Save the Colorado et al v. Semonite et al

1:18-cv-03258CodApr 3, 2025

Full text

IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF COLORADO
Judge Christine M. Arguello
Civil Action No. 18-cv-03258-CMA
SAVE THE COLORADO,
THE ENVIRONMENTAL GROUP,
WILDEARTH GUARDIANS,
LIVING RIVERS,
WATERKEEPER ALLIANCE, and
SIERRA CLUB,
Petitioners,
v.
TODD T. SEMONITE, in his official capacity as the Chief of the U.S. Army Corps of
Engineers,
RYAN ZINKE, in his official capacity as Secretary of the Interior, and
MARGARET EVERSON, in her official capacity as Acting Director of the U.S. Fish and
Wildlife Service,
Respondents, and
CITY AND COUNTY OF DENVER, ACTING BY AND THROUGH ITS BOARD OF
WATER COMMISSIONERS,
Respondent-Intervenor.
ORDER ON REMEDIES
I. 	BACKGROUND
On October 16, 2024, this Court entered its Order on Petition for Review of
Agency Action finding that the U.S. Army Corps of Engineers (the “Corps”) had failed to
comply with the Clean Water Act (“CWA”), Administrative Procedure Act (“APA”), and
National Environmental Policy Act (“NEPA”) when it issued the dredge-and-fill permit
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 1
of 22
2
allowing the City and County of Denver’s Board of Water Commissioners (“Denver
Water”) to expand the Gross Dam and Reservoir. Specifically, the Court found that the
Corps violated the CWA, the § 404(b)(1) guidelines, 33 C.F.R. § 323.6, and § 706(2) of
the APA. (Doc. # 151.) The Court also found that the Corps violated NEPA, its
concomitant regulations, and § 706(2) of the APA. (Id.)
At the request of the parties, the Court deferred the matter of a specific remedy
to allow the parties to brief the Court on the appropriate remedy. (Id. at 86.) The parties
have submitted multiple remedies briefs, taking differing positions on whether vacatur is
appropriate and what amount of additional construction is reasonable and necessary to
make the dam safe.1 Petitioners argue for remand with vacatur, asserting that the new
arch dam, which is currently 60 percent complete, can be built to the 340-foot height of
the old gravity dam with a new temporary spillway. See (Docs. ## 157, 165).
Respondents and Respondent-Intervenor (“Intervenor” or “Denver Water”) argue for
remand without vacatur, asserting that construction of the new arch dam must be fully
completed. See (Docs. ## 155–56, 170, 172).
For the reasons explained below, this Court orders remand with vacatur of the
Corps’ Record of Decision (“ROD”), Final Environmental Impact Statement (“FEIS”),
and Section 404 Permit (“Permit”) for the Moffat Collection System Project.
1 In compliance with the Court’s Order (see Doc. # 151 at 86), the parties represent that counsel for all
parties conferred and attempted in good faith to reach an agreement upon a remedy but were unable to
reach such an agreement.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 2
of 22
3
The Court also preliminarily enjoins any further construction on the Gross Dam
pending a hearing on what is reasonable and necessary to ensure that the dam, as it is
currently constructed, will be structurally safe.
Finally, the Court orders a permanent injunction prohibiting enlargement of the
Gross Reservoir, including tree removal, water diversion, and impacts to wildlife.
II. 	LEGAL STANDARD
A. 	REMAND WITH OR WITHOUT VACATUR
The APA states that a “reviewing court shall ... hold unlawful and set aside
agency action, findings, and conclusions found to be ... arbitrary, capricious, an abuse
of discretion, or otherwise not in accordance with law.” 5 U.S.C. § 706(2). Accordingly,
“[v]acatur of agency action is a common, and often appropriate form of injunctive relief
granted by district courts.” Diné Citizens Against Ruining Our Env’t v. Haaland, 59 F.4th
1016, 1048 (10th Cir. 2023) (quoting Diné Citizens Against Ruining Our Env’t v.
Bernhardt, 923 F.3d 831, 859 (10th Cir. 2019)). “But many courts have held that while
remand with vacatur is the preferred remedy under the APA, it is not the only
permissible remedy.” Id. (citing Allied-Signal, Inc. v. U.S. Nuclear Regulatory Comm’n,
et al., 988 F.2d 146, 150–51 (D.D.C. 1993); Black Warrior Riverkeeper, Inc. v. U.S.
Army Corps of Eng’rs, et al., 781 F.3d 1271, 1290 (11th Cir. 2015) (collecting cases that
have adopted the Allied-Signal test)).
