General Injectables & Vaccines, Inc. v. Robert M. Gates, SECRETARY OF DEFENSE

2007-1119Court of Appeals for the Federal CircuitJun 3, 2008

Full text

United States Court of Appeals for the Federal Circuit
2007-1119
GENERAL INJECTABLES & VACCINES, INC.,
Appellant,
v.
Robert M. Gates, SECRETARY OF DEFENSE,
Appellee.
Bruce E. Fader, Proskauer Rose LLP, of New York, New York, filed a combined
petition for panel rehearing and rehearing en banc for appellant. With him on the petition
was James F. Segroves, of Washington, DC.
Appealed from: Armed Services Board of Contract Appeals
Administrative Judge Carroll C. Dicus, Jr.

-- 1 of 9 --

United States Court of Appeals for the Federal Circuit
2007-1119
GENERAL INJECTABLES & VACCINES, INC.,
Appellant,
v.
Robert M. Gates, SECRETARY OF DEFENSE,
Appellee.
Appeal from the Armed Services Board of Contract Appeals
In No. 54930
___________________________
DECIDED: June 3, 2008
___________________________
ON PETITION FOR REHEARING
Before MAYER and BRYSON, Circuit Judges, and FOGEL, District Judge.*
BRYSON, Circuit Judge.
General Injectables & Vaccines, Inc. (“GIV”) has filed a petition for rehearing in
which it contends that the panel’s interpretation of the “excusable delays” provision at
issue in this case, FAR 52.212-4(f), conflicts with several Court of Claims decisions,
Poloron Products v. United States, 116 F. Supp. 588 (Ct. Cl. 1953), Climatic Rainwear
Co. v. United States, 88 F. Supp. 415 (Ct. Cl. 1950), and H.B. Nelson Construction Co.
* Honorable Jeremy Fogel, District Judge, United States District Court for
the Northern District of California, sitting by designation.

-- 2 of 9 --

v. United States, 87 Ct. Cl. 375 (1938). We think it appropriate to supplement our
earlier opinion to address that contention.
FAR 52.212-4(f) reads as follows:
The Contractor shall be liable for default unless nonperformance is caused
by an occurrence beyond the reasonable control of the Contractor and
without its fault or negligence such as, acts of God or the public enemy,
acts of the Government in either its sovereign or contractual capacity,
fires, floods, epidemics, quarantine restrictions, strikes, unusually severe
weather, and delays of common carriers.
The panel opinion interpreted that provision consistently with the general rule that an
unexcused default by a subcontractor does not excuse nonperformance by the prime
contractor. See Johnson Mgmt. Group CFC, Inc. v. Martinez, 308 F.3d 1245, 1252
(Fed. Cir. 2002) (“A contractor is responsible for the unexcused performance failures of
its subcontractors.”) (citing cases); Hutton Contracting Co. v. City of Coffeyville, 487
F.3d 772, 779 (10th Cir. 2007) (“The most reasonable interpretation of ‘fault of [Hutton]’
in the force-majeure clause is ‘fault of Hutton and those to whom it delegates its
responsibilities under the contract.’”); Mary Rogers Manley dba Mary Rogers Real
Estate, HUDBCA No. 76-27, 78-2 B.C.A. (CCH) ¶ 13,519, at 66248 (Oct. 25, 1978)
(“The principle is well established that the prime contractor is responsible for unexcused
failures of performance by its subcontractors.”); Pelton Water Wheel Co., IBCA 16, 1955
WL 7210 (Oct. 12, 1955) (“Delays of a subcontractor do not excuse the prime contractor
from performing on time unless the subcontractor’s difficulty itself results from an
excusable cause under the contract.”). 1
1 In a 1950 decision, the Armed Services Board of Contract Appeals refused to
grant the government’s request for liquidated damages under a pre-FAR “Delays-
Liquidated Damages” clause when a subcontractor’s nonperformance caused the
contractor’s performance to be delayed. John Andresen & Co., ASBCA No. 633 (Dec.
2007-1119 2

