CourtListener 10602906•Water Audit California v. Merced Irrigation District
Water Audit California v. Merced Irrigation District
CourtListener 10602906CalctappJun 11, 2025
Full text
Filed 5/13/25; Certified for Partial Pub. 6/11/25 (order attached)
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FIFTH APPELLATE DISTRICT
WATER AUDIT CALIFORNIA,
F088084
Plaintiff and Appellant,
(Super. Ct. No. 22CV-03034)
v.
MERCED IRRIGATION DISTRICT, OPINION
Defendant and Respondent.
APPEAL from a judgment of the Superior Court of Merced County. Brian L.
McCabe and Susan J. Matcham,* Judges.
William McKinnon; Law Office of Adam Keats and Adam Keats for Plaintiff and
Appellant.
Rob Bonta, Attorney General, Tracy L. Winsor, Assistant Attorney General,
Russell B. Hildreth and Jeffrey P. Reusch, Deputy Attorneys General, as Amicus Curiae
for the California Department of Fish and Wildlife on behalf of Plaintiff and Appellant.
Duane Morris, Colin L. Pearce, Jolie-Anne S. Ansley and B. Alexandra Jones for
Defendant and Respondent.
-ooOoo-
*Retired Judge of the Monterey Superior Court, assigned by the Chief Justice pursuant to
article VI, section 6 of the California Constitution.
A fishway is a device or structure that facilitates the movement of fish over or
around a dam. (See Fish & G. Code, § 5931.) A fish ladder is a type of fishway. In
simple terms, fish ladders are “water-covered steps” that enable fish to “climb over”
dams. (Idaho ex rel. Evans v. Oregon (1983) 462 U.S. 1017, 1021.) “Designs vary …,
but the general principle is the same for all fish ladders: the ladder contains a series of
ascending pools that are reached by swimming against a stream of water. Fish leap
through the cascade of rushing water, rest in a pool, and then repeat the process until they
are out of the ladder.” (National Ocean Service, National Oceanic and Atmospheric
Administration, U. S. Dept. of Commerce (2024) Ocean Facts
<https://oceanservice.noaa.gov/facts/fish-ladder.html>[as of May. 12, 2025]. archived at
<https://perma.cc/L6LT-BAWB>.)
This case involves a fish ladder at a dam on the Merced River. The dam is owned
by defendant Merced Irrigation District. According to the pleadings, the fish ladder has
been closed for decades.
Fish and Game Code section 5935 states, “The owner of any dam upon which a
fishway has been provided shall keep the fishway in repair and open and free from
obstructions to the passage of fish at all times.” Section 5936 of the same code prohibits
willfully obstructing “any fishway.” Merced Irrigation District alleges it is unable to
comply with these statutes without the direction and consent of other government
agencies.
Plaintiff Water Audit California is a nongovernmental organization seeking to
enforce the fishway statutes as a private attorney general. Plaintiff alleges Merced
Irrigation District has the sole duty and ability to comply with the statutes. Accordingly,
and because the fish ladder remains closed and obstructed, plaintiff filed a superior court
action for public nuisance and traditional mandamus relief.
This appeal is taken from a judgment of dismissal. The judgment was entered
after a demurrer to the third amended complaint and petition for writ of mandate was
2.
sustained without leave to amend. The cause of action for public nuisance was dismissed
“for failure to join indispensable parties.” The writ petition was deemed untimely based
on an unspecified statute of limitations. The trial court’s explanation was that plaintiff
failed to allege “a specific action by a specific agency occurring on a specific date that is
not time barred.”
“Appellate courts affirm a judgment of dismissal if it is correct on any ground
stated in the demurrer, independent of the trial court’s stated reasons.” (Bichai v. Dignity
Health (2021) 61 Cal.App.5th 869, 877.) We conclude the public nuisance claim was
properly dismissed on another ground asserted in the demurrer: lack of standing. A
private party lacks standing to bring a public nuisance action unless it has suffered a
special injury different in kind from the harm suffered by the general public. (Civ. Code,
§ 3493.) Plaintiff did not adequately plead such an injury. Despite defendant’s pointed
argument on this issue, plaintiff does not substantively address it. The judgment will thus
be affirmed as to the cause of action for public nuisance.
Regarding the writ petition, we conclude plaintiff has pleaded a basis for invoking
the continuous accrual doctrine. Judicially recognized theories of continuous accrual
prevent “the inequities that would arise if the expiration of the limitations period
following a first breach of duty or instance of misconduct were treated as sufficient to bar
suit for any subsequent breach or misconduct.” (Aryeh v. Canon Business Solutions, Inc.
(2013) 55 Cal.4th 1185, 1198.) This allows plaintiffs to “pursue actionable wrongs for
which the statute of limitations has not yet expired, even if earlier wrongs would be
barred.” (Orange County Water Dist. v. Sabic Innovative Plastics US, LLC (2017) 14
Cal.App.5th 343, 395.) Although generally reserved for cases involving “recurring” acts
of wrongdoing, the focus is on whether the duty allegedly breached is “a continuing one”
that is “susceptible to recurring breaches.” (Aryeh, at p. 1200, italics added.)
Merced Irrigation District argues it had a legal excuse for closing the fish ladder in
1970. Regardless of whether that is true, there remains a factual dispute about if and
3.
when any legal justification for keeping the fishway closed ceased to exist. Even if we
assume the initial closure triggered a statute of limitations, there are disputed factual
issues regarding whether a duty to reopen the fish ladder (and breach of that alleged duty)
arose closer in time to the filing of plaintiff’s lawsuit. Moreover, defendant’s own
evidence shows it reopened and then reclosed the fish ladder after the lawsuit
commenced but shortly before the third amended pleading was filed. Therefore, if
necessary, plaintiff could plead supplemental allegations of a fresh breach of the alleged
duty within any applicable limitations period.
Merced Irrigation District argues there are other grounds for affirming the entire
judgment, including nonjoinder of necessary and indispensable parties. In making those
arguments, it relies on the truth and subjective interpretation of matter contained in
documents of which the trial court took judicial notice. The evidence was not judicially
noticeable for those purposes, and it does not establish Merced Irrigation District’s
various defenses as a matter of law at the pleading stage. The judgment will be reversed
as to the dismissal of the petition for writ of mandate.
FACTUAL AND PROCEDURAL BACKGROUND
We preliminarily note both parties’ extensive reliance on material outside the
pleadings, even in their summaries of the “factual” background. Early versions of
plaintiff’s complaint/petition were accompanied by contemporaneously filed attorney
declarations that authenticated multiple documents. We assume the attachments to the
declarations were intended to constitute exhibits to the pleadings. The operative third
amended pleading, however, was filed without a supporting declaration or any exhibits.
“An ‘amended’ complaint supersedes all prior complaints. ‘“It alone will be
considered by the reviewing court.”’ [Citation.] The original ceases to ‘“perform any
function as a pleading.”’ [Citation].” (Lee v. Bank of America (1994) 27 Cal.App.4th
197, 215, citing and quoting Foreman & Clark Corp. v. Fallon (1971) 3 Cal.3d 875,
884.) The only exception is the sham pleading doctrine, under which “plaintiffs are
4.
precluded from amending complaints to omit harmful allegations, without explanation,
from previous complaints to avoid attacks raised in demurrers or motions for summary
judgment.” (Deveny v. Entropin, Inc. (2006) 139 Cal.App.4th 408, 425.)
In light of the above principles, there are few pleaded facts to summarize. The
operative pleading is 26 pages long, but it is filled with recitals of statutory text, legal
arguments with case citations, and conclusory legal assertions. All quotations in the
following summary are taken from the operative pleading. All locations and distances
are approximated.
Pleaded Allegations
Water Audit California (plaintiff or Water Audit) is a public benefit corporation.
(Corp. Code, §§ 5060, 5110 et seq.) It is “dedicated to protecting natural watercourses
and the associated life.” “Water Audit has repeatedly taken action to protect the public
trust in the state of California” and “has an additional and specific interest in the free
passage of fish in the waterways of California.”
Merced Irrigation District (sometimes defendant or MID) is a public agency. MID
owns and operates four dams on the Merced River, including the Crocker-Huffman Dam
(C-H Dam). The C-H Dam is also known as the “Crocker-Huffman diversion dam,” thus
indicating its role in MID’s “water delivery system.”
Built in 1910, the C-H Dam is located at River Mile 52 of the Merced River.
Three miles upstream is the Merced Falls Dam, built in 1901. One mile upstream from
Merced Falls Dam is the McSwain Dam, built in 1966. MID’s fourth dam, the New
Exchequer, is located six miles upstream from the McSwain Dam. The New Exchequer
Dam was built in 1967 and forms Lake McClure.
“The upper three dams, [i.e.,] the New Exchequer, McSwain and Merced Falls, are
undergoing FERC [Federal Energy Regulatory Commission] relicensing.” “The New
Exchequer and the McSwain Dams are administered as FERC Project No. 2179, and the
Merced Falls Dam as FERC Project No. 2467. [Citation.] [¶] This matter concerns only
5.
the [C-H Dam], [citation] which is not subject to the federal jurisdiction of FERC
review.” (Boldface omitted.)
The statements in the previous paragraph necessarily imply that the C-H Dam does
not generate hydroelectric power. The relevance of this fact, and of the quoted
statements, will be explained later in the opinion.
The C-H Dam has a concrete fish ladder. The fish ladder “has been closed since
approximately 1972.” Consequently, a natural spawning route for anadromous fish is
blocked. The C-H Dam is “the most upstream point [on the Merced River that] a salmon
or steelhead is able to migrate for spawning purposes.” “Central Valley steelhead,
federally listed as threatened, occur within the San Joaquin River and likely occur in the
Merced River downstream of [the C-H Dam].”
“Although [Merced Irrigation District] knew and knows that its fishway was and is
blocking the passage of fish, prior to the initiation of this litigation, no mitigation to abate
the inoperable fishway [was] undertaken.” “By letter dated August 30, 2022, Water
Audit made a demand on [Merced Irrigation District] to reopen the fishway and gave
notice of its intention to commence litigation if remediation was not promised.” Merced
Irrigation District “continues to intentionally block the fishway and has additionally
failed to maintain the fishway in good operating condition ….”
Procedural History
In September 2022, plaintiff filed a verified complaint and petition alleging causes
of action for declaratory, injunctive, and mandamus relief. Merced Irrigation District was
named as the defendant and respondent. An attorney declaration filed in support of the
pleading authenticated roughly 200 pages of attached documents “received from NOAA
Fisheries in response to a Freedom of Information Act request.”1
1“NOAA Fisheries, also known as the National Marine Fisheries Service, is an office of
the National Oceanic and Atmospheric Administration within the Department of Commerce.”
(National Marine Fisheries Service, National Oceanic and Atmospheric Administration, U. S.
Dept. of Commerce <https://www.fisheries.noaa.gov/about-us> [as of May. 12, 2025], archived
6.
On November 14, 2022, Merced Irrigation District filed a demurrer. In support of
this demurrer, MID requested judicial notice of 12 documents labeled as exhibits A
through L. The exhibits consisted of approximately 250 pages of material.
While the demurrer was pending, plaintiff voluntarily amended its pleading.
(Code Civ. Proc., § 472, subd. (a).) A verified first amended complaint and petition was
filed in January 2023. Plaintiff alleged causes of action for public nuisance, declaratory
relief, mandamus relief, and “Violation of the Equal Protection Clause [of the] California
Constitution.” (Boldface omitted.) In addition to Merced Irrigation District being named
as defendant and respondent, the following parties were named as real parties in interest:
California Department of Fish and Wildlife; “NOAA Fisheries (NOAA), also known as
the National Marine Fisheries Service (NMFS)”; the California State Water Resources
Control Board; and the United States Fish and Wildlife Service.
An attorney declaration with attachments was filed in support of the first amended
complaint/petition. It was similar to the previous declaration and contained the same
documents, plus 30 additional pages of material. With exception of an e-mail from
plaintiff’s counsel to defendant’s counsel, the new material was reportedly obtained
“from NOAA Fisheries in response to a Freedom of Information Act request.” (See fn. 1,
ante.)
Defendant withdrew its original demurrer and, in February 2023, filed a demurrer
to the first amended pleading. A request for judicial notice was filed in support of the
second demurrer. Although nearly identical to the earlier request for judicial notice, this
filing intentionally omitted a document previously labeled as “Exhibit J.” Documents
previously labeled as exhibits “K” and “L” in the prior request were now relabeled as
exhibits “J” and “K,” respectively.
at <https://perma.cc/E3AR-6GTU>.) The quoted information is confirmed by a document filed
in this case by the United States Attorney for the Eastern District of California on behalf of
NOAA Fisheries and other federal agencies.
7.
On March 3, 2023, plaintiff filed multiple documents concerning the second
demurrer. They included an opposition to the demurrer, a supporting attorney declaration
with close to 1,000 pages of exhibits, and a request for judicial notice of those exhibits
plus “[a]ll records previously submitted to the Court by Water Audit during this
proceeding.” In addition, plaintiff filed a request for leave to amend its pleading by
deleting the “Equal Protection” cause of action and removing all “Real Party in Interest”
allegations. Plaintiff also filed objections to defendant’s request for judicial notice.
The request to amend the pleading in advance of the demurrer hearing was never
ruled upon. Plaintiff’s objections to defendant’s request for judicial notice were
impliedly overruled. (See further discussion, post.) There was no ruling on plaintiff’s
own request for judicial notice.
The demurrer to the first amended complaint/petition was heard on March 21,
2023. We assume this was an unreported hearing, as there is no corresponding transcript
in the appellate record. The minute order indicates the parties argued, and the court
deferred its ruling to “do some more research.”
On April 11, 2023, the trial court issued a decision by minute order. The court
granted defendant’s request for judicial notice filed “on November 14, 2022,” i.e., the
request filed in support of its demurrer to the original pleading. Thus, the judicially
noticed documents included the original “Exhibit J.”2 The following explanation was
provided: “This Court finds that the matters discussed in the above documents [exhibits
A through L] constitute official acts of government agencies for which judicial notice is
proper pursuant to Evidence Code [section] 452 [subdivisions] (c) & (d) and constitute
admissible evidence of the subject actions by such agencies.”
2Defendant’s original request for judicial notice describes “Exhibit J” as the “Water
Quality Certification for Merced Irrigation District’s Merced River Hydroelectric Project and
Merced Falls Hydroelectric Project, Project Nos. 2179 and 2467,” issued by the California State
Water Resources Control Board on or about July 31, 2020. The relevance of this document is
explained later in the opinion.
8.
The demurrer to the first amended complaint/petition was sustained as follows:
“The Demurrer for failure to allege exhaustion of administrative
remedies or plead around such administrative remedies is SUSTAINED
WITH LEAVE TO AMEND.
“The Demurrer brought on the grounds that the Federal Power Act
preempts state regulation (See California v. F.E.R.C (1990) 495 U.S. 490,
496-500) is SUSTAINED WITH LEAVE TO AMEND to either plead
around preemption or state a claim that is not preempted by the Federal
Power Act.
“The Demurrer to the Petition for Writ of Mandate on the grounds
that discretionary decisions are not subject to review by Writ of Mandate is
SUSTAINED WITH LEAVE TO AMEND.
“The Demurrer on the grounds that the claims regarding the 1970
closing of the fish ladder at issue are time barred is SUSTAINED WITH
LEAVE TO AMEND to plead around the statute of limitations.
“The Demurrer on the grounds that declaratory relief is not available
to challenge agency action is SUSTAINED WITHOUT LEAVE TO
AMEND. The sole remedy for attacking the official actions of an
administrative agency is a Petition for Writ of Mandate. [Citations.] Since
the basic issue raised in the Complaint/Petition is the application of law by
an administrative agency, [the] Cause of Action for Declaratory Relief
[does] not and cannot state a cause of action.
“A ruling on the demurrer on the grounds of the doctrine of
abstention is DEFERRED AS MOOT given the above rulings [on] the
other demurrers raised by Defendant. The doctrine of abstention will be
addressed if and when Plaintiff has otherwise stated a valid claim.
“The Demurrer to the Cause of Action for Public Nuisance is
SUSTAINED WITH LEAVE TO AMEND to state an act of nuisance by
Defendant Merced Irrigation District that was not authorized or permitted
by [the California Department of Fish and Wildlife] and other state and
federal regulatory agencies.
“The Demurrer to the Cause of Action for violation of the Equal
Protection Clause is SUSTAINED WITH LEAVE TO AMENDED [sic] to
allege a violation of rights of a recognized protected class in a manner
unequal to the rights of other classes.”
9.
In June 2023, plaintiff filed a verified second amended complaint and petition.
The alleged causes of action were for public nuisance and mandamus. This pleading
named only Merced Irrigation District as defendant and respondent. No real parties in
interest were identified. The record does not show any exhibits or supporting
declarations were filed.
Merced Irrigation District filed another demurrer and another request for judicial
notice. The request for judicial notice was substantively identical to the one previously
filed in support of the demurrer to the first amended complaint and petition.
In July 2023, plaintiff requested a continuance of the demurrer hearing due to a
reported possibility Merced Irrigation District would reopen the fish ladder in the near
future. The trial court granted the request. Plaintiff later filed an opposition to the
demurrer.
On October 26, 2023, the demurrer to the second amended complaint/petition was
heard and argued. This is the only reported hearing in the appellate record. During the
hearing, plaintiff’s counsel alleged the fish ladder was “opened on a temporary basis
about a month ago, but then [Merced Irrigation District] reclosed it, and it remains
closed.” Later, the trial court questioned plaintiff’s counsel about defendant’s joinder
arguments: “And is it your argument that MID has autonomy to act irregardless of any
effect on the Endangered Species Act, Clean Water Act or any other act; is that your
contention?” Although such autonomy had already been alleged in the pleadings and
earlier in the oral argument, the attorney would only say MID had a “duty to reopen the
fishway.” The trial court accused plaintiff’s counsel of “skirting the question.”