Under the Allied-Signal test, courts must consider two factors—(1) “the
seriousness of the [agency action’s] deficiencies (and thus the extent of doubt whether
the agency chose correct),” and (2) “the disruptive consequences of an interim change
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 3
of 22
4
that may itself be changed.” Id. at 1049 (alteration in original) (citing Allied-Signal, 988
F.2d at 150–51). Importantly, with respect to the first factor, “[w]hen an agency
bypasses a fundamental procedural step, the vacatur inquiry asks not whether the
ultimate action could be justified, but whether the agency could, without further
explanation, justify its decision to skip that procedural step.” Id. (quoting Standing Rock
Sioux Tribe, et al. v. U.S. Army Corps of Eng’rs, et al., 985 F.3d 1032, 1052 (D.D.C.
2021), cert. denied sub nom. Dakota Access, LLC v. Standing Rock Sioux Tribe, et al.,
142 S. Ct. 1187 (2022)).
Further, regarding the second factor, the court looks to “the disruptive
consequences to the [relevant] industry, as well as the potential environmental damage
that might continue unabated while [the Corps] revisits its determinations.” Id. (citing
Black Warrior Riverkeeper, 781 F.3d at 1290). Application of the Allied-Signal factors
requires a fact-intensive inquiry that is typically left to the discretion of the district court.
Id. (citing Black Warrior Riverkeeper, 781 F.3d at 1291).
B. 	INJUNCTIVE RELIEF
To show that permanent injunctive relief is warranted, the proponent must
demonstrate
(1) that [they] ha[ve] suffered an irreparable injury; (2) that remedies
available at law, such as monetary damages, are inadequate to
compensate for that injury; (3) that, considering the balance of hardships
between the [petitioner] and [respondents], a remedy in equity is
warranted; and (4) that the public interest would not be disserved by a
permanent injunction.
Id. at 1049–50 (citing Monsanto Co. v. Geertson Seed Farms, 561 U.S. 139, 156–57
(2010)).
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 4
of 22
5
When assessing the first two factors in the context of environmental harm, courts
recognize that “[e]nvironmental injury, by its nature, can seldom be adequately
remedied by money damages and is often permanent or at least of long duration, i.e.,
irreparable.” Id. at 1050 (quoting Amoco Prod. Co. v. Vill. of Gambell, 480 U.S. 531, 545
(1987)). “Additionally, when assessing the balance of hardships, financial harms should
be considered but ‘financial concerns alone generally do not outweigh environmental
harm,’ especially if the financial harm is ‘self-inflicted.’” Id. (quoting Valley Comty. Pres.
Comm'n v. Mineta, 373 F.3d 1078, 1086 (10th Cir. 2004)). Some courts have found that
“where a project has already begun, the public interest in continuing a project is much
stronger” than the “public interest favor[ing] compliance with NEPA.” See Hayes, Tr. for
Paul B. Hayes Fam. Tr., Dated Apr. 30, 2010 v. Haaland, No. 4:16-cv-00615-JAR-FHM,
2024 WL 1906435, at *6 (N.D. Okla. May 1, 2024 ) (slip copy) (citing Valley Comty.
Pres. Comm’n, 373 F.3d at 1087). As with vacatur, whether to issue an injunction is
within the discretion of the district court. Diné, 59 F.4th at 1050 (citing eBay Inc. v.
MercExchange, L.L.C., 547 U.S. 388, 391 (2006)).
III. 	ANALYSIS
A. 	REMAND WITH VACATUR IS APPROPRIATE
Vacatur is the preferred/presumptive remedy under the APA and the Court finds
it to be the appropriate remedy in this case. Both factors of the Allied-Signal test weigh
in favor of remand with vacatur of the Corps’ ROD, FEIS, and Permit for the Moffat
Collection System Project. In its October 16, 2024 Order, the Court found that the Corps
had failed to comply with the CWA, APA, and NEPA. The Corps’ violations were serious
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 5
of 22
6
and will necessitate that, among other things, the Corps re-define the project purpose,
consider a multitude of alternatives that were eliminated without analysis, reassess its
“Least Environmentally Damaging Practicable Alternative” (“LEDPA”) finding, use a
supported cost metric, and seriously consider the implications of climate data. See
(Doc. # 151).
1. 	The seriousness of the agency action’s deficiencies
Respondents and Intervenor argue that remand without vacatur is appropriate
because “there is at least a serious possibility that the Corps can justify the issuance of
the permit after more NEPA and CWA work is completed.” (Doc. # 156 at 6–7.)
