DO-DECISION AND ORDER ON THE MERITS NUMBER OF PAGES 8 JUDGE GOLDEN DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION — 2026TLN00121

2026TLN00121Dol Oalj

Full text

UNITED STATES DEPARTMENT OF LABOR
BOARD OF ALIEN LABOR CERTIFICATION APPEALS
Washington, DC
______________
Issue Date: 22 September 2026
BALCA Case No.: 2026-TLN-00121
ETA Case No.: H-400-26189-086203
In the Matter of:
SUNSHINE FORMOSA LLC,
Employer.
____________________________
Certifying Officer:
Erin O’Connell, Office of Foreign Labor Certification
Appearances:
Lu Wang, Esq., Duluth, Georgia
For the Employer
Before:
Jason A. Golden, Administrative Law Judge
DECISION AND ORDER AFFIRMING DENIAL OF CERTIFICATION
This case arises from Employer Sunshine Formosa LLC, d/b/a WoodOne Ramen’s request
for administrative review of the Certifying Officer’s (CO) Final Determination-Denial in an H-2B
temporary alien labor certification matter issued on August 20, 2026. The H-2B non-immigrant
program permits employers to hire foreign workers to perform temporary nonagricultural work
within the United States on a one-time occurrence, seasonal, peakload, or intermittent basis, as
defined by the United States Department of Homeland Security (DHS).1
Employers who seek to hire foreign workers under this program must apply for and
receive labor certification from the Office of Foreign Labor Certification (OFLC), Employment
and Training Administration, United States Department of Labor (DOL) using a Form ETA-9142B,
Application for Temporary Employment Certification. A certifying officer in the OFLC reviews
1 See 8 U.S.C. § 1101(a)(15)(H)(ii)(b); 8 C.F.R. § 214.2(h)(6). The definition of temporary need is governed
by 8 C.F.R. § 214.2(h)(6)(ii)(B). Consolidated Appropriations Act, 2016, Pub. L. No. 114-113, Division H,
Title I, § 113 (2015). This definition has remained in place through subsequent appropriations legislation,
including the current legislation. See Consolidated Appropriations Act, 2026, Pub. L. No. 119-75, Division
B, Title I, § 111 (2026).
2
applications for temporary labor certification. Following the certifying officer’s denial of an
application under 20 C.F.R. § 655.53, an employer may request review by the Board of Alien
Labor Certification Appeals. 20 C.F.R. § 655.61(a).
The Employer submitted its timely appeal to the Board.
I. BACKGROUND
Employer filed an Application for Temporary Employment Certification for three line
cooks for a peakload need beginning October 2, 2026 and ending June 30, 2027. AF 145.2
Employer requested the workers for the Miami-Fort Lauderdale-west Palm Beach, Florida
Metropolitan Statistical Area. AF 148.
A. Employer's Alleged Temporary Need
Employer explained its temporary need as follows:
ALTHOUGH THE RESTAURANT OPERATES YEAR-ROUND AND MONTHLY SALES ARE
RELATIVELY CONSISTENT, WE ARE EXPANDING INTO THE ADJACENT SPACE. THIS
EXPANSION WILL TEMPORARILY INCREASE OUR OPERATING AREA, SEATING
CAPACITY, KITCHEN PREPARATION NEEDS, SERVICE VOLUME, AND OVERALL
WORKLOAD DURING THE OPENING AND RAMP-UP PERIOD. OUR CURRENT
PERMANENT STAFF CAN SUPPORT OUR EXISTING OPERATION, BUT ADDITIONAL
TEMPORARY WORKERS ARE NEEDED TO SUPPLEMENT OUR U.S. WORKFORCE
DURING THIS EXPANSION PERIOD. THE H-2B WORKERS WILL NOT REPLACE
PERMANENT EMPLOYEES AND WILL NOT BE PART OF OUR REGULAR YEAR-ROUND
STAFFING ONCE OPERATIONS STABILIZE. THE BUSY PERIOD BEGINS IN OCTOBER
BECAUSE THE RESTAURANT IS LOCATED IN FLORIDA, WHERE CUSTOMER TRAFFIC
TYPICALLY BEGINS TO INCREASE IN THE FALL AS WEATHER IMPROVES, TOURISM
ACTIVITY GROWS, AND SEASONAL RESIDENTS BEGIN RETURNING BEFORE THE
WINTER PEAK SEASON. OCTOBER IS THE START OF OUR RAMP-UP PERIOD,
ALLOWING US TO PREPARE FOR INCREASED RESTAURANT DEMAND DURING THE
FALL AND WINTER MONTHS. . . .
