AC 47464•Angiolillo v. Nevard
Full text
************************************************ The “officially released” date that appears near the beginning of an opinion is the date the opinion will be published in the Connecticut Law Journal or the date it is released as a slip opinion. The operative date for the beginning of all time periods for the filing of postopinion motions and petitions for certification is the “officially released” date appearing in the opinion. All opinions are subject to modification and technical correction prior to official publication in the Connecti- cut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports. In the event of discrepancies between the advance release version of an opinion and the version appearing in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports, the latest version is to be considered authoritative. The syllabus and procedural history accompanying an opinion that appear in the Connecticut Law Journal and subsequently in the Connecticut Reports or Connecticut Appellate Reports are copyrighted by the Secretary of the State, State of Connecticut, and may not be reproduced or distributed without the express written permission of the Commission on Official Legal Publications, Judicial Branch, State of Connecticut. ************************************************
Angiolillo v. Nevard GLENN ANGIOLILLO ET AL. v. BARRETT NEVARD ET AL. (AC 47464) Alvord, Moll and Seeley, Js.* Syllabus The plaintiffs appealed from the trial court’s judgment for the defendants on the plaintiffs’ complaint for, inter alia, breach of contract, and in part on the defendants’ counterclaim seeking a declaratory judgment, in connection with two real estate sales contracts for two of the defendants’ properties. The plaintiffs claimed, inter alia, that the court improperly interpreted various provisions of the parties’ contracts. Held: The trial court properly interpreted the contracts to set January 16, 2019, as the extended closing deadline following the defendant B’s extension of the original closing date, as the contracts, in clear and unambiguous terms, established January 16, 2019, as the extended closing deadline, and this court rejected the plaintiffs’ proposition that the parties had an additional twenty-one days following that date to close on the properties. This court concluded that, although the trial court misconstrued the con- tracts to provide that, with respect to the closing, time was of the essence, that error did not warrant reversal of the court’s judgment against the plaintiffs as they alleged, as the error was not integral to its adjudication of the plaintiffs’ claims or the defendants’ counterclaim. The plaintiffs’ claim that there was no contractual basis to determine that they made an implied election to terminate the contracts failed, as the con- tracts did not designate any particular method by which the plaintiffs must make an election to accept or reject such title as B could convey, and there was nothing in the contracts that prohibited a determination that, through their conduct, the plaintiffs made an implicit election to cancel the contracts. There was an adequate factual basis supporting the trial court’s determination that the plaintiffs made an implied election of cancellation of the contracts, as it was reasonable for B to have concluded that the plaintiffs’ conduct in commencing the present action indicated an unwillingness to proceed with the purchase of both properties in light of a title defect with respect to one of the properties, and the passage of the extended closing deadline also sup- ported that determination. Argued December 9, 2025—officially released September 29, 2026 *The listing of judges reflects their seniority status on this court as of the date of oral argument.
Angiolillo v. Nevard Procedural History Action to recover damages for, inter alia, breach of contract, and for other relief, brought to the Superior Court in the judicial district of Stamford-Norwalk, where the defendants filed a counterclaim; thereafter, the case was tried to the court, Hon. Kenneth B. Povodator, judge trial referee; judgment for the defendants on the amended complaint and in part on the counterclaim, from which the plaintiffs appealed to this court. Affirmed. Karen L. Dowd, with whom was Kenneth J. Bartschi, for the appellants (plaintiffs). Edward N. Lerner, for the appellees (defendants). Opinion MOLL, J. The plaintiffs, Glenn Angiolillo (Glenn) and Gian Angiolillo (Gian), appeal from the judgment of the trial court rendered in favor of the defendants, Barrett Nevard, the Leila B. Nevard Living Trust, and Susan J. Nevard,1 with respect to the plaintiffs’ amended com- plaint and in part as to the defendants’ counterclaim. On appeal, the plaintiffs claim that the court improperly (1) interpreted the real estate sales contracts at issue and (2) determined that Barrett properly treated their conduct as demonstrating an “implied” contractual election to terminate the contracts. We affirm the judgment of the trial court. 1The summons filed in the present action lists two defendants: (1) Barrett Nevard; and (2) “Susan J. & Leila B. Nevard Living Trust.” The plaintiffs’ original and amended complaints, however, reference three defendants: (1) Barrett Nevard; (2) the Leila B. Nevard Living Trust, with Barrett Nevard acting as trustee or cotrustee; and (3) Susan J. Nevard. The parties’ respective pleadings and appellate briefs further reflect an apparent understanding that there are three defendants in the present action, with Susan J. Nevard being distinct from the Leila B. Nevard Living Trust. This discrepancy is not germane to our analy- sis of the plaintiffs’ claims on appeal. In the interest of simplicity, we refer in this opinion to (1) Barrett Nevard, the Leila B. Nevard Living Trust, and Susan J. Nevard collectively as the defendants and (2) the individual parties by first name.
