2.) However,
Flatiron contends that the Teaming Agreement governed the parties’ obligations prior to
the submission of a proposal for the Project; Flatiron characterizes these obligations as
the “Pre-Award Services” or the “pre-bid” work, in part citing a provision of the Teaming
Agreement. (ECF No. 101 at 4 ¶ 2 (citing ECF No. 37-1 at 2 § 5).)
The Teaming Agreement sets forth various provisions relevant here. In the
Teaming Agreement, the parties “agree[d] to negotiate in good faith a subcontract (the
‘Subcontract’) for design services to be provided for the Project subject to negotiation . .
. .” (ECF No. 37-1 at 2 § 3.) Specifically, AECOM agreed to provide “the design and
engineering services (the ‘Pre-Award Services’) required for the Project in order for
Contractor Members to submit the required [Statement of Qualifications], and the
[Request for Proposals] Proposal.” (ECF 37-1 at 3 § 5.) Further, the Teaming
Agreement provides that
[t]his Agreement shall terminate in the event [of] . . . (vi)
execution of the Subcontract. . . . If the Parties enter into the
Subcontract the terms of this Agreement shall be
superseded by the Subcontract, Upon [sic] any such
termination, this Contractor/Designer Teaming Agreement
shall have no further effect; provided, however, those
provisions which, by their terms are intended to survive
termination, including and [sic] Section 10 (non-
disclosure/confidentiality), Section 12 (liability upon
withdrawal), Section 15 (limitation on damages) and Section
17 (Procurement Integrity) shall specifically survive
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 3 of 13
4
termination, [sic][.]
(ECF No. 37-1 at 3 § 4.) In Section 15, the Teaming Agreement sets forth the limitation
on damages provision, which provides in part:
. . . The Parties hereto agree that the provisions of this
Agreement which, by their nature, are intended to survive
termination or expiration of this Agreement, including, but not
limited to, releases or limitations on liability or remedies,
shall survive and continue in full force and effect following
any such termination or expiration. To the fullest extent
permitted by law, limitations on liability set forth in this
Agreement are intended to apply even in the event of
default, negligence or strict liability on the part of the Party
whose liability is limited or released.
(ECF No. 37-1 at 6 § 15.) The Teaming Agreement also provided that the Subcontract
would include certain terms that the parties would negotiate, including: “Overall
limitation of liability capped at 100% of the final design portion of the agreed-upon
Subcontract amount;” “Subcap on schedule-related damages of 20% of the final design
portion of the agreed-upon Subcontract amount;” and “Mutual waiver of
consequential damages.” (ECF No. 37-1 at 7 § 20.) According to Flatiron, the Teaming
Agreement contains no provision limiting liability, other than a mutual consequential
damages waiver. (ECF No. 101 at 6 ¶ 16.)
B. 	Subcontract
On April 4, 2016, CDOT awarded the Project to Flatiron. (ECF No. 96 at 4 ¶ 7;
ECF No. 80-1 at 2.) On May 23, 2016, the parties entered into the Subcontract. (ECF
Nos. 37-2, 37-3.)
The Subcontract states that the “Lump Sum Base Design Fee Amount” for
AECOM’s work is $9,058,493.65.2 (ECF No. 37-2 at 2.) Additionally, the Subcontract
2 AECOM states that the Total Design Fee is “an evolving number,” which is evolving in
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 4 of 13
5
requires AECOM to obtain “project specific professional liability coverage . . . which
covers the complete scope of [the] Subcontract,” with coverage limits per claim and in
the aggregate of $10 million. (ECF No. 37-2 at 4 § 2.)
Under the Terms and Conditions/Scope of Services/Responsibilities Generally
section of the Subcontract, “Design Services includes any additional services provided
by Designer in accordance with this Subcontract and all services provided by Designer
pursuant to any ‘Teaming Agreement’ or similar agreement between the Parties
regarding the Project (‘Teaming Agreement’).” (ECF No. 37-3 at 16 § 1.1 (emphasis
added).) However, in another portion of the Subcontract under the heading Exhibit 5 -
Design Assumptions, it states that “Pre-Award services are not included in the Base
Design Fee or scope of work.” (ECF No. 37-2 at 25 (emphasis added).)
The Subcontract contains a Limitations of Liability provision in Exhibit 1, stating in
relevant part:
Limitations of Liability. Designer’s aggregate liability to
Contractor for any damages, claims, costs, or expenses
arising under the Subcontract, whether in contract, tort or
otherwise, shall be limited to 100% of the Lump Sum in the
aggregate, less direct costs, plus additional design fees
incurred pursuant to this Agreement (“Total Design Fee”).
Any project specific insurance proceeds shall not count
toward this cap. . . .
