SensorMetrix v. Dzine Unlimited CA4/1

CourtListener 10585799CalctappMay 16, 2025

Full text

Filed 5/16/25 SensorMetrix v. Dzine Unlimited CA4/1
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or
ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for
purposes of rule 8.1115.

COURT OF APPEAL, FOURTH APPELLATE DISTRICT

DIVISION ONE

STATE OF CALIFORNIA

SENSORMETRIX, D084143

Plaintiff and Respondent,

v. (Super. Ct. No. 37-2023-
00024668-CU-PA-CTL)
DZINE UNLIMITED, INC.,

Defendant and Appellant.

APPEAL from a judgment of the Superior Court of San Diego County,
Eddie C. Sturgeon, Judge. Affirmed.
Decker Law, James Decker, Griffin Schindler and Christopher Jones
for Defendant and Appellant.
Amin Wasserman Gurnani and William P. Cole for Plaintiff and
Respondent.
SensorMetrix entered into a government contract to make a technology
and subcontracted with Dzine Unlimited, Inc. for a portion of the contract.
When a dispute arose, Dzine and SensorMetrix submitted it to arbitration
under the terms of their subcontract. The arbitrator found in favor of
SensorMetrix, and the superior court confirmed the arbitration award over
Dzine’s motion to vacate. On appeal, Dzine contends the court erred in
confirming the award because the arbitrator exceeded his powers by basing
his decision on an interpretation of the subcontract contrary to its express
provisions. We discern no error and accordingly affirm.
I.
A.
SensorMetrix contracted with a branch of the United States military to
design and demonstrate a non-contact hit sensor (NCHS) to measure bullet
trajectories. SensorMetrix sent Dzine a request for proposal to participate as
a subcontractor. The request contemplated three phases of Dzine’s work:
(a) “an ‘alpha’ phase, in which Dzine would design and build an NCHS
version to permit an initial evaluation and testing; (b) a ‘beta’ phase,
involving a revised design and building of a mechanical version of the NCHS
system; and (c) the demonstration phase, in which Dzine would incorporate
final design changes and oversee the physical production of the” NCHS
systems.
Effective February 2020, SensorMetrix subcontracted with Dzine to
perform ten tasks related to these phases. The subcontract was an
incrementally funded “Firm Fixed Price Completion subcontract,” under
which Dzine would receive approximately $285,000 for completing the ten
tasks. The agreement expired December 6, 2021.
At the time of execution, roughly $58,000 was funded for three tasks.
SensorMetrix was not liable for payments exceeding that amount “unless
additional funds are made available and are incorporated as a modification to
this subcontract.” Dzine, meanwhile, was not obligated to perform services
exceeding the price of initial funding “until such time [as] additional contract

2
value and funding is agreed to by the parties for continued performance
under this agreement.”
The subcontract contained an integration clause providing: “This
Agreement and all attached Exhibits contain the entire agreement and
understanding between the parties as to its subject matter” and “[a]ny
modification to this Agreement shall be in writing, executed by an authorized
official of each party.”
The subcontract also included a nonwaiver provision, under which
“[t]he failure of a party in any instance to insist upon the strict performance
of the terms of this Agreement will not be construed to be a waiver or
relinquishment of any of the terms of this Agreement, either at the time of
the party’s failure to insist upon strict performance or at any time in the
future, and such terms will continue in full force and effect.”
The subcontract further contained an arbitration clause providing that
“[a]ny dispute arising under or related to this Agreement shall be resolved in
binding arbitration, before a single arbitrator, pursuant to the Commercial
Arbitration Rules of the American Arbitration Association.” “The decision of
the arbitrator resolving the dispute may be entered in any court of competent
jurisdiction.”
The parties twice modified the subcontract in writing to incrementally
increase the funded maximum to roughly $190,000 for additional tasks.
In February 2021, the parties entered into a second and separate
subcontract to calibrate the NCHS system.
B.
Dzine performed under the subcontract through the end of 2021. As of
November 30, SensorMetrix had paid roughly $247,000 to Dzine. That day,