Angiolillo v. Nevard The following undisputed facts, as found by the trial court or as gleaned from the record, and procedural history are relevant to our resolution of this appeal. In September 2018, the plaintiffs and Barrett executed two real estate sales contracts (contracts), with one contract governing the sale of 19 Henry Street in Greenwich (19 Henry Street contract) and the other contract govern- ing the sale of 23 Henry Street in Greenwich (23 Henry Street contract).2 Before executing the contracts, Barrett represented to the plaintiffs that both properties were three-family dwellings. The plaintiffs made a $132,000 deposit in accordance with the contracts. The contracts, which are substantially identical in terms, contain the following relevant provisions. Para- graph 4 of the contracts provides in relevant part that the respective property deed “shall be delivered . . . on the 17th day of December, 2018, at 2:00 P.M. or sooner by mutual agreement of the parties . . . .” Moreover, the contracts provide that the closing on one property is con- tingent on a simultaneous closing on the other property. Paragraph 6 (a) of the contracts provides in relevant part: “If, upon the date for the delivery of the [respective property] deed . . . [Barrett] shall be unable to deliver or cause to be delivered a deed or deeds conveying a good and marketable title to the [respective property], subject only to the items set forth in Schedule A3 and [p]aragraph [6 (e)]4 . . . then [Barrett] shall be allowed a reasonable 2The court found that “[t]he parties” entered into the contracts. The contracts, which were admitted in full into the record, identify Barrett as the seller of the properties; however, the contracts further reflect that Susan J. Nevard and the Leila B. Nevard Living Trust had interests in one or both properties in September 2018, and the contracts contemplate certain deeds being “duly executed and recorded on the Greenwich [l]and [r]ecords thereby establishing 100 [percent] owner- ship in Barrett . . . .” In the interest of simplicity, we refer to Barrett as the seller of the properties. 3Schedule A appended to each contract sets forth a description of the respective property and provides that said property is to be conveyed subject to, inter alia, “[a]ny and all provisions of any ordinance, munici- pal regulation or public or private law.” 4Paragraph 6 (e) of the contracts provides that the respective prop- erty will be conveyed subject to, inter alia, governmental restrictions,
Angiolillo v. Nevard postponement of closing not to exceed thirty (30) cal- endar days, or such shorter time as may be within the term of the [plaintiffs’] mortgage commitment, within which to perfect title. If at the end of said time [Bar- rett] is still unable to deliver or cause to be delivered a deed or deeds conveying a good and marketable title to [the respective property], subject as aforesaid, then the [plaintiffs] (i) may elect to accept such title as [Barrett] can convey, without modification of the purchase price, or (ii) may reject such title. Upon such rejection, all sums paid on account hereof, together with any nonrefundable expenses actually incurred by the [plaintiffs] in the aggre- gate not to exceed the cost of an A.L.T.A. Homeowner’s Policy (or the equivalent thereof) based on the amount of the purchase price shall be paid to the [plaintiffs] without interest thereon. Upon receipt of such payment, [the respective contract] shall terminate and the parties . . . shall be released and discharged from all further claims and obligations [t]hereunder. [Barrett] shall be entitled to require [the plaintiffs] to provide reasonable proof of payment of said expenses.” (Footnotes added.) Paragraph 16 of the contracts provides in relevant part: “In no event shall the closing, or any extension thereof, take place later than twenty-one (21) calendar days from the date of closing set forth in [p]aragraph 4 . . . subject to the provisions of [p]aragraphs 6 and 11.5 . . .” (Footnote added.) Paragraph 26 of the contracts provides in relevant part: “[A]ll representations by [Barrett] are made to the best of [Barrett’s] knowledge and belief and without duty of inquiry. [Barrett] shall have an affirmative obligation to notify [the plaintiffs] if any of [the] representations [made in the respective contract] are no longer true. Except in the event of an intentional misrepresentation, limitations, regulations, ordinances, and/or public laws, provided that said property is not in violation of the same at the time of the closing. 5Paragraph 11 of the contracts concerns risk of loss or damage by fire or other casualty. As the trial court, Hon. Kenneth B. Povodator, judge trial referee, determined, and we agree, the provisions of paragraph 11 are immaterial to the claims adjudicated in the present action.
Angiolillo v. Nevard if [the plaintiffs discover] prior to the closing of title any material representation contained in [the respective contract] . . . to be untrue or inaccurate, the remedy of the parties shall be those available to them in the event of a valid defect in or objection to title, as set forth in paragraph [6 (a)] . . . .” Attached to and incorporated into the contracts is a purchaser’s rider, which provides in relevant part: “[Bar- rett] represents that all certificates of occupancy or other governmental approvals in connection with the current use of the [respective property] as three residential units . . . have been obtained. . . . If, prior to [c]losing, [the plaintiffs learn] that a violation exists, the remedy of the parties shall be those available to them in the event of a defect in title. Notwithstanding the foregoing, [Bar- rett] shall have a good faith obligation to cure any and all violations prior to [c]losing.” On November 2, 2018, the plaintiffs6 emailed Barrett’s real estate attorney, Christopher A. Kristoff, raising a concern as to whether the 23 Henry Street property was approved by the town of Greenwich (town) to be a three- family dwelling and requesting proof of such approval. On November 6, 2018, Attorney Kristoff replied that “the [t]own carrie[d] [the 23 Henry Street property] as a [three-family dwelling] . . . .” On December 4, 2018, Attorney Kristoff emailed Glenn a letter stating that the town’s building department identified the 23 Henry Street property as a two-family dwelling, such that Barrett did “not have ‘all certifi- cates of occupancy or other governmental approvals in connection with the current use of the [p]remises as three residential units’ ” as required under the 23 Henry Street contract. This letter further stated that “[i]t is [Barrett’s] position that this represents a defect in title that cannot be cured under the [t]own’s current [b]uilding [c]ode and [z]oning laws. Now that [the plaintiffs have] 6The November 2, 2018 email was sent by Glenn with Gian copied on the email. In the interest of simplicity, we treat emails sent to or by Glenn with Gian copied as having been sent to or by the plaintiffs collectively.
Angiolillo v. Nevard this information, unless [the plaintiffs are] prepared to close simultaneously on both [properties] . . . [Barrett] is prepared to return to [the plaintiffs] all sums paid under the [c]ontract[s] . . . .” Additionally, this letter stated that, until the aforementioned issue was resolved, Bar- rett could not confirm a closing that had been scheduled for December 10, 2018, with respect to the 19 Henry Street property.7 On December 7, 2018, the plaintiffs emailed Attorney Kristoff stating that Barrett was obligated to close on the 19 Henry Street property, and, if he refused to close on December 10, 2018, the plaintiffs “intend[ed] to pursue all of their legal remedies . . . .” Additionally, as to the 23 Henry Street property, the plaintiffs stated in relevant part that (1) pursuant to the 23 Henry Street contract, Barrett had a good faith obligation to cure any and all violations prior to closing, (2) Barrett had not informed the plaintiffs as to what steps had been taken to cure the “violation” caused by the 23 Henry Street property not being approved by the town as a three-family dwelling, and (3) Barrett’s failure to cure this “violation” consti- tuted a breach of the 23 Henry Street contract. On December 14, 2018, Attorney Kristoff emailed the plaintiffs an offer to reduce the price of the 23 Henry Street property by $25,000.8 The plaintiffs “apparently rejected” this offer. On December 17, 2018, the original closing date identi- fied in the contracts, Attorney Kristoff emailed a letter to 7In a December 3, 2018 email to Attorney Kristoff, which was admit- ted in full into the record, the plaintiffs, in accordance with a provision in the 19 Henry Street contract, provided advance notice to Barrett that a closing on the 19 Henry Street property was to be scheduled for December 10, 2018. 8In the December 14, 2018 email, which was admitted in full into the record, Attorney Kristoff further requested that (1) the $25,000 price reduction be effectuated by way of an amendment to the 23 Henry Street contract, (2) other provisions of the 23 Henry Street contract be amended with respect to “the [three] family and violation issues,” (3) the parties agree to mutual releases “given the threat of lawsuits,” and (4) the parties close on both properties on December 21, 2018.