(ECF No. 37-2 at 6 § 1 (emphasis added).) In the next section, the Subcontract
provides:
Liability for Schedule. In the event Designer fails to timely
perform the Design Services resulting in a demonstrable
delay to the Project’s critical path of construction, then
Flatiron’s favor. (ECF No. 96 at 11 n.3.) According to AECOM, subsequent change orders are
increasing the Total Design Fee, which is now in excess of $11 million and may still change
because the Project is ongoing and more change orders may be executed. (Id.)
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 5 of 13
6
Designer shall be liable to Contractor for the Owner’s
liquidated damages (“LDs”) the Contractor is charged to the
extent directly resulting from this delay, along with
Contractor’s other direct costs and time related project
overhead arising from such delay, including acceleration and
other mitigation costs. Contractor shall use commercially
reasonable efforts to mitigate such delay. Such liability for
delay (including but not limited to LDs) shall be limited to
20% of the Total Design Fee in the aggregate which shall be
included as part of the overall limitation of liability.
(ECF No. 37-2 at 6 § 2.) The parties also waived consequential damages under the
Subcontract. (ECF No. 37-2 at 8 § 12.)
The Subcontract contains certain provisions which refer to the Teaming
Agreement. In the Order of Precedence section, the Subcontract states:
Order of Precedence. ln the event of a conflict between the
Teaming Agreement and this Subcontract, this Subcontract
shall prevail, except with respect to the calculation of pre-bid
compensation in which case the Teaming Agreement shall
prevail. Section 16.10 is amended by adding the following
sentence to the end of the section: “In the case of a conflict
between the terms of this Subcontract and the Design/Build
Agreement and any incorporated document, the terms of this
Subcontract shall take precedence.”
(ECF No. 37-2 at 7 § 7.) At the end of the Subcontract is the merger clause, which
provides:
Entire Agreement. This Agreement (together with any
exhibits and documents incorporated herein by reference
and any terms of a Teaming Agreement between the Parties
regarding the Project not inconsistent with this Subcontract),
represent the entire agreement between Designer and
Contractor and supersedes all prior negotiations,
representations and agreements regarding the Project,
whether written or oral and cannot be amended except with
the written approval of all Parties.
(ECF No. 37-3 at 33 § 16.10.)
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 6 of 13
7
C. 	Procedural History
On October 2, 2019, AECOM filed its Complaint against Flatiron, alleging claims
for: (1) breach of the Subcontract; and (2) unjust enrichment. (ECF No. 1.) AECOM
alleges that Flatiron only partially paid AECOM for services performed under the
Subcontract and now refuses to pay the remaining amounts due. (Id. at 1–2.) On April
9, 2020, Flatiron filed its Answer and Amended Counterclaim, alleging counterclaims
for: (1) breach of the Teaming Agreement; (2) negligent misrepresentation; and (3)
breach of the design Subcontract. (ECF No. 37.)
On February 23, 2021, the Court granted in part and denied in part AECOM’s
Motion to Dismiss the Amended Counterclaim Pursuant to Fed. R. Civ. P. 12(b)(6) and
9(b) (ECF No. 46). (ECF No. 97.) In the Order, the Court dismissed with prejudice
Flatiron’s negligent misrepresentation counterclaim and left pending Flatiron’s claims for
breach of the Teaming Agreement and breach of the Subcontract. (Id.)
On February 15, 2021, AECOM filed the Motion. (ECF No. 96.) Flatiron filed a
response in opposition (ECF No. 101), to which AECOM replied (ECF No. 109). Thus,
the Motion is ripe for review.
III. ANALYSIS
In the Motion, AECOM argues that the Court should enter partial summary
judgment in its favor, and against Flatiron, on Flatiron’s contract claims confirming that:
(1) AECOM’s total liability for breach of contract claims is capped at the amount of the
Total Design Fee per the Subcontract and any applicable insurance coverage; (2)
AECOM’s liability for schedule-related damages for breach of contract claims is further
capped at 20% of the Total Design Fee; and (3) Flatiron’s consequential damages are
waived, whether pursuant to the terms of the Subcontract or the Teaming Agreement.
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 7 of 13
8
(ECF No. 96 at 15.)
Specifically, AECOM argues that the Subcontract’s limitation of liability provisions
apply to work it performed under the Teaming Agreement and the Subcontract. (ECF
No. 109 at 4.) According to AECOM, even if the Court determines that the Teaming
Agreement survives despite the merger clause and other provisions which it contends
indicate the Subcontract supersedes the Teaming Agreement, the definition of “Design
Services” demonstrates that the limitation of liability provisions apply to both AECOM’s
pre- and post-bid work. (Id. at 6.) AECOM points to the language which defines
“Design Services” to include “all services provided by [AECOM] pursuant to any
‘Teaming Agreement . . . between the Parties regarding the Project . . . .” (Id.) Based
on this definition, AECOM asserts that where the parties reference “Design Services” in
the Subcontract, they are also referencing all services AECOM performed under the
Teaming Agreement. (Id.) Thus, according to AECOM, it would be impossible to give
meaning to the Subcontract’s definition of “Design Services” without also giving effect to
the Subcontract’s limitation of liability for those same services. (Id. at 7.)