Plaintiff’s counsel eventually admitted it was “conceivable” that reopening the fishway
could implicate the Endangered Species Act, but also noted defendant had failed to
identify “any portion of the Endangered Specifies Act or the Fish and Game Code that
excuses [it] from performance.”
10.
The October 2023 hearing concluded with an oral ruling sustaining the demurrer
with leave to amend to “add the indispensable parties.” The minute order identified only
one defect in the pleading: “[F]ailure to name indispensable parties, specifically CDFW
[California Department of Fish and Wildlife], FERC [Federal Energy Regulatory
Commission], USFWS [United States Fish and Wildlife Service], and NMFS [National
Marine Fisheries Service].”
In December 2023, plaintiff filed a verified third amended complaint and petition.
Two causes of action were alleged: one for public nuisance and the other for traditional
mandamus. Merced Irrigation District was named as defendant and respondent, and four
parties were named as real parties in interest: California Department of Fish and
Wildlife; “NOAA Fisheries (NOAA), also known as the National Marine Fisheries
Service (NMFS)”; the United States Fish and Wildlife Service; and the Federal Energy
Regulatory Commission. The record does not show any supporting declarations or
exhibits were filed.
Merced Irrigation District responded with another demurrer. The California
Department of Fish and Wildlife did not file a response. The federal agencies named as
real parties in interest filed a document entitled, “Special Appearance Contesting
Jurisdiction re: Non-Waiver of Sovereign Immunity….”
The federal agencies declined to consent to being named in the lawsuit. They
warned they would remove the case to federal court and then move for dismissal. The
special appearance filing also included the following explanation: “Under California law,
a real party in interest, although not a nominal party, may be bound by the judgement for
res judicata purposes, [citations], and under certain circumstances may incur other
liabilities such as payment of attorney fees.” The last statement presumably alluded to
Water Audit’s pleaded intention to seek “reasonable attorney fees according to the
California Code of Civil Procedure, section 1021.5, and other provisions of law.” (Italics
omitted.)
11.
In January 2024, the parties stipulated to dismissing the federal agencies. The trial
court accepted the stipulation and ordered those parties dismissed. The California
Department of Fish and Wildlife remained in the case as a named real party in interest.
In support of its final demurrer, MID requested judicial notice of approximately
270 pages of documents. Some of the documents were judicially noticed earlier in the
case, while others had only come into existence in recent months. The trial court never
ruled on the request.
Plaintiff’s opposition to the demurrer included a “Table of Exhibits” listing nearly
all evidence it had filed up to that point, including exhibits to the earlier pleadings. It
appears plaintiff believed or assumed the trial court had granted its prior request for
judicial notice of the exhibits and other documents. (See Evid. Code, § 456.) The record
does not expressly indicate whether the trial court considered any of plaintiff’s evidence
in ruling on defendant’s final demurrer.
The final demurrer was not argued. By a minute order issued on February 22,
2024, the demurrer was sustained without leave to amend. The stated grounds were as
follows:
“The Demurrer [to the first cause of action, i.e., public nuisance,] is
SUSTAINED WITHOUT LEAVE TO AMEND for failure to join
indispensable parties, a defect that does not appear to be curable by
amendment given the January 19, 2024 Stipulation and Order Dismissing
Federal Agencies NOAA FISHERIES AKA NATIONAL MARINE
FISHERIES SERVICE (NOAA/NMFS), UNITED STATES FISH and
WILDLIFE SERVICE (USFWS or FWS), [and] FEDERAL ENERGY
REGULATORY COMMISSION (FERC) BASED ON LACK OFA-
JURISDICTION. [Sic.]
“The Demurrer [to the second cause of action, i.e., the petition for
writ of mandate,] is SUSTAINED WITHOUT LEAVE TO AMEND.
Despite Fourt [sic] opportunities, Plaintiff has failed to state a cause of
action for Writ of Mandate addressing a specific action by a specific agency
occurring on a specific date that is not time barred.”
12.
A judgment of dismissal was entered in March 2024. Plaintiff’s timely notice of
appeal was filed in May 2024. The initial appellate briefing was completed in January
2025.
The California Department of Fish and Wildlife requested permission to file an
amicus curiae brief in support of plaintiff’s appeal. The request was granted, and the
brief was filed on March 3, 2025. Merced Irrigation District filed a 37-page response to
the amicus brief.
DISCUSSION
I. Public Nuisance
A. Standard of Review
“In reviewing an order sustaining a demurrer, we examine the operative complaint
de novo to determine whether it alleges facts sufficient to state a cause of action under
any legal theory.” (T.H. v. Novartis Pharmaceuticals Corp. (2017) 4 Cal.5th 145, 162.)
All “properly pleaded material facts” are accepted as true, but no weight is given to
conclusory allegations of fact or law. (Southern California Gas Leak Cases (2019) 7
Cal.5th 391, 395.) “The plaintiff has the burden of showing that the facts pleaded are
sufficient … and overcoming all of the legal grounds on which the trial court sustained
the demurrer, and if the defendant negates any essential element, we will affirm the order
sustaining the demurrer as to the cause of action.” (Martin v. Bridgeport Community
Assn., Inc. (2009) 173 Cal.App.4th 1024, 1031.)
“If a complaint is insufficient on any ground properly specified in a demurrer, an
order sustaining the demurrer must be upheld even though the particular ground upon
which the court sustained it may be untenable.” (Irwin v. City of Manhattan Beach
(1966) 65 Cal.2d 13, 20; accord, Hendy v. Losse (1991) 54 Cal.3d 723, 742.) “Where the
demurrer was sustained without leave to amend, we consider whether the plaintiff could
cure the defect by an amendment.” (T.H. v. Novartis Pharmaceuticals Corp., supra, 4
13.
Cal.5th at p. 162.) It is the plaintiff’s burden, however, to explain how the defect can be
cured. (Ibid.; Hendy, at p. 742.) When no amendments are proposed, the issue may be
treated as forfeited. (See Webb v. City of Riverside (2018) 23 Cal.App.5th 244, 251;
Rakestraw v. California Physicians’ Service (2000) 81 Cal.App.4th 39, 43–44; see
generally Paterno v. State of California (1999) 74 Cal.App.4th 68, 106 [appellate courts
are not required to make arguments for the parties].)
B. Law and Analysis
A nuisance is defined as anything “injurious to health, …or … indecent or
offensive to the senses, or an obstruction to the free use of property, … or [that]
unlawfully obstructs the free passage or use, in the customary manner, of any navigable
lake, or river, bay, stream, canal, or basin, or any public park, square, street, or highway.”
(Civ. Code, § 3479.) Therefore, the pollution, obstruction, or diversion of a waterway
may legally constitute a nuisance. (Helix Land Co. v. City of San Diego (1978) 82
Cal.App.3d 932, 949.)
Actionable nuisances are classified as public, private, or both. (Mendez v. Rancho
Valencia Resort Partners, LLC (2016) 3 Cal.App.5th 248, 261–262.) Plaintiff alleges
only a public nuisance. “A public nuisance is one which affects at the same time an
entire community or neighborhood, or any considerable number of persons, although the
extent of the annoyance or damage inflicted upon individuals may be unequal.” (Civ.
Code, § 3480.)
The trial court dismissed the nuisance claim for failure to join indispensable
parties. For reasons explained post, its conclusion appears based on legal errors that
include judicially noticing defendant’s evidence for its truth and improperly weighing the
evidence to make factual findings. Defendant argued additional grounds, however,
including lack of standing. “Standing is the threshold element required to state a cause of
action and, thus, lack of standing may be raised by demurrer.” (Martin v. Bridgeport
14.
Community Assn., Inc., supra, 173 Cal.App.4th at p. 1031; accord, Tarr v. Merco Constr.
Engineers, Inc. (1978) 84 Cal.App.3d 707, 713 [standing may be challenged by general
demurrer].)
“[T]he public nuisance doctrine in California is ‘aimed at the protection and
redress of community interests.’ [Citation.] To avoid a multiplicity of actions regarding
the invasion of such common rights, public nuisances are generally remedied by
designated public prosecutors, with a limited exception for suits by private individuals in
exceptional circumstances.” (Rincon Band of Luiseño Mission Indians etc. v. Flynt
(2021) 70 Cal.App.5th 1059, 1103, italics omitted.) The ability of private parties to sue
for public nuisance is restricted by statute. “A private person may maintain an action for
a public nuisance, if it is specially injurious to himself, but not otherwise.” (Civ. Code,
§ 3493; see Code Civ. Proc., § 731.) This means private plaintiffs “must adequately
allege the existence of a nuisance affecting the community at large, and also that they
sustained a special injury, distinct in some way from the more general public harm.”
(Flynt, at p. 1102.)
Plaintiff argues it has standing because of its “special status” as “a public benefit
corporation dedicated to protecting natural watercourses and the associated life.” The
argument is made without supporting authority, and it fails to persuade. “A public-
nuisance-abatement action must be prosecuted by a governmental entity and may not be
initiated by a private party unless the nuisance is personally injurious to that private
party.” (County of Santa Clara v. Superior Court (2010) 50 Cal.4th 35, 55.) “The
damage suffered must be different in kind, not merely in degree, from that suffered by
other members of the public.” (Kempton v. City of Los Angeles (2008) 165 Cal.App.4th
1344, 1349.)
“Code of Civil Procedure section 731 confers standing only on private persons, as
opposed to the enumerated public prosecutors, ‘whose property is injuriously affected, or
whose personal enjoyment is lessened by a nuisance.’” (Rincon Band of Luiseño Mission
15.
Indians etc. v. Flynt, supra, 70 Cal.App.5th at p. 1103.) In other words, “the types of
harms one would expect those in the community affected by the alleged nuisance to
suffer.” (Ibid.) The record indicates plaintiff is based in Napa, California. The pleadings
do not identify any real property interests in the community where the alleged nuisance is
located, nor any particular connection to that community or even the Central Valley.
Plaintiff essentially claims to have standing because it cares more about California’s
rivers and fish than other members of the general public. If personal passions were
sufficient, the statutory restrictions could always be circumvented by forming an interest
group and publishing a mission statement tailored to the subject matter.
The case of Hacala v. Bird Rides, Inc. (2023) 90 Cal.App.5th 292 illustrates
legitimate private party standing. There, a defendant’s business model allowed people in
Los Angeles to rent motorized scooters using a “smartphone ‘app.’” The company was
able “to control, unlock, and rent its scooters to customers who downloaded the app from
[its] website.” (Id. at p. 300.) Customers could “pick up and leave scooters at any public
location without the inconvenience of retrieving or returning the scooters to a designated
docking location.” (Ibid.) The scooters were sometimes discarded in a careless manner,
which allegedly affected “‘a considerable number of people by creating tripping
hazards.’” (Id. at p. 324.) The Hacala plaintiff had standing to bring a claim for public
nuisance because she tripped over a scooter on a sidewalk, “fell, and sustained serious
physical injuries.” (Id. at pp. 300; see id. at p. 327 [“We conclude the allegations are
sufficient to state a private action for public nuisance to redress this personal injury”].)
We note the operative complaint alleges plaintiff’s expenditure of “approximately
$250,000 on scientists, technologists and counsel in an attempt to understand [Merced
Irrigation District’s] unlawful injury to the free passage of fish” constitutes a special
injury that meets the standing requirement. Plaintiff does not discuss this theory in its
briefing, which is reason enough to disregard it. (See Keyes v. Bowen (2010) 189
Cal.App.4th 647, 656 [“The appellant may not simply incorporate by reference
16.
arguments made in papers filed in the trial court, rather than briefing them on appeal”].)
Two cases are cited in the complaint, Mangini v. Aerojet-General Corp. (1991) 230
Cal.App.3d 1125 and Tesoro Refining & Marketing Co. LLC v. City of Long Beach
(C.D.Cal. 2017) 334 F.Supp.3d 1031, but “citing cases without any discussion of their
application to the present case results in forfeiture.” (Allen v. City of Sacramento (2015)
234 Cal.App.4th 41, 52.) Although it is unnecessary, we will explain why neither case is
supportive.
In Mangini, the owners of 2,400 acres of land in Sacramento County sued parties
who had “leased the property from prior owners and who allegedly contaminated the
property with hazardous waste during the leasehold.” (Mangini v. Aerojet-General
Corp., supra, 230 Cal.App.3d at p. 1130.) The civil complaint alleged the defendants
were liable for creating a public and private nuisance. (Id. at p. 1132.) One of several
issues on appeal was whether a demurrer to the public nuisance claim was properly
sustained for failure to allege a special injury. The appellate court reversed based on
allegations of financial obligations imposed upon the plaintiffs as a result of the
defendants’ conduct. The plaintiffs alleged they were “compelled” and “required” by
local government authorities “to undertake testing of the property.” (Id. at pp. 1132,
1138.) The testing costs were held to constitute a “‘special injury’” under Civil Code
section 3493. (Mangini, at p. 1138.) The key distinction here is Water Audit’s failure to
allege compelled or unavoidable expenditures as opposed to voluntary spending in
furtherance of its litigation objectives.
In Tesoro, the plaintiffs had ownership interests in a property (the Site) that was
contaminated by chemical pollutants. (Tesoro Refining & Marketing Co. LLC v. City of
Long Beach, supra, 334 F.Supp.3d at pp. 1039–1040.) The lawsuit alleged multiple
defendants were responsible for the contamination and liable for public nuisance. In
moving to dismiss the claim, the defendants argued “that Plaintiffs’ only alleged unique
harm is the costs associated with cleanup of the Site, which, according to the
17.
[defendants], Plaintiffs [had] voluntarily assumed.” (Id. at p. 1053.) But it was
“undisputed that a public entity … [had] ordered the cleanup and remediation of the
Site.” (Id. at p. 1054.) The district court ruled there were sufficient allegations the
plaintiffs “did not voluntarily assume the duty to comply” with the remediation order but
were instead legally “bound to do so.” (Id. at p. 1053.) In other words, they pleaded
around the rule “that ‘voluntarily incurred costs do not suffice to satisfy the special injury
requirement for public nuisance standing.’” (Id. at pp. 1053–1054.)
Water Audit cites no authority for the proposition that standing can be
manufactured by spending money to explore the possibility of suing the government and
calling the expenditures a financial injury. Water Audit does not substantively address
the special injury requirement in its appellate briefing, nor does it propose any curative
amendments. It references the public trust and private attorney general doctrines, but
cites no authority suggesting either provide an exception to the standing requirement of
Civil Code section 3493. Failure to provide legal authority and analysis to support a
contention forfeits the contention. (Ewald v. Nationstar Mortgage, LLC (2017) 13
Cal.App.5th 947, 948.) Therefore, Water Audit has not met its burden to show reversible
error in the dismissal of its cause of action for public nuisance.
II. The Petition for Writ of Mandate
A. Legal Overview
The following information is essential to understanding the parties’ arguments
concerning the writ petition, especially the issue of necessary and indispensable parties.
By enactment of the Federal Power Act (16 U.S.C. §§ 791a-828c) (sometimes
FPA), Congress centralized the process for licensing hydroelectric facilities “by
establishing one federal agency as gatekeeper for most hydropower developments: the
Federal Power Commission,” now known as the Federal Energy Regulatory Commission
(FERC). (Allen v. United States (E.D.Mich. 2021) 572 F.Supp.3d 411, 419.) The
18.
Federal Power Act “makes it unlawful for any person, State, or municipality to
‘construct, operate, or maintain’ a hydroelectric power project that is within FERC’s
jurisdiction without a valid license from FERC or a federal permit issued prior to 1920.”
(City of Oswego, N.Y. v. F.E.R.C. (D.C. Cir. 1996) 97 F.3d 1490, 1492, quoting 16
U.S.C. § 817(1); see S. D. Warren Co. v. Maine Bd. of Environmental Protection (2006)
547 U.S. 370, 373.) In short, most parties “seeking to construct, operate or maintain a
hydroelectric power facility must obtain a license from FERC.” (High Country
Resources v. F.E.R.C. (9th Cir. 2001) 255 F.3d 741, 742; see Turlock Irrigation Dist. v.
FERC (D.C. Cir. 2022) 36 F.4th 1179, 1181 & fn. 1 [explaining FERC has licensing
authority over “private, municipal and State hydroelectric projects subject to federal
jurisdiction” but not “[f]ederally-owned hydroelectric projects”].)
“Project” is a defined term in the Federal Power Act.3 The parties’ use of this
term in the pleadings and briefs impliedly refers to the FPA definition. The operative
pleading impliedly alleges, and plaintiff’s briefs explicitly contend, that the C-H Dam is
not part of any FERC-licensed projects. Merced Irrigation District concedes this is true.
The issue relates to the parties’ ostensible dispute over whether other government
agencies control MID’s ability to reopen the C-H Dam fish ladder. Under the FPA,
FERC’s licensing authority is generally limited to hydroelectric projects and “project
works,” with the latter term defined as “the physical structures of a project” (16 U.S.C.
§ 796(12)). (Allen v. U. S. (6th Cir. 2023) 83 F.4th 564, 570; see Niagara Mohawk
3“‘[P]roject’ means complete unit of improvement or development, consisting of a power
house, all water conduits, all dams and appurtenant works and structures (including navigation
structures) which are a part of said unit, and all storage, diverting, or forebay reservoirs directly
connected therewith, the primary line or lines transmitting power therefrom to the point of
junction with the distribution system or with the interconnected primary transmission system, all
miscellaneous structures used and useful in connection with said unit or any part thereof, and all
water-rights, rights-of-way, ditches, dams, reservoirs, lands, or interest in lands the use and
occupancy of which are necessary or appropriate in the maintenance and operation of such unit.”