Angiolillo v. Nevard the plaintiffs, which letter was addressed to Glenn only, (1) maintaining that a title defect existed as to the 23 Henry Street property and (2) exercising Barrett’s right under paragraph 6 (a) of the contracts to “a reasonable postponement of the closing not to exceed thirty (30) calendar days . . . within which to perfect title by seek- ing a variance with the [t]own to convert [the] 23 Henry Street [property] to a [three]-family house.” Attorney Kristoff further represented that, alternatively, “[Bar- rett] is prepared to return to [the plaintiffs] all sums paid under the [c]ontract[s] pursuant to the terms of said [paragraph 6 (a)], should [the plaintiffs] so desire.” On December 19, 2018, Attorney Kristoff emailed a letter to Glenn accompanied by a copy of a zoning viola- tion notice that he had received with respect to the use of the 23 Henry Street property as a three-family dwelling. This letter stated that (1) on the basis of communications with the town’s zoning enforcement officer about apply- ing for a variance to permit the 23 Henry Street property to be utilized as a three-family dwelling, “all indications are that the [t]own would deny that request based upon current [r]egulations,” and (2) Barrett had decided to submit an application seeking the town’s approval to treat the third unit at the 23 Henry Street property as an affordable housing unit under the town’s regulations, and he was “cautiously optimistic” about securing such approval, “thereby allowing [him] to perfect title and move forward with a simultaneous closing o[n] [both properties] within a reasonable time.” Additionally, this letter requested that Glenn inform Attorney Kristoff if he “object[ed] to this approach or prefer[red] [that Bar- rett] . . . return all sums paid under the [c]ontract[s] . . . .” The plaintiffs subsequently rejected this proposal. On December 26, 2018, Glenn emailed Attorney Krist- off requesting a phone call, whereupon he received an automatic response reflecting that Attorney Kristoff was out of the office from December 21, 2018, through January 2, 2019. On January 7, 2019, Attorney Kristoff emailed a letter to Glenn setting forth a “ ‘final offer’ ” to
Angiolillo v. Nevard be effectuated by way of an amendment to the 23 Henry Street contract (January 7, 2019 letter). The January 7, 2019 letter proposed in relevant part that (1) the price for the 23 Henry Street property be reduced by $30,000, (2) the plaintiffs acknowledge that a title defect exists as to the 23 Henry Street property that Barrett can- not cure, (3) the plaintiffs accept title to the 23 Henry Street property with the title defect, and (4) the parties exchange mutual releases. The January 7, 2019 letter further provided that (1) “[n]o agreement exists unless and until the [p]arties have executed and exchanged an amendment to the [23 Henry Street] [c]ontract” and (2) “[i]n the alternative, if these terms are not acceptable, [Barrett] will take the position that the defect in title cannot be cured and will return to [the plaintiffs] all sums paid under the [c]ontract[s] per [p]aragraph [6 (a)].” On January 15, 2019, the plaintiffs commenced the present action. On January 16, 2019, Attorney Kristoff sent a letter to Glenn (January 16, 2019 letter). Attor- ney Kristoff stated that he was interpreting the lack of a response to the January 7, 2019 letter “as a rejection of [the defective] title [to the 23 Henry Street property] per paragraph [6 (a)] of the [c]ontract[s]” and that he was enclosing a check in the amount of $132,000, thereby tendering a return of the plaintiffs’ deposit on both properties. Thus, by way of the January 16, 2019 letter, Barrett withdrew the offer proposed in the January 7, 2019 letter and deemed the contracts to be terminated. In their amended complaint dated July 3, 2023, which was the operative complaint,9 the plaintiffs asserted claims for (1) breach of contract and (2) breach of the implied covenant of good faith and fair dealing.10 In support of their breach of contract claim, the plain- tiffs alleged that (1) the defendants failed, refused, or 9The plaintiffs filed the amended complaint with leave of the trial court, Hon. Kenneth B. Povodator, judge trial referee. 10The amended complaint also set forth counts sounding in (1) fraud, (2) so-called “fraud by negligent misrepresentation,” and (3) a viola- tion of the Connecticut Unfair Trade Practices Act, General Statutes § 42-110a et seq. These counts are not relevant to this appeal.
Angiolillo v. Nevard neglected to convey the title to the 19 Henry Street prop- erty to them notwithstanding that they had informed the defendants that they were ready, willing, and able to consummate the 19 Henry Street contract and to close on December 10, 2018, and (2) the defendants failed to comply with various provisions of the 23 Henry Street contract and made a materially false representation that the 23 Henry Street property was a three-family dwell- ing. In support of their breach of the implied covenant of good faith and fair dealing claim, the plaintiffs alleged that the defendants had acted in bad faith by misleading and misrepresenting the legal use and value of the 23 Henry Street property, “refusing to cure the defects,” and failing to adjust the price of the 23 Henry Street property. The amended complaint also contained a stand- alone count seeking specific performance with respect to both properties.11 On June 5, 2019, the defendants filed an answer denying the plaintiffs’ material allegations or leaving the plaintiffs to their proof.12 Additionally, on June 5, 2019, the defendants filed a two count counterclaim (1) seeking a declaratory judg- ment that the contracts had been terminated and (2) alleging slander of title. On June 14, 2019, the plaintiffs filed an answer denying the defendants’ material allega- tions or leaving the defendants to their proof. 11In their original complaint, the plaintiffs sought specific performance with respect to the 19 Henry Street property only. In their amended com- plaint, the plaintiffs sought specific performance as to both properties. 12The defendants also asserted special defenses as to each claim asserted by the plaintiffs. On June 14, 2019, the plaintiffs filed a reply denying the defendants’ special defenses. The defendants’ answer and special defenses were directed to the plaintiffs’ original complaint. The defendants did not plead further. See Practice Book § 10-61 (“When any pleading is amended the adverse party may plead thereto within the time provided by Section 10-8 or, if the adverse party has already pleaded, alter the pleading, if desired, within ten days after such amendment or such other time as the rules of practice, or the judicial authority, may prescribe, and thereafter pleadings shall advance in the time provided by that section. If the adverse party fails to plead further, pleadings already filed by the adverse party shall be regarded as applicable so far as possible to the amended pleading.”).