However, the standard focused on by Respondents and Intervenor has been uniformly
rejected by the courts as a proper formulation of the Allied-Signal test. See Standing
Rock Sioux Tribe, 985 F.3d at 1052 (“[T]he vacatur inquiry asks not whether the
ultimate action could be justified, but whether the agency could, with further explanation,
justify its decision to skip that procedural step.”); Diné, 59 F.4th at 1049 (same).
Moreover, Respondents and Intervenor have had ample opportunity to explain
how the Corps could provide such justification but have failed to do so. The deficiencies
found by the Court are extensive and serious. They are not of the type that can simply
be supported by better reasoning. As such, the deficiencies are not “curable upon
remand” without vacatur. See W. Watersheds Project v. Haaland, 69 F.4th 689, 723
(10th Cir. 2023).
The Court therefore finds that vacatur is appropriate under factor one of the
Allied-Signal test.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 6
of 22
7
a. 	The Corps’ inappropriately framed purpose-and-need statement
supports vacatur
The EPA advised the Corps that its framing of the Proposed Action’s2 purpose-
and-need statement unduly constrained the definition of “practicability.” Nonetheless,
the Corps ignored that advice and proceeded to combine the basic project purpose and
overall project purpose contending that they were inextricably interconnected to the
point that they had to be resolved simultaneously. See (Doc. # 151 at 4–6, 19–21, 23–
25, 27–28, 64–65, 70–76). As the Court noted, “Tellingly, neither Respondents nor
Intervenor points to anywhere in the record where the Corps actually articulates an
explanation as to why the two purposes[, the basic project purpose and overall project
purpose,] are inextricably interconnected to the point that they must be resolved
simultaneously, and, for that reason alone, the Corps’ purpose-and-need statement is
unduly narrow in violation of NEPA.” (Id. at 71–72.)
In their remedies briefing, the only statement made by Respondents or Intervenor
specifically addressing this deficiency is, “The Corps can reexamine the purpose and
need statement and modify it or provide more explanation on remand.” See (Doc. # 156
at 7 (citing to Doc # 156-1, Decl. of Eric Laux, ¶ 17)). This is hardly convincing.
The Corps’ erroneous practicability definition led it to reject “sixteen storage sites
[with] corresponding water supplies, two water supply management strategies, and one
conveyance component” that avoided the disturbance of wetlands. (Doc. # 151 at 56–
57.) Mindful that the Corps, by law, must disprove every potentially practicable
2 The Proposed Action refers to Denver Water’s desire to expand the Gross Dam and Reservoir.
Throughout the parties’ briefs and the administrative record, the Proposed Action is also referred to as the
“Moffat Collection System Project.”
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 7
of 22
8
alternative that does not disturb special aquatic sites, the dearth of information on these
nineteen alternatives led this Court to presume that all of them were practicable and
available. (Id. at 57.) The fact that the Corps began its analysis with such a serious error
weighs heavily in favor of vacatur.
b. 	The Corps’ need to analyze a multitude of proper alternatives
based on a reframed purpose supports vacatur
The Corps’ erroneous multifaceted project purpose also animated its alternatives
analysis in the Draft Environmental Impact Statement (“DEIS”), which began with a
“preliminary” alternatives screening process that whittled down 303 potential
alternatives to five—all of which involved some degree of tampering with the Gross
Dam. See (Doc. # 151 at 19–20). As this Court stated, “The fact that all five alternatives
that received a ‘hard look’ involved tampering with the Gross Dam was not by
coincidence—because an alternative’s practicability derives in part from its capacity to
serve the project’s purpose.” (Id. at 20.)
Respondents argue that “NEPA does not require agencies to reach any
substantive outcome after taking the requisite hard look at significant environmental
impacts and considering a reasonable range of alternatives.” (Doc. # 156 at 7 (citing
Robertson v. Methow Valley Citizens Council, 490 U.S. 332, 350 (1989).) The Court
does not agree that the mere five alternatives given a hard look, all involving tampering
with the Gross Dam, was a reasonable range in this case.3
3 By way of example, Denver Water concedes that it has built infrastructure to move water from the South
to North System before yet claims that any iteration of that solution would be impracticable as applied to
the instant case. See (Doc. # 151 at 65 n.34 (citing AR 129541)). In fact, one alternative considered just
that. “Conduit X,” one proposed alternative highlighted by the organization “Colorado Trout Unlimited,”
proposed bridging the South and North Systems via pipeline, which would theoretically address Denver
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 8
of 22
9
This serious deficiency includes the Corps’ failure to clearly demonstrate that the
Proposed Action by Denver Water “is the LEDPA.” (Doc. # 151 at 30 (citing AR
000049–50).) A clear demonstration of the LEDPA requires comparisons to practicable
alternatives and the process of elimination. The Corps’ mandatory obligations under
both NEPA and the CWA turn on discussions of practicability, and practicability derives
in part from whether the alternative can satisfy the purpose and need of the proposed
project. As addressed immediately above, reframing the purpose-and-need statement
and considering a multitude of practicable alternatives that avoid the disturbance of
wetlands weighs heavily in favor of vacatur.