(16 U.S.C. § 796(11).)
19.
Power Corp. v. Hudson River-Black River Regulating Dist. (2d Cir. 2012) 673 F.3d 84,
95–98.) “So while the [FPA] empowers FERC to exercise ‘operational control’ over
federal power projects, [citation], non-project facilities that lie outside project boundaries
‘remain[] under the jurisdiction of the States.’” (City of Salisbury, North Carolina v.
FERC (D.C. Cir. 2022) 36 F.4th 1164, 1171.)
The Federal Power Act authorizes FERC to issue licenses for periods of up to 50
years. (16 U.S.C. § 799.) “When any such licenses come up for renewal, the applicant
must begin a lengthy and complex relicensing process. [Citation.] If FERC does not
issue a new license before the expiration of the existing license, FERC is required to issue
annual licenses ‘to the then licensee under the terms and conditions of the original
license’” while the application is pending. (Natural Resources Defense Council v.
Kempthorne (E.D.Cal. 2009) 621 F.Supp.2d 954, 974, underscoring omitted.) Existing
licensees are not automatically entitled to receive another long-term license; FERC has
numerous options that include taking over the project itself. (16 U.S.C. §§ 807, 808; City
of Tacoma, Washington v. F.E.R.C. (D.C. Cir. 2006) 460 F.3d 53, 71.)
“[I]n addition to the power and development purposes for which licenses are
issued, [FERC] shall give equal consideration to the purposes of energy conservation, the
protection, mitigation of damage to, and enhancement of, fish and wildlife (including
related spawning grounds and habitat), the protection of recreational opportunities, and
the preservation of other aspects of environmental quality.” (16 U.S.C. 797(e).) Simply
stated, “FERC must consider environmental issues when deciding whether to issue
hydropower licenses.” (U. S. Dept. of Interior v. F.E.R.C. (D.C. Cir. 1992) 952 F.2d 538,
543.)
The Federal Power Act “specifies that each project license shall include conditions
for the protection, mitigation and enhancement of fish, wildlife and related spawning
grounds and habitat, based on recommendations received from various federal and state
fish and wildlife agencies.” (State of Cal. v. F.E.R.C. (9th Cir. 1992) 966 F.2d 1541,
20.
1547, citing 16 U.S.C. § 803(j).) The federal agencies are the National Marine Fisheries
Service (see fn. 1, ante) and the United States Fish and Wildlife Service. (16 U.S.C.
§ 803(j)(1).) In California, the relevant state agencies include the Department of Fish and
Wildlife. (See, e.g., California v. FERC (1990) 495 U.S. 490, 495.)
As stated in footnote 1, ante, the National Marine Fisheries Service (sometimes
NMFS) is part of the Department of Commerce. The United States Fish and Wildlife
Service (sometimes USFWS) is part of the Department of the Interior. Consulting with
these agencies is required not only by the Federal Power Act, but other federal laws,
including the Endangered Species Act (sometimes ESA). (See 16 U.S.C. § 1536; 50
C.F.R. § 402.14 (2025); Conservation Congress v. Finley (9th Cir. 2014) 774 F.3d 611,
615.) “The [USFWS] administers the ESA with respect to species under the jurisdiction
of the Secretary of the Interior, while the National Marine Fisheries Service (NMFS)
administers the ESA with respect to species under the jurisdiction of the Secretary of
Commerce.” (National Assn. of Home Builders v. Defenders of Wildlife (2007) 551 U.S.
644, 651.)
The California Department of Fish and Wildlife (sometimes CDFW) is part of the
California Natural Resources Agency.4 (Fish & G. Code, § 700, subd. (a).) CDFW
administers and enforces the Fish and Game Code “through regulations adopted [by
CDFW], except as otherwise specifically provided by [that] code.” (Id., § 702.) CDFW
is separate and distinct from the Fish and Game Commission, though the latter is also part
of the Natural Resources Agency. (Id., § 101; Wildlife Alive v. Chickering (1976) 18
Cal.3d 190, 205.)
4Prior to 2013, CDFW was known as the Department of Fish and Game. (Coastside
Fishing Club v. California Fish & Game Com. (2013) 215 Cal.App.4th 397, 405, fn. 2.)
“Whenever the term ‘Department of Fish and Game’ appears in a law, the term means the
‘Department of Fish and Wildlife.’” (Fish & G. Code, § 700, subd. (c).)
21.
Although FERC must consider and give weight to agency recommendations on
licensing conditions, it is not ordinarily bound to adopt them. (See 16 U.S.C. § 803(j)(2);
California v. FERC, supra, 495 U.S. at pp. 499–500.) The Federal Power Act contains a
specific provision, however, that requires FERC to impose conditions for “the
construction, maintenance, and operation” of “such fishways as may be prescribed by the
Secretary of Commerce … or the Secretary of the Interior.” (16 U.S.C. § 811.)
Therefore, if FERC has licensing authority over a dam, the USFWS and NMFS have the
ability to require fish passage measures as a condition of licensure. (Wisconsin Power &
Light Co. v. F.E.R.C. (D.C. Cir. 2004) 363 F.3d 453, 460; American Rivers v. F.E.R.C.
(9th Cir. 1999) 201 F.3d 1186, 1206–1210.)
Another exception to FERC’s broad authority over licensing conditions is imposed
by the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.), better known as
the Clean Water Act. “Section 401 of the Clean Water Act [33 U.S.C. § 1341] ‘requires
States to provide a water quality certification before a federal license or permit can be
issued for activities that may result in any discharge into intrastate navigable waters.’
[Citation.] States may adopt water quality standards that are more stringent than federal
law requires, and any limitation included in the state certification becomes a condition on
any federal license.” (California State Water Resources Control v. FERC (9th Cir. 2022)
43 F.4th 920, 924, quoting PUD No. 1 of Jefferson Cnty. v. Wash. Dept. of Ecology
(1994) 511 U.S. 700, 707.) “A FERC hydroelectric license thus is ineffective until the
relevant state issues or waives a water quality certification, [citation], which may impose
conditions to control pollution or implement other state laws.” (City of Salisbury, North
Carolina v. FERC, supra, 36 F.4th at p. 1166.) In California, water quality certifications
are issued by the State Water Resources Control Board (sometimes SWRCB). (See
County of Butte v. Department of Water Resources (2022) 13 Cal.5th 612, 623.)
22.
B. The Parties’ Evidence and Related Contentions
1. Applicable Law re: Judicial Notice
Merced Irrigation District argues the “actual facts presented to the trial court and
subject to judicial notice directly contradict [plaintiff’s] factual allegations and legal
claims ….” MID also submits that we “‘may take judicial notice of facts not subject to
judicial notice by the trial court.’” We are unsure of what MID is suggesting, but the
limitations on judicially noticing documents for the truth of their contents apply to both
trial courts and appellate courts.5
“In ruling on a demurrer, a court may consider facts of which it has taken judicial
notice. [Citation.] This includes the existence of a document. When judicial notice is
taken of a document, however, the truthfulness and proper interpretation of the document
are disputable.” (StorMedia Inc. v. Superior Court (1999) 20 Cal.4th 449, 456, fn. 9.)
The same restriction applies when judicial notice is taken of official acts and
government records. (Evid. Code., § 452, subds. (c), (d).) Most of the documents of
which the trial court expressly took judicial notice are letters authored by, and exchanged
between, government agency officials. “Although we could take judicial notice of the
existence, content, and authenticity of such letters, doing so would not establish the truth
of critical factual matters asserted in those documents.” (People v. Castillo (2010) 49
Cal.4th 145, 157, fn. omitted.)
In filings below, defendant argued certain documents were subject to the hearsay
exception described in Evidence Code section 1280 for writings “made by and within the
scope of duty of a public employee.” (Id., subd. (a).) The argument was misguided.
Evidence Code section 1280 generally concerns admissibility of evidence
5The quote relied upon by MID comes from People v. Superior Court (J.C. Penney
Corp., Inc.) (2019) 34 Cal.App.5th 376 at pages 386–387, citing Taliaferro v. County of Contra
Costa (1960) 182 Cal.App.2d 587 at page 592. What Taliaferro actually says is, “An appellate
court may judicially notice a fact even though the record does not show that notice thereof was
taken by the trial court.” (Taliaferro, at p. 592.)
23.
notwithstanding the hearsay rule; judicial notice is a separate issue. When judicial notice
is taken of an official act, “what is being noticed is the existence of the act, not that what
is asserted in the act is true. [Citation.] The truth of any factual matters that might be
deduced from official records is not the proper subject of judicial notice.” (Lockley v.
Law Office of Cantrell, Green, Pekich, Cruz & McCort (2001) 91 Cal.App.4th 875, 885;
accord, In re Vicks (2013) 56 Cal.4th 274, 314.)
Lastly, we address the lack of rulings on plaintiff’s request for judicial notice and
some of defendant’s requests for judicial notice. “If the trial court denies a request to
take judicial notice of any matter, the court shall at the earliest practicable time so advise
the parties and indicate for the record that it has denied the request.” (Evid. Code, § 456.)
Since no such advisements were given in this case, we assume all requests for judicial
notice were granted. (E.g., Casey v. Hill (2022) 79 Cal.App.5th 937, 975, fn. 16;
Aaronoff v. Martinez-Senftner (2006) 136 Cal.App.4th 910, 919.)
The following summary of the parties’ evidence is unfortunately necessary to
explain their arguments regarding the grounds asserted on demurrer. We do not assume
the truth of these purported facts. Insofar as either party may complain some statements
constitute uniformed or otherwise erroneous interpretations of the evidence, such
complaints only illustrate why the purposes for which judicially noticed documents can
be used are limited.
2. Factual Contentions Based on Evidence Outside the Petition6
The operative pleading alleges the “New Exchequer and the McSwain Dams are
administered as FERC Project No. 2179, and the Merced Falls Dam as FERC Project
6Parenthetical citations to “MID RJN” indicate defendant’s request for judicial notice in
support of its demurrer to the operative pleading. Parenthetical citations to “WAC RJN” indicate
plaintiff’s request for judicial notice filed in opposition to MID’s demurrer to the first amended
complaint/petition. Because plaintiff’s evidence was attached to various declarations filed by its
attorney, William McKinnon, further citations to the date and exhibit will be provided. For
example, “WAC RJN, McKinnon Dec. [3/3/23], Ex. N” refers to plaintiff’s request for judicial
notice of the document marked as Exhibit N attached to the Declaration of William McKinnon
24.
No. 2467.” These projects are also respectively known as the “Merced River Project”
and “Merced Falls Project.” (MID RJN, Ex. A) Long-term licenses for these projects
were issued by the Federal Power Commission (FERC’s predecessor) in 1964 and 1969,
respectively. (MID RJN, Ex. E & “Exhibit J” to MID’s original RJN) Both licenses
expired in 2014, and the projects have since been operated pursuant to annual licenses.
The Merced Falls Dam was previously owned by Pacific Gas and Electric
Company (PG&E). (MID RJN, Ex. G & “Exhibit J” to MID’s original RJN) A transfer
of ownership from PG&E to Merced Irrigation District reportedly occurred in 2017.
(“Exhibit J” to MID’s original RJN) The Merced Falls Dam has a fish ladder, which is
not to be confused with the fish ladder at the downstream C-H Dam. (MID RJN Exs. A,
C)
As noted, the Merced Falls Project was federally licensed in 1969. In 1971, a
series of letters were exchanged between state and federal agencies regarding the fish
ladder at the Merced Falls Dam (then owned by PG&E). A letter dated March 25, 1971,
from the California Department of Fish and Game (see fn. 4, ante) to PG&E contained
the following statements by the department’s regional manager:
“… There is no reason that Pacific Gas and Electric Company
should continue passing water over the fish ladder on the Merced Falls
Dam as long as fish water releases are provided past Merced Falls Dam in
accordance with those releases specified on the Merced Irrigation District’s
license for [the Merced River Project]. Requirement for fish water in the
ladder at Merced Falls Dam had a value before McSwain Reservoir was
constructed; now there is no spawning area available above Merced Falls.
“The Department of Fish and Game has also requested the Merced
Irrigation District to make the fish ladder on their Crocker Huffman Dam
inoperable, so that salmon would not pass this ladder but turn into a
spawning channel which has been constructed. This is part of the program
to restore salmon runs in the Merced River. [¶] We suggest that you notify
filed March 3, 2023. In some instances the same document was proffered by both parties, which
will not always be indicated.
25.
the Federal Power Commission that the Department of Fish and Game no
longer requires this release of water over the fish ladder at Merced Falls
Dam.” (MID RJN, Ex. L)
In a letter dated June 22, 1971, from the Department of the Interior to the Federal
Power Commission, a deputy assistant to the Secretary of the Interior wrote that the
Secretary had “no objection to discontinuing operation of the fish ladder at the Merced
Falls dam.” (MID RJN, Ex. D) Six weeks later, the Federal Power Commission sent a
letter to PG&E that stated, in relevant part, “The proposed action of making the Merced
Falls dam fishway inoperable … hereby is approved by the Commission.” (MID RJN,
Ex. C)
Defendant relies on the 1971 letters for the truth of all statements therein. The
letter from the California Department of Fish and Game to PG&E allegedly proves that
state officials “ordered” Merced Irrigation District to close the C-H Dam fish ladder in
1970. The other letters are cited as proof “the Department of Interior and the Federal
Energy Regulatory Commission … concurred in the closure of the upstream fish ladder at
Merced Falls Dam.”7 (Italics added.)
In terms of the chronological history, there is a 35-year gap in the parties’
evidence. Next in time are excerpts from a 100-page report entitled, “A Feasibility
Investigation of Reintroduction of Anadromous Salmonids above Crocker-Huffman Dam
on the Merced River.” (MID RJN, Ex. B) Dated “December 2007,” the report was
“prepared for the U.S. Fish and Wildlife Service Anadromous Fish Restoration Program”
by a scientist named David Vogel of “Natural Resource Scientists, Inc.” This evidence is
7It is unclear why defendant perceives evidence of federal agency approval regarding the
fish ladder at the Merced Falls Dam to be supportive of its positions. There is no dispute FERC
has federal licensing jurisdiction over the Merced Falls Dam by virtue of its authority over the
Merced Falls Project. We observe defendant proffered no similar evidence regarding the alleged
closure of the C-H Dam fish ladder in 1970. The absence of such evidence could be viewed as
supportive of plaintiff’s argument that because the C-H Dam is not part of a federally licensed
project, defendant does not need the permission of any federal agencies to reopen the C-H Dam
fish ladder.
26.
heavily relied upon by defendant, and for ease of reference it is hereafter cited as the
Vogel study or Vogel report.
The Vogel study included “an examination of the presently [as of 2007] non-
functional fishway on [the C-H Dam] to determine measures that would be necessary to
modify or replace the fishway should suitable anadromous salmonid habitats be found
upstream of the dam and fish were reintroduced into upstream areas.” As relevant here,
Mr. Vogel concluded the C-H Dam fish ladder has “an outdated design and would
probably limit upstream migration of anadromous salmonids if the ladder were made
operational (i.e., opening up [water] flow into the ladder). Because operation of the
existing ladder would probably cause fish delay or blockage leading to stress or injury, it
is likely that one or more new fish ladders meeting modern-day criteria would have to be
added to the dam.” Relatedly, Mr. Vogel opined that “reintroduction of anadromous
salmonids upstream of Crocker-Huffman Dam would be a very difficult measure to
successfully implement; the opportunities are few and the constraints are many.”
We pause to note the Vogel report was one of the documents Merced Irrigation
District argued “[fell] within the hearsay exception for public records” under Evidence
Code section 1280. The trial court took judicial notice of the excerpts “and the contents
therein,” ruling the “documents constitute official acts of government agencies.” At best,
the Vogel report implies that the United States Fish and Wildlife Service took the official
act of commissioning a study. The study was apparently conducted and reported on by
one or more independent contractors, i.e., nongovernmental third parties. No aspect of
the report upon which defendant relies was judicially noticeable for its truth except,
arguably, the fact that the study and report were commissioned by the government.
In November 2008, Merced Irrigation District gave written notice to FERC of its
“intent to file an application for a new license for the Merced River Hydroelectric
Project,” i.e., the project involving the McSwain Dam and New Exchequer Dam. (MID
RJN, Ex. E) Thus began a complex relicensing process that defendant contends is still
27.
ongoing more than 16 years later. In April 2009, PG&E gave FERC written notice of its
intent to apply for a new license for the Merced Falls Project. (MID RJN, Ex. F)
In October 2009, in connection with its Merced River Project relicensing
application, defendant filed with FERC a motion to dismiss “the Notices of Study Plan
Dispute filed October 5, 2009 by the [USFWS] of the U.S. Department of the Interior,
and the [NMFS] of the U.S. Department of Commerce.” (WAC RJN, McKinnon Dec.
[1/10/23], Ex. I) The crux of the matter, in very simple terms, was whether USFWS
and/or NMFS had authority to take certain actions in the relicensing process under
section 18 of the Federal Power Act.
Section 18 of the FPA (16 U.S.C. § 811) is the previously discussed statute that
requires FERC to adopt fishway measures prescribed by USFWS and/or NMFS as a
condition of licensing if FERC has licensing authority over the dams in question. The
imposition of such measures for the McSwain and New Exchequer Dams would
necessarily presume the availability of fish passage at the downstream C-H Dam, i.e.,
reopening the C-H Dam fish ladder. Defendant argued Section 18 of the FPA could not
be invoked because, inter alia, FERC had already “found that Crocker-Huffman is not a
licensed project facility and, consequently, that [FERC] has ‘no authority to alter the
operation of Crocker-Huffman,’” i.e., the C-H Dam.