Angiolillo v. Nevard The case was tried to the court, Hon. Kenneth B. Povo- dator, judge trial referee, on July 6 and 7, 2023. The court heard testimony from several witnesses and admit- ted various exhibits into the record. Following trial, the parties filed posttrial briefs. On February 26, 2024, the court issued a memorandum of decision rendering judgment in the defendants’ favor with respect to (1) the entirety of the plaintiffs’ amended complaint and (2) the portion of their counterclaim seek- ing declaratory relief.13 The court made the following relevant findings and conclusions. Barrett’s representa- tion to the plaintiffs that the 23 Henry Street property was a three-family dwelling constituted an unintentional misrepresentation, which created a “defect-in-title” issue subject to paragraph 6 (a) of the contracts. With respect to the closing, the contracts (1) provide that time was of the essence and (2) authorize Barrett to exercise an option for a single extension of the original closing date for up to thirty days (that is, up to January 16, 2019), in order to perfect a defective title, which option Barrett exercised. In the weeks leading up to January 16, 2019, the plaintiffs made “no substantive communications that might be characterized as the [plaintiffs partici- pating] in an [attempt] to resolve the [title defect] issue . . . .” (Internal quotation marks omitted.) In contrast, Barrett made “documented efforts . . . to keep the plain- tiffs informed about [his] efforts to correct the problem and propos[ed] alternatives . . . .” Specifically, Barrett proposed (1) applying for approval to convert the third unit at the 23 Henry Street property into an affordable housing unit, which the plaintiffs rejected, (2) applying for approval to convert the 23 Henry Street property into a legal three-family dwelling, which, as Barrett reason- ably determined, was not a reasonably feasible option “based on the high likelihood of it being unsuccessful (with time and expense presumably to be incurred in a likely futile effort)”; (footnote omitted); (3) structurally 13The court rendered judgment in the plaintiffs’ favor on the portion of the defendants’ counterclaim alleging slander of title. The defendants have not cross appealed from that portion of the judgment.
Angiolillo v. Nevard converting the 23 Henry Street property into a legal two- family dwelling, which “[t]here had been no indication of any willingness of the plaintiffs to accept” and which, as Barrett reasonably determined, was not a reasonably feasible option because “there was no credible evidence that the entire process of [evicting the tenant of the third unit] and renovation could be accomplished in a reason- able time and at a reasonable cost,” and (4) amending the 23 Henry Street contract, inter alia, to reduce the price of the 23 Henry Street property by $25,000, which the plaintiffs “apparently rejected . . . .” Subsequently, by way of the January 7, 2019 letter, Barrett offered to amend the 23 Henry Street contract, inter alia, by reducing the price of the 23 Henry Street property by $30,000, but “the [plaintiffs’] only known ‘answer’ to the offer” was the commencement of the present action on January 15, 2019. Barrett reasonably construed the commencement of the present action as a rejection of the offer proposed in the January 7, 2019 letter, as well as to the sales contemplated by the con- tracts as executed. Rather than electing one of the two options available to them under paragraph 6 (a) of the contracts following Barrett’s inability to cure the title defect as to the 23 Henry Street property—accepting the defective title to the 23 Henry Street property as is or rejecting said title and cancelling the contracts—“[t]he plaintiffs appar- ently elected a third option [which was to] do nothing, insist that [Barrett] had not done enough or offered to do enough, [and] start litigation, all the while stating that they were under no obligation to make an election of the contract option they chose to assert.” Indeed, there was no evidence that, at any relevant time, the plaintiffs were willing to elect a contractually designated remedy in response to Barrett’s failure to cure the title defect. Moreover, there was no credible evidence reflecting that, prior to amending their original complaint in the present action in 2023, the plaintiffs were willing to proceed with a closing on both properties with the title defect in place
Angiolillo v. Nevard or in accordance with the offer proposed in the January 7, 2019 letter.14 In contrast, Barrett was willing either to proceed with a closing on both properties, including at a reduced price, with the title defect in place or to refund the plaintiffs’ deposit. Additionally, the January 16, 2019 letter “technically might be considered to have been ‘early’ by a matter of hours,” as the extended closing deadline expired on Janu- ary 16, 2019. Nevertheless, “[a]s a practical matter, that [was] of no consequence [because] [t]here was no evidence that anyone was prepared to go forward with a closing on January 16, 2019, but for the [January 16, 2019] letter, with an overlay of no evidence that the plaintiffs would have been willing to go forward with a closing on [the] 23 Henry Street [property] based on the situation then existing.” As to the plaintiffs’ breach of contract claim, the court concluded that the defendants did not materially breach the contracts. First, insofar as the plaintiffs asserted that the defendants breached the contracts by failing to convey the 19 Henry Street property separately from the 23 Henry Street property, the court determined that the contracts expressly required that both properties be conveyed simultaneously, such that the plaintiffs were not entitled to a standalone sale of the 19 Henry Street property. Second, insofar as the plaintiffs asserted that the defendants breached the contracts by failing to sched- ule a closing on or before January 16, 2019, the court determined that there was no evidence that the plaintiffs were prepared to proceed with a closing on both properties on or before that date, ergo no closing could have been scheduled. Third, insofar as the plaintiffs asserted that the defendants breached the contracts by failing to cure the title defect regarding the 23 Henry Street property prior to January 16, 2019, the court iterated that (1) 14The court determined that the plaintiffs made a “strategic and intentional” decision to seek specific performance with respect to the 19 Henry Street property only in their original complaint, whereas they sought specific performance with regard to both properties in their amended complaint. See footnote 11 of this opinion.
Angiolillo v. Nevard the contracts permitted Barrett to extend the closing up to January 16, 2019, and (2) there were no feasible options to correct the defect within a reasonable period of time, even if January 16, 2019, were not the “outer limit for a closing . . . .”15 Fourth, insofar as the plaintiffs asserted that the defendants breached the contracts by withdrawing the offer proposed in the January 7, 2019 letter to sell the 23 Henry Street property at a reduced price, the court determined that the offer “was not part of any existing obligation, but it tend[ed] to reinforce the desire of [Barrett] to proceed with the transaction, even with a price adjustment not required or suggested as part of the contract performance obligation of [Bar- rett]. It [was] a measure of good faith in attempting to make the deal feasible.” Additionally, the court rejected the plaintiffs’ request for specific performance with respect to both properties because “[t]here [was] no breach that would support such a remedy. [Barrett was] not only willing to proceed with the . . . contracts as a package, as intended by the provisions of the [contracts], but extracontractually [he] had offered to reduce the price for [the] 23 Henry Street [property]. The court has concluded that [he] reasonably concluded, in good faith, that it was unlikely that [he] could obtain a change in legal characterization of the [23 Henry Street] property from the [town’s] appropri- ate land use agency . . . and that other options were not 15The court further determined that one of the corrective options proposed by Barrett—structurally converting the 23 Henry Street property into a legal two-family dwelling—would not cure the title defect because “[t]he defect was the representation that the structure could legally be used as a three-unit structure and removal of a unit would not correct the defect to the extent that the defect properly is characterized as a representation that the [23 Henry Street] property legally could have three tenants. Simplistically, this would eliminate any illegality of use of the structure, but would not cure the inaccurate and improper representation that the [23 Henry Street] property could legally be used for occupancy by three tenants . . . . In a sense, then, this would be similar to the price reduction proposal—a possible means to facilitate the transaction but requiring something in the nature of a modification to the [23 Henry Street contract] rather than a cure of a contractually defined title defect.”