THE NEED ENDS AROUND JUNE 30, 2027 BECAUSE THE TEMPORARY PEAK-LOAD
NEED IS TIED TO THE RESTAURANTS EXPANSION, OPENING PREPARATION, RAMP-UP
PERIOD, AND INCREASED DEMAND DURING FLORIDAS FALL, WINTER, AND SPRING
BUSY SEASON. BY JUNE 30, 2027, WE EXPECT THE EXPANDED RESTAURANT
OPERATION TO BE FULLY STABILIZED, WITH REGULAR STAFFING LEVELS
ESTABLISHED AND THE TEMPORARY INCREASE IN WORKLOAD REDUCED. AT THAT
POINT, THE H-2B WORKERS WILL NO LONGER BE NEEDED TO SUPPLEMENT OUR
PERMANENT U.S. WORKFORCE.
2 Citations in this Decision to the appeal file are abbreviated as “AF” followed by the page number.
3
THREE ADDITIONAL LINE COOKS ARE NEEDED . . . . OUR CURRENT KITCHEN STAFF
CAN SUPPORT THE EXISTING OPERATION, BUT NOT THE ADDITIONAL WORKLOAD
AND LONGER OPERATING HOURS DURING THE EXPANSION AND RAMP-UP PERIOD.
THE THREE LINE COOKS ARE NEEDED TO PROVIDE PROPER STATION COVERAGE,
SHIFT ROTATION, AND DAYS-OFF COVERAGE WHILE SUPPLEMENTING OUR CURRENT
U.S. WORKFORCE.
DURING THE OFF-SEASON, THE RESTAURANT MAINTAINS ITS REGULAR PERMANENT
STAFF FOR NORMAL YEAR-ROUND OPERATIONS. . . . THE ADDITIONAL H-2B . . . WILL
SUPPLEMENT, NOT REPLACE, OUR REGULAR PERMANENT EMPLOYEES.
THESE THREE WORKERS WILL NOT BECOME PART OF THE RESTAURANTS
PERMANENT YEAR-ROUND STAFFING BECAUSE THEIR NEED IS TIED ONLY TO THE
TEMPORARY EXPANSION AND RAMP-UP PERIOD. AFTER THE ADJACENT-SPACE
EXPANSION IS COMPLETED, EXTENDED-HOUR DEMAND STABILIZES, AND REGULAR
STAFFING LEVELS ARE ADJUSTED, THE RESTAURANT EXPECTS TO OPERATE WITH ITS
NORMAL PERMANENT STAFF. . . .
AF 150.
B. The CO’s Final Determination
The CO denied Employer’s application for two states reasons: (1) failure to establish the
job opportunity as temporary in nature; and (2) failure to establish temporary need for the
number of workers requested. AF 31, 35. Before denying Employer’s application, the CO issued
a Notice of Deficiency (NOD). See AF 133-143. The NOD explained the purported deficiencies
with the application and listed specific information and documents the Employer should submit
to overcome the stated deficiencies. See id.3
Employer submitted a written response to the CO addressing the NOD. AF 39.
Employer’s response was accompanied by supporting documents, including: (1) its business
history and operations statement, annual operating schedule, line cook payroll and staffing
records, Forms 941, food and beverage sales records, tax records, and its Xiao Long Bao menu
launch and employee training plan (Launch & Training Plan). See AF 39-132. In response to
deficiency nos. 1 and 2, the response itself merely states: “The Employer’s supporting materials
explain the temporary increase in kitchen labor associated with the planned menu rollout,
training, operational transition, and increased business activity during the requested period.”
AF 39. Discussion of the CO’s analysis of supporting documents is provided below.
II. DISCUSSION AND APPLICABLE LAW
3 The NOD lists a deficiency that is not included in the Final Determination. The Board assumes that the
deficiency not included in the Final Determination was cured by Employer. The Board will not address
cured deficiencies in this Decision as they are not bases for the Final Determination.
4
A. Applicable Regulations
The Board’s standard of review in H-2B cases is limited. The Board may only consider
the appeal file prepared by the CO, the legal briefs submitted by the parties, and the
Employer’s request for administrative review, which may only contain legal arguments and
evidence that the Employer actually submitted to the CO before the date the CO issued a final
determination. 20 C.F.R. § 655.61. After considering the evidence of record, the Board must: (1)
affirm the CO’s determination; (2) reverse or modify the CO’s determination; or (3) remand the
case to the CO for further action. 20 C.F.R. § 655.61(e).