In Merced Irrigation District’s October 2009 motion to FERC, it further argued (as
it continues to allege in this case) the C-H Dam fish ladder was “disabled at the direction
of the California Department of Fish and Game … in the early 1970s in association with
the construction of a salmon spawning channel just downstream of Crocker-Huffman
Dam.” MID summarized its position as follows: “[W]hile [USFWS] is correct that the
Federal Power Act gives it the authority to prescribe fishways as a condition of a FERC
license, that authority does not exist in this proceeding with respect to anadromous
salmonids because a structure downriver of the licensed project—admittedly outside of
FERC jurisdiction [the C-H Dam]—presents an absolute obstacle to fish migration.
28.
Since [USFWS] cannot prescribe a fishway in connection with this relicensing
proceeding, it lacks jurisdiction to initiate a study plan dispute.” MID asserted that
NMFS lacked jurisdiction for the same reasons.
In November 2009, in the midst of MID’s dispute with the federal agencies, MID
received a letter from the California Department of Fish and Game, i.e., CDFW (see fn.
4, ante). (MID RJN, Ex. Q; WAC RJN, McKinnon Dec. [9/19/22], Ex. A) This letter
features prominently in the current arguments of both defendant and plaintiff. The letter
states, in relevant part:
“The [CDFW] has reviewed our previous direction regarding the fish
ladder at Merced Irrigation District’s [MID] Crocker-Huffman Diversion
Dam, in the context of current condition of the anadromous fish populations
in the Merced River, historic and ongoing efforts to manage those
populations, and Fish and Game Code (FGC) § 5901, which provides that
‘it is unlawful to construct or maintain’ any barrier ‘that prevents, impedes,
or tends to prevent or impede, the passing of fish up and down stream,’
unless otherwise authorized by the FGC.
“[CDFW and MID] have made several adaptive changes at the
Crocker-Huffman Diversion Dam over the years to reduce the impact the
diversion and dam have on fish resources. At one time, [MID] operated a
fishway at Crocker-Huffman. Then, in the early 1970s, [CDFW]
recommended closing the fish ladder in conjunction with construction of an
experimental spawning channel adjacent to the diversion dam. At that
time, [CDFW] believed a spawning channel, along with minimum flow
releases required by [FERC] from upstream hydropower projects
(Nos. 2467 and 2179), would provide the best opportunity for restoring
salmon on the Merced River. Unfortunately the spawning channel
experiment failed and [MID] may no longer rely on [CDFW’s] letter from
the 1970s. Additional management actions are necessary to maintain and
recover anadromous fish in the Merced River.
“Today, the [C-H Dam] impedes the passage of resident and
anadromous fish up and down stream except during rare high flow events.
Meanwhile, the fall-run Chinook salmon (Oncorhynchus tshawytscha) and
steelhead rainbow trout (O. mykiss) anadromous fish populations in the
Merced River have deteriorated to extremely low levels. Given this
background and the current situation, [CDFW] has determined that fish
passage at the [C-H Dam] must be restored. FGC §5935 states ‘the owner
29.
of any dam upon which a fishway has been provided shall keep the fishway
in repair and open and free from obstructions to the passage of fish at all
times’. The [CDFW] directs [MID] to consult with [CDFW] to i) make a
determination regarding anadromous fish passage adequacy of the existing
(but closed) [C-H Dam] fishway and ii) assist [MID] in developing a
Crocker-Huffman anadromous fish passage plan.”
In a footnote, CDFW wrote, “This plan would include, but not be limited to,
identifying the timeframes for fish passage implementation, restoration of anadromous
fish habitat upstream of Crocker-Huffman in conjunction with passing fish upstream of
Crocker-Huffman, and development of provisions to preclude further impacts to the
Merced River anadromous fish populations as a result of operation of a fishway at
Crocker-Huffman Dam.” The letter concluded by saying CDFW did not “expect nor
desire that opening the existing fishway take place in an immediate and unplanned
manner, but rather in a thoughtful and collaborative manner that leads to improved fish
habitat and fish populations, as well as fitting with [MID’s] operational needs to the
greatest extent possible.”
In December 2009, FERC sent a letter to Merced Irrigation District. (WAC RJN,
McKinnon Dec. [3/3/23], Ex. S) In relevant part, the letter stated FERC’s position that
the C-H Dam “is maintained by MID for the implementation of its irrigation program, is
not a licensed project facility, and therefore, is not within [FERC’s] jurisdiction.”
In November 2010, the National Marine Fisheries Service sent a letter to both
Merced Irrigation District and PG&E. (MID RJN, Ex. R) In this letter, NMFS opined
“that fish passage at Crocker-Huffman Dam and Merced Falls Dam should be re-
established as a near-term, interim measure toward habitat restoration and recovery of
Merced River’s anadromous fish populations.” Accordingly, NMFS requested
“hydraulic start-up testing [of the fish ladders at both locations] beginning in January or
February, 2011.” NMFS also “recommend[s] hydraulic evaluation and testing of the
now-defunct ‘spawning channel’ as an alternate means of fish passage at the Crocker-
Huffman site.”
30.
In April 2011, Merced Irrigation District sent a letter to the National Marine
Fisheries Service regarding the C-H Dam fish ladder. (MID RJN, Ex. M) The letter
informed NMFS of MID’s view that reopening the fish ladder, even for testing, would be
“premature” since “little would be gained by establishing fish passage at [the C-H Dam].”
MID cited the 2007 Vogel study as justification for declining to perform the requested
testing.
In January 2012, NMFS sent another letter to Merced Irrigation District and
PG&E. (MID RJN, Ex. S) The letter states that NMFS’s request for fish ladder testing
was based on “detailed, on-site assessments of the fish ladders” performed by NMFS
“fish passage engineers and biologists” in late 2010. Based on those inspections, NMFS
“determined the fish ladders could function hydraulically if water were once again
allowed to flow through them.” The letter further states, “Unfortunately, both MID and
PG&E declined to comply with NMFS’ request to start up their respective fish ladders.
Therefore, NMFS is investigating whether unauthorized ‘take’ of threatened Central
Valley (CV) steelhead [within the meaning of the federal Endangered Species Act] is
occurring on an annual or seasonal basis downstream of the Crocker-Huffman Dam on
the Merced River.” In concluding statements, NMFS “again urge[d] MID and PG&E to
take immediate steps toward reinstating fish passage operations at Crocker-Huffman and
Merced Falls dams” and “invite[d]” them “to plan and implement hydraulic start-up
testing activities beginning in January or February of 2012.” Both dam owners declined
the invitation.
In January 2014, NMFS sent a letter to FERC enclosing a report from an NMFS-
funded “Merced River Fish Passage Feasibility Study” conducted the previous year.
(MID RJN, Ex. G) The letter states that “despite NMFS repeated efforts to obtain
information about potential anadromous fish habitat, or to further study the inactive fish
ladders, neither [FERC] nor [Merced Irrigation District or PG&E] adopted NMFS’
requests for anadromous fish-related information, activation of the fish ladders, or study
31.
in areas upstream of New Exchequer Dam.” Like the 2007 Vogel study, the NMFS-
funded study appears to have been conducted by nongovernmental third parties. Unlike
the Vogel study, the “Merced River Fish Passage Feasibility Study” reached the
following notable conclusions:
“Reinstating the existing fish ladder [at the C-H Dam] would be the
least costly and least time intensive approach to providing some [fish]
passage over the dam.… Although the ladder is expected to perform below
modern standards, the fish ladder could improve fish passage over the dam
at certain flows. Reinstating the ladder is not considered a long term
solution but it is a feasible alternative for providing some improvements to
upstream and downstream migration passage.”
“The habitat above Crocker‐Huffman provides habitat for salmonids,
including spawning habitat. Fish have used it in the past, and will use it in
the future if passage is provided. The highest value below New Exchequer
is in the reach immediately above Crocker‐Huffman. Passage into this
reach should be provided as soon as possible. [¶] … [¶] The existing fish
ladder will at least provide an immediate route for passage…. We
recommend that the ladder be utilized either as is or with modifications.
However, a long‐term solution should be put into place by utilizing the
former spawning channel or constructing a new ladder and associated
facilities.”
In December 2015, FERC issued a “Final Environmental Impact Statement”
(FEIS) for the Merced River Project and Merced Falls project.8 (MID RJN, Ex. A)
Defendant cites this document as evidence that “fish passage at C-H Dam” was
considered “as part of the relicensing process … due largely to the [California State
Water Resources Control Board’s] inclusion of passage planning in its preliminary water
quality certification for the relicensing. [Record citation.] While FERC staff did not
recommend specific measures to require fish passage at C-H Dam, FERC recognized that
8In defendant’s responsive brief, MID alleges FERC is currently “preparing a
supplemental environmental impact statement, and on April 26, 2022, NMFS requested it
include further evaluations of anadromous fish species and habitat in the Merced River up to C-
H Dam.” (Citing MID RJN, Ex. J)
32.
any conditions in a water quality certification issued by the SWRCB would be mandatory
conditions in the license.”
As reflected in the 2015 FEIS, the State Water Resources Control Board submitted
a preliminary licensing condition with two alternatives: “Develop… a fish passage or
habitat restoration plan that would result in [(1)] fish passage over Crocker-Huffman,
McSwain, and New Exchequer dams or [(2)] decreasing water temperature in and
downstream of the project.” (Italics added.) However, when the SWRCB submitted its
final water quality certification in 2020, it removed the fish passage requirement.
(“Exhibit J” to MID’s original RJN)
Defendant’s briefing glosses over the absence of any conditions regarding the fish
ladder in the final water quality certification. Without citing the actual document, MID
writes, “In 2020, the SWRCB issued a final water quality certification that reserved its
authority concerning anadromous fish reintroduction.” The statement presumably refers
to the following language in the document:
“The State Water Board reserves the authority to modify or add conditions
to this certification if State Water Board staff determine that it is reasonably
foreseeable that state or federally listed anadromous fish species will be
reintroduced into Projects-affected streams to ensure adequate protection of
SR/SJR Basin Plan objectives and beneficial uses. For this condition,
‘reasonably foreseeable’ includes, but is not limited to, a comprehensive
reintroduction effort or plan that has a reasonable likelihood of
implementation within the following 18 months. [¶] The State Water Board
also reserves the authority to require the Licensee to develop and conduct
studies if it is reasonably foreseeable that listed anadromous fish species
will be reintroduced into Projects-affected areas.”
Plaintiff eventually learned about the controversy over the fish ladder. In a letter
to Merced Irrigation District dated August 29, 2022, plaintiff alleged that for “over a
decade, [MID] has failed to respond to requests by state and federal regulators to repair
and reopen” the C-H Dam fish ladder. (WAC RJN, McKinnon Dec. [1/10/23], Ex. G) In
a letter from defendant to plaintiff dated September 8, 2022, defendant stated it was “not
33.
able to respond to the claims and arguments … pending further action by FERC. We
instead expect FERC, and other agencies with jurisdiction, will address the issues you
raise, including issues related to ‘fishways’ … and MID’s duties under the Fish and
Game Code and other provisions of State and Federal Law….” (WAC RJN, McKinnon
Dec. [1/10/23], Ex. H)
A few months after the lawsuit was filed, the California Department of Fish and
Wildlife contacted defendant about the fish ladder. In a letter dated December 8, 2022,
CDFW wrote that it was “aware of the verified complaint and petition (complaint) Water
Audit California (WAC) has filed against Merced Irrigation District (MID).” (WAC
RJN, McKinnon Dec. [1/10/23], Ex. J) The second paragraph of the letter reads as
follows:
“CDFW agrees that fish passage needs to be restored at the dam. Indeed, in
a letter to MID dated November 16, 2009, [i.e., 13 years earlier,] CDFW
explained that fish passage at Crocker-Huffman ‘must be restored.’ To that
end, CDFW directed MID to consult with CDFW to determine the
adequacy of the existing fishway at the dam to pass fish and to develop a
fish passage plan. To CDFW’s knowledge, MID did not respond to the
letter and, as you know, the fishway remains closed. CDFW is willing to
meet with MID, presumably with NMFS, to offer technical assistance to
accomplish these goals with the understanding that restoring fish passage at
the dam, whether by using the existing fishway or by some other means,
remains MID’s responsibility.” (Fn. omitted.)
Two weeks later, in a letter dated December 20, 2022, defendant responded to
CDFW. (MID RJN, Ex. N) The letter contains the following statements:
“[T]here have been various discussions over time regarding fish passage at
[the C-H] Dam; the CDFW fish hatchery; and other related items and
issues. These discussions have occurred in various forums, including as
part of the larger relicensing process. On a larger scale, MID is involved in
ongoing discussions with regulatory agencies, including CDFW and
NMFS, in numerous forums regarding the management and improvement
of fish species and habitat on the Merced River …. The discussions are
part of the ongoing FERC relicensing proceedings that began in 2008 for
the Merced River and Merced Falls hydroelectric projects, the related
34.
Endangered Species Act consultations with NMFS, [and] the related Clean
Water Act Section 401 water quality certification proceedings in front of
the State Water Resources Control Board (SWRCB) ….”
Defendant’s comments in its December 2022 letter to CDFW were evidently
brought to the attention of NMFS. A letter dated January 5, 2023, sent by NMFS to
defendant, contains the following statements:
“… NMFS would appreciate specific information on these
opportunities to collaborate, as we are not aware of Crocker-Huffman Dam
ladder operations being part of discussions in the referenced arenas. We
also note that FERC has stated Crocker-Huffman Dam is not part of the
Project that is the subject of the referenced FERC licensing proceedings.
[Citation.] MID itself has also stated that FERC has no jurisdiction over
the Crocker-Huffman Dam in those proceedings. [Citations.]
“NMFS continues to support expeditious reopening of the fish ladder
at Crocker-Huffman Dam to reestablish upstream and downstream fish
passage, as well as initiating discussions between MID, NMFS, and
CDFW, focused on further study to evaluate improvements to fish passage
at this facility. NMFS supports CDFW’s recent proposal to engage in
technical assistance discussions with MID and is ready to participate in
such discussions.” (WAC RJN, McKinnon Dec. [1/10/23], Ex. L)
The California Department of Fish and Wildfire communicated with defendant
again in a letter dated January 27, 2023. (WAC RJN, McKinnon Dec. [3/3/23], Ex. N)
The letter contains the following statements:
“By letter dated December 8, 2022, the California Department of
Fish and Wildlife (CDFW) informed the Merced Irrigation District (MID)
that fish passage needs to be restored at the Crocker-Huffman Dam and
offered to meet with MID to offer technical assistance to accomplish this
goal. MID declined CDFW’s offer. Instead, in response to CDFW’s letter,
you explained that MID would stay involved in ‘ongoing proceedings and
forums that consider a broad array of interrelated and important issues on
the Merced River and downstream[,]’ including ‘the ongoing [Federal
Energy Regulatory Commission’s (FERC)] relicensing proceedings that
began in 2008 for the Merced River and Merced Falls hydroelectric
projects’.
“CDFW agrees there are many issues affecting fish species and
habitat on the Merced River that are interrelated. However, this does not
35.
mean that each of these issues need to, will, or can be addressed at the same
time or in one proceeding or forum. As the National Marine Fisheries
Service (NMFS) explained in its January 5, 2023 letter to MID on this same
topic, Crocker-Huffman Dam is not part of the FERC licensing proceedings
for the two projects mentioned above.… In short, CDFW is not aware of
any discussions regarding fish passage at the dam in any ongoing
proceeding or forum, but even if that were the case, it would not preclude
MID from obtaining technical assistance and developing a fish passage
plan, nor would these other processes excuse MID from its present and
ongoing legal obligation to provide fish passage. (See Fish & G. Code,
§§ 5901, 12025.1, subd. (a).)” (Fns. omitted.)
In June 2023, shortly after plaintiff filed its second amended complaint/petition,
defendant sent a letter to NMFS. (MID RJN, Ex. O) In this letter, MID summarized
“major points of [a] meeting” the previous month between MID, NMFS, and CDFW.
MID referred to a tentative agreement for it to conduct testing of the C-H Dam fish ladder
under certain conditions dictated by MID. Elsewhere in the letter, MID stated its
disagreement with NMFS on various issues including MID’s position on the potential
downsides of reopening the fish ladder. For example: “[MID does] not agree that ‘there
[are] no risks or major impacts to flows and infrastructure as a result of opening the fish
ladder other than the potential cost of screening the MID’s main diversion canal.’ [MID
has] pointed out that if fish passed upstream and the Main Canal intake was screened, fish
could be injured as they pass over the Crocker-Huffman Diversion Dam spillway and
[MID] could be held liable for such injury.” (Italics omitted.)
In late September 2023, while defendant’s penultimate demurrer was pending,
NMFS sent a letter to FERC. (MID RJN, Ex. P) It contains these statements:
“This letter is in regard to the recent opening of MID’s fish ladder at
Crocker-Huffman Dam for the purposes of hydraulic testing.… [¶] … On
September 19, 2023, while the fish ladder was open, NMFS, filed a letter
[citation] with MID restating the request that MID leave the Crocker-
Huffman’s Dam’s Fish Ladder open after hydraulic testing of the ladder.
… However, as noted in a summary e-mail of the hydraulic testing activity
[citation], MID reclosed the fish ladder.”
36.
C. Applicable Law re: Traditional Mandamus
Superior courts have mandamus jurisdiction under article VI, section 10, of the
California Constitution. “Mandamus” and “mandate” are interchangeable terms referring
to a type of extraordinary relief granted by the issuance of a writ. (See Code Civ. Proc.,
§ 1084; Henneberque v. City of Culver City (1985) 172 Cal.App.3d 837, 840, 844.) Two
forms of mandamus are available to challenge government actions: traditional and
administrative. (Code Civ. Proc., §§ 1085, 1094.5; Malott v. Summerland Sanitary Dist.