Angiolillo v. Nevard practical or had been rejected by the plaintiffs.” The court further determined that (1) the plaintiffs were not ready, willing, and able to proceed with a closing on both properties on or before January 16, 2019, and (2) it would be inequitable to order the sale of both properties on the basis of terms negotiated more than five years earlier, particularly as there was no evidence that the plaintiffs had been willing to purchase both properties on an as is basis prior to the commencement of the present action, and in light of the possible impact of the COVID-19 pan- demic on property values.16 As to the plaintiffs’ breach of the implied covenant of good faith and fair dealing claim, the court stated that “[t]here appear to be only two . . . categories of conduct [following the execution of the contracts] seemingly alleged [by the plaintiffs] and presented via evidence.”17 First, the plaintiffs asserted that Barrett did not act diligently in seeking to cure the defect vis-à-vis the 23 Henry Street property, particularly by failing to apply for a variance to permit its use as a three-family dwell- ing. The court determined that Barrett did not act in bad faith in this regard because there were no “reasonable mechanisms for curing the [title defect] in a reasonable time and at a reasonable expense . . . .” With respect to the 16The court also determined that “there were . . . critical gaps—an almost total lack of evidence—as to damages for each of the plaintiffs’ claimed causes of action.” 17Insofar as the plaintiffs relied on Barrett’s misrepresentation regard- ing the 23 Henry Street property to support their breach of the implied covenant of good faith and fair dealing claim, the court rejected that reliance because “conduct before a contract was signed cannot be bad faith performance of that contract.” See Macomber v. Travelers Prop- erty & Casualty Corp., 261 Conn. 620, 638, 804 A.2d 180 (2002) (“It is axiomatic that the . . . duty of good faith and fair dealing is a covenant implied into a contract or a contractual relationship. . . . The covenant of good faith and fair dealing presupposes that the terms and purpose of the contract are agreed upon by the parties and that what is in dispute is a party’s discretionary application or interpretation of a contract term. . . . In accordance with these authorities, the existence of a contract between the parties is a necessary antecedent to any claim of breach of the [cov- enant] of good faith and fair dealing.” (Citations omitted; emphasis omitted; internal quotation marks omitted.)).
Angiolillo v. Nevard plaintiffs’ proposition that Barrett should have applied for a variance, the court “credit[ed] the reasonableness of [Barrett’s] assessment of the situation” and iterated that “an administrative procedure such as that would require some period of time . . . [and] would require an indefinite extension [of the closing] with no assurance of success (or even reasonable basis that the application would be successful).” The court further determined that Barrett acted in good faith by offering to reduce the price of the 23 Henry Street property, comprising “an extracontractual effort to effectuate performance of the contract[s] . . . .” As the court summarized, “there is a failure [by the plaintiffs] to explain how or why offering to comply with contractual remedies—with an added option of an offered adjustment of the sale[s] price for [the] 23 Henry Street [property]—might be considered a breach of the [implied] covenant of good faith and fair dealing. [Barrett] did not do anything that, in bad faith, deprived the plaintiffs of a benefit to which they were entitled under the contracts.” The court next considered the plaintiffs’ contention that Barrett acted in bad faith by deeming the contracts terminated by way of the January 16, 2019 letter. The court stated that the evidence “was equivocal” as to whether the January 16, 2019 letter stemmed directly from the commencement of the present action the day before or “simply coincided with the end of the maxi- mum thirty day extension for a closing”; nevertheless, “to the extent that the commencement of the [present action] may have been the triggering event for deem- ing the contracts terminated . . . the court conclude[d] that that was not a violation of the [implied] covenant of good faith and fair dealing.” As the court elaborated, “[b]eing sued approximately one week after having made an offer to reduce the price for [the] 23 Henry Street [property]—with being served the only known ‘answer’ to the offer—it would not be unreasonable [for Barrett] to interpret that answer as ending discussions, including
Angiolillo v. Nevard rejection of a nonrequired offer to reduce the price.”18 The court further concluded that “[t]he expiration of the thirty day extension for a closing also constituted a good cause basis to terminate the process.”19 Finally, the court addressed the defendants’ request for declaratory relief. The court iterated that, pursu- ant to the contracts, time was of the essence as to the closing. The court continued: “Even if the court were in error in this respect, the [contractual] language relating to an obligation to correct defects in title is subject to a reasonableness or good faith standard, and the plaintiffs offered no credible evidence to counter the conclusion that had been reached by [Barrett] that based on [his] inquiries, it would be futile—with a substantial cost and delay—even to try to obtain formal approval of [the] 23 Henry Street [property] as a legal three-family structure. Absent a reasonable basis to challenge that conclusion, the ‘obvious’ options were to accept the impracticality of that as a solution, or pursue that unlikely to succeed course of action, or leave everything in limbo, indefi- nitely. [Barrett] reasonably relied on the expiration of the authorized thirty day extension [of the closing date] without any prospect for cure, leaving the options of the plaintiffs accepting the [23 Henry Street] property with the [title] defect or the contracts being terminated with the [plaintiffs’] deposit returned. The plaintiffs’ refusal 18In addition, the court determined that there was no credible evidence demonstrating that the plaintiffs made “any attempt to get discussions back on track relating to curing the problem with [the] 23 Henry Street [property] or making the election of remedy as set forth in [paragraph 6 (a) of] the contracts, after [Barrett] returned (tendered return) of the . . . [plaintiffs’] deposit. In other words, even if [Barrett] overreacted, and assuming that the plaintiffs actually did not want to terminate the [contracts], the plaintiffs appear to have taken no steps (no documented steps) to try to restore the relationship to one of cooperatively working towards addressing the problem as to [the] 23 Henry Street [property]; no steps appear to have been taken to convince [Barrett] that [he] had acted rashly.” (Emphasis omitted.) 19In addressing the plaintiffs’ breach of the implied covenant of good faith and fair dealing claim, the court also rejected their assertion that Barrett failed to provide them with material information that they had requested following the execution of the contracts.