c. 	The Corps’ unsupported cost analysis supports vacatur
The Corps inexplicably chose to ignore massive costs that vary considerably by
circumstance. The Corps’ failure to prove the financial feasibility of the Proposed Action
means it failed to meet its burden of clearly demonstrating that the Proposed Action is
the LEDPA in violation of 33 C.F.R. § 323.6. See (Doc. # 151 at 60–61). Respondents
and Intervenor have had multiple opportunities to explain the cost metric used but have
utterly failed to do so.
Intervenor relied on the unremarkable observation that the guidelines do not
obligate the Corps to conduct a “formal ‘cost-benefit’ analysis” and concluded (without
explanation) that the Corps’ comment defending its cost metric is a “rational” response.
See (Doc. # 151 at 60 (citing Doc. # 138 at 41)). In fact, Respondents did not bother to
Water’s desire to fortify its system through rebalancing without the need for a massive dam construction
project. (Doc. # 151 at 17 (citing AR 176261).)
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg 9
of 22
10
address this problem in their prior briefing and have failed to provide even a modicum of
evidence in their remedies briefing that the Corps would be able to appropriately
address this problem on remand without vacatur. The Court therefore finds that starting
over and developing a reasonable cost analysis when the Corps considers all
practicable alternatives is the appropriate remedy.
d. 	The Corps’ complete failure to quantify climate change’s effects on
precipitation supports vacatur
Yet another serious defect is that the Corps failed to quantify climate change’s
effects on precipitation.4 The Corps acknowledged that climate change could decrease
or eliminate firm yield and recognized that climate change’s impact on hydrology might
render the Proposed Action ineffective enough to warrant the need for “additional
replacement sources [of water] to ensure adequate supply.” See (Doc. #151 at 62).
Despite this, the Corps declined to quantify the impacts of climate change or even
provide an educated guess for purposes of discussion. See (id.). Neither Respondents
nor Intervenor provide any argument on this point in remedies briefing. Instead, they
only mention it as a concern for further construction delays. See (Doc. # 172 at 5). The
Court finds that this is also a serious defect supporting vacatur.
In sum, the amalgamation of these serious defects supports the Court’s finding
that vacatur is appropriate under factor one of the Allied-Signal test. To allow an attempt
4 The Court is aware that an imminent ruling from the United States Supreme Court may hold that
agencies do not have to consider indirect effects that are out of their direct regulatory control, which could
allow agencies to ignore indirect climate change impacts. See Seven Cty. Infrastructure Coalition v. Eagle
Cty., Colo., 144 S. Ct. 2680 (2024). The Supreme Court heard oral argument on December 10, 2024, but
has not yet issued a decision, so this potential ruling is not the law at the time of this Order. Further,
climate change in this case arguably has a direct, not indirect, impact on the firm yield of water at issue.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
10 of 22
11
by the Corps to retroactively explain away these serious errors on remand without
vacatur would render the required analysis under the CWA, APA, and NEPA
meaningless.
2. 	The disruptive consequences of an interim change that may itself be
changed
The second factor of the Allied-Signal test has the Court consider the potential
disruptive consequences to the Proposed Action and any potential environmental
damage that may continue unabated while the Corps redoes its analysis. See Diné, 59
F.4th at 1049. On this issue, the parties have much to say about the disruption, or lack
thereof, that will result if the Court vacates the Corps' Section 404 Permit. The Court
concludes that this factor also weighs in favor of remand with vacatur.
Petitioners argue that “the paramount consideration under the second vacatur
factor is whether the Court can restore the status quo ante” and that the Court’s remand
with vacatur would accomplish this. See (Doc. # 157 at 14–15). Respondents and
Intervenor, on the other hand, argue that vacatur would not actually disrupt construction
of the new arch dam, since it would not require construction to stop under the Federal
Energy Regulatory Commission (“FERC”) license issued to Denver Water. See (Docs.