The Employer bears the burden of proving that it is entitled to temporary labor
certification. 8 U.S.C. § 1361; see Alter & Son Gen. Eng’g, 2013-TLN-00003, slip op. at 4 (Nov. 9,
2012); BMGR Harvesting, 2017-TLN-00015, slip op. at 4 (Jan. 23, 2017). To obtain certification
under the H-2B program, Employer must establish that its need for workers qualifies as
temporary under one of the four temporary need standards: one-time occurrence, seasonal,
peakload, or intermittent. 20 C.F.R. §§ 655.6(b), 655.11(a)(3).
The applicable regulation at 8 C.F.R. § 214.2(h)(6)(ii) provides:
(A) Definition. Temporary services or labor under the H-2B classification
refers to any job in which the petitioner’s need for the duties to be
performed by the employee(s) is temporary, whether or not the underlying
job can be described as permanent or temporary.
(B) Nature of petitioner’s need. Employment is of a temporary nature when
the employer needs a worker for a limited period of time. The employer
must establish that the need for the employee will end in the near, definable
future. Generally, that period of time will be limited to one year or less, but
in the case of a one-time event could last up to 3 years. The petitioner’s need
for the services or labor shall be a one-time occurrence, a seasonal need, a
peak load need, or an intermittent need.
* * *
(3) Peakload need. The petitioner must establish that it regularly employs
permanent workers to perform the services or labor at the place of employment and
that it needs to supplement its permanent staff at the place of employment on a
temporary basis due to a seasonal or short-term demand and that the temporary
additions to staff will not become a part of the petitioner's regular operation.4
4 Additionally, 20 C.F.R. § 655.6 provides:
5
B. The CO’s Determination is Not Arbitrary and Capricious
Review of the CO’s determination of H-2B applications is governed by the “arbitrary and
capricious” standard. Three Seasons Landscape Contracting Service, Inc., 2016-TLN-00045, slip
op. at 19 (Jun. 15, 2016); Brooks Ledge, Inc., 2016-TLN-00033, slip op. at 4-5 (May 10, 2016).
Under the arbitrary and capricious standard, if there is any rational basis for the CO’s
determination, it must be sustained. See Dellew Corp. v. United States, 108 Fed. Cl. 357, 368
(Fed. Cl. 2012); Erinys Iraq Ltd. v. United States, 78 Fed. Cl. 518, 525 (Fed. Cl. 2007); see also
Spokane County Legal Services, Inc. v. Legal Services Corp., 614 F.2d 662, 669, n.11 (9th Cir.
1980).
Employer argues that the CO erred by focusing on Employer’s asserted seasonal basis
for its need rather than its planned implementation, testing, training, and stabilization period
for the rollout of its machine-assisted Xiao Long Bao production (Bao Production Plan). Thus,
the CO did not adequately consider Employer’s alternative basis for its alleged peakload need –
its Bao Production Plan. Empl. Br. 4-7. Employer also essentially argues that the CO gave too
much weight to certain documents in her consideration while failing to consider others. Id. at 7-
8. Lastly, Employer argues that the record demonstrates all the elements of peakload need. Id.
at 8-9.
In deciding that Employer failed to establish the job opportunity as temporary in nature
(deficiency no. 1), the CO stated that the submitted Annual Schedule of Operations “is a
document that is based on the employer’s annual kitchen activity that separates monthly the
number of permanent line cooks and the additional hours worked.” AF 34. However, the
Annual Schedule of Operations does not show “the additional hours worked.” Rather, it shows
the additional hours needed during the rollout of Employer’s Bao Production Plan. See AF 46.
This error is not significant enough, when all the submitted documentation is considered, to
undermine the reasonableness of the CO’s conclusion regarding Employer’s seasonal need.
In analyzing the submitted Monthly Line Cook Payroll Summary and Explanation, the CO
states that the “hourly breakdown information shows that not all permanent workers were
working full-time hours at all times, let alone indicate any increase in hours worked above
normal business operations during the period requested compared to the months of no need.”
(a) An employer seeking certification under this subpart must establish that its need for
non-agricultural services or labor is temporary, regardless of whether the underlying job
is permanent or temporary.
(b) The employer's need is considered temporary if justified to the CO as one of the
following: A one-time occurrence; a seasonal need; a peakload need; or an intermittent
need, as defined by DHS regulations. Except where the employer's need is based on a
one-time occurrence, the CO will deny a request for an H-2B Registration or an
Application for Temporary Employment Certification where the employer has a need
lasting more than 9 months.
6
AF 34. The CO is correct regarding not all permanent workers working full-time hours at all
times. And, depending upon how the data is analyzed, the CO is correct about the hours
worked because there are months in Employer’s non-peak period (July through September)
that have greater hours worked by its line cooks than in certain months during its peak period
(October through June). The CO used a reasonable method of analyzing this data.
