Intek Construction Corp v. Tegrity Contractors, Inc.

5:25-cv-05211ArwdFeb 18, 2026

Full text

1
IN THE UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF ARKANSAS
FAYETTEVILLE DIVISION
INTEK CONSTRUCTION CORP. 	PLAINTIFF
V. 	CASE NO. 5:25-CV-5211
TEGRITY CONTRACTORS, INC. 	DEFENDANT
OPINION AND ORDER
Before the Court is Defendant Tegrity Contractors, Inc.’s Motion to Compel
Arbitration (Doc. 7) and Brief in Support (Doc. 8), to which Plaintiff Intek Construction
Corp. filed a Response in Opposition (Doc. 9) and Tegrity filed a Reply (Doc. 12). On
February 10, 2026, the Court held a hearing on the Motion.
The sole question before the Court is whether the parties’ dispute should be sent
to arbitration. The Court evaluates Tegrity’s Motion under Federal Rule of Civil Procedure
12(b)(6), as the Court has not considered any facts outside the record in evaluating the
parties’ arguments and arriving at its decision. See Seldin v. Seldin, 879 F.3d 269, 272
(8th Cir. 2018). To survive a motion to dismiss for failure to state a claim, “a complaint
must contain sufficient factual matter, accepted as true, to ‘state a claim to relief that is
plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp.
v. Twombly, 550 U.S. 544, 570 (2007)). When analyzing a motion to dismiss, “a court
must accept the allegations contained in the complaint as true and make all reasonable
inferences in favor of the nonmoving party.” Martin v. Iowa, 752 F.3d 725, 727 (8th Cir.
2014).
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 1 of 7 PageID #:
<pageID>
2
I. 	BACKGROUND
In mid-2024 Tegrity, a Texas contractor, hired Intek, an Arkansas subcontractor,
to perform renovation work at certain hospital buildings operated by the Veterans
Administration in Little Rock, Arkansas, and in Fayetteville, Arkansas. See Doc. 3, ¶¶ 7–
8. The parties executed a Master Subcontract Agreement (“MSA”) setting forth Intek’s
scope of work. Included in the MSA was the following arbitration clause:
Any dispute, controversy, or claim arising out of or related to this Agreement
or any Purchase Order, or any breach or termination of this Agreement or
any Purchase Order, and any alleged violation of any federal, state, or local
statute, regulation, common law, or public policy, whether sounding in
contract, tort, or statute, shall be submitted to and decided by binding
arbitration.
(Doc. 3-1, ¶ 12.05). Critically, the arbitration clause specified that “[a]rbitration shall be
administered by the American Arbitration Association and held in Collin County, Texas
before a single arbitrator . . . .” Id. (emphasis added). Representatives from Intek and
Tegrity manifested their agreement to all terms in the MSA by signing the face sheet of
the document and initialing every page, including the page with the arbitration clause.
The parties’ business relationship quickly soured, and on March 18, 2025, Tegrity
terminated the MSA. See Doc. 3, ¶¶ 17–18. Intek claims that it substantially performed a
majority of its contract work at both the Little Rock and Fayetteville construction sites
before it was terminated, but Tegrity failed to reimburse Intek for its labor and materials,
which combined exceeds $1.5 million. See id. Rather than bring these claims before an
arbitrator, as agreed, Intek filed a lawsuit against Tegrity in Arkansas state court on
September 11, 2025, claiming breach of contract and tortious interference with business
expectancy, as well as alternative claims for equitable relief. Intek anticipated the parties’
current dispute over arbitration: Count I of the Amended Complaint is a claim for
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 2 of 7 PageID #:
<pageID>
3
declaratory judgment, which asks the Court to find that the arbitration clause in the MSA
is void under Arkansas law. See id. ¶¶ 41–51. According to Arkansas Code § 4-56-104(c),
an arbitration clause in a construction contract is void if the arbitration venue is
somewhere other than Arkansas.
Tegrity removed the case to federal court, citing diversity as the basis for federal
subject matter jurisdiction. See Doc. 2 (citing 28 U.S.C. § 1441). In Tegrity’s view, the
Federal Arbitration Act (“FAA”), 9 U.S.C. §§1–16, preempts Arkansas Code § 4-56-104(c)
and renders the MSA’s arbitration clause valid and enforceable.