## 155 at 15, 156 at 10–11, 172 at 2–3). Respondents and Intervenor conflate this
vacatur factor with Petitioners’ requested injunction. See, e.g., (Docs. ## 155 at 15, 172
at 2–3). Respondents further argue that vacating the Section 404 Permit would remove
the Corps’ power to enforce “special conditions” Denver Water must follow that are not
included in the FERC license, “which survive the initial discharge of dredged and fill
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
11 of 22
12
material into waters of the United States,” thereby allowing potential environmental
harms. (Doc. # 156 at 4, 10 (listing several of the conditions).)
The Court finds Respondents’ and Intervenor’s arguments on this factor
unavailing. First, the Court disagrees that vacatur has no impact on further construction
as discussed in more detail in the injunction section immediately below. Second, the
Court disagrees that remand with vacatur would cause environmental harm, primarily
because this Court has the power to order mitigation of adverse environmental effects
resulting from prior construction or that would result from any necessary further
construction. See, e.g., Fla. Wildlife Fed’n v. U.S. Army Corps of Eng’rs, 404 F. Supp.
2d 1352, 1366 (enjoining construction under invalid CWA permit, but not enjoining
“mitigation measures designed to compensate for the environmental harm caused by”
project construction to date); Sierra Club v. Van Antwerp, 719 F. Supp. 2d 77, 80
(D.D.C. 2010) (vacating CWA permit but not affecting “several current permit conditions
pertain[ing] to the continued operation and maintenance of the storm water
management system and ongoing stabilization of the site” to promote the purposes of
NEPA and the CWA); Colo. Envtl. Coal. v. Off. of Legacy Mgmt., 819 F. Supp. 2d 1193,
1223–25 (D. Colo. 2011), as amended on reconsideration, Colo. Envtl. Coal. v. Off. of
Legacy Mgmt., No. 08-cv-01624-WJM-MJW, 2012 WL 628547, at *3 (D. Colo. Feb. 27,
2012) (vacating and enjoining action that violated NEPA, but allowing activities, subject
to notification to the Court and parties, “that are absolutely necessary to remediate
dangers to the public health, safety, and environment”).
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
12 of 22
13
The Court therefore finds that vacatur is also appropriate under factor two of the
Allied-Signal test.
B. 	THE COURT PRELIMINARILY ENJOINS FURTHER CONSTRUCTION ON
THE DAM PENDING A HEARING
1. 	A preliminary injunction is appropriate pending a hearing
The four factors of a preliminary injunction are slightly different than for a
permanent injunction. To receive a preliminary injunction, the proponent must establish:
(1) a substantial likelihood of success on the merits of the case; (2) irreparable injury to
the movant if the preliminary injunction is denied; (3) the threatened injury to the movant
outweighs the injury to the other party under the preliminary injunction; and (4) the
injunction is not adverse to the public interest. Valley Comty. Pres. Comm’n, 373 F.3d at
1083. The Court finds that all four factors warranting a preliminary injunction are present
pending a hearing described below, which will guide the Court in its final decision on a
tailored permanent construction injunction.
a. 	Substantial likelihood of success on the merits
Petitioners have already successfully prevailed on this factor pursuant to the
Court’s October 16, 2024 Order and this Order’s vacatur of the Corps’ ROD, FEIS, and
Permit for the Moffat Collection System Project.
Respondents and Intervenor spend much of their remedies briefing arguing that
the FERC license is distinct from the Corps’ permitting and that Petitioners do not
actually challenge this license (nor can they in this Court). They argue that this thereby
renders the Court’s decision to remand with vacatur meaningless when it comes to
construction of the new arch dam. See (Docs. ## 155 at 6–8, 10 n.1, 156 at 5 & 9–10,
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
13 of 22
14
170 at 4–5, 172 at 2). Respondents further argue that “[t]here is no basis for injunctive
relief against FERC, a non-party . . . .” (Doc. # 156 at 10.) However, the injunction
entered pursuant to this Order prohibits Denver Water, not FERC, from taking further
action. Respondents and Intervenor also argue that an injunction would be
inappropriate, because all the permitted discharges of dredged and fill material into the
jurisdictional wetlands which was allowed by the Corps’ Section 404(b)(1) permit has
been completed. See (Docs. ## 155 at 12, 156 at 11).
These are disingenuous arguments that oversimplify and misrepresent the larger
scale of the Proposed Action and the Corps’ authority.5 As pointed out by Petitioners,
Respondents have already twice lost on the argument of the Corps’ limited authority
over the scope of the Project. See (Doc. # 165 at 5–7). The Tenth Circuit panel
explained that the Project contains a hydroelectric dam component, over which FERC
and the Corps have dual authority, which is subsumed within the broader Project
requiring only the Corps’ approval due to the foreseeable “effect of discharges on a
massive water supply crossing several counties,” in contrast to FERC’s “consider[ation]
[of] only the effect of the dam and reservoir on a single reservoir in Boulder County.” (Id.