-- 3 of 9 --

GIV argues that Poloron Products, Climatic Rainwear, and H.B. Nelson stand for
the proposition that if the contractual delay provision does not separately state that the
contractor is liable for the unexcused actions of its subcontractor, then subcontractor
delays are excusable as long as the contractor acted reasonably in selecting the
subcontractor. In fact, those cases do not state that rule expressly, nor can the cases
fairly be read as adopting such a rule implicitly.
The delay provisions in all three of the cited cases specified that the contractor
would not be liable for delays due to “unforeseeable causes” beyond its control. The
court in each of those cases focused on the foreseeability of the problem that resulted in
the delay, not on whether the problem was foreseeable to the contractor as opposed to
the subcontractor. In fact, in Climatic Rainwear, the court observed that the problem
was “clearly unforeseeable on the part of everyone associated with the contract,”
including the subcontractor. 88 F. Supp. at 426. In Poloron Products, the court found
the delay caused by the subcontractor to be foreseeable to the contractor and therefore
not excused. 116 F. Supp. at 595. And in H.B. Nelson the court regarded the failure of
common carriers to deliver undamaged goods to be unforeseeable, without addressing
the question whether the common carriers should be regarded as subcontractors for
purposes of determining whether the plaintiff had established a valid excuse to
performance. 87 Ct. Cl. at 375.
13, 1950). The language of standard government contract clauses was subsequently
changed to overcome the Andresen case, and GIV has not relied on Andresen or any of
the other contemporaneous ASBCA decisions. In any event, the ASBCA has since
characterized Andresen as an example of the “exceptional circumstances which have at
times led the Board to relieve an appellant contractor of . . . responsibility [for its
supplier’s unexcused defaults].” L & P Food Serv. Equip. Co., ASBCA No. 11007, 66-1
B.C.A. (CCH) ¶ 5659, at 26,405 (June 29, 1966).
2007-1119 3

-- 4 of 9 --

In a subsequent decision, the Armed Services Board of Contract Appeals noted
that the H.B. Nelson case focused on the issue of foreseeability and did not establish
any broad principle limiting the normal rule that a contractor is liable for the unexcused
defaults of its subcontractors. See Hogan Mech., Inc., ASBCA No. 21612, 78-1 B.C.A.
(CCH) ¶13,164, at 64,334 (Mar. 30, 1978) (“The Nelson case ignored the subcontractor
issue and premised its decision completely upon the foreseeability issue”). We agree
with that characterization, and we think the characterization applies equally to the other
two cases on which GIV relies. We thus do not regard those cases as implicitly
rejecting the longstanding rule discussed in the panel opinion and applied in this case.
In fact, both the Court of Claims and this court, in cases post-dating the three cases on
which GIV relies, have endorsed the principle that prime contractors are ordinarily
responsible for the unexcused performance failures of their subcontractors. See
Johnson Mgmt. Group, 308 F.3d at 1252; Olson Plumbing & Heating Co. v. United
States, 602 F.2d 950, 957 (Ct. Cl. 1979).
The H.B. Nelson case is distinguishable on another ground as well: it dealt with a
failure of proper and timely delivery by a common carrier. A common carrier stands in a
very different position from a supplier of the goods that the contractor has agreed to
provide to the government. The Veterans Administration Board of Contract Appeals in
Malan Construction Corp., VABCA No. 262, 1960 WL 151 (June 17, 1960),
distinguished H.B. Nelson on that ground: “The court obviously considered the case as
involving an accident, the circumstances of which were not known, occurring when the
equipment was in the custody of common carriers and beyond the control of the
subcontractor who fabricated it and the contractor who ordered it.” Id. at 4. The
2007-1119 4

-- 5 of 9 --

importance of the distinction between a supplier and a common carrier is underscored
by the fact that the H.B. Nelson case would not be decided differently under the FAR
provision that was applied in this case. That provision, FAR 52.212-4(f), includes
“delays of common carriers” among the conditions that constitute valid excuses for
nonperformance because they are considered “beyond the reasonable control of the
Contractor.” Thus, nothing in the H.B. Nelson case is contrary to our ruling that under
FAR 52.212-4(f) the failure of a contractor’s supplier does not provide a valid excuse for
contractor nonperformance unless the supplier’s failure is shown to be excusable.
It is worth noting the implications of GIV’s argument if it were to be adopted.
GIV’s contention that failure on the part of a subcontractor/supplier results in an
excusable delay for the contractor would place a contractor who procures contract
goods through subcontract in a better position with respect to the risk of
nonperformance than a contractor who manufactures the contract goods itself. Thus, if
the government had contracted directly with Chiron for the production of the vaccine,
and the same problem had developed in Chiron’s production facilities, Chiron would
have had to show that the problem fell within the “excuse” clause in order to avoid
default. See 14 James P. Nehf, Corbin on Contracts § 74.16, at 104 (2001) (burden of
proving impossibility rests on party asserting it). By virtue of the subcontract
arrangement, however, GIV contends that it can avoid liability for breach even if it
cannot show that Chiron’s failure to produce the vaccine is excusable. To allow that
form of risk reallocation through subcontracting would be difficult to justify as a matter of
procurement policy.
2007-1119 5