3
Dzine submitted two invoices taking the total several hundred dollars over
the fixed price for the subcontract, yet SensorMetrix paid them in full.
According to Dzine, the “beta” systems failed due to SensorMetrix’s
design failures. SensorMetrix then requested additional “alpha” and “beta”
parts allegedly not included in the subcontract. Dzine explained to
SensorMetrix that it thought this request was a “third” project beyond those
contemplated by the two subcontracts. After a telephone call, however, Dzine
confirmed there were only two agreements between the parties.
Dzine did not complete the work by December 6. In late December
2021 and early January 2022, Dzine sent two invoices to SensorMetrix for
roughly $56,000. SensorMetrix did not pay them, instead sending a letter
informing Dzine the subcontract was expired and it had defaulted on its
contractual obligations to SensorMetrix’s detriment.
C.
Dzine filed a demand for arbitration against SensorMetrix seeking
payment of the last two invoices. SensorMetrix counterclaimed for breach of
contract. Over six days, the arbitrator took evidence, including the testimony
of the parties, and heard argument. None of the proceedings were recorded.
In a 19-page decision, the arbitrator found in favor of SensorMetrix on
Dzine’s claim. He found credible and truthful the testimony of one of
SensorMetrix’s principals that he forgot to issue a third modification of the
subcontract and concluded “Sensor[M]etrix’s willingness to have Dzine
continue to work on the NCHS subcontract after completion of [amendments]
1 and 2, served as a replacement for, or a waiver of the requirement for
executed subsequent [amendments] called for under that subcontract.”
The arbitrator further found Dzine had breached the subcontract in
numerous ways. He awarded SensorMetrix roughly $55,000 in damages.

4
D.
SensorMetrix petitioned to confirm the arbitration award in superior
court. Dzine opposed and moved to vacate the award, contending the
arbitrator exceeded his powers by admitting and relying on improper
extrinsic evidence, “arbitrarily mak[ing] up” an oral contract, “rema[king]”
the subcontract “largely based on the improper extrinsic evidence,” and
admitting and relying on improper hearsay testimony.
In a minute order, the trial court denied the motion to vacate. The
court concluded the arbitrator did not exceed his authority by considering
extrinsic evidence, something arbitrators and courts “regularly consider” in
construing contracts. It also found the arbitrator’s award was based on the
written contracts rather than an oral contract. The court noted hearsay is
allowed in arbitration proceedings. As the court found no ground to vacate
the arbitration award, it confirmed it.
II.
Dzine contends the arbitrator exceeded his powers by using extrinsic
evidence not to interpret the subcontract’s terms, but instead to waive or
modify them in a way that contradicted the express terms of the subcontract.
Dzine argues the contract was fully integrated and any modifications were
required to be in writing. Accordingly, the arbitration award must be
vacated. We disagree.
A.
In private arbitration, like here, “the scope of arbitration is a matter of
agreement between the parties, and the powers of an arbitrator are limited
and circumscribed by the” arbitration agreement. (Moncharsh v. Heily &
Blase (1992) 3 Cal.4th 1, 8-9 [cleaned up].) “[U]nless specifically required to
act in conformity with rules of law,” arbitrators “may base their decision upon

5
broad principles of justice and equity, and in doing so may expressly or
impliedly reject a claim that a party might successfully have asserted in a
judicial action.” (Id. at pp. 10-11 [cleaned up].) Thus, “it is the general rule
that [t]he merits of the controversy between the parties are not subject to
judicial review,” and “courts will not review the validity of the arbitrator’s
reasoning.” (Id. at p. 11 [cleaned up].) “In other words, it is within the power
of the arbitrator to make a mistake either legally or factually. When parties
opt for the forum of arbitration they agree to be bound by the decision of that
forum knowing that arbitrators . . . are fallible.” (Id. at p. 12 [cleaned up].)
“Any party to an arbitration in which an award has been made may
petition the court to confirm, correct[,] or vacate the award.” (Code Civ. Proc.,
§ 1285.) “[T]he court shall confirm the award as made” unless, as relevant
here, it vacates the award because “[t]he arbitrator[ ] exceeded their powers
and the award cannot be corrected without affecting the merits of the
decision upon the controversy submitted.” (§§ 1286, 1286.2, subd. (a)(4).)
We review de novo the superior court’s order on whether the arbitrator
exceeded their authority, but not the arbitrator’s award itself. (Advanced
Micro Devices, Inc. v. Intel Corp. (1994) 9 Cal.4th 362, 376, fn. 9.) Public
policy strongly favors arbitration as a means to expeditiously and finally
resolve disputes and avoid the courts, so courts “indulge every intendment to
give effect to such proceedings.” (Moncharsh, 3 Cal.4th at p. 9 [cleaned up].)
Accordingly, “arbitration awards are generally subject to extremely narrow
judicial review. Courts will not review the merits of the controversy, the
validity of the arbitrator’s reasoning[,] or the sufficiency of the evidence
supporting the arbitrator’s award.” (Hoso Foods, Inc. v. Columbus Club, Inc.
(2010) 190 Cal.App.4th 881, 887.)