(quoting Save the Colo. v. Spellmon, 50 F.4th 954, 963 (10th Cir. 2022).)
b. 	Irreparable injury
Environmental injury is often the very definition of irreparable harm—often
permanent or at least of long duration. See Diné, 59 F.4th at 1050; Amoco, 480 U.S. at
5 Further, Respondents’ and Intervenor’s completed discharge and fill material argument ignores the fact
that the Corps’ ROD and FEIS have been vacated.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
14 of 22
15
545. All parties agree that there will be environmental harm resulting from completion of
the Moffat Collection System Project, including the destruction of 500,000 trees, water
diversion from several creeks, and impacts to wildlife by the sudden loss of land.
Further, as explained above, the fact that the discharges of dredged and fill material for
construction of the new Gross Dam have already happened does not make the
environmental impact of this Project any less. The Tenth Circuit acknowledged, and this
Court will not ignore, the foreseeable effect of this Project’s discharges on a massive
water supply crossing several counties. The Court therefore rejects Respondents’ and
Intervenor’s attempts to distinguish environmental impacts resulting from completion of
the dam itself from those resulting from the entire Proposed Action. The Court finds that,
without an injunction, irreparable injury would occur.
c. 	Threatened injury to the movant outweighs the injury to the other
party
While this Court can consider financial harms to Intervenor, “financial concerns
alone generally do not outweigh environmental harm, especially if the financial harm is
self-inflicted.” Diné, 59 F.4th at 1050 (citing Valley Comty. Pres. Comm’n, 373 F.3d at
1086) (internal quotation marks omitted). As stated above, the environmental harm that
will occur as a result to the Moffat Collection System Project is indisputable.
The Court does not find Respondents’ and Intervenor’s arguments about alleged
cost, delay, and the alleged urgent need to address droughts persuasive because these
alleged hardships are largely self-inflicted. Not only did Denver Water wait three years
between the Corps’ 2017 ROD and submitting its FERC application, but it also filed an
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
15 of 22
16
unsuccessful motion to dismiss, delaying this case for two more years.6 Further, Denver
Water concedes that it has built infrastructure to move water from the South to North
System before, so could presumably do so again in the event of a drought. See (Doc. #
151 at 65 n.34 (citing AR 129541)).
The Court therefore finds that this factor also weighs in favor of a preliminary
injunction pending a hearing.
d. 	Public interest
“The public has an undeniable interest in the [Corps’] compliance with NEPA’s
environmental review requirements and in the informed decision-making that NEPA is
designed to promote.” Colo. Wild Inc. v. U.S. Forest Serv., 523 F. Supp. 2d 1213, 1223
(D. Colo. 2007). In December 2003, in response to the Corps’ “Scoping Summary,”
there were a myriad of comments begging the Corps not to uncritically adopt Denver
Water’s framing of the project purposes. See (Doc. # 151 at 18 (citing to AR 175578–
6043)). Multiple environmental organizations also submitted public comments urging the
Corps to frame the scope of the project in a way that would consider Denver Water’s
needs separately, because doing so would avoid the need to install or enlarge a major
dam. (Id. at 17 (citing AR 176258, 176263).) Years later, the Corps’ DEIS also fomented
a torrent of criticism. See (id. (citing AR 128487–134705 (documenting and responding
6 Along these same lines, the Court does not find Intervenor’s laches argument persuasive. See (Doc. #
155 at 10–12). Respondents and Intervenor had warnings of potential environmental law violations from
Petitioners and the EPA for years but decided to commence the Project in the face of this uncertainty
anyway.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
16 of 22
17
to at least 2,500 submissions containing nearly 5,000 individual comments)).7 The Court
found that these public concerns were valid, finding multiple serious environmental law
violations by the Corps. See (Doc # 151).
Further, the Court finds Respondents’ and Intervenor’s argument that halting the
Project is against the public interest unavailing. Although some courts have found that
the public interest in continuing a project that has already begun is stronger than the
public interest in complying with NEPA,8 this Court will not reward Denver Water for
starting construction on the Project despite being aware of the seriousness of the
environmental law challenges by Petitioners.