II. 	DISCUSSION
Before getting into the specifics of Arkansas Code § 4-56-104(c), it is clear from
the outset that the FAA applies to the MSA’s arbitration clause, which the parties executed
by mutual consent. See Volt Info. Scis., Inc. v. Bd. of Trs. of Leland Stanford Junior Univ.,
489 U.S. 468, 479 (1989) (“Arbitration under the [FAA] i[s] a matter of consent, not
coercion.”). Section 2 of the FAA is a congressional “declaration [of] a national policy
favoring arbitration”; it broadly governs “contracts evidencing a transaction involving
commerce.” Southland Corp. v. Keating, 465 U.S. 1, 10 (1984) (citing 9 U.S.C. § 2). The
MSA falls under § 2 of the FAA because the contract involved parties from different states
and a construction project that utilized materials flowing through interstate commerce.
Since the FAA governs the arbitration clause, the Court’s role is “limited to determining
(1) whether a valid agreement to arbitrate exists and, if it does, (2) whether the agreement
encompasses the dispute.” Pro Tech Indus., Inc. v. URS Corp., 377 F.3d 868, 871 (8th
Cir. 2004).
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 3 of 7 PageID #:
<pageID>
4
Arkansas is one of thirty-two states to have enacted a “home-court” statute to
govern the litigation and arbitration of construction contracts. See Daniel D. McMillan, et
al., Construction Home-Court Statutes: Scope, Enforcement, and Preemption Under the
Federal Arbitration Act, 43 Construction Law. 9, 2 (Fall 2024). A home-court construction
statute prohibits parties to a construction contract from agreeing to litigate or arbitrate
outside the state where the construction work took place. Arkansas Code § 4-56-104(c)
is a typical home-court construction statute in that it renders “void and unenforceable” any
“provision, covenant, clause, or understanding written in a construction agreement or
construction contract . . . that requires any litigation, arbitration, or other alternative
dispute resolution proceeding arising from the construction agreement or construction
contract to be conducted in another state.” If a construction contract’s arbitration clause
specifies an out-of-state venue, that clause will be severed “and shall not cause the entire
. . . contract to become unenforceable.” Ark. Code Ann. § 4-56-104(d).
Returning to the two-step process for analyzing arbitration clauses under the FAA,
step one asks whether the clause is valid and enforceable. Setting aside for a moment
the issue of whether Arkansas Code § 4-56-104(c) (hereafter, “Home-Court Statute”)
voids 	the 	MSA’s 	arbitration 	clause, 	the 	Court 	finds 	that 	the 	clause 	is 	otherwise
enforceable 	because 	it 	manifests 	mutual 	agreement 	and 	mutual 	assent, 	legal
consideration, and a meeting of the minds. See Alltel Corp. v. Sumner, 360 Ark. 573, 576
(2005). 	At 	the 	hearing, 	Intek’s 	counsel 	argued 	that 	the 	arbitration 	clause 	was
unconscionable because Tegrity drafted the entire MSA and supposedly “embedded” the
arbitration agreement in the contract without explaining or highlighting it. Intek’s counsel
conceded, however, that Intek’s representative presumably read the entire contract and
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 4 of 7 PageID #:
<pageID>
5
did, in fact, initial every page. It is black-letter law that a party to a contract—particularly
a sophisticated party like Intek—is presumed to have read and understood all the
contract’s express provisions. See Jordan v. Diamond Equip. & Supply Co., 362 Ark. 142,
151–52 (2005). Furthermore, the Amended Complaint fails to assert any positive act of
fraud or concealment by Tegrity and contains no facts to plausibly suggest the arbitration
clause is unenforceable. Intek simply regrets its agreement to arbitrate in Texas, which is
not a legal reason to find the arbitration clause invalid.
With respect to the second step of the analysis, Intek agrees that—but for the
application of the Home-Court Statute—all claims in the Amended Complaint fall within
the agreement to arbitrate because they arise out of the work performed pursuant to the
MSA.1
Turning now to the crux of the dispute, the Home-Court Statute, the Court begins
its analysis by observing that the FAA’s purpose is to “ensur[e] that private agreements
to arbitrate are enforced according to their terms,” Volt, 489 U.S. at 479, which means
that a court must enforce an otherwise valid arbitration clause, “save upon grounds as
exist at law or in equity for the revocation of any contract.” 9 U.S.C. § 2. According to the
Supreme Court, the “grounds” referred to in § 2 are only those “generally applicable
contract defenses, such as fraud, duress, or unconscionability.” Doctor’s Assocs. v.