Angiolillo v. Nevard to do what was needed—make an election—could not be allowed [as] the status quo [would] persist indefinitely. The refusal of the plaintiffs to make an election under the contract[s], and their decision to commence litiga- tion before the [extended January 16, 2019] deadline [for the closing] had expired, are convincing evidence that the plaintiffs were refusing to make an election (other than insisting that the parties should close on [the] 19 Henry Street [property] and leave the status of [the] 23 Henry Street [property] open, indefinitely, contrary to the intent of the parties . . . that, absent a default, the properties were to be conveyed simultaneously).” Accordingly, the court “declar[ed] that [Barrett] prop- erly treated the plaintiffs’ refusal to make an election to proceed with the purchase of both properties under one of the two options available to them in the case of a defect in title that cannot be cured despite reasonable good faith efforts, and especially in the context of a lawsuit having been started and with the contractual time for a closing having expired, as an implied election of cancellation of the [contracts].”20 This appeal followed. Additional facts and procedural history will be set forth as necessary.21 The plaintiffs raise two principal claims on appeal. First, the plaintiffs assert that the court misconstrued the contracts (1) to establish January 16, 2019, as the extended closing deadline following Barrett’s extension of the original closing date and (2) to provide that time was of the essence with respect to the closing. Second, the plaintiffs contend that the court incorrectly determined that Barrett properly treated their conduct as demon- strating that they made an “implied” contractual election 20The court further determined that the plaintiffs were entitled to a return of their deposit on both properties, without interest, as well as to certain additional expenses associated with a termination of the contracts. 21On June 6, 2024, the defendants filed a motion for attorney’s fees and costs. On February 14, 2025, the court awarded the defendants $44,440 in attorney’s fees. The plaintiffs appealed from the award of attorney’s fees, which separate appeal has been stayed pending the final disposition of this appeal. See Angiolillo v. Nevard, Connecticut Appel- late Court, Docket No. 48673 (appeal filed March 4, 2025).
Angiolillo v. Nevard to terminate the contracts. The plaintiffs maintain that these errors are fatal to the court’s conclusions that the defendants (1) did not breach the contracts, and that the plaintiffs were not entitled to specific performance, (2) did not breach the implied covenant of good faith and fair dealing, and (3) were entitled to declaratory relief.22 We address these claims in turn. I We first turn to the plaintiffs’ claims that the trial court improperly construed the contracts (1) to establish January 16, 2019, as the extended closing deadline after Barrett had extended the original closing date and (2) to provide that time was of the essence vis-à-vis the closing. We disagree with the plaintiffs’ first claim and, although we agree with their second claim, we conclude that the court’s error was not integral to its adjudication of the plaintiffs’ claims or the defendants’ counterclaim. “The law governing the construction of contracts is well settled. When a party asserts a claim that chal- lenges the trial court’s construction of a contract, we must first ascertain whether the relevant language in the agreement is ambiguous. . . . When the language of a contract is ambiguous, the determination of the parties’ intent is a question of fact . . . . [When] there is definitive contract language, [however] the determination of what the parties intended by their contractual commitments is a question of law. . . . It is implicit in this rule that the determination as to whether contractual language is plain and unambiguous is itself a question of law subject to plenary review. . . . “We accord the language employed in the contract a rational construction based on its common, natural and ordinary meaning and usage as applied to the subject mat- ter of the contract. . . . Where the language is unambiguous, 22The plaintiffs have not appealed from the portion of the judgment rendered in the defendants’ favor on the counts of their amended complaint sounding in fraud, so-called “fraud by negligent misrepre- sentation,” and a violation of the Connecticut Unfair Trade Practices Act, General Statutes § 42-110a et seq. See footnote 10 of this opinion.
Angiolillo v. Nevard we must give the contract effect according to its terms. . . . Where the language is ambiguous, however, we must construe those ambiguities against the drafter [some- times referred to as the contra proferentem rule]. . . . A contract is unambiguous when its language is clear and conveys a definite and precise intent. . . . The court will not torture words to impart ambiguity where ordinary meaning leaves no room for ambiguity. . . . Moreover, the mere fact that the parties advance different interpreta- tions of the language in question does not necessitate a conclusion that the language is ambiguous. . . . In con- trast, a contract is ambiguous if the intent of the parties is not clear and certain from the language of the contract itself. . . . [A]ny ambiguity in a contract must emanate from the language used by the parties. . . . The contract must be viewed in its entirety, with each provision read in light of the other provisions . . . and every provision must be given effect if it is possible to do so. . . . If the language of the contract is susceptible to more than one reasonable interpretation, the contract is ambiguous.” (Citations omitted; internal quotation marks omitted.) C & H Shoreline, LLC v. Rubino, 203 Conn. App. 351, 356–57, 248 A.3d 77 (2021). The following contractual provisions are relevant to our resolution of the plaintiffs’ claims. Paragraph 4 of the contracts provides in relevant part that the respec- tive property deed “shall be delivered . . . on the 17th day of December, 2018, at 2:00 P.M. or sooner by mutual agreement of the parties . . . .” Paragraph 6 (a) of the contracts provides in relevant part: “If, upon the date for the delivery of the [respective property] deed . . . [Barrett] shall be unable to deliver or cause to be delivered a deed or deeds conveying a good and marketable title to the [respective property], subject only to the items set forth in Schedule A and [p]aragraph [6 (e)] . . . then [Barrett] shall be allowed a reasonable postponement of closing not to exceed thirty (30) calendar days, or such shorter time as may be within the term of
Angiolillo v. Nevard the [plaintiffs’] mortgage commitment, within which to perfect title. . . .” Paragraph 16 of the contracts provides in relevant part: “In no event shall the closing, or any extension thereof, take place later than twenty-one (21) calendar days from the date of closing set forth in [p]aragraph 4 . . . subject to the provisions of [p]aragraphs 6 and 11. . . .” Attached to and incorporated into the contracts is a seller’s rider. Paragraph 4 of the seller’s rider provides: “Except for the closing date as set forth [in the respective contract], as to all other dates, time shall be considered of the essence.” Additionally, the prefatory language of the seller’s rider provides in relevant part: “In the event of any conflict between the terms of the [respective contract] (or any other addenda and/or riders thereto) and the terms of [the seller’s] [r]ider, the terms of [the seller’s] [r]ider shall control . . . .” A The plaintiffs contend that the court misinterpreted the contracts to set January 16, 2019, as the extended closing deadline following Barrett’s extension of the original closing date. We disagree. In its decision, the court determined that, “[i]n terms of timing . . . paragraph 16 [of the contracts] required the closing to take place no later than twenty-one days after December 17, 2018, except that paragraph 6 (a) allowed a closing no later than January 16, 2019 (thirty days thereafter).” Additionally, the court referred to January 16, 2019, as the “outer limit date” and the “hard deadline” for the closing, and stated that “the language of the [contracts] provided only for a single up to thirty day extension of the closing.” The plaintiffs contend that, read together, paragraphs 4, 6 (a), and 16 of the contracts provide that, in the event that Barrett exercised his option to extend the closing under paragraph 6 (a), the deadline for the closing was twenty-one days after January 16, 2019. As the plaintiffs
Angiolillo v. Nevard explain: “[O]nce [Barrett] postpone[d] the closing date for thirty days pursuant to paragraph 6 [(a)], the twenty-one days under paragraph 16 ran from that extended closing date. That is, once the December 17, 2018 closing pursu- ant to paragraph 4 was extended by [Barrett] pursuant to paragraph 6 [(a)] until January 16, 2019, paragraph 16 required the closing [to] occur twenty-one days after the new closing date of January 16, 2019.” This conten- tion is unavailing. We conclude that the contracts, in clear and unambigu- ous terms, establish January 16, 2019, as the extended closing deadline. Pursuant to paragraph 16, the closing was to occur no later than twenty-one days following December 17, 2018 (or an earlier date had the parties mutually agreed), “subject to the provisions of [p]ara- graphs 6 and 11.” Paragraph 6 (a) authorizes Barrett to extend the closing for a period “not to exceed thirty (30) calendar days . . . .” Put simply, we interpret these provisions to permit a maximum thirty day extension of the original December 17, 2018 closing date, with the twenty-one day extension language of paragraph 16 applying only in the event that the original closing date was not extended under the provisions of paragraphs 6 or 11.23 Thus, we reject the plaintiffs’ proposition that the parties had an additional twenty-one days following January 16, 2019, to close on the properties. B The plaintiffs also contend that the court misconstrued the contracts to provide that, with respect to the closing, time was of the essence. We agree but conclude that the court’s error was not integral to its adjudication of the plaintiffs’ claims or the defendants’ counterclaim. “When it is said that time is of the essence, the proper meaning of the phrase is that the performance by one party at the time specified in the contract or within the period specified in the contract is essential in order to enable 23As we previously noted, the terms of paragraph 11 of the contracts are not germane to this appeal. See footnote 5 of this opinion.