2. 	The Court defers ruling on a permanent injunction pending a hearing
Petitioners do not ask this Court for a permanent injunction that would require
Denver Water to tear down the partially built dam or restore the unlawfully filled
wetlands. (Doc. # 165 at 14.) Instead, acknowledging that Denver Water needs to
address safety concerns to stabilize the new dam, Petitioners argue that the new arch
dam, which is currently 60 percent complete, can be built to the 340-foot height of the
7 As previously explained by this Court, “Although it is true that the Corps responded to public comments,
responding itself does not support a conclusion that the comment response is necessarily sound. The
Court’s review of the comment responses reveals that the Corps’ responses exhibited reasoning that was
perfunctory at best and, as explained above with respect to the CWA, in direct contradiction of the §
404(b)(1) guidelines.” (Doc. # 151 at 74 (citing AR 129310 (concluding that “it is appropriate to integrate
several underlying needs into one defined purpose, since the multiple needs of the applicant are not
‘independent’ but rather are ‘interconnected’” without any further explanation).)
8 The cases relied on by Intervenor are distinguishable from this case. In both Valley Comty. Pres.
Comm'n v. Mineta, 373 F.3d 1078 (10th Cir. 2004) and Hayes, Tr. for Paul B. Hayes Fam. Tr., Dated Apr.
30, 2010 v. Haaland, No. 4:16-cv-00615-JAR-FHM, 2024 WL 1906435 (N.D. Okla. May 1, 2024 ) (slip
copy), the court found that all appropriate alternatives were considered. In this case, the Court has
already found that the Corps’ did not consider several practicable alternatives.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
17 of 22
18
old gravity dam with a new temporary spillway, thereby reinstating the status quo ante.
See (Doc. # 157 at 9). Respondents and Intervenor, on the other hand, argue that
construction of the new arch dam must be fully completed for the following reasons:
• As described in the Supplemental Declaration of Project Manager Jeff Martin,
the Dam has been reengineered from the original gravity dam to an arch dam.
Denver Water cannot just stop work now, when the new Dam is 60% of the way
to its final height. Now that the prior foundation and abutments have been
excavated, completion of the new "arch" structure to the FERC-ordered height is
the only way to ensure the Dam is safe and structurally sound.
• The original gravity dam has been deconstructed and its foundation excavated,
exposing steep rock slopes that depend on bolts to temporarily shore them up.
Timely completion of the dam raise is necessary to permanently stabilize and
support those surfaces.
• The Dam currently has no spillway or auxiliary outlet works, compromising the
ability to respond to flooding events. While FERC anticipated that would be true
for a relatively brief period during construction, the need to expeditiously re-install
those key elements for Dam safety and functionality is part of why FERC ordered
Denver Water to complete construction on the established schedule.
• Until the spillway and outlet works are re-installed, Gross Reservoir must
remain drawn down below the amount of water that could previously be stored.
See (Doc. # 155 at 7–8) (citations to Supplemental Decl. of Jeff Martin omitted).
Allowing the construction of the new arch damn to proceed without limitation
undermines and renders meaningless the Court’s October 16, 2024 Order which found
serious violations of environmental laws.
Although, the Court is concerned about the safety issues referenced in
Respondent’s and Intervenor’s briefing, it is not clear to the Court that the only means of
addressing those safety issues is by completing construction of the dam to the
specifications originally contemplated in the Proposed Action. The Court needs to hear
the testimony of engineering experts regarding what amount, if any, of additional
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
18 of 22
19
construction is reasonable and necessary to make the existing dam safe, including what
is necessary for continued site stabilization, monitoring, and maintenance activities. It is
for this reason that the Court does not enter a permanent injunction, but rather, enters
only a preliminary injunction enjoining any further construction on the Gross Dam
pending a hearing which will guide the Court in its final decision on a tailored permanent
construction injunction.
C. 	THE COURT GRANTS A PERMANENT INJUNCTION PROHIBITING
ENLARGEMENT OF THE GROSS RESERVOIR
The Court permanently enjoins enlargement of the Gross Reservoir, finding that
Petitioners have met all four factors to show that permanent injunctive relief is
warranted.
1. 	Irreparable injury and available remedies at law
The first two factors Petitioners must show to prove that permanent injunctive
relief is warranted are (1) irreparable injury and (2) inadequate remedies at law. As
noted above, the Court recognizes that environmental injury is often the very definition
of irreparable harm and can seldom be remedied by money damages. See Diné, 59
F.4th at 1050; Amoco, 480 U.S. at 545. Again, all parties agree that there will be
environmental harm resulting from enlargement of the Gross Reservoir, including the
destruction of 500,000 trees, water diversion from several creeks, and impacts to
wildlife by the sudden loss of land.
