UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF CALIFORNIA
RALPH COLEMAN, et al.,
Plaintiffs,
v.
GAVIN NEWSOM, et al.,
Defendants.
No. 2:90-cv-0520 KJM SCR P
On November 14, 2025, the Receiver presented a proposal outlining how she plans to
carry out the field auditing and CQIT testing required to assess compliance with the remedy in
this case and use the information gathered through auditing and testing to effect compliance on
the schedule set out in the Receiver Action Plan the court has approved. See Receiver’s Plan for
Resumption of Field Monitoring, CQIT Testing, and Development of a Rigorous and Sustainable
Quality Assurance Plan, ECF No. 8812. The court gave the parties an opportunity to file
responses to the Receiver’s auditing and testing proposal, which they did. ECF Nos. 8815, 8816.
On December 11, 2025, the court held a special status to clarify with the Receiver certain
provisions of her proposal, and to allow the parties to provide further comments. ECF No. 8830
(minutes). Having carefully considered the Receiver’s clarifications and the parties’ comments,
the court approves the auditing and testing proposal subject to the clarifications provided below.
It also briefly addresses plaintiffs’ concerns that the Receiver’s proposal does not adequately
provide for continuity of monitoring and retention of institutional memory.
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 1 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
2
Clarifications
First, the court confirms what it explained at the beginning of the special status on
December 11th. The court did ask the Receiver if she requested the opportunity to present an
amended proposal based on the parties’ comments, as suggested by plaintiffs. But the Receiver
advised the court she did not plan to submit an amendment. Tr. at 5, ECF No. 8835. The court
understands the Receiver’s position reflects her very regular communications with the parties to
clarify and refine the proposal without altering its substance. Any amendment would quickly
become stale and inevitably require further clarification, taking away from time best spent, in the
Receiver’s view, on getting the work done to ensure actual auditing and testing can begin as soon
as possible in 2026. The court accepts the Receiver’s position and has not required her to present
an amended proposal.
In approving the proposal, the court memorializes its understanding of certain provisions,
as confirmed by the Receiver at the special status:
— Hiring of team to conduct auditing and testing. The court previously determined the
Receiver and the Special Master had reached an impasse in their efforts to agree on a plan for the
Office of the Special Master to conduct the next round of field monitoring, with the Special
Master reporting to the Receiver as contemplated by the Receiver Action Plan. The Special
Master then conveyed his intent to resign his position, during a meeting the court had with the
Special Master and his team. The Receiver reports she or a member of her team now has spoken
to every member of the Special Master’s team who expressed an interest in speaking with her. At
the special status she represented she will be making offers to a person to serve as Senior Advisor
and to members of the Special Master’s team before the end of this year. The court understands
the Receiver will be retaining persons with independent mental health expertise to serve as
members of her auditing team. The court also understands the Receiver will have a team in place
by early January 2026 to promptly prepare for and as soon as possible thereafter begin actual
auditing and testing as envisioned by the proposal.
— Start date for auditing and testing. During the first quarter of 2026, the Receiver plans
to train staff and begin auditing and testing a relatively small number of facilities. Auditing and
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 2 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
3
testing will continue and accelerate throughout the remainder of the year, without pauses for
lengthy report writing. The Receiver plans to complete a first round by September 2026, with
additional auditing continuing into the fourth quarter of 2026 and the quarters after that. While
the approach her team will deploy differs from the method previously used by the Office of the
Special Master, it is designed to cover the equivalent number of institutions in the equivalent
amount of time. Her team will prepare streamlined reports on a rolling basis, which will allow
her to implement targeted remedial measures soon after identifying noncompliance. In response
to plaintiffs’ position that they should have continued access to institutions, see, e.g., ECF No.
8816 at 9-11, the Receiver has made a commitment to facilitating plaintiffs’ access commensurate
with past practices in this case. The court expects she will continue her regular dialogue with
plaintiffs’ counsel, as well as defendants’ counsel, in the course of which she can clarify the
contours of plaintiffs’ access in response to their concerns and in a manner that serves the best
interests of the case overall.