Casarotto, 517 U.S. 681, 687 (1996). As no such defenses appear in the Home-Court
1 Intek’s concession in this regard is not surprising, as broad arbitration clauses like the
one here, encompassing “[a]ny dispute, controversy, or claim arising out of or related to
this Agreement,” (Doc. 3-1, ¶12.05), are to be construed broadly. The Eighth Circuit views
the “strong national policy in favor of arbitration” as requiring all “doubts about whether
an arbitration clause should be construed to cover a particular dispute” to be resolved “in
favor of arbitration.” CD Partners, LLC v. Grizzle, 424 F.3d 795, 800 (8th Cir. 2005).
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 5 of 7 PageID #:
<pageID>
6
Statute, the law contains no “grounds” to revoke the otherwise valid arbitration clause.
Moreover, the requirements of the Home-Court Statute are not “generally applicable” to
all Arkansas contracts because they only apply to construction contracts. Finally, the state
legislature did not craft the language of the Home-Court Statute with the aim of salvaging
otherwise enforceable arbitration clauses. Instead, the Statute deems all nonconforming
clauses “void and unenforceable,” thus destroying any mutual agreement to arbitrate and
contravening the driving purpose of the FAA. Ark. Code Ann. §§ 4-56-104(c).
Though the Court is cognizant of the fact that no other court has yet opined on
FAA preemption relative to Arkansas’s Home-Court Statute, many other courts have ruled
similarly with respect to their respective states’ home-court statutes. See, e.g., OPE Int’l
LP v. Chet Morrison Contractors, Inc., 258 F.3d 443, 447 (5th Cir. 2001) (affirming district
court’s finding that Louisiana’s home-court construction statute was preempted by FAA);
KKW Enters., Inc. v. Gloria Jean’s Gourmet Coffees Franchising Corp., 184 F.3d 42, 49
(1st Cir. 1999) (reversing district court and finding Rhode Island’s franchise agreement
statute’s home-court provision preempted by FAA); Global Indus. Contractors v. Red
Eagle Pipeline, LLC, 617 F. Supp. 3d 633, 638 (S.D. Tex. 2022) (finding Texas’s home-
court construction statute preempted); SOS Constr. & Roofing, Inc. v. Sterling Constr.,
2015 WL 12564176, at *6 (D. Neb. Feb. 17, 2015) (finding Nebraska’s home-court
construction statute preempted); Cahill v. Alt. Wines, Inc., 2013 WL 427396, at *5 (N.D.
Iowa Feb. 4, 2013) (finding Iowa’s franchise agreement statute’s home-court provision
preempted); GEM Mech. Servs., Inc. v. DV II, LLC, 2012 WL 4094476 (D. R.I. Sept. 17,
2012) (finding Rhode Island’s home-court construction statute preempted); M.C. Constr.
Corp. v. Gray Co., 17 F. Supp. 2d 541, 548 (W.D. Va. 1998) (finding Virginia’s home-court
Case 5:25-cv-05211-TLB Document 17 Filed 02/18/26 Page 6 of 7 PageID #:
<pageID>
7
construction statute preempted); R.A. Bright Constr., Inc. v. Weis Builders, Inc., 402 Ill.
App. 3d 248, 255 (Ill. Ct. App. 2010) (finding Illinois’s home-court construction statute
preempted).
Because the Court finds that the Home-Court Statute is preempted by the FAA,
the arbitration clause in the MSA is enforceable and the parties will be compelled to
arbitrate their dispute.
III. CONCLUSION
IT IS THEREFORE ORDERED that the Motion to Compel Arbitration (Doc. 7) is
GRANTED, and the parties are ORDERED to arbitrate, per their agreement. The case is
STAYED, and the Clerk of Court is DIRECTED to ADMINISTRATIVELY TERMINATE it.
The parties may move to reopen the case if further action of the Court is required after
arbitration is complete.
IT IS SO ORDERED on this 18 th day of February, 2026.
__________________________________
TIMOTHY L. BROOKS
CHIEF UNITED STATES DISTRICT JUDGE