Respondents and Intervenor argue that enlargement of the Gross Reservoir can
only happen after the Gross Dam is complete and is thus not imminent. See (Docs. ##
155 at 9, 172 at 3–4). However, this argument rings hollow given Denver Water’s
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
19 of 22
20
impatience with the Project thus far, choosing to immediately begin construction despite
repeated warnings from Petitioners that they intended to challenge the Corps’ discharge
permit. It also rings hollow given Denver Water’s alleged current plans to recommence
construction despite this Court’s Order finding serious environmental law violations.
Given this impatience, the Court will not wait for a motion for an emergency injunction
some time down the road in the event Denver Water decides to go ahead and cut down
trees while the dam construction is being completed. Further, as stated above, the
Court will not ignore the foreseeable effect of this Project’s discharges on a massive
water supply crossing several counties.9
Moreover, neither Respondents nor Intervenor have argued that remedies
available at law, such as monetary damages, are adequate to compensate for the
environmental injury. The Court therefore finds that the first two elements of a
permanent injunction of Gross Reservoir enlargement have been met.
2. 	Balance of hardships and public interest
The third and fourth factors Petitioners must show for permanent injunctive relief
are (3) that, considering the balance of hardships between Petitioners and
Respondents, a remedy in equity is warranted; and (4) that the public interest would not
be disserved by a permanent injunction. The balance of hardships and public interest
factors merge when the government is the opposing party. See Ctr. for Pub. Integrity v.
U.S. Dep’t of Def., 411 F. Supp. 3d 5, 14 (D.D.C. 2019) (citations omitted).
9 Therefore, Valley Comty. Pres. Comm'n v. Mineta, 373 F.3d 1078 (10th Cir. 2004) and Hayes, Tr. for
Paul B. Hayes Fam. Tr., Dated Apr. 30, 2010 v. Haaland, No. 4:16-cv-00615-JAR-FHM, 2024 WL
1906435 (N.D. Okla. May 1, 2024 ) (slip copy) are also distinguishable from this case because, unlike in
those cases, the Court does find imminent environmental harm.
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
20 of 22
21
As articulated in Section III.B.1.b. above, there is strong public interest in
government agencies’ compliance with environmental laws and, as it specifically relates
to enlargement of the Gross Reservoir, the public has raised concerns for years with
respect to the Corps’ failure to consider alternatives that avoid the disturbance of
wetlands. These grave concerns have been affirmed in the Court’s findings. Again, this
Court will not reward Denver Water for starting construction on the Project despite being
repeatedly warned by Petitioners, the public, and the EPA that it could be put in
jeopardy by serious environmental law violations.
Additionally, as articulated in Section III.B.1.c. above, the environmental harm
that will occur as a result of the Moffat Collection System Project outweighs any
financial concerns articulated by Denver Water when assessing the balance of
hardships in this case. The environmental harm that will occur as a result of the Gross
Reservoir enlargement is indisputable and irreparable.
The Court therefore finds that the second two elements of a permanent injunction
have also been met and a permanent injunction of Gross Reservoir enlargement is
appropriate.
IV. 	CONCLUSION
For the foregoing reasons, the Court ORDERS remand with vacatur of the U.S.
Army Corps of Engineers’ Record of Decision (“ROD”), Final Environmental Impact
Statement (“FEIS”), and Section 404 Permit (“Permit”) for the Moffat Collection System
Project. It is
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
21 of 22
22
FURTHER ORDERED that any further construction on the Gross Dam is
ENJOINED pending a hearing on what is reasonable and necessary to make the
currently existing structure safe, including what is necessary for continued site
stabilization, monitoring, and maintenance activities, to guide the Court’s decision on a
tailored permanent injunction regarding construction of the dam. At this hearing, the
Court expects the parties to present testimony from one or more experts on both sides
of this case. Because the Court is aware that time is of the essence, although the Court
has three weeks of trial scheduled in April, it will make available the following dates for a
full day hearing: April 22–25 and May 5–9, 12–14. The parties are to confer, agree on
an acceptable date for the hearing, and email the Court at
arguello_chambers@cod.uscourts.gov with that date. It is
FURTHER ORDERED that the Court GRANTS a permanent injunction
prohibiting enlargement of the Gross Reservoir, including tree removal, water diversion,
and impacts to wildlife.
DATED: April 3, 2025
BY THE COURT:
_____________________________
CHRISTINE M. ARGUELLO
United States District Judge
Case No. 1:18-cv-03258-SKC Document 176 filed 04/03/25 USDC Colorado pg
22 of 22

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.