— Future suicide prevention audits. While the Receiver’s auditing proposal does not
specifically mention future suicide prevention audits, the Receiver clarified at hearing that her
auditing and testing proposal assumes robust continuation of suicide prevention audits, consistent
with the priority assigned this aspect of the Coleman remedy in the Receiver Action Plan. Tr. at
7–8.
— Auditing of Department of State Hospitals (DSH). In response to the plaintiffs’ request
for the court to clarify the Receiver’s responsibility for auditing within DSH, the Receiver agreed
it would be appropriate for the court to amend the order conferring authority upon her as Receiver
to expressly provide the authority to audit compliance with aspects of the remedy dependent on
DSH compliance. Previously, the Receiver has reported to the court DSH’s understanding it is
subject to auditing, and its agreement to cooperate in submitting to auditing. At the special status,
defendants’ counsel did not object in substance to the court’s amending the scope of the
Receiver’s authority in this way. Tr. at 8. The court is issuing a separate order shortly, amending
the Receiver’s authority to cover auditing of DSH.
/////
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 3 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
4
— Data remediation and data governance. The Receiver confirmed the parties’ joint
position is correct, that the most recent version of the CQIT Guidebook is dated May 2025. Tr. at
10. She clarified the training and end-user testing her proposal envisions, to ensure Key
Performance Indicators (KPIs) function as needed, will take place early in 2026, given the
parties’ substantial familiarity with the important data remediation project compliance earlier this
year. See, e.g., ECF 8815 at 4:23-5:4. The Receiver also confirmed there will be no changes to
KPIs or remediated data unless or until the court-approved KPIs have been tested and deployed in
field auditing to assess their functionality. Tr. at 9–10. Only after at least one round of field
auditing might the Receiver propose modification to KPIs, after consultation with the parties, if
she believes modification is required to facilitate compliance with the remedy and achievement of
durability in compliance. The court understands the Receiver may propose modifications to
KPIs, if any, at the same time she proposes compliance thresholds in or about April 2027. See
Receiver Action Plan at 25 (identifying date for recommending compliance thresholds). Upon
the court’s approval of the compliance thresholds, and a final set of KPIs, the Receiver will then
have a refined tool for carrying out the next phase of remediation, moving aggressively toward
the goal of full and durable remediation within five to seven years, by 2032 at the outside. Id. at
8, 15–16 (anticipated timeline for achieving compliance to allow case closure).
— Responsibility for and mode of auditing. The Receiver clarified her proposal’s
reference, for example, to “internal audits by MHSDS” and “independent audits by the Receiver’s
team” does not refer to duplicative or competing audits or the use of any auditing other than
guided by the court-ordered remedy in this case. See Tr. at 10–11. Fundamentally, the auditing
the Receiver plans will be independent in that it will be conducted by the Receiver’s own team.
To the extent her proposal references internal auditing conducted by MHSDS, that auditing will
be subject to close oversight by the Receiver’s auditors in the course of assessing transfer of the
knowledge and skill sets required to conduct internal auditing and maintain durability. Id.
— Determining compliance and durability. The Receiver clarified that her determination
of sustained compliance with the remedy in any given institution will be made on a case by case
basis. Tr. at 12–13. An institution may not achieve compliance with all aspects of the remedy at
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 4 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
5
the same time. While the Receiver may be able to reduce the scope and frequency of audits of
certain components of the remedy at a given institution, auditing may still continue of other
aspects of the remedy, such as suicide prevention. Ultimately, before the Receiver would notify
the court she recommends termination of the case because full compliance has been achieved, she
anticipates one final full round of auditing of all aspects of the remedy to ensure compliance has
in effect been maintained. Id.
— Reporting: The Receiver confirmed she will file quarterly reports with the court
beginning in 2026, as required by the Receiver Action Plan. Tr. at 6–7. These reports will
include detailed information on her auditing and auditing results. The Receiver also will publish
additional information between quarterly reports, on the MHSDS website and the Receiver’s own
website.