(2020) 55 Cal.App.5th 1102, 1109.) The operative pleading cites to Code of Civil
Procedure section 1085, thus indicating a cause of action for traditional mandamus.
“A writ of mandate under Code of Civil Procedure section 1085 is a legal tool to
compel a public agency to perform a legal, typically ministerial, duty.” (California
Privacy Protection Agency v. Superior Court (2024) 99 Cal.App.5th 705, 721, fn.
omitted; see Common Cause v. Board of Supervisors (1989) 49 Cal.3d 432, 442
[“Mandamus, rather than mandatory injunction, is the traditional remedy for the failure of
a public official to perform a legal duty”].) “The writ will issue against a county, city, or
other public body, or against a public officer.” (Ochoa v. Anaheim City School Dist.
(2017) 11 Cal.App.5th 209, 223.)
A cause of action for traditional mandamus has two essential elements: “‘(1) A
clear, present and usually ministerial duty on the part of the respondent … ; and (2) a
clear, present and beneficial right in the petitioner to the performance of that duty ….’”
(Santa Clara County Counsel Attys. Assn. v. Woodside (1994) 7 Cal.4th 525, 539–540.)
These elements imply a third requirement, which is the respondent’s ability to perform
the duty. (See Siskiyou Hospital, Inc. v. County of Siskiyou (2025) 109 Cal.App.5th 14,
41 [“a traditional writ of mandate will only lie where there is a ministerial duty capable of
direct enforcement”]; Collins v. Thurmond (2019) 41 Cal.App.5th 879, 915.) In addition,
the petitioner must ordinarily show “‘there is not a plain, speedy, and adequate remedy,
37.
in the ordinary course of law.’” (Flores v. Department of Corrections & Rehabilitation
(2014) 224 Cal.App.4th 199, 205, quoting Code Civ. Proc., § 1086.)
“A respondent may test the legal sufficiency of a petition for writ of mandate by
demurrer.” (Committee for Sound Water & Land Development v. City of Seaside (2022)
79 Cal.App.5th 389, 399.) The rules governing demurrers to civil complaints also apply
to mandamus actions. (Pinto Lake MHP LLC v. County of Santa Cruz (2020) 56
Cal.App.5th 1006, 1012, citing Code Civ. Proc., § 1109.) On appeal, the reviewing court
independently determines whether the petition states a viable claim. (Santa Paula
Animal Rescue Center, Inc. v. County of Los Angeles (2023) 95 Cal.App.5th 630, 638;
accord, City of Seaside, at p. 399 [“On appeal from an order of dismissal after a demurrer
is sustained without leave to amend, our review is de novo”].)
D. Standing
Plaintiff’s lack of standing to sue for public nuisance does not necessarily preclude
mandamus relief. “As a general rule, a party must be ‘beneficially interested’ to seek a
writ of mandate.” (Save the Plastic Bag Coalition v. City of Manhattan Beach (2011) 52
Cal.4th 155, 165, quoting Code Civ. Proc., § 1086.) A beneficial interest is “‘some
special interest to be served or some particular right to be preserved or protected over and
above the interest held in common with the public at large.’” (Save the Plastic Bag
Coalition, at p. 165.) The concept of “‘public interest standing’” is an exception to the
general rule. (Id. at p. 166; see Reynolds v. City of Calistoga (2014) 223 Cal.App.4th
865, 874 [noting the “public interest standing exception has been consistently applied
only in the context of mandamus proceedings”].)
“‘“[W]here the question is one of public right and the object of the mandamus is to
procure the enforcement of a public duty, the [petitioner] need not show that he has any
legal or special interest in the result, since it is sufficient that he is interested as a citizen
in having the laws executed and the duty in question enforced.”’ [Citation.] This
38.
‘“public right/public duty” exception to the requirement of beneficial interest for a writ of
mandate’ ‘promotes the policy of guaranteeing citizens the opportunity to ensure that no
governmental body impairs or defeats the purpose of legislation establishing a public
right.’” (Save the Plastic Bag Coalition v. City of Manhattan Beach, supra, 52 Cal.4th at
p. 166.)
The public interest exception is discretionary and may be rejected where “‘the
policy underlying the exception [is] outweighed … by competing considerations of a
more urgent nature,’” or the lawsuit “‘is driven by personal objectives rather than
“broader public concerns.”’” (People for Ethical Operation of Prosecutors etc. v. Spitzer
(2020) 53 Cal.App.5th 391, 408.) The trial court never questioned plaintiff’s standing,
and defendant challenges standing only with respect to the public nuisance claim.
Although corporations are technically not citizens, the public right/public duty exception
is generally available to legal entities “[a]bsent compelling policy reasons” to disallow it.
(Save the Plastic Bag Coalition v. City of Manhattan Beach, supra, 52 Cal.4th at p. 168.)
As the issue appears uncontested and the record is supportive of the basic requirements,
we conclude public interest standing was adequately pleaded.
E. Mandatory Duties
1. Relevant Law
“Mandamus will lie to compel a public official to perform an official act required
by law. [Citation.] Mandamus will not lie to control an exercise of discretion, i.e., to
compel an official to exercise discretion in a particular manner. Mandamus may issue,
however, to compel an official both to exercise his discretion (if he is required by law to
do so) and to exercise it under a proper interpretation of the applicable law.” (Common
Cause v. Board of Supervisors, supra, 49 Cal.3d at p. 442.)
Discretion is “the power conferred on public functionaries to act officially
according to the dictates of their own judgment.” (Rodriguez v. Solis (1991) 1
39.
Cal.App.4th 495, 502.) “Where a statute or ordinance clearly defines the specific duties
or course of conduct that a governing body must take, that course of conduct becomes
mandatory and eliminates any element of discretion.” (Id. at pp. 504–505.) In this
context, “mandatory” and “ministerial” duties are generally synonymous.
To restate the basic requirement, a petitioner “must establish the existence of a
public officer’s or a public entity’s ‘“clear, present, and ministerial duty”’” to act or
refrain from acting in a certain way. (Herron v. San Diego Unified Port Dist. (2025) 109
Cal.App.5th 1, 10.) “A ministerial duty is an act that a public agency or officer is
required to perform in a prescribed manner in obedience to the mandate of legal authority
without regard to any personal judgment concerning the propriety of the act.” (Siskiyou
Hospital, Inc. v. County of Siskiyou, supra, 109 Cal.App.5th at p. 41; accord, Kavanaugh
v. West Sonoma County Union High School Dist. (2003) 29 Cal.4th 911, 916.) Generally
speaking, “[a] ministerial duty is one which is required by statute.” (County of Los
Angeles v. City of Los Angeles (2013) 214 Cal.App.4th 643, 653; see County of Los
Angeles v. Superior Court (2002) 102 Cal.App.4th 627, 639 [“An enactment creates a
mandatory duty if it requires a public agency to take a particular action”].)
“A trial court must determine whether the agency had a ministerial duty capable of
direct enforcement or a quasi-legislative duty entitled to a considerable degree of
deference.” (County of Los Angeles v. City of Los Angeles, supra, 214 Cal.App.4th at p.
653.) If the issue requires statutory interpretation, it is reviewed de novo. (Ibid.;
Crestwood Behavioral Health, Inc. v. Baass (2023) 91 Cal.App.5th 1, 15.) “In order to
construe a statute as imposing a mandatory duty, the mandatory nature of the duty must
be phrased in explicit and forceful language.” (Quackenbush v. Superior Court (1997) 57
Cal.App.4th 660, 663.) If the agency’s performance is “‘unqualifiedly required, it is not
discretionary, even though the manner of its performance may be discretionary.’”
(Redwood Coast Watersheds Alliance v. State Bd. of Forestry & Fire Protection (1999)
70 Cal.App.4th 962, 970.)
40.
2. Analysis
Fish and Game Code section 5900 et seq. is a statutory scheme governing “the
damming of rivers and streams which are naturally frequented by fish.” (State of
California v. San Luis Obispo Sportsman’s Assn. (1978) 22 Cal.3d 440, 448.) Numerous
provisions impose “affirmative duties on dam owners to take steps to preserve and
protect the fish population. (See, e.g., Fish & G. Code, §§ 5931, 5933, 5938, 5942.)
They derive from the long-settled principle that the fish within the waters of the state are
owned by the state in trust for the people and from the state’s authority to regulate to
protect and preserve this valuable public resource.” (San Luis Obispo Sportsman’s Assn.,
at pp. 448–449.)
Fish and Game Code section 5901 broadly prohibits constructing or maintaining
“any device or contrivance that prevents, impedes, or tends to prevent or impede, the
passing of fish up and down stream.” Violations are punishable, inter alia, by a fine of up
to $8,000. (Id., § 12025.1, subd. (a).) “Each day that a violation of Section 5901 occurs
or continues without a good faith effort by the person to cure the violation after receiving
notice from the [CDFW] shall constitute a separate violation.”9 (Ibid.)
Fish and Game Code section 5935, upon which plaintiff also (and primarily)
relies, consists of one sentence: “The owner of any dam upon which a fishway has been
provided shall keep the fishway in repair and open and free from obstructions to the
passage of fish at all times.” The next provision in the statutory scheme declares, “It is
unlawful to wilfully [sic] destroy, injure, or obstruct any fishway.” (Fish & G. Code,
§ 5936.) We will focus on section 5935.
9The full text of Fish and Game Code section 5901 reads: “Except as otherwise provided
in this code, it is unlawful to construct or maintain in any stream in Districts 1, 1⅜, 1½, 2, 2¼,
2½, 3, 3½, 4, 4⅛, 4½, 4¾, 11, 12, 13, 23, and 25, any device or contrivance that prevents,
impedes, or tends to prevent or impede, the passing of fish up and down stream.” By express
reference to Districts 1 and 3, the statute applies to all parts of Merced County. (See Fish & G.
Code, §§ 41, 11001, 11008.)
41.
“Under the plain meaning rule, when the language of a statute is clear, we need go
no further. [Citation.] In that case, ‘no court need, or should, go beyond that pure
expression of legislative intent. [Citation.]’” (Switzer v. Wood (2019) 35 Cal.App.5th
116, 128, quoting Green v. State of California (2007) 42 Cal.4th 254, 260.) “‘If the
words themselves are not ambiguous, we presume the Legislature meant what it said, and
the statute’s plain meaning governs.’” (Young v. Fish & Game Com. (2018) 24
Cal.App.5th 1178, 1193.)
The common and legal definitions of “duty” speak of obligations generally arising
from the obligor’s position or status. (See Amezcua v. Los Angeles County Civil Service
Com. (2019) 44 Cal.App.5th 391, 398; Black’s Law Dict. (12th ed. 2024) p. 636.)
Section 5935 places an obligation on “the owner of any dam upon which a fishway has
been provided” to “keep the fishway in repair and open and free from obstructions to the
passage of fish at all times.” (Fish & G. Code, § 5935.) The statute plainly describes a
duty applicable to certain dam owners.
Next, we consider whether the party with the duty is “required to perform it in a
prescribed manner when a given state of facts exists.” (Hudson v. County of Los Angeles
(2014) 232 Cal.App.4th 392, 408; accord, Lockyer v. City and County of San Francisco
(2004) 33 Cal.4th 1055, 1082.) The answer is yes. If a dam is equipped with a fish
ladder, the dam’s owner must keep the fish ladder open and unobstructed. (Fish & G.
Code, § 5935.)
Does the statute indicate the “‘mandatory nature of the duty’” by phrasing it “‘in
explicit and forceful language’”? (Collins v. Thurmond, supra, 41 Cal.App.5th at p. 914.)
Yes, it does. “The owner of any dam upon which a fishway has been provided shall keep
the fishway in repair and open and free from obstructions to the passage of fish at all
times.” (Fish & G. Code, § 5935, italics added.)
As used throughout the Fish and Game Code, “‘[s]hall’ is mandatory and ‘may’ is
permissive.” (Fish & G. Code, § 79; see id., § 2.) “Use of the mandatory language
42.
‘shall’ indicates a legislative intent to impose a mandatory duty; no discretion is granted.”
(In re Luis B. (2006) 142 Cal.App.4th 1117, 1123; accord, California Privacy Protection
Agency v. Superior Court (2024) 99 Cal.App.5th 705, 723, citing In re Luis B., at p.
1123.) Section 12000 of the same code further suggests the mandatory nature of the
duty: “Except as expressly provided otherwise in this code, any violation of this code, or
of any rule, regulation, or order made or adopted under this code, is a misdemeanor.”
(Fish & G. Code, § 12000, subd. (a).)
By all indications, compliance with Fish and Game Code section 5935 is not
discretionary for dam owners. Put differently, the owner of a dam upon which a fishway
has been provided cannot choose to keep the fishway open or closed “according to the
dictates of their own judgment.” (Rodriguez v. Solis, supra, 1 Cal.App.4th at p. 502
[defining discretion for purposes of traditional mandamus].) The prosecutorial discretion
of the California Department of Fish and Wildlife is an entirely separate issue, as is the
possibility that noncompliance may be legally excused under a given set of facts.
In Goddard v. Department of Fish & Wildlife (2015) 243 Cal.App.4th 350, this
district considered the language of Fish and Game Code section 5935 in resolving an
issue regarding CDFW’s alleged civil liability for the condition of an out-of-service dam
it did not own. The allegedly dangerous condition “was caused by [a] fish ladder
washing away after its installation.” (Goddard, at p. 364.) Relying on section 5935,
CDFW argued the duty to maintain the fish ladder fell upon the dam’s owner and not
CDFW. (Goddard, at pp. 364–365.)
The Goddard opinion states, in relevant part: “[CDFW] exists to enforce the Fish
and Game Code [citation], not to exercise control over dams or their remnants. … At
best, [CDFW] exercised a regulatory role with respect to the dam remnant. But, as
[CDFW] points out, that does not equate to control.” (Goddard v. Department of Fish &
Wildlife, supra, 243 Cal.App.4th at p. 366.) In other words, CDFW does not itself
perform the duty Fish and Game Code section 5935 imposes upon dam owners.
43.
Merced Irrigation District argues it has no current duty under Fish and Game Code
section 5935 because its evidence shows CDFW ordered/authorized the closing of the C-
H Dam fish ladder in 1970. Losing sight of the difference between a demurrer and a
motion for summary judgment, MID further argues there is “no evidence of a direct order
by CDFW or any other agency to MID to immediately open the fish ladder or otherwise
restore fish passage at C-H Dam.” MID also writes, “With the opening of the [Merced
River Hatchery] in 1970, CDFW directed that the C-H Dam fish ladder be rendered
inoperable so that CDFW could operate a spawning channel.” These are all defensive
factual allegations not found in the operative pleading.
Paragraph 29 of the operative pleading alleges, “The fishway at the Crocker-
Huffman Dam has been closed since approximately 1972.” The next paragraph alleges,
“CDFW operates the Merced River Hatchery (‘MRH’) downstream of the Crocker-
Huffman Dam.” There are no further contentions regarding the initial closing of the fish
ladder, and the relevance of the Merced River Hatchery is never explained.
Assuming the truth of defendant’s factual allegations would not change the
mandatory nature of Fish and Game Code section 5935. Defendant’s arguments concern
the possible existence of affirmative defenses, i.e., legal excuses for not complying with
the statute. The arguments raise mixed questions of law and fact that cannot be
determined at this juncture. For example, CDFW sent three letters to MID between 2009
and 2023 arguably indicating that any prior justification for keeping the fish ladder closed
was no longer viewed as such by CDFW. The 2009 letter states, “[MID] may no longer
rely on [CDFW’s] letter from the 1970s.… [¶] … [CDFW] has determined that fish
passage at the Crocker-Huffman Diversion Dam must be restored. [Fish and Game Code
section] 5935 states ‘the owner of any dam upon which a fishway has been provided shall
keep the fishway in repair and open and free from obstructions to the passage of fish at
all times’.”
44.
In the 2023 letter, CDFW cited Fish and Game Code section 5901, and the
corresponding penalty provision (id., § 12025.1), in support of the following statement:
“CDFW is not aware of any discussions regarding fish passage at the dam
in any ongoing proceeding or forum, but even if that were the case, it would
not preclude MID from obtaining technical assistance and developing a fish
passage plan, nor would these other processes excuse MID from its present
and ongoing legal obligation to provide fish passage.” (Italics added.)
MID argues CDFW “would not have allowed the fish ladder to remain closed
since 1970” if the duty to keep fish ladders open were mandatory. The argument ignores,
inter alia, the concept of prosecutorial discretion. (See Heckler v. Chaney (1985) 470
U.S. 821, 831 [“[A]n agency’s decision not to prosecute or enforce, whether through civil
or criminal process, is a decision generally committed to an agency’s absolute
discretion”].) “[P]ast nonenforcement does not necessarily reflect a formal
administrative interpretation precluding enforcement, but could instead reflect the
exercise of prosecutorial discretion or limited resources ….” (Siskiyou County Farm
Bureau v. Department of Fish & Wildlife (2015) 237 Cal.App.4th 411, 443.) More to the
point, CDFW’s “previous lack of enforcement does not rewrite the statute.” (Ibid.)
In a last-ditch effort, MID selectively quotes from other provisions within the
statutory scheme. Those statutes will be discussed in numerical order. We discuss them
only briefly, however, because (1) MID’s arguments again relate to potential defenses not
yet factually established and (2) MID acknowledges that the only discretion reflected in
the statutes lies with the California Department of Fish and Wildlife and/or the California
Fish and Game Commission.
Fish and Game Code section 5931 provides:
“If, in the opinion of the [Fish and Game Commission], there is not free
passage for fish over or around any dam, the [CDFW] shall cause plans to
be furnished for a suitable fishway, and order in writing the owner of the
dam to provide the dam, within a specified time, with a durable and
efficient fishway, of such form and capacity and in such location as shall be
45.
determined by [CDFW]. Such fishway shall be completed by the owner of
the dam to the satisfaction of the [CDFW] within the time specified.”