In response, Flatiron contends that genuine factual disputes exist over whether
Flatiron’s damages arise under the Teaming Agreement or the Subcontract; that the
Subcontract’s limitation of liability provisions are not enforceable under Colorado law;
and that SOLIDFX, LLC v. Jeppesen Sanderson, Inc., 841 F.3d 827, 838–41 (10th Cir.
2016), does not control the legal analysis of whether the limitation of liability provisions
are enforceable. (See generally ECF No. 101.) Flatiron contends that the Teaming
Agreement governs the parties’ pre-bid conduct and the Subcontract governs their post-
bid conduct. (Id. at 9.)
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 8 of 13
9
For support, Flatiron points to various provisions in the two contracts which it
argues show that the Teaming Agreement was not meant to be subsumed by the
Subcontract. First, Flatiron cites language from the Subcontract’s limitation of liability
provision which states that it applies to “damages, claims, costs, or expenses arising
under the Subcontract.” (Id. (quoting ECF No. 37-2 at 6 § 1(emphasis added)).)
Second, Flatiron quotes the provision from the Design Assumptions exhibit, which
states that “Pre-Award services are not included in the Base Design Fee or scope of
work.” (Id. (quoting ECF No. 37-2 at 25).) Third, Flatiron points to language in the
Teaming Agreement which states that multiple provisions will survive the Teaming
Agreement. (Id. (quoting ECF No. 37-1 at 5 § 15 (“limitations on liability. . ., shall
survive and continue in full force and effect following any such termination or
expiration”); ECF No. 37-1 at 2 § 4 (“Upon any such termination . . . Section 15
(limitation on damages) . . . shall specifically survive termination.”)).) In addition,
Flatiron observes that the Teaming Agreement contains no limitation on AECOM’s
liability for breaches of the Teaming Agreement and that the Subcontract’s limitation of
liability provision specifically states it applies to damages “arising under the
Subcontract.” (Id. at 10.)
To interpret the contracts at issue, the Court applies Colorado law.3 See Shady
Grove Orthopedic Assocs., P.A. v. Allstate Ins. Co., 559 U.S. 393, 417 (2010) (“It is a
long-recognized principle that federal courts sitting in diversity apply state substantive
law and federal procedural law.” (internal quotation marks and citation omitted))
(concurring, J. Stevens). Under Colorado law, “ambiguity in a written contract may be
3 The Court has diversity jurisdiction under 28 U.S.C. § 1332(a). (ECF No. 1 ¶ 4.)
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 9 of 13
10
resolved by looking to extrinsic evidence demonstrating the intent of the parties.” Fed.
Deposit Ins. Corp. v. Fisher, 292 P.3d 934, 940–41 (Colo. 2013) (dissenting opinion). “It
is similarly well-accepted, both in and outside this jurisdiction, that an ambiguity
permitting resort to extrinsic evidence is established where different provisions of a
contract are in irreconcilable conflict.” Id. (citing Ryan v. Fitzpatrick Drilling Co., 342
P.2d 1040 (Colo. 1959); People v. Johnson, 618 P.2d 262, 266 (Colo. 1980); 11
Richard A. Lord, Williston on Contracts § 30:4, at 46 (4th ed. 1999); 5 Margaret N. Kiffin,
Corbin on Contracts § 24.23, at 252 (Joseph M. Perillo ed., 1998)).
In Colorado, “[w]hile consideration of the contract as a whole in light of various
interpretative aids may help to determine that an apparent conflict between individual
words or provisions of the contract does not present an actual conflict at all, if
apparently conflicting provisions are not reconcilable by the language of the contract
itself, then there exists a facial ambiguity.” Id. The Colorado Supreme Court has “held
not only that once a court determines a document to be ambiguous, it may consider
extrinsic evidence bearing on the intent of the parties, but also that extrinsic evidence
may be conditionally admitted to determine whether the contract is actually ambiguous
in the first place.” Id. (citing E. Ridge of Fort Collins, L.L.C. v. Larimer & Weld Irrigation
Co., 109 P.3d 969, 974 (Colo. 2005)).
Upon due consideration, the Court will deny AECOM’s Motion because
provisions of the Subcontract render it ambiguous on its face.4 Of particular importance
to the Court’s conclusion is the apparent clear conflict between two provisions that
4 In ruling on the Motion, the Court has considered the parties’ numerous and far-
reaching arguments on all of the points raised. However, for the sake of conserving judicial
resources, the Court only addresses the arguments and evidence on which this Order depends.