-- 6 of 9 --

GIV’s implicit response to such policy objections is that the government could
cure the problem by specifically including a reference to subcontractors in its “excusable
delays” clause and that not having inserted such a reference in FAR 52.212-4(f), the
government must live with the consequences. We do not agree with GIV, however, that
contractors should be liable for unexcused nonperformance by their subcontractors only
if the contract contains a specific clause covering such a contingency. Instead, we
interpret the default rule, absent contractual language to the contrary, to be that
contractors are bound by the unexcused nonperformance of their subcontractors.
Moreover, we are not persuaded that the “excusable delays” provision in FAR 52.212-
4(f) was intended to depart from that rule, and we are not persuaded that the older
Court of Claims cases on which GIV relies require us to interpret the “excusable delays”
clause in a manner that would put it at odds with that rule.
GIV acknowledges that the normal rule under the FAR is that the contractor is
responsible for the unexcused defaults of its subcontractors or suppliers. See John
Cibinic, Jr., Ralph C. Nash, Jr., & James F. Nagle, Administration of Government
Contracts 555 (4th ed. 2006) (“Under the clauses currently in use . . . before the
contractor can be excused, it must be shown that the cause of delay was beyond the
control and without the fault or negligence of the contractor and all intervening
contractors including the delayed subcontractor.”). GIV argues, however, that the
“excusable delays” clause at issue in this case, FAR 52.212-4(f), must be interpreted to
include subcontractor nonperformance among the causes of excusable delay because
other FAR provisions dealing with default and excusable delay contain express
language excluding unexcused subcontractor defaults. See FAR 52.249-8(c)-(d),
2007-1119 6

-- 7 of 9 --

52.249-9(c)-(d), 52.249-10(b)(1), 52.249-14. The inference that GIV wishes us to draw
from the fact that other FAR clauses use different language is weakened by the fact that
FAR 52.212-4(f) was added to the FAR in 1995, long after the other cited clauses.
Moreover, whatever force that inference may have is outweighed by the fact that the
Federal Acquisition Circular issued at the time FAR 52.212-4 was promulgated stated
that the new regulation “contains the terms and conditions believed to be consistent with
customary commercial practice.” 60 Fed. Reg. 48,206, 48,207 (1995). In that respect,
the regulations complied with the directive in section 8002(b)(1)(B) of the Federal
Acquisition Streamlining Act, Pub. L. No. 103-355, 108 Stat. 3243, 3386 (1994), codified
at 41 U.S.C. § 264 note, which provided that the new FAR regulations governing the
acquisition of commercial items should include contract clauses “that are determined to
be consistent with standard commercial practice.” As applied to the issue of “excusable
delays,” we interpret those statements as indicating an intention to adopt the normal
rule that “[t]he contractor alone is responsible for the deficiencies of its suppliers and its
subcontractors absent a showing of impossibility.” Olson Plumbing & Heating, 602 F.2d
at 957. See Wellington House v. GSA, GSBCA No. 14665, 99-1 B.C.A. (CCH)
¶ 30,279, at 149,734 (Mar. 3, 1999) (stating, in a case governed by FAR 52.212-4(f),
that “an ‘excusable default’ is normally said to be one which is beyond the control, fault
or negligence of both the contractor and the subcontractor”).
Nearly a century ago, the Supreme Court provided an admirably succinct
explanation of the rationale for the rule we have applied here, in an opinion dealing with
a contract to supply goods to the government. In that case, Carnegie Steel Co. v.
United States, 240 U.S. 156 (1916), the Court stated that difficulties in procuring goods
2007-1119 7

-- 8 of 9 --

2007-1119 8
that were to be supplied under the contract were not the kinds of unavoidable causes of
delay, “such as fires, storms, labor strikes, actions of the United States, etc.” that would
render the delay excusable. The Court explained:
It would seem that the very essence of the promise of a contract to deliver
articles is to procure or make them. . . . [The contract] would have no
sense or incentive, no assurance of fulfillment, otherwise; and a delay
resulting from the absence of such ability is not of the same kind
enumerated in the contract—is not a cause extraneous to it and
independent of the engagements and exertions of the parties.
240 U.S. at 164-66. As in Carnegie Steel, GIV’s sole responsibility under the contract in
this case was to deliver vaccines to the government. GIV bore the risk of not being able
to perform unless it could show that the reason for its failure to perform fell within the
causes set forth in the “excusable delay” clause. It could not shift that risk to the
government simply by subcontracting production of the vaccine to a third party.
The other arguments GIV presents in its petition for rehearing have already been
addressed in the original panel opinion.
The petition for rehearing is denied.