Angiolillo v. Nevard him to require performance from the other party. . . . Its commonly understood meaning is that insofar as a time for performance is specified in the contract, failure to comply with the time requirement will be considered to be a material breach of the agreement.” (Internal quotation marks omitted.) New Milford v. Standard Demolition Services, Inc., 212 Conn. App. 30, 85 n.23, 274 A.3d 911, cert. denied, 345 Conn. 908, 283 A.3d 506 (2022). “In real estate contracts, the fact that a specific time is fixed for payment or for conveyance does not make time of the essence—at least, it does not make per- formance at the specified time of the essence. . . . When the parties to a real estate contract want to fix a specific date for performance, we generally have required them to express specifically in the contract that time is of the essence; otherwise, performance within a reasonable time will satisfy the contract.” (Citations omitted; emphasis omitted; internal quotation marks omitted.) Tulisano v. Schonberger, 74 Conn. App. 101, 105–106, 810 A.2d 806 (2002); see also Lipshie v. George M. Taylor & Son, Inc., 265 Conn. 173, 182 n.7, 828 A.2d 110 (2003) (“[u]nless a contract for the purchase of real estate provides that time is of the essence, a failure to meet a closing date does not automatically establish a breach; the law provides that the parties must close within a reasonable time of the closing date”); United Cleaning & Restoration, LLC v. Koskerides, 234 Conn. App. 401, 420–21, 343 A.3d 830 (2025) (“Where the agreement does not specifically state that time is of the essence, it is presumed not to be unless the parties have expressed a contrary intent. . . . The fact that a contract states a date for performance does not necessarily make time of the essence.” (Internal quotation marks omitted.)). The following additional procedural history is relevant to our resolution of this claim. In their posttrial brief, the plaintiffs argued that, on January 16, 2019, “[Bar- rett] wrongfully unilaterally terminated the [contracts], claiming ‘defect of title.’ The parties were in the midst of communicating, however strained and in writing, back and forth as they attempted to resolve the issue of
Angiolillo v. Nevard whether [the] 23 Henry Street [property] was a three- family or two-family [dwelling]. Nothing prevented the parties, once they agreed, to close title on both or either of the properties. . . . Before the parties could reach an agreement or an amendment, [Barrett] unilaterally ended the discussions and terminated the [contracts].” The plaintiffs further contended that the closing date was not subject to a “time is of the essence” provision. In its decision, the court acknowledged that the plain- tiffs were asserting that the contracts did not contain a “time is of the essence” provision vis-à-vis the closing, “such that a further (indefinite?) extension of time for a closing would not conflict with the intent of the . . . [contracts].” The court stated that “there does not appear to be explicit use of the term ‘time is of the essence’ or a variation on those words [in the contracts]”; nevertheless, the court reasoned that, pursuant to paragraph 16, “time is, in substance, stated to be of the essence, in that a hard deadline is established [for the closing] . . . .” (Emphasis omitted.) The court continued: “In terms of timing . . . paragraph 16 required the closing to take place no later than twenty-one days after December 17, 2018, except that paragraph 6 (a) allowed a closing no later than Janu- ary 16, 2019 (thirty days thereafter). Presumably, the parties could have agreed to waive these limits, but any suggestion that the [contracts] did not provide for a time is of the essence approach to a closing is in direct conflict with the language of the [contracts] . . . . The parties did not contemplate an open-ended approach to closing on the properties . . . .” (Footnote omitted.) The plaintiffs assert that the court’s determination that time was of the essence as to the closing is unten- able in light of the terms of the seller’s rider, which the court did not consider as part of its analysis. We agree.24 24In their appellate brief, the defendants contend that the court correctly construed the contracts in concluding that time was of the essence vis-à-vis the closing; however, beyond reciting the provision of the seller’s rider on which the plaintiffs rely, the defendants do not provide any analysis of that provision.
Angiolillo v. Nevard In its decision, after stating that the contracts did not appear to contain express “time is of the essence” language, the court relied on paragraphs 6 (a) and 16 of the contracts to conclude that time was of the essence as to the closing. In so concluding, however, the court did not examine or make any reference to the seller’s rider, which, by its express terms, takes precedence over con- flicting language located elsewhere in the contracts.25 The seller’s rider provides in relevant part that, “[e]xcept for the closing date as set forth [in each respective con- tract], as to all other dates, time shall be considered of the essence.” Stated otherwise, in contrast to all other dates identified in the contracts, time was not of the essence with respect to the closing. Accordingly, in light of the clear and unambiguous language of the control- ling seller’s rider, we conclude that the court improperly interpreted the contracts to provide that time was of the essence as to the closing. We now address the consequences of the court’s improper determination that, pursuant to the contracts, time was of the essence as to the closing. The plaintiffs argue that this error, alone, warrants reversal of the court’s judgment against them. Reviewing the entirety of the court’s decision, however, we do not agree that this error unravels its conclusions that (1) the plaintiffs failed to prove their claims of breach of contract and breach of the implied covenant of good faith and fair dealing, and that they were not entitled to specific per- formance, and (2) the defendants were entitled to declara- tory relief. Moreover, as we conclude in part II B of this opinion, there was an adequate factual basis supporting the court’s determination that Barrett reasonably deter- mined that the plaintiffs made an “implied” election to terminate the contracts regardless of whether time was of the essence with respect to the closing. Accordingly, we reject the plaintiffs’ argument. 25We note that the plaintiffs did not direct the trial court’s attention to the provision of the seller’s rider at issue during trial or in their posttrial brief.