6
B.
Bearing these principles in mind, on this record we conclude the trial
court correctly determined the arbitrator did not exceed his powers.
No one disputes the subcontract is fully integrated and contains a
nonwaiver provision. Contrary to Dzine’s argument, however, these
provisions do not expressly constrain the arbitrator’s right to rely on extrinsic
evidence. (Cf. Bonshire v. Thompson (1997) 52 Cal.App.4th 803, 806, 810,
811 [arbitrator who “must have relied on extrinsic evidence” exceeded powers
because integration clause provided “‘no extrinsic evidence whatsoever may be
introduced in any . . . arbitral proceeding . . . involving this agreement’”].)
Rather, the integration clause here contains standard language that cannot
be fairly read to prohibit the arbitrator from considering extrinsic evidence.
(See, e.g., Ennico, Closely Held Corporations: Forms and Checklists (Mar.
2025 update), ch. 9, § 9:17 [form independent contractor agreement
containing identical integration clause].)
Dzine claims that, even if the arbitrator had the power to consider
extrinsic evidence, he could only do so to interpret the contract; yet here the
arbitrator used it to modify the subcontract’s terms, as the evidence “did not
supplement the integrated Subcontract; it contradicted it.” According to
Dzine, the arbitrator’s decision cannot reasonably be construed as an
interpretation because the integration clause cannot reasonably be
interpreted to permit oral modifications to the contract.
This argument presupposes and depends on there being an oral
modification to the contract that violated the nonwaiver provision. Even
assuming waiver is how the arbitrator arrived at his decision, however, we do
not review “the validity of the arbitrator’s reasoning.” (Hoso Foods, Inc.,
190 Cal.App.4th at p. 887.) On this record, the arbitrator’s decision could

7
reasonably be viewed as an interpretation rather than a modification of the
subcontract.
The subcontract itself—not extrinsic evidence—sets out the maximum
fixed price as well as the entirety of the tasks to be completed by Dzine.
Dzine was not obligated to provide services exceeding the initial funding until
further “funding is agreed to by the parties for continued performance under
this agreement.” Under the subcontract, Dzine’s claims shall not “exceed the
total [initial] contract value” of roughly $58,000 “unless the parties mutually
agree to an increase to the contract value for additional scope herein.” Both
clauses refer to mutual agreement but do not require formal modification of
the subcontract. The drafters knew how to require modification—which
would have to be written—had they wanted to; for example, SensorMetrix
could not be held liable for more than the funded amount “unless additional
funds are made available and are incorporated as a modification to this
subcontract.” (Italics added.)
The arbitrator could reasonably construe these provisions as allowing
the parties to continue to work toward more milestones in exchange for
additional funding without formally modifying the agreement. Such an
interpretation would not add an oral third amendment to the subcontract,
but rather harmonize its terms and the parties’ course of conduct. And such
an interpretation would not necessarily contradict the integration and
nonwaiver clauses.
In sum, the arbitrator did not exceed his powers. The arbitrator
decided the dispute before him—Dzine’s claim to a right to payment and
SensorMetrix’s breach of contract counterclaim—and not any matter the
parties never submitted to arbitration. (O’Flaherty v. Belgum (2004)
115 Cal.App.4th 1044, 1055.) The arbitrator did not necessarily “remake[ ]”

8
the subcontract, much less arbitrarily so. (Id. at pp. 1055-1056.) No one
asserts the arbitrator lacked subject matter jurisdiction, the subcontract was
illegal, or that the award violates public policy or any party’s statutory rights.
(Id. at p. 1056.) The remedy is rationally related to the contract as
reasonably interpreted and the issues before the arbitrator. (Ibid.) To the
extent the arbitrator may have considered equitable principles in addition to
the subcontract’s express terms in interpreting the instrument and
fashioning an appropriate remedy, an arbitrator is entitled to do so.
(See Moncharsh, 3 Cal.4th at pp. 8-9.) Thus, the trial court appropriately
confirmed the arbitration award.
Given our determination, we need not address the remainder of the
parties’ arguments, such as whether the nonwaiver provision was waivable or
whether waiver is a question of fact.
III.
We affirm. SensorMetrix is entitled to its costs on appeal.

CASTILLO, J.

WE CONCUR:

IRION, Acting P. J.

DATO, J.

9