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 10 of 13
11
appear in the Subcontract itself. AECOM correctly observes that the definition of
“Design Services” appears to incorporate work performed under the Teaming
Agreement and the Subcontract. (ECF No. 37-3 at 16 § 1.1.) Of course, this reading
supports AECOM’s overarching contention that the limitation of liability applies to work it
performed under both contracts. (ECF No. 101 at 7.)
However, the Court agrees with Flatiron that the language in the Design
Assumptions portion of the Subcontract which provides that “Pre-Award Services are
not included in the Base Design Fee or scope of work,” points toward a different
conclusion. (ECF No. 101 at 9; ECF No. 37-2 at 25.) AECOM’s steadfast reliance on
the definition of “Design Services” is simply insufficient to overcome the conflict between
these provisions in the Subcontract. Additionally, as Flatiron emphasizes, the limitation
of liability provision of the Subcontract specifies that it pertains to damages “arising
under the Subcontract.” (ECF No. 37-2 at 6 § 1.) While it is possible that AECOM’s
interpretation is accurate, it is far from clear at this point in the litigation. On this basis,
the Court finds that these material terms of the Subcontract are in direct conflict,
rendering the document ambiguous, and as a consequence the Court cannot on this
record grant summary judgment in AECOM’s favor.
In addition, as Flatiron has explained, various provisions of the Teaming
Agreement and the Subcontract call into question the parties’ intent regarding whether
and to what extent the Teaming Agreement survives the Subcontract. The conflicting
interpretations of what the parties intended regarding the limitation of liability provisions
and how the Teaming Agreement and the Subcontract would interact are factual
questions that are not susceptible to resolution on an early motion for partial summary
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 11 of 13
12
judgment. Therefore, the Court will deny AECOM’s Motion.5
IV. CONCLUSION
For the reasons stated above, the Court ORDERS:
1. 	AECOM Technical Services, Inc.’s Amended Early Motion for Partial Summary
Judgment (ECF No. 96) is DENIED;
2. 	The Court sua sponte extends the page limits for summary judgment briefing as
follows:
a. 	Motions for summary judgment and responses thereto may be no
more than 50 pages, exclusive of certificates of service and
attorney signature blocks;
b. 	Reply briefs may be no more than 25 pages, exclusive of
certificates of service and attorney signature blocks; and
c. 	The parties will continue to adhere to the scheduling deadlines set
by the United States Magistrate Judge (see ECF No. 121);
3. 	If either party raises the issue of the enforceability of the contracts’ limitation of
liability provisions in summary judgment motion practice, the Court DIRECTS
them to address the nature and type of extrinsic evidence the Court may
consider in the course of interpreting the relevant provisions of the Teaming
Agreement and Subcontract. Specifically, the parties must provide the legal
5 One of AECOM’s requests for relief in the Motion is that the Court enter summary
judgment finding that Flatiron’s consequential damages are waived, whether pursuant to the
terms of the Subcontract or the Teaming Agreement. (ECF No. 96 at 15.) In its response,
Flatiron states that “As for the consequential damages waiver, Flatiron does not seek
consequential damages.” (ECF No. 101 at 3 n.2.) Although the Court will deny AECOM’s
Motion, the Court will hold Flatiron to its representation that it is not seeking consequential
damages.
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 12 of 13
13
underpinning for the permissible scope of this extrinsic evidence, and the
requisite indicia of reliability of that evidence, if any, that the Court should look to
before it may properly consider same in the context of a motion for summary
judgment; and
4. 	In previous briefing, the parties have complied with the undersigned’s Revised
Practice Standards III.F.3-4, to the extent that “[e]ach statement of fact must be
accompanied by a specific reference to supporting evidence in the record.” The
Court expects the parties’ continued compliance with this Revised Practice
Standard. To aid the Court in efficiently reviewing the citations to exhibits, for all
future briefing, including dispositive motion practice, the Court DIRECTS the
parties to add to all citations the docket entry number and page number from
the CM/ECF headers. To the extent a pin citation is included, such as a
deposition page and line number, or a BATES stamp number, those citations
shall remain. For example, a typical citation from a Statement of Material Facts,
Smith Dep. 53:7-18, 60:19-23, June 19, 2019, should appear as follows: (ECF
No. 626-57 at 4, 5; Smith Dep. 53:7-18, 60:19-23, June 19, 2019).6
Dated this 17 th day of September, 2021.
BY THE COURT:
______________________
William J. Martinez
United States District Judge
6 To the extent the parties have technical questions about this directive, they should first
contact the Clerk’s office. Should any questions remain, the parties may then contact
chambers.
Case No. 1:19-cv-02811-WJM-KAS Document 168 filed 09/17/21 USDC Colorado
pg 13 of 13