Defendant contends the quoted language shows “that fish passage obligations are
[not] automatic, ministerial and absolute, … [nor] solely the obligation and
responsibility” of dam owners. This carefully worded argument seems intended to
distract or mislead. Plaintiff does not allege all statutes concerning fish passage are
“automatic” and “absolute,” i.e., not subject to exceptions and contingencies, or that all
“fish passage obligations” in the statutory scheme fall upon dam owners. Plaintiff’s
cause of action is specific to the duties of those who own dams “upon which a fishway
has been provided.” (Fish & G. Code. § 5935.)
A fishway enables “free passage for fish” within the meaning of Fish and Game
Code section 5931. (California Trout, Inc. v. State Water Resources Control Bd. (1989)
207 Cal.App.3d 585, 606.) The C-H Dam is already equipped with a fishway, and it is
possible the Fish and Game Commission would conclude the existing fishway provides
free passage for fish when open and unobstructed. Nothing in the language of Fish and
Game Code section 5931 indicates that section 5935 is discretionary, i.e., that the owner
of a dam upon which a fishway has been provided has discretion to close or otherwise
obstruct the fishway.
Also, as noted in CDFW’s amicus curiae brief, Fish and Game Code section 5931
concerns actions to be taken by CDFW if the Fish and Game Commission makes certain
findings. “Here, there is no evidence that the Commission made any findings, or that the
Commission or [CDFW] issued any orders.” Nor do the pleadings contain any
allegations of such findings or orders.
Defendant also cites Fish and Game Code section 5933. This statute is applicable
“[w]henever an application for approval of plans and specifications for a new dam …, or
for the enlargement of [an existing] dam …, is filed with the Department of Water
Resources.” If a dam is proposed to be built or enlarged, the Fish and Game Commission
46.
determines whether “the construction of a fishway over such a dam is necessary for the
preservation and protection of fish ….” (Ibid.) Defendant quotes from the statute
without explaining how it is even potentially relevant to the interpretation of section 5935
or this case in general.
Next is Fish and Game Code section 5938, which “authorizes the development of
a fish hatchery in lieu of the construction of a fishway over or around a dam, if that
proves impracticable.” (California Trout, Inc. v. State Water Resources Control Bd.,
supra, 207 Cal.App.3d at p. 606, italics added.) Defendant argues that is “exactly what
occurred with the fishway at C-H Dam” in 1970, ignoring that its own evidence shows
the fishway was in existence (i.e., had already been constructed) before the Merced River
Hatchery was built. We need not interpret section 5938, however, because defendant is
merely alleging a legal justification for initially closing the fish ladder. The occurrence
of subsequent unexcused and continuing violations of section 5935 is a disputed issue
involving mixed questions of fact and law. “[A] court ruling on a demurrer cannot decide
a question that may depend on disputed facts by means of judicial notice.” (Fremont
Indemnity Co. v. Fremont General Corp. (2007) 148 Cal.App.4th 97, 115.)
Lastly, defendant notes “Fish and Game Code Section 5942 also states that the
Fish and Game Commission may ‘in lieu of a fishway, … order the owner of the dam to
plant, under the supervision of [CDFW], the young of such fish as naturally frequent the
waters of the stream or river, at such times, in such places, and in such numbers as the
[Fish and Game Commission] may order.” The quote is accurate, but the statute is
unhelpful without any allegations or evidence of the Fish and Game Commission ever
issuing such orders with regard to the C-H Dam. Moreover, as with all other provisions
discussed, the statute does not confer any discretion upon dam owners.
In summary, mandamus is available “to challenge an agency’s failure to perform
an act required by law.” (Danser v. Public Employees’ Retirement System (2015) 240
Cal.App.4th 885, 890; accord, Common Cause v. Board of Supervisors, supra, 49 Cal.3d
47.
at p. 442.) Control over discretionary aspects of the required performance will not be
mandated, but petitioners may seek “to compel some action upon the subject involved
under a proper interpretation of the applicable law.” (Morris v. Harper (2001) 94
Cal.App.4th 52, 63, italics added; see Johnson v. State of California (1968) 69 Cal.2d
782, 788 [“‘[I]t would be difficult to conceive of any official act, no matter how directly
ministerial, that did not admit of some discretion in the manner of its performance, even
if it involved only the driving of a nail’”].) Plaintiff has emphasized it seeks only to
compel statutory compliance and not the manner in which the duty is performed.
None of defendant’s arguments refute the mandatory nature of the duty imposed
upon dam owners to keep existing fishways “in repair and open and free from
obstructions.” (Fish & G. Code, § 5935.) As such, we conclude plaintiff has alleged the
required existence of a duty. Whether defendant’s performance of the duty is impossible,
impracticable, or otherwise legally excused are fact-based affirmative defenses that have
yet to be established. (See TracFone Wireless, Inc. v. County of Los Angeles (2008) 163
Cal.App.4th 1359, 1368 [“Questions of fact may be resolved on demurrer only when
there is only one legitimate inference to be drawn from the allegations of the
complaint”].)
F. Statutes of Limitations
“‘The statute of limitations applicable to a writ of mandamus under Code of Civil
Procedure section 1085 depends upon the nature of the obligation sought to be enforced.
[Citation.]’ [Citation.] ‘It is often difficult to decide which statute of limitations governs
an action for writ of mandate. The code provisions authorizing this action are silent as to
the time within which it must be filed. [Citation.] Accordingly, the courts have
developed the rule that the question is to be resolved not by the remedy prayed for but by
the nature of the underlying right or obligation that the action seeks to enforce.”
(Branciforte Heights, LLC v. City of Santa Cruz (2006) 138 Cal.App.4th 914, 926.)
48.
“In order for the bar of the statute of limitations to be raised by demurrer, the
defect must clearly and affirmatively appear on the face of the complaint.” (McMahon v.
Republic Van & Storage Co., Inc. (1963) 59 Cal.2d 871, 874.) “Questions concerning
whether an action is barred by the applicable statute of limitations are typically questions
of fact.” (Sahadi v. Scheaffer (2007) 155 Cal.App.4th 704, 713.) The issue is
determinable as a matter of law only if all relevant facts are undisputed. (Ibid.)
Therefore, “‘“[a] demurrer based on a statute of limitations will not lie where the action
may be, but is not necessarily, barred.… [I]t is not enough that the complaint shows that
the action may be barred.”’” (Committee for Green Foothills v. Santa Clara County Bd.
of Supervisors (2010) 48 Cal.4th 32, 42.)
The trial court’s stated ground for dismissing the mandamus claim was plaintiff’s
failure to plead “a specific action by a specific agency occurring on a specific date that is
not time barred.” Defendant argues the ruling is correctly based on an implied
determination that plaintiff is challenging “CDFW’s closure of the fish ladder in 1970,
and such claims [are] therefore barred by the applicable statutes of limitation.” (Italics
added.) In making this argument, defendant ignores the pleaded contentions.
Paragraph 72 of the operative pleading states, “The injury being addressed by this
litigation is not that the fishway was closed fifty years ago, but that Merced [Irrigation
District] continues to block the fishway today.” Paragraph 78 explains plaintiff is
challenging defendant’s “continuing refusal to provide passage for fish in breach of its
present statutory duties ….” (Italics added.) Paragraph 91 cites California Trout, Inc. v.
State Water Resources Control Bd., supra, 207 Cal.App.3d 585 for the proposition that
ongoing breaches of public duties may be viewed as “‘“continuing” and hence
“abatable,” despite the fact that the acts or omissions have been conducted for a period
beyond that of the pertinent statute of limitations.’”
Defendant contends the limitations period is either 90 days or three or four years.
The first contention is based on unexplained citations to Code of Civil Procedure sections
49.
1094.5 and 1094.6. By necessary implication, defendant insinuates the fish ladder was
closed pursuant to an adjudicatory decision resulting from formal administrative
proceedings. (See ibid.) Nothing in the record suggests, nor do the pleadings allege, any
such proceedings ever occurred.
The other contentions are based on Code of Civil Procedure sections 338 and 343.
The former prescribes a three-year limitations period for actions “upon a liability created
by statute, other than a penalty or forfeiture.” (Id., § 338, subd. (a).) The latter is “a
catchall provision that provides a statute of limitations in situations where no specific
limitations period applies.” (Geneva Towers Ltd. Partnership v. City and County of San
Francisco (2003) 29 Cal.4th 769, 773.)
Plaintiff, and the California Department of Fish and Wildlife as amicus curiae, rely
on California Trout, Inc. v. State Water Resources Control Bd., supra, 207 Cal.App.3d
585 (California Trout) to argue there is no statute of limitations to remedy an
encroachment on the public trust interest in fish and fishery resources. (See id. at pp.
630–631.) We need not decide whether California Trout supports such a broad
proposition. The “public trust” analysis was one of two alternative rationales upon which
the California Trout court relied in resolving a statute of limitations issue. The other was
a variation of the continuous accrual doctrine. (See id. at pp. 626–629.) Plaintiff and
CDFW also rely on continuous accrual theories, and those arguments are well taken.
In California Trout, private organizations petitioned for writs of mandate to
compel the recission of licenses issued by the State Water Resources Control Board to the
City of Los Angeles and one of its departments. The licenses confirmed rights to
appropriate water “by means of dams from four creeks in Mono County.” (California
Trout, supra, 207 Cal.App.3d at p. 592.) The petitioners alleged the licenses violated
Fish and Game Code section 5946, which prohibits the SWRCB from issuing licenses or
permits to appropriate water from parts of Mono and Inyo Counties unless such licenses
or permits are conditioned upon compliance with Fish and Game Code section 5937.
50.
(California Trout, at p. 592; Fish & G. Code, § 5946, subd. (b).) The latter provision
states, in relevant part, “The owner of any dam shall allow sufficient water at all times to
pass through a fishway, or in the absence of a fishway, allow sufficient water to pass
over, around or through the dam, to keep in good condition any fish that may be planted
or exist below the dam.” (Fish & G. Code, § 5937.)
The appeal in California Trout followed a trial court’s dismissal of the writ
petitions. The appellate court reversed the judgments of dismissal. One of several issues
decided was a claim the petitions were time-barred under various statutes, including the
outermost limitations period of four years under Code of Civil Procedure section 343.
(California Trout, supra, 207 Cal.App.3d at p. 628.)
The California Trout respondents argued a position similar to the one taken by
Merced Irrigation District in this case. Much like MID’s attempt to characterize the
lawsuit as a challenge to the closing of the fish ladder in 1970, the California Trout
respondents argued the petitioners were seeking judicial review of the “action granting
issuance of the licenses” several years earlier. (California Trout, supra, 207 Cal.App.3d
at p. 626.) However, “the petitions alleged facts showing a continuing duty of the
[SWRCB] to apply [Fish and Game Code] section 5946 to the licenses,” and the licenses
were “subject to [SWRBC’s] ‘ongoing’ power of revocation.” (Ibid.) Therefore, the
historical act of issuing the licenses was “open to a present correction to bring them into
conformity with section 5946.” (Ibid.) The appellate court rejected the argument that
mandamus relief would necessarily “‘call for the [SWRCB] to look backward and review
its past decisions which have become final by the passage of time.’” (Id. at p. 627.)
The purpose of Fish and Game Code section 5946, i.e., the statute at issue in
California Trout, “is to obtain the release of sufficient water in the future to sustain fish
in streams in [the subject region] from which water is appropriated.” (California Trout,
supra, 207 Cal.App.3d at p. 628.) Restated, “the purpose is to maintain fisheries in such
streams on an ongoing basis. Hence, the failure to affix to the licenses language
51.
conditioning future diversion upon such releases” was held to constitute “a continuing
violation of the statute as to which no statute of limitations prevents remediation.” (Ibid.)
The mandamus action was thus described as being “of such a nature that it is outside the
ambit of the generic statutes of limitation,” i.e., Code of Civil Procedure sections 338 and
343. (California Trout, at p. 628.)
The relevant holding of California Trout was based in part on the “wholly
prospective and ministerial” nature of the relief sought. (California Trout, supra, 207
Cal.App.3d at p. 627.) The appellate court analogized to a rule governing equitable
actions for the abatement of a public nuisance. (Id. at p. 628; see City of Norwalk v. City
of Cerritos (2024) 99 Cal.App.5th 977, 990 [“public nuisance liability has no statute of
limitations because such nuisances are a continuing wrong”].) “If the nuisance is the sort
of ongoing conduct that can be discontinued by an order to stop acts or omissions it is
viewed as ‘continuing’ and hence ‘abatable,’ despite the fact that the acts or omissions
have been conducted for a period beyond that of the pertinent statute of limitations.
[Citations.] The same principle has been applied to other ongoing wrongs.” (California
Trout, at pp. 628–629.)
The “continuous accrual doctrine” is a designation that came into use after the
California Supreme Court applied a “theory of continuous accrual” in Howard Jarvis
Taxpayers Assn. v. City of La Habra (2001) 25 Cal.4th 809. (Id. at p. 822; see id. at pp.
818–825; Armstrong Petroleum Corp. v. Tri-Valley Oil & Gas Co. (2004) 116
Cal.App.4th 1375, 1388 [referring to “what Justice Werdegar has termed a ‘theory of
continuous accrual’”].) The issue there was the point of accrual for “an action against a
city for allegedly imposing and collecting a general tax on its residents without the voter
approval mandated by [law].” (City of LaHabra, at p. 812.) It was unanimously held
“that if, as alleged, the tax is illegal, its continued imposition and collection is an ongoing
violation, upon which the limitations period begins anew with each collection.” (Ibid.)
52.
Although California Trout predates the modern nomenclature, its holding rests on
the same basic concept. “Generally speaking, continuous accrual applies whenever there
is a continuing or recurring obligation: ‘When an obligation or liability arises on a
recurring basis, a cause of action accrues each time a wrongful act occurs, triggering a
new limitations period.’” (Aryeh v. Canon Business Solutions, Inc., supra, 55 Cal.4th at
p. 1199, italics added.)
The continuous accrual doctrine “is a response to the inequities that would arise if
the expiration of the limitations period following a first breach of duty or instance of
misconduct were treated as sufficient to bar suit for any subsequent breach or
misconduct; parties engaged in long-standing misfeasance would thereby obtain
immunity in perpetuity from suit even for recent and ongoing misfeasance.” (Aryeh v.
Canon Business Solutions, Inc., supra, 55 Cal.4th at p. 1198.) “In addition, where
misfeasance is ongoing, a defendant’s claim to repose, [i.e.,] the principal justification
underlying the limitations defense, is vitiated.” (Ibid.) “The effect of the doctrine is that
‘a suit for relief may be partially time-barred as to older events but timely as to those
[acts of wrongdoing occurring] within the applicable limitations period.’” (Gilkyson v.
Disney Enterprises, Inc. (2016) 244 Cal.App.4th 1336, 1341; accord, Orange County
Water Dist. v. Sabic Innovative Plastics US, LLC, supra, 14 Cal.App.5th at p. 395.)
The doctrine is typically applied in cases where periodic or recurring breaches of
duty have caused financial injury. In Aryeh, for example, the defendant was accused of
periodically inserting unjustified and/or fraudulent charges into monthly bills. (Aryeh v.
Canon Business Solutions, Inc., supra, 55 Cal.4th at pp. 1190, 1200.) To determine
whether the continuous accrual doctrine applied, the California Supreme Court analyzed
“the nature of the obligation allegedly breached.” (Id. at p. 1200.) The alleged “duty not
to impose unfair charges in monthly bills” was inherently “a continuing one, susceptible
to recurring breaches. Accordingly, each alleged breach [was] treated as triggering a new
statute of limitations.” (Ibid., italics added.)
53.
Merced Irrigation District argues “there is no evidence of or indication that [it] is
breaching ‘a recurring obligation.’” The question is not whether a duty periodically
arises, but whether a continuing duty is breached on a recurring or ongoing basis. The
fact pattern here is atypical because the pleadings do not allege periodic reopening and
reclosing of the C-H Dam fish ladder. However, plaintiff alleges ongoing violations of
Fish and Game Code section 5901, which prohibits maintaining “any device or
contrivance that prevents, impedes, or tends to prevent or impede, the passing of fish up
and down stream.” Plaintiff alleges MID’s breach of the duty to keep the fish ladder
open and unobstructed (Fish & G. Code, §§ 5935, 5936) is the manner in which MID
continues to violate section 5901. Under the Fish and Game Code, ongoing violations of
section 5901 are viewed as recurring violations. “Each day that a violation of Section
5901 occurs or continues without a good faith effort by the person to cure the violation
after receiving notice from [CDFW] shall constitute a separate violation.” (Fish & G.
Code, § 12025.1, subd. (a).)
In any event, under California Trout, a writ of mandamus to compel performance
of continuing duties under the fishway statutes may be sought regardless of whether
statutes of limitations that would otherwise be applicable have already expired.
(California Trout, supra, 207 Cal.App.3d at p. 628.) Defendant makes no real effort to
distinguish California Trout. Instead, it repeats the same fact-based defense asserted
throughout its briefs:
“MID cannot be engaging in a continuing or ongoing violation of the
purported statutes addressing fish passage where it is simply following the
prior direction and orders of CDFW to close the fish ladder, and where
CDFW and other agencies have not ordered MID to reopen the fish ladder
or otherwise restore fish passage at C-H Dam.”
We reject MID’s argument that the availability of mandamus necessarily turns on
“CDFW’s initial closure of the fish ladder in 1970, and the lack of any subsequent order
or direction to MID to immediately reopen the fish ladder or restore fish passage at C-H
54.