Angiolillo v. Nevard II Having concluded in part I of this opinion that the trial court (1) properly construed the contracts to establish January 16, 2019, as the deadline for the closing fol- lowing Barrett’s extension of the original closing date but (2) improperly construed the contracts to provide that time was of the essence as to the closing, we turn to the plaintiffs’ second claim. The plaintiffs assert that the court incorrectly determined that Barrett properly treated their conduct as demonstrating an “implied elec- tion of cancellation of the [contracts]” under paragraph 6 (a), whereupon, by way of the January 16, 2019 letter, Barrett deemed the contracts to be terminated. The plaintiffs maintain that there was neither a contractual nor a factual basis to support that determination, such that the court committed error in “justif[ying] [Bar- rett’s] unilateral termination of the contracts” and the resulting breach thereof. We disagree.26 “[T]he scope of our appellate review depends upon the proper characterization of the rulings made by the trial court. To the extent that the trial court has made find- ings of fact, our review is limited to deciding whether such findings were clearly erroneous. When, however, the trial court draws conclusions of law, our review is plenary and we must decide whether its conclusions are legally and logically correct and find support in the facts that appear in the record.” (Internal quotation marks omitted.) Walters v. Servidio, 227 Conn. App. 1, 29, 320 A.3d 1008 (2024). A We first turn to the plaintiffs’ assertion that there was no contractual basis to determine that they made an “implied” election to terminate the contracts. The plain- tiffs maintain that paragraph 6 (a) of the contracts gave 26The plaintiffs also challenge the court’s damages analysis. See footnote 16 of this opinion. Because we conclude that the court prop- erly determined that the defendants did not breach the contracts or the implied covenant of good faith and fair dealing, we need not address their claim as to damages.
Angiolillo v. Nevard them the exclusive authority to decide how to proceed in the event that Barrett could not cure the title defect vis-à-vis the 23 Henry Street property and that Barrett had no right to deem the contracts to be terminated. We reject this claim. Pursuant to the clear and unambiguous language of paragraph 6 (a) of the contracts, if Barrett could not produce a good and marketable title to the respective property after electing to extend the original closing date, then the plaintiffs had the option either to “(i) . . . elect to accept such title as [Barrett] can convey, without modification of the purchase price, or (ii) . . . reject such title” and cancel the contracts. The contracts, however, do not designate any particular method by which the plaintiffs must make an election under paragraph 6 (a). Moreover, we discern nothing in the contracts that prohibits a determination that, through their conduct, the plaintiffs made an implicit election to cancel the contracts. Thus, the plaintiffs’ claim fails. B We next address the plaintiffs’ assertion that there was no factual basis supporting the determination that they made an “implied” election to terminate the contracts. In particular, they assert that neither (1) the commence- ment of the present action on January 15, 2019, nor (2) the passage of the extended closing deadline on January 16, 2019, supported that determination.27 We are not persuaded. We first consider the plaintiffs’ commencement of the present action on January 15, 2019. Viewed in the proper context, the plaintiffs commenced the present action after (1) Barrett had made good faith efforts to cure the title defect vis-à-vis the 23 Henry Street property or to salvage the sale of both properties, which efforts either 27Additionally, in their principal appellate brief, the plaintiffs cite to testimony elicited from Glenn during trial that he was away on vacation in Antarctica from January 7 to 18, 2019, such that he was unaware of the January 7, 2019 letter until he returned. The court did not make any findings to that effect.
Angiolillo v. Nevard the plaintiffs rejected or Barrett reasonably deemed to be futile, and (2) Attorney Kristoff had emailed the January 7, 2019 letter to Glenn, representing that the title defect could not be cured and proposing a final offer to facilitate the sale of both properties. It was reason- able, as the court found, for Barrett to have treated the plaintiffs’ commencement of the present action as being indicative of a rejection of the offer proposed in the January 7, 2019 letter, as well as the purchase of both properties with the title defect in place. Addition- ally, as the court aptly observed, the plaintiffs’ origi- nal complaint sought specific performance as to the 19 Henry Street property only, and it was not until they filed their amended complaint in July 2023 that they sought specific performance as to both properties. See footnotes 11 and 14 of this opinion. In other words, on the basis of their original complaint, the plaintiffs were not seeking to proceed with the purchase of both proper- ties in light of the title defect when they commenced the present action. Thus, we reject the plaintiffs’ contention that their commencement of the present action did not support the determination that they made an “implied” election to terminate the contracts. We next address the passage of the extended closing deadline on January 16, 2019. The plaintiffs maintain that (1) the extended closing deadline had not yet expired when Barrett deemed the contracts to be terminated on January 16, 2019, and, in any event, (2) time was not of the essence as to the closing, such that the passage of the extended closing deadline could not serve to demonstrate that they implicitly elected to cancel the contracts. As the court reasonably determined, however, the plaintiffs did not express any willingness to accept the defective title to the 23 Henry Street property until they amended their complaint in the present action in 2023, with their conduct—particularly the commencement of the present action on January 15, 2019, which followed the trans- mission of the January 7, 2019 letter—demonstrating a rejection of such title before the January 16, 2019 letter had been sent. Thus, it was reasonable for Barrett
Angiolillo v. Nevard to deem the contracts to be terminated on the extended closing deadline, regardless of whether the January 16, 2019 letter was sent on that date or time was not of the essence as to the closing. Accordingly, the plaintiffs’ contention concerning the passage of the extended clos- ing deadline fails. Considering the court’s factual findings in their entirety, we conclude that there was an adequate factual basis supporting the court’s determination that Barrett properly treated the plaintiffs’ conduct as reflecting an “implied election of cancellation of the [contracts].”28 The judgment is affirmed. In this opinion the other judges concurred. 28In distinct sections at the end of their principal appellate brief, the plaintiffs raise additional issues concerning the court’s rejections of their request for specific performance and their breach of the implied covenant of good faith and fair dealing claim. Insofar as our analyses in parts I and II of this opinion do not wholly dispose of those additional issues, we conclude that they have no merit.
Wondering how this text applies to your situation?
Free consultation, no commitment
Describe your situation. Our team will contact you by email about your consultation.
Continue your research in ChatGPT or Claude
Connect Omnilex to search the legal corpus from your AI assistant.