However, looking at the hours worked in a more aggregate fashion shows that the
average monthly hours worked by Employer’s line cooks during the peak period for 2024 was
645.84 hours compared to 596.06 average monthly hours during the non-peak period that year.
Similarly, the average monthly hours worked by Employer’s line cooks during the peak period
for 2025 was 672.8 hours compared to 407.26 average monthly hours that year.5 Had the CO
used this method of analyzing the data, she might have reached a different conclusion.
Nonetheless, the fact that the CO chose one reasonable method of analyzing certain data, i.e.,
the Monthly Line Cook Payroll Summary and Explanation, to the exclusion of another
reasonable method does not make her determination arbitrary and capricious.
The CO’s analysis of additional submitted documents also compares months within
Employer’s peak period compared with its non-peak period. And, the CO’s analysis of those
documents supports her conclusion regarding Employer having failed to establish a seasonal
basis in support of its claimed Peakload need.
With respect to Employer’s argument that the CO did not adequately consider
Employer’s alternative basis for its alleged peakload need – its Bao Production Plan, the CO’s
discussion of the Bao Production Plan consists of the following:
The employer indicates that its need is due to the business expansion, "transitioning
from primarily handmade production to machine-assisted Xiao Long Bao
production", and implementation and employee training period, which afterwards
the employer's permanent workforce will be able to incorporate the production into
its normal business operation and temporary workers are no longer need. However,
the employer also indicates that it "anticipates increased restaurant activity
associated with the South Florida fall, winter and spring business seasons, including
increased traffic from seasonal residents, visitors, tourists, holiday diners and local
customers" in addition to its business expansion and "permanent soup dumpling/
Xiao Long Bao, menu machine production rollout project." Therefore, it remains
unclear what events cause a seasonal or short-term demand that create the
employer's need "to supplement its permanent staff at the place of employment
on a temporary basis." No clear supporting documentation to establish an increase
of business operations during period requested due to increased traffic or South
Florida fall, winter and spring business seasons.
5 Monthly Line Cook Payroll Summary and Explanation provides information for 2026 for only January
through July.
7
AF 35 (boldface added). The Board interprets the CO’s reasoning as follows: Employer failed to
demonstrate that it needs three additional line cooks on a temporary basis because of seasonal
demand, and thus, it also necessarily failed to demonstrate such need because of a short-term
demand.
Employer’s argument that the CO must determine whether either a seasonal demand or
a short-term demand justifies its alleged need is undercut by its own documentation.
Specifically, the Employer Business History and Business Activities Statement states that:
[T]he employer anticipates increased restaurant activity associated with the South
Florida fall, winter and spring business seasons . . . . At the same time, WoodOne
Ramen will be carrying out a permanent soup dumpling/ Xiao Long Bao, menu
machine-production rollout project.
The rollout project will include recipe testing, production setup, employee training,
limited menu introduction, full menu launches and operational stabilization by
machine. These temporary activities, together with the anticipated seasonal
increase in customer orders, will require additional kitchen labor hours beyond the
capacity of the employer’s normal permanent Line Cook workforce.
AF 43-44. Seasonal demand and short-term demand are not presented to the CO as alternative
bases for Employer’s alleged temporary need. Rather, each type of demand is conglomerated
to justify Employer’s alleged need. Thus, when one type of demand, seasonal, is not proven the
other type, short-term, necessarily also fails to offer independent, adequate justification for
Employer’s alleged need.6
The CO examined the data relevant to deficiency no. 1 and articulated a satisfactory
explanation for her denial of Employer’s application based on deficiency no. 1. The CO’s
explanation is consistent with the evidence. Thus, the CO’s decision was rational and supported
by the evidence. It was not arbitrary and capricious.
Because the Board affirms the CO’s decision based upon deficiency no. 1, there is no
need to address whether the CO’s decision based upon deficiency no. 2 is arbitrary and
capricious. Because the arbitrary and capricious standard requires that the CO’s determination
be sustained if there is any rational basis for it, the Board must affirm the CO’s denial decision.
See Dellew Corp., 108 Fed. Cl. at 368; Erinys Iraq Ltd., 78 Fed. Cl. at 525; see also Spokane
County Legal Services, Inc., 614 F.2d at 669, n.11.
6 Had Employer made it clear that its Bao Production Plan did not depend upon its alleged increase in
seasonal demand at all, and that the Bao Production Plan and its alleged seasonal demand were two
completely separate and independent basis for its alleged need, the outcome of this appeal may have
been different.
8
III. ORDER
For the foregoing reasons, it is ORDERED that the Certifying Officer’s Final
Determination denying certification is AFFIRMED.
For the Board:
Jason A. Golden
Administrative Law Judge