Dam.” MID uses the word “immediately” in multiple instances to suggest it cannot be
found in breach of the alleged fishway duties unless CDFW or some other agency
demanded immediate statutory compliance. As we have explained, the alleged
justification for closing the fish ladder 55 years ago is not dispositive because there are
mixed questions of fact and law regarding if, and when, the alleged justification ceased to
exist. Those issues are not resolvable at the pleading stage.
Furthermore, defendant’s own evidence unequivocally indicates defendant
reopened and reclosed the fish ladder in September 2023, before the operative pleading
was filed. There are photographs allegedly depicting the reopened fish ladder. This
evidence was judicially noticed and, without assuming the truth of its contents, would
provide a basis for supplementing the operative pleading (see Code Civ. Proc., § 464)
with allegations of a fresh breach of defendant’s alleged duties within a three- or four-
year limitations period (id., §§ 338, subd. (a), 343).10 (See Blank v. Kirwan (1985) 39
Cal.3d 311, 318 [An order sustaining a demurrer without leave to amend should be
reversed if there is a “reasonable possibility that the defect can be cured by amendment”];
Flood v. Simpson (1975) 45 Cal.App.3d 644, 647 [“It is the general policy that courts
should exercise liberality in permitting the filing of supplemental pleadings [under Code
of Civil Procedure section 464] when the alleged ‘occurring-after’ facts are pertinent to
the case”].)
In summary, the statute of limitations for a traditional mandamus action is
determined “by the nature of the underlying right or obligation that the action seeks to
enforce.” (Green v. Obledo (1981) 29 Cal.3d 126, 141, fn. 10.) “To determine whether
10Defendant freely admits conducting “hydraulic testing of the fish ladder at C-H Dam,”
but its briefs state the testing occurred in 2022. However, defendant’s record citations all
indicate the year was 2023. Plaintiff’s original pleading was filed in September 2022, so either
date would fall well within a three- or four-year statute of limitations. If the fish ladder was
opened and closed in both 2022 and 2023, those circumstances would further demonstrate the
recurring nature of the alleged misconduct.
55.
the continuous accrual doctrine applies here, we look … to the nature of the obligation
allegedly breached.” (Aryeh v. Canon Business Solutions, Inc., supra, 55 Cal.4th at p.
1200.) Plaintiff seeks to enforce statutory duties of a continuing nature that are
“susceptible to recurring breaches.” (Ibid.) Those circumstances, along with allegations
of ongoing and/or recurring breaches of those duties, permit reliance upon a continuous
accrual theory and defeat an untimeliness challenge on demurrer. (Id. at p. 1201.)
Moreover, analogous claims were held to be “outside the ambit of [Code of Civil
Procedure sections 338 and 343]” in California Trout, supra, 207 Cal.App.3d at page
628. Plaintiff’s cause of action is not time barred on the face of the pleadings or by
judicial notice of the parties’ evidence. The trial court erred by concluding otherwise.
G. Nonjoinder of Parties
“As the petition in a mandamus proceeding serves as the complaint, it must name
all of the parties.” (Tracy Press, Inc. v. Superior Court (2008) 164 Cal.App.4th 1290,
1297.) Code of Civil Procedure section 430.10, subdivision (d) authorizes a demurrer on
the ground of “a defect or misjoinder of parties.” This language encompasses nonjoinder
of necessary and indispensable parties. (See Organizacion Comunidad de Alviso v. City
of San Jose (2021) 60 Cal.App.5th 783, 791; Van Zant v. Apple Inc. (2014) 229
Cal.App.4th 965, 973.)
The trial court cited “failure to join indispensable parties” as the basis for
sustaining the demurrer to plaintiff’s cause of action for public nuisance, but not for the
mandamus cause of action. The reason why is not apparent. Defendant argues,
somewhat impliedly, that the court must have reached the same conclusion with regard to
both claims. As we now explain, such a determination would not have been supported by
the record before the trial court. The issue of necessary and indispensable parties was/is
premature given (1) the pleaded allegations and (2) the limited purpose for which the
parties’ judicially noticed evidence can been used.
56.
1. Relevant Law
The determination of whether a party is indispensable is governed by Code of
Civil Procedure section 389. (County of San Joaquin v. State Water Resources Control
Bd. (1997) 54 Cal.App.4th 1144, 1149.) The statute describes a two-part test.
Subdivision (a) provides the criteria for who should be included in the lawsuit if joinder
is possible, “sometimes referred to as ‘necessary’ parties.” (County of San Joaquin, at p.
1149.) “A determination that a person is a necessary party is the predicate for the
determination whether he or she is an indispensable party.” (TG Oceanside, L.P. v. City
of Oceanside (2007) 156 Cal.App.4th 1355, 1365.)
A party is considered necessary if:
“(1) in his absence complete relief cannot be accorded among those
already parties or”
“(2) he claims an interest relating to the subject of the action and is
so situated that the disposition of the action in his absence may”
“(i) as a practical matter impair or impede his ability to protect that
interest or”
“(ii) leave any of the persons already parties subject to a substantial
risk of incurring double, multiple, or otherwise inconsistent obligations by
reason of his claimed interest.” (Code Civ. Proc., § 389, subd. (a).)
If a party is deemed necessary but cannot be joined, (e.g., because the court does
not have jurisdiction over the party), the court must then determine “whether in equity
and good conscience the action should proceed among the parties before it” or should be
dismissed because the absent parties are “indispensable.” (Code Civ. Proc., § 389, subd.
(b).)
“The factors to be considered by the court include:”
“(1) to what extent a judgment rendered in the person’s absence
might be prejudicial to him or those already parties;”
57.
“(2) the extent to which, by protective provisions in the judgment, by
the shaping of relief, or other measures, the prejudice can be lessened or
avoided;”
“(3) whether a judgment rendered in the person’s absence will be
adequate;”
“(4) whether the plaintiff or cross-complainant will have an adequate
remedy if the action is dismissed for nonjoinder.” (Code Civ. Proc., § 389,
subd. (b).)
Failure to join an indispensable party is not a jurisdictional defect, even in a writ
proceeding. (Doe v. Regents of University of California (2022) 80 Cal.App.5th 282,
305.) Put differently, it “‘does not deprive a court of the power to make a legally binding
adjudication between the parties properly before it.’” (Ibid.) The consequence of
nonjoinder is that indispensable parties are not bound by the judgment. (Ibid.) “‘“It is
for reasons of equity and convenience, and not because it is without power to proceed,
that the court should not proceed with a case where it determines that an ‘indispensable’
party is absent and cannot be joined.”’” (Tracy Press, Inc. v. Superior Court, supra, 164
Cal.App.4th at pp. 1298–1299.)
2. Analysis
“Whether a party is necessary and/or indispensable is a matter of trial court
discretion in which the court weighs ‘factors of practical realities and other
considerations.’” (Hayes v. State Dept. of Developmental Services (2006) 138
Cal.App.4th 1523, 1529.) The standard of review is abuse of discretion. (Ibid.;
TruConnect Communications, Inc. v. Maximus Inc. (2023) 91 Cal.App.5th 497, 515.)
However, the trial court’s determination is inherently fact intensive. (See Verizon
California Inc. v. Board of Equalization (2014) 230 Cal.App.4th 666, 680–681.)
“Whether the absent [parties] claim an interest in the subject of the action, whether that
interest will be impaired, and whether they have the ability to protect their interests are
questions of fact that are reviewed for substantial evidence.” (Id. at p. 681.) Those are
58.
just examples. Substantial evidence must support all factual findings made in relation to
the factors listed in Code of Civil Procedure section 389.
In ruling on plaintiff’s nuisance claim, the trial court found three absent parties
were indispensable: National Marine Fisheries Service, United States Fish and Wildlife
Service, and FERC. Although no explanation was provided for those findings, we must
“presume that the trial court considered the relevant factors” (Dreamweaver Andalusians,
LLC v. Prudential Ins. Co. of America (2015) 234 Cal.App.4th 1168, 1177) and imply all
findings necessary to support the judgment. However, the doctrine of implied findings
has limited application here given the need for substantial evidence to support factual
determinations implicitly made at the pleading stage.
“A demurrer, by its very nature, involves no issue of fact. For example, a
defendant cannot make allegations of fact in his demurrer which, if true, would disclose a
defect in the complaint. [Citation.] Nor can he strengthen the demurrer by asserting
evidence which would make the complaint defective.” (Hayward v. Henderson (1979)
88 Cal.App.3d 64, 71.)
Nonjoinder as a ground for demurrer must appear on the face of the pleading or
“matter of which the court is required to or may take judicial notice.” (Code Civ. Proc.,
§ 430.30, subd. (a).) Otherwise “the objection may be taken by answer.” (Id., subd. (b).)
Thus, “a defendant may not make allegations of defect or misjoinder of parties in the
demurrer if the pleadings do not disclose the existence of the matter relied on; such
objection must be taken by plea or answer.” (Harboring Villas Homeowners Assn. v.
Superior Court (1998) 63 Cal.App.4th 426, 429.)
“The fact that [litigants] have raised their objections to nonjoinder of parties by
demurrer … does not necessarily require that the trial court make an immediate
determination of what parties, if any, must ultimately be joined.” (Union Carbide Corp.
v. Superior Court (1984) 36 Cal.3d 15, 22.) “‘A joinder question should be decided with
reasonable promptness, but decision may properly be deferred if adequate information is
59.
not available at the time. Thus the relationship of an absent person to the action, and the
practical effects of an adjudication upon him and others, may not be sufficiently revealed
at the pleading stage; in such a case it would be appropriate to defer decision until the
action was further advanced.’” (Ibid.)
“A demurrer is particularly unsuited to resolving questions of fact regarding the
misjoinder of parties because ‘a demurrer lies only for defects appearing on the face of
the pleadings.’” (Verizon California Inc. v. Board of Equalization, supra, 230
Cal.App.4th at p. 680.) In Verizon California Inc., the pleadings “did not disclose the
existence of the facts on which” the defendant relied to argue certain absent parties were
necessary and indispensable. On appeal, it was determined “there was no substantial
evidence to support the trial court’s finding that the absent [parties] claimed an interest in
the subject of the action that would be impaired if they were omitted from the action.”
(Id. at p. 681.) “Consequently, the trial court abused its discretion in sustaining the
demurrer.” (Ibid.)
Here, the operative pleading does not facially establish the necessity of joining the
federal agencies referenced therein or show they are “indispensable” parties. Such a
determination could only have been made—assuming it was made as to the mandamus
claim—by judicially noticing the parties’ evidence for the truth of its contents,
interpreting the evidence, and then weighing the evidence to make factual findings and
conclusions. We have already explained why that is improper.
To recapitulate, “[t]aking judicial notice of a document is not the same as
accepting the truth of its contents or accepting a particular interpretation of its meaning.”
(Joslin v. H.A.S. Ins. Brokerage (1986) 184 Cal.App.3d 369, 374.) “When judicial notice
is taken of a document, … the truthfulness and proper interpretation of the document are
disputable.” (StorMedia Inc. v. Superior Court, supra, 20 Cal.4th 449, 456, fn. 9.)
“Utilizing judicially noticed documents in ruling on a demurrer is only proper when the
60.
documents are not used to determine disputed factual issues.” (Richtek USA, Inc. v. uPI
Semiconductor Corp. (2015) 242 Cal.App.4th 651, 653–654.)
Likewise, “the taking of judicial notice of the official acts of a governmental entity
does not in and of itself require acceptance of the truth of factual matters which might be
deduced therefrom, since in many instances what is being noticed, and thereby
established, is no more than the existence of such acts and not, without supporting
evidence, what might factually be associated with or flow therefrom.” (Cruz v. County of
Los Angeles (1985) 173 Cal.App.3d 1131, 1134.) “While courts take judicial notice of
public records, they do not take notice of the truth of matters stated therein.” (Herrera v.
Deutsche Bank National Trust Co. (2011) 196 Cal.App.4th 1366, 1375.)
“‘“A demurrer is simply not the appropriate procedure for determining the truth of
disputed facts.” [Citation.] The hearing on demurrer may not be turned into a contested
evidentiary hearing through the guise of having the court take judicial notice of
documents whose truthfulness or proper interpretation are disputable.’” (Fremont
Indemnity Co. v. Fremont General Corp., supra, 148 Cal.App.4th at pp. 113–114.) Yet it
appears that is exactly what happened in this case. Having generally explained why
dismissal of the mandamus action cannot be affirmed for nonjoinder of parties, we
address defendant’s specific arguments regarding the parties it alleges are necessary and
indispensable.
(a) California Department of Fish and Wildlife
Defendant argues CDFW is a necessary and indispensable party to this case.
There is a problem with this argument as a ground for demurrer: CDFW is a party to the
case. As a named real party in interest, CDFW has/had a right to be heard. (See Code
Civ. Proc., §§ 1089, 1089.5; Sonoma County Nuclear Free Zone ’86 v. Superior Court
(1987) 189 Cal.App.3d 167, 173.) CDFW acknowledged receipt of service of the writ
61.
petition but chose not to respond. It has since filed an amicus curiae brief in support of
plaintiff’s appeal.
Defendant’s argument that CDFW must be named as a respondent in the
mandamus action is not persuasive. First, the trial court made no such finding. In ruling
on defendant’s demurrer to the second amended complaint/petition, the trial court
sustained it for “failure to name indispensable parties, specifically CDFW, FERC,
USFWS, and NMFS.” When ruling on the demurrer to the operative third amended
complaint/petition, after plaintiff had named CDFW as a real party in interest, the only
parties identified by the trial court as necessary and indispensable were the federal
agencies.
Second, a “writ may only issue against a respondent with a clear duty to perform a
ministerial act and with a legal authority to discharge that duty.” (Sonoma County
Nuclear Free Zone ’86 v. Superior Court, supra, 189 Cal.App.3d at p. 178.) Plaintiff is
not seeking to compel any action by CDFW, nor does plaintiff allege CDFW shares any
of the duties in question with defendant. Plaintiff alleges the opposite. Paragraph 37 of
the operative pleading contends: “Agencies with regulatory oversight of fish species and
habitat on the Merced River are not responsible for the maintenance and operation of
Merced [Irrigation District’s] fishway. That is the duty of the dam owner.” Legal
contentions in a pleading need not be accepted as true, but this one is supported by legal
authority. (See Fish & G. Code, § 5935; Goddard v. Department of Fish & Wildlife,
supra, 243 Cal.App.4th at p. 366 [observing CDFW “exists to enforce the Fish and Game
Code [citation], not to exercise control over dams”].)
Defendant repeatedly cites to Center for Biological Diversity, Inc. v. FPL Group,
Inc. (2008) 166 Cal.App.4th 1349 (FPL Group), which is distinguishable. There, private
party plaintiffs sued private party owners of energy-producing wind turbines. It was
alleged the defendants, “by the operation of their wind turbines, [were] responsible for
killing and injuring raptors and other birds in violation of the public trust doctrine.” (Id.
62.
at p. 1354.) The plaintiffs sought declaratory and injunctive relief. (Id. at p. 1356.) A
judgment on the pleadings was entered in favor of the defendants. (Id. at p. 1359.)
The appeal in FPL Group was “directed solely to the propriety of the [trial] court’s
ruling … that ‘[n]o statutory or common law authority supports a cause of action by a
private party for violation of the public trust doctrine arising from the destruction of wild
animals.’” (FPL Group, supra, 166 Cal.App.4th at p. 1356.) Most of the opinion is
devoted to explaining why the trial court erred in that regard. (Id. at pp. 1360–1370.)
The remainder explains the reason for affirming the judgment despite that error: the
lawsuit was filed “against the wrong parties.” (Id. at p. 1367.)
The FPL Group defendants operated their wind turbines under the authority of
permits issued by the Alameda County Board of Supervisors. The issuance of those
permits was a matter of public controversy, and the appellate court took judicial notice of
various administrative and judicial proceedings related thereto. (FPL Group, supra, 166
Cal.App.4th at pp. 1354–1358.) “Although other public interest groups dissatisfied with
the action taken by the Alameda County Board of Supervisors filed petitions for a writ of
mandate challenging that action … plaintiffs filed no writ proceedings and did not
proceed against any of the public agencies.” (Id. at pp. 1368–1369.)
The appellate court in FPL Group relied on the judicial abstention doctrine, which
we discuss in the next part of this opinion. On the issue of necessary parties, Merced
Irrigation District relies on the following statements: “A challenge to the permissibility
of defendants’ conduct must be directed to the agencies that have authorized the conduct.
If plaintiffs believe that the board of supervisors or any other agency or subdivision of the
state has failed to discharge its responsibilities under the public trust, they may bring an
appropriate action against those agencies. … But there is no basis for recognizing an
action that is not directed against the appropriate state agency responsible for authorizing
the wind farm operations.” (FPL Group, supra, 166 Cal.App.4th at p. 1370, fns.
omitted.)
63.
Merced Irrigation District repeats its mantra that CDFW authorized it to close the
fish ladder in 1970, so CDFW is the party responsible for the fish ladder remaining
closed. As we have explained several times, MID’s affirmative defense of legal
justification for statutory noncompliance involves disputed issues of fact. The undisputed
facts do not conclusively show whether MID’s present and ongoing noncompliance is
authorized by CDFW or is otherwise legally excused.
For example, MID strenuously argues that CDFW has “never ordered [it] to
reopen the fish ladder.” That may (or may not) be literally true, but in a letter from
CDFW to MID in January 2023, MID was told it had a “present and ongoing legal
obligation to provide fish passage.” CDFW’s admonishment included a citation to Fish
and Game Code sections 5901 and 12025.1. In the amicus curiae brief, CDFW argues
“the record reflects [its] disapproval of the ongoing closure” of the fish ladder. The
judicially noticed documents are certainly susceptible of that interpretation.