To address a minor housekeeping issue, the Receiver confirmed her use of the phrase
“findings and recommendations” on page 9 of her proposal should be read as referencing prior
court orders. Tr. at 14.
Continuity of Independent Oversight and Retention of Institutional Memory
Plaintiffs raise an important point about the need for continuity and retention of
institutional memory. Based on the clarifications provided above, the court is satisfied the
Receiver will have a qualified team in place to carry out independent auditing in early 2026. The
schedule she contemplates is slightly delayed by the unexpected unavailability of the Office of
the Special Master as previously constituted. But the Receiver and her team have now
undertaken a comprehensive and expedited process to designate independent professionals that
will be well positioned to implement the Receiver’s refined vision for auditing using the approach
outlined in the Receiver Action Plan. Her approach is designed to gather all the information
required to test CQIT and measure compliance, and use that information strategically to improve
compliance and achieve full implementation of the remedy.
Institutional memory matters too, of course — to the extent that memory informs future
constructive effort laser-focused on finally delivering the promise to the individual members of
the Coleman class embodied in the remedy the court adopted long ago. The court and the
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 5 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
6
Receiver had fully expected the Office of the Special Master would work within the Receivership
to continue monitoring adapted to the Receiver’s Action Plan. That expectation has not been
realized, not for lack of good faith time and effort. At this point, the Receiver indicates she is in
the process of retaining members of the Office of the Special Master in forming the new team her
auditing proposal describes. Because she currently is completing the employment-related
processes required to finalize hiring, those details are not available at the time the court is issuing
this order. But the court is satisfied they are forthcoming very soon. Ultimately, the court is
satisfied she will have concluded hiring very soon to ensure qualified persons with deep,
constructive institutional memory will be members of her auditing team.
Members of both plaintiffs’ and defendants’ teams of attorneys have their own knowledge
of the case and what matters when it comes to full remediation. The court expects those attorneys
to draw on their institutional knowledge as needed and in good faith, touched by the better angels
of their nature, to meet and confer with the Receiver and her team if they believe some law of the
case or past practice bears on the Receiver’s plans. And of course the court’s public docket
memorializes the complete history of the case, at times in excruciating detail. The Receiver and
her exceptionally qualified staff have full access to the docket and will continue to plumb it for
the wisdom it offers to the person the court has placed in charge of the remedy’s implementation.
The history of this case also is plagued with unhelpful memories, unnecessary litigation
detours, and perceptions of other players that too often have ossified into obstinate barriers to
forward progress. As the court has observed before, if all the resources poured into resisting
compliance with court oversight and litigating soup to nuts had been applied in constructive effort
and collaboration, this case could have been closed well before now. To the extent the
dysfunctional history of this case has burdened it unnecessarily, that history should no longer
hamper forward progress.
The Receiver comes to this case with a fresh perspective, with a clear vision and the
energy and qualifications to realize it on behalf of the court. She understands the need to take
account of the past while charting a course to a better future for those inmates within California’s
prisons whose right to constitutionally adequate mental health services the court has vindicated.
Case 2:90-cv-00520-TLN-SCR Document 8842 Filed 12/19/25 Page 6 of 7
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
7
The court does not expect the road ahead to be without some bumps and hiccups. But the court is
confident the Receiver is the right person for the job today.
Conclusion
The court accepts the Receiver’s clarifications provided on the record at the special status
on December 11th, summarized above. With these clarifications, having satisfied itself that
independent and rigorous auditing will begin early in 2026 and the Receiver is assembling an
independent auditing team that will move forward with an understanding of the history of this
case as required, the court APPROVES the Receiver’s proposal. In doing so, it seeks to honor the
memory of Ralph Coleman, whom the court had hoped would live to see the day the case bearing
his name could be closed because his goals had been achieved. The court of course retains
ultimate authority to ensure the remedy in this case is delivered in full. The Receiver,
implementing her proposal as an important part of the Receiver Action Plan, has the authority and
primary responsibility in the field to bring that day closer now.
This order APPROVES the Receiver’s proposal filed on the court’s docket at ECF No.
8812.
SO ORDERED.
DATED: December 19, 2025.