In response to CDFW’s brief, MID attempts to reframe the pleadings by insisting
plaintiff’s lawsuit challenges CDFW’s exercise of prosecutorial discretion in not
enforcing the fishway statutes itself. As support for this argument, MID contends Los
Angeles Waterkeeper v. State Water Resources Control Bd. (2023) 92 Cal.App.5th 230 is
“directly applicable.” We disagree.
In Los Angeles Waterkeeper, a private interest group sought writs of mandamus to
compel certain performance by two public agencies, one of which was the State Water
Resources Control Board. (Los Angeles Waterkeeper v. State Water Resources Control
Bd., supra, 92 Cal.App.5th at pp. 245–248.) MID purports to rely on holdings
concerning the SWRCB. The claims against the SWRCB pertained to a “highly
discretionary” duty relating to its investigatory and enforcement powers. (Id. at p. 277.)
The relevant holding on appeal was “that when an agency has broad discretion in
directing its investigatory and enforcement resources, its choice to direct those resources
64.
at some potential violations and not others is [not] subject to review on mandamus.” (Id.
at pp. 282–283.)
Plaintiff is very clearly not seeking to compel the California Department of Fish
and Wildlife to exercise its regulatory enforcement powers in a particular way. Plaintiff
is not attempting to compel CDFW to do anything. The relief sought is mandated
compliance by Merced Irrigation District with nondiscretionary duties imposed by
statute. Nothing in the pleadings or judicially noticed documents conclusively shows
CDFW to be a necessary respondent in the mandamus action.
(b) The Federal Agencies
Defendant’s arguments regarding FERC, NMFS and USFWS are carefully worded
to sound impressive and convincing, but when scrutinized they contain little substance.
For example, these agencies are said to have “regulatory and approval authority over
operations and impacts of the fish ladder.” That particular statement is made without a
supporting citation.
Elsewhere defendant makes the following assertion: “MID’s ability to reopen and
operate the fish ladder is dependent, at least in part, on the approval and authority of
FERC, NMFS, [and] USFWS…. (12 CT 3506-3587; 13 CT 3608– 3684; 13 CT 3695-
3727.)” Block citations to the record are neither appropriate nor helpful. (Bullock v. City
of Antioch (2022) 78 Cal.App.5th 407, 422; Bernard v. Hartford Fire Ins. Co. (1991) 226
Cal.App.3d 1203, 1205.) The first of those citations is to FERC’s 2015 FEIS for the
Merced River Project and Merced Falls project. Even if the contents were judicially
noticeable for their truth, we fail to see how they show defendant cannot reopen the fish
ladder without the approval of FERC, NMFS, and/or USFWS. The second block citation
is to a series of letters exchanged between 2014 and 2022. Notwithstanding the limited
purpose for which judicial notice of these letters is allowed, we again fail to see the
support. The last block includes a 2011 letter from MID to NMFS declining a request to
65.
open the fish ladder for testing, and correspondence from 2023 alleging MID reopened
the fish ladder for testing but reclosed it again despite NMFS’s request that it be kept
open.
Even if the contents of all judicially noticed documents were considered for their
truth, and assuming they could be interpreted to support defendant’s position, the
evidence as a whole could also be viewed as supporting plaintiff’s position. That is
especially true with regard to defendant’s alleged inability to reopen the fish ladder
without the direction and consent of the federal agencies. The evidence could be viewed
as showing those agencies tried for over a decade to coax, cajole, and incentivize
defendant to reopen the fish ladder because they lacked the power to compel such
performance.
Defendant provides no legal authority showing the federal agencies have control
over its operation of the C-H Dam. Defendant argues NMFS and USFWS have
jurisdiction “over certain fish species under the Endangered Species Act.” This is true.
The argument, which the trial court seemed receptive to earlier in the case, is that
reopening the fish ladder could actually do more harm than good for the fish. That would
potentially subject defendant to liability under the ESA. But defendant relies on the truth
of the 2007 Vogel report, which is not judicially noticeable for that purpose, and there is
other evidence in the record that is conflicting.
It is also hard to ignore NMFS’s staunch advocacy for “expeditious reopening of
the fish ladder at Crocker-Huffman Dam.” After this lawsuit was filed, NMFS sent a
letter to MID containing the following statement: “As has long been NMFS’s stated
view, reopening the fish ladder at Crocker-Huffman Dam would promote the
conservation of anadromous salmonids in the Merced River ….”
Under the joinder statute, “a party claiming an interest relating to the subject of the
action may be deemed necessary if the disposition of the action in [the party’s] absence
may ‘leave any of the persons already parties subject to a substantial risk of incurring
66.
double, multiple, or otherwise inconsistent obligations by reason of his claimed interest.’”
(Van Zant v. Apple Inc., supra, 229 Cal.App.4th at p. 977, quoting Code Civ. Proc.,
§ 389, subd. (a).) Speculative contentions are insufficient. (Van Zant, at p. 977.) “‘[A]
“substantial risk” means more than a theoretical possibility of the absent party’s asserting
a claim that would result in multiple [or inconsistent] liability. The risk must be
substantial as a practical matter.’” (Ibid., quoting Union Carbide Corp. v. Superior
Court, supra, 36 Cal.3d at p. 21.)
Aside from allegedly possible inconsistent obligations, and unsubstantiated claims
about control, defendant’s briefing is peppered with generalities about the agencies
having an interest in matters related to the fish ladder. For example, defendant claims
“USFWS has taken an active interest in fish passage issues at C-H Dam.” Merely having
an “interest” does not make a party’s involvement necessary or indispensable. A
necessary party is one who “claims an interest relating to the subject of the action and is
so situated that the disposition of the action in his absence may … as a practical matter
impair or impede his ability to protect that interest ….” (Code Civ. Proc., § 389, subd.
(a), italics added.) Plaintiff has argued the relief it seeks will promote and further the
interests of the federal agencies, and some of the judicially noticed evidence can certainly
be viewed as corroborative.
To reiterate, the joinder issue is premature and cannot be resolved by judicially
noticing volumes of evidence that is open to conflicting interpretations. Defendant is free
to assert nonjoinder as an affirmative defense when answering the petition. The trial
court can then decide the issue on the merits, based on admissible evidence, at an
appropriate stage of the proceedings. (See Union Carbide Corp. v. Superior Court,
supra, 36 Cal.3d at p. 24; Harboring Villas Homeowners Assn., supra, 63 Cal.App.4th at
pp. 429–430 [“a trial court does not have to make an immediate determination of what
parties must be joined at the pleading stage”].)
67.
(c) California State Water Resources Control Board
Defendant cursorily argues SWRCB is another necessary and indispensable party.
The trial court never found, even in its earlier demurrer rulings, that SWRCB is a
necessary or indispensable party to the action. Defendant does not explain how
SWRCB’s absence would preclude complete relief from being granted as between
plaintiff and defendant, nor how the relief sought creates a substantial risk of defendant
having liability or inconsistent obligations vis-à-vis SWRCB, nor how SWRCB’s
absence would impair or impede SWRCB’s ability to protect its own interest in the
outcome of the case. (Code Civ. Proc., § 389, subd. (a).)
Furthermore, an “indispensable” finding would require a showing SWRCB is not
only a necessary party, but for some reason “cannot be made a party” to the case. (Code
Civ. Proc., § 389, subd. (b).) Defendant does not address this issue. As previously noted,
defendant may plead nonjoinder as an affirmative defense when it responds to the
petition for writ of mandate.
H. Judicial Abstention
“Under the doctrine of judicial abstention, a trial court has discretion to abstain
from adjudicating an action if: (1) ‘“‘granting the requested relief would require a trial
court to assume the functions of an administrative agency, or to interfere with the
functions of an administrative agency’”’; (2) the action ‘“‘involves determining complex
economic policy, which is best handled by the Legislature or an administrative agency’”’;
or (3) ‘“‘granting injunctive relief would be unnecessarily burdensome for the trial court
to monitor and enforce given the availability of more effective means of redress.’”’”
(People ex rel. Elliot v. Kaiser Foundation Health Plan, Inc. (2024) 105 Cal.App.5th
1114, 1128.)
Judicial abstention applies only in cases of equity and is a recognized ground for
demurrer in such actions. (Shuts v. Covenant Holdco LLC (2012) 208 Cal.App.4th 609,
625; see Arce v. Kaiser Foundation Health Plan, Inc. (2010) 181 Cal.App.4th 471, 481–
68.
482.) A trial court decision to abstain is reviewed for abuse of discretion. (Arce, at p.
482.) In this case, however, the trial court did not make an abstention ruling.
The ruling on defendant’s demurrer to the first amended complaint/petition
included the following explanation: “A ruling on the demurrer on the grounds of the
doctrine of abstention is DEFERRED AS MOOT given the above rulings [on] the other
demurrers raised by Defendant. The doctrine of abstention will be addressed if and when
Plaintiff has otherwise stated a valid claim.” (Italics added.) Because the trial court
never found any of plaintiff’s causes of action to be viable, the record does not permit the
inference of implied reliance upon the abstention doctrine in sustaining the operative
third amended complaint/petition.
Defendant continues to argue abstention principles, seemingly expecting this court
to decide the issue de novo. It is uncommon for the appellate courts of this state to
invoke the judicial abstention doctrine sua sponte. The FPL Group case relied upon by
defendant is a rare example of it being done. There, however, abstention was one of two
reasons cited for affirming a judgment of dismissal. The other, as previously discussed,
was because the lawsuit was “brought against the wrong parties.” (FPL Group, supra,
166 Cal.App.4th at p. 1367; see id. at p. 1372.)
For many of the reasons discussed regarding the joinder issue, we will not make
findings and conclusions on the propriety of judicial abstention in the first instance.
Neither the pleadings nor mere judicial notice of the parties’ evidence allow us to render
a fully informed decision on the issue. Defendant is not precluded from raising this issue
again as the matter proceeds in the trial court.
I. Federal Preemption
In its amicus curiae brief, the California Department of Fish and Wildlife
discusses federal law out of concern this court might consider whether the Federal Power
Act preempts state law—Fish and Game Code sections 5901, 5935, and 5936—with
69.
specific regard to the C-H Dam. Merced Irrigation District, in response, states “CDFW
does not appear to understand MID’s position,” and submits CDFW’s briefing on the
subject is “misplaced, unnecessary and unrelated” to the issues before us. It appears
CDFW and MID are in agreement that we should not decide any federal preemption
issues.
Frankly, MID’s position is not as clear as it purports to have made it. At page 37
of the respondent’s brief, MID seemingly alleges the operative pleading is somehow
deficient with regard to federal preemption, and specifically concerning the Federal
Power Act. On the very same page, however, MID writes, “[Plaintiff] is correct—as
MID has continuously acknowledged—that FERC has determined to date that the C-H
Dam is not directly or expressly part of the hydroelectric projects subject to relicensing
on the Merced River, and thus its jurisdiction.” But that sentence is immediately
followed by this one: “The fact remains, however, that the ongoing FERC relicensing
process has involved and will involve actions regulating fish passage at C-H Dam, and
federal authority and jurisdiction over this issues [sic] preempts this Court’s
consideration of those issues.” The last quoted statement is made without citation to
authority.
Despite MID’s occasional use of the word “preempted” (and variations thereof), it
does not appear MID is making any federal preemption claims. In the response to
CDFW’s brief, MID explains that it “brought the ongoing FERC proceeding to the trial
court’s attention in further support of its argument that the court should abstain from
considering [plaintiff]’s claims because there were other agencies already considering
fish passage at the [C-H] Dam in another forum.” In other words, MID contends the
federal agencies should be considered indispensable parties because of the “collaborative
process” that has allegedly taken place in connection with the federal relicensing
applications.
70.
We have already discussed the Federal Power Act and explained the significance
of whether the C-H Dam is or is not part of a FERC-licensed project. It suffices for us to
conclude the operative pleading does not facially reveal a federal preemption defect.
Plaintiff alleges, and defendant agrees for purposes of demurrer, the C-H Dam is not a
federally licensed facility or otherwise part of a “project” as defined by the FPA.
“[W]hile preemption ‘can’ be decided on demurrer in a proper case, [any]
implication that it should be decided on demurrer is erroneous. There are numerous
circumstances in which the facts must be determined in order to decide whether a claim is
preempted by federal law, and it is not uncommon to have preemption claims decided
based on an evidentiary showing. Indeed, preemption is an affirmative defense as to
which defendants have the burden of proof.” (Apollo Capital Fund LLC v. Roth Capital
Partners, LLC (2007) 158 Cal.App.4th 226, 250–251.) Accordingly, we make no further
determinations regarding federal preemption.
J. Exhaustion of Administrative Remedies
The exhaustion of administrative remedies “is a term of art that refers to the
requirement that administrative remedies be pursued as a jurisdictional prerequisite to
seeking judicial relief from an administrative action.” (California Correctional Peace
Officers Assn. v. State Personnel Bd. (1995) 10 Cal.4th 1133, 1148.) “When seeking
relief under traditional mandamus, the exhaustion requirement speaks to whether there
exists an adequate legal remedy.” (Unnamed Physician v. Board of Trustees (2001) 93
Cal.App.4th 607, 620; see Code Civ. Proc., § 1086.) “If an administrative remedy is
available and has not yet been exhausted, an adequate remedy exists and the petitioner is
not entitled to extraordinary relief.” (Unnamed Physician, at p. 620.)
“‘The rule that a party must exhaust his administrative remedies prior to seeking
relief in the courts “has no application in a situation where an administrative remedy is
unavailable or inadequate.”’” (Ramos v. County of Madera (1971) 4 Cal.3d 685, 691.)
71.
The operative pleading alleges there is “no administrative procedure established
for the reopening of a fishway.” Relatedly, there are allegations that “[n]either the
Crocker-Huffman Dam nor its fishway is part of any administrative process by any other
agency and … [¶] [t]here is no federal or state administrative or regulatory process with
the capacity to compel Merced [Irrigation District] to reopen the fishway.”
Defendant claims the allegations are insufficient, and “plaintiff should have but
failed to exhaust any of the remedies available to it.” However, defendant declines to
specify what the available remedies are/were. It contends “numerous regulatory agencies
… are engaging in processes and proceedings to address fish passage at C-H Dam,” and
the pleading is defective for not alleging efforts “to participate in these processes or
present … claims to CDFW and the other agencies in the course of or in connection with
these ongoing regulatory processes and proceedings.”
The unspecified “processes and proceedings” are/were apparently different from
the federal relicensing proceedings for the Merced River Project and Merced Falls
Project, in which plaintiff “also” failed to “allege or establish” its participation. Those
federal proceedings supposedly afforded “opportunities for comments and remedies for
challenging FERC determinations regarding fish passage issues and C-H Dam,” even
though defendant elsewhere concedes FERC does not have federal licensing jurisdiction
over the C-H Dam. We do not find these arguments convincing.
“The mere possession by some official body of a continuing supervisory or
investigatory power does not itself suffice to afford an administrative remedy unless the
statute or regulation under which that power is exercised establishes clearly defined
machinery for the submission, evaluation and resolution of complaints by aggrieved
parties.” (Horsemen’s Benevolent & Protective Assn. v. Valley Racing Assn. (1992) 4
Cal.App.4th 1538, 1552–1553; accord, Common Cause v. Board of Supervisors, supra,
49 Cal.3d at p. 441.) Courts have thus “declined to impose an exhaustion requirement
when a purported administrative remedy did not incorporate ‘clearly defined machinery
72.
for the submission, evaluation and resolution of complaints by aggrieved parties.’” (Hill
RHF Housing Partners, L.P v. City of Los Angeles (2021) 12 Cal.5th 458, 479.)
Furthermore, “[e]ven when exhaustion of administrative remedies is required, there may
be factual issues that may not be resolved on demurrer.” (TracFone Wireless, Inc. v.
County of Los Angeles, supra, 163 Cal.App.4th at p. 1363, fn. 2.)
On the record before us, we are not convinced plaintiff was required to prove a
negative on demurrer with regard to the exhaustion requirement. At the very least, there
are disputed issues of fact concerning the existence and adequacy of administrative
remedies. As such, plaintiff sufficiently pleaded the nonexistence of a “plain, speedy,
and adequate remedy” by means other than a writ of mandate. (Code Civ. Proc., § 1086.)
DISPOSITION
The judgment of dismissal is reversed. The order sustaining the demurrer to the
third amended complaint and petition for writ of mandate is affirmed as to the cause of
action for public nuisance and reversed as to the cause of action for traditional
mandamus. The parties shall bear their own costs on appeal.
PEÑA, Acting P. J.
WE CONCUR:
DE SANTOS, J.
FAIN, J.†
†Judge of the Fresno Superior Court, assigned by the Chief Justice pursuant to article VI,
section 6 of the California Constitution.
73.
Filed 6/11/25
CERTIFIED FOR PARTIAL PUBLICATION
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FIFTH APPELLATE DISTRICT
WATER AUDIT CALIFORNIA,
F088084
Plaintiff and Appellant,
(Super. Ct. No. 22CV-03034)
v.
MERCED IRRIGATION DISTRICT,
Defendant and Respondent.
It appearing that part of the nonpublished opinion filed in the above entitled matter
on May 13, 2025, meets the standards for publication specified in California Rules of
Court, rule 8.1105(c), IT IS ORDERED that the opinion be certified for publication in the
Official Reports with the exception of part I, part II.D, and parts II.G through J of
Discussion.
PEÑA, Acting P. J.
WE CONCUR:
DE SANTOS, J.
FAIN, J.*
*Judge of the Fresno Superior Court, assigned by the Chief Justice pursuant to article VI,
section 6 of the California Constitution.
Wondering how this text applies to your situation?
Free consultation, no commitment
Describe your situation. Our team will contact you by email about your consultation.
Continue your research in ChatGPT or Claude
Connect Omnilex to search the legal corpus from your AI assistant.