Sierra Club v. Del Puerto Water District CA5

CourtListener 10324204CalctappJan 30, 2025

Full text

Filed 1/30/25 Sierra Club v. Del Puerto Water District CA5

NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIFTH APPELLATE DISTRICT

SIERRA CLUB et al.,
F085896/F086218
Plaintiffs and Appellants,
(Super. Ct. No. CV-20-005193)
v.

DEL PUERTO WATER DISTRICT, OPINION
Defendant and Respondent;

SAN JOAQUIN RIVER EXCHANGE
CONTRACTORS WATER AUTHORITY,

Real Party in Interest and Appellant.

APPEAL from a judgment of the Superior Court of Stanislaus County. John R.
Mayne, Judge.
Law Office of Donald B. Mooney and Donald B. Mooney for Plaintiffs and
Appellants.
Remy Moose Manley, James G. Moose, Christopher L. Stiles and Laura M.
Harris; Minasian Law and Andrew John McClure for Defendant and Respondent.
Minasian Law and Andrew John McClure for Real Party in Interest and Appellant.
-ooOoo-
The Del Puerto Water District (DPWD)1 and the San Joaquin River Exchange
Contractors Water Authority seek to build a reservoir near Patterson, California to store
their water allotments from the Central Valley Project. The Sierra Club et al., challenged
the Environmental Impact Report (EIR) for the reservoir project on several grounds. The
trial court rejected several of those challenges, but accepted others and ordered the EIR to
be decertified.
The Sierra Club appealed the judgment and the Exchange Contractors cross-
appealed. The Exchange Contractors also appealed the trial court’s denial of their motion
to vacate the judgment, and we have consolidated that appeal with this one.
We conclude that each party has at least one meritorious contention, and will
reverse the judgment in part and remand with instructions.
BACKGROUND
I. Water in California
Broadly speaking, much of California’s water is in the north and much of its
demand is in the south. (Natural Resources Defense Council v. Kempthorne (2009) 621
F.Supp.2d 954, 959–960.) As a result, the government created “‘“a system of dams,
reservoirs, levees, canals, pumping stations, hydropower plants, and other
infrastructure”’” (North Coast Rivers Alliance v. Westlands Water Dist. (2014) 227
Cal.App.4th 832, 840) in order to store surplus flows from the rivers in the north and
transport them south. (San Luis & Delta-Mendota Water Authority v. U.S. Dept. of
Interior (E.D.Cal., Mar. 2, 2015, No. 1:11-cv-00952 LJO GSA) 2015 U.S. Dist. Lexis
24970.) The system, called the Central Valley Project (CVP), delivers water to hundreds
of water contractors pursuant to various delivery contracts, primarily for agricultural use
in the Central Valley. (North Coast, supra, at p. 840.)

1 We will refer to Del Puerto Water District and its board of directors, both of which are
parties on appeal, as DPWD.

2.
Friant Dam and the Exchange Contract
In the mid-1930’s, the federal government wanted the CVP to extend into the
Bakersfield area. (Westlands Water Dist. v. Patterson (1994) 864 F.Supp. 1536, 1539
(Westlands Water Dist.).) To accomplish this, the San Joaquin River would need to be
diverted into the Friant-Kern and Madera Canals. (Ibid.) This diversion would be
effected by building Friant Dam.
To accomplish this, the federal government needed to acquire the water rights
necessary for such a diversion. (State Water Resources Control Bd. Cases (2006) 136
Cal.App.4th 674, 692.) It did so in 1939 by entering into two contracts with the existing
water rights holders (i.e., the Exchange Contractors): a purchase contract and an
exchange contract. (Westlands Water Dist., supra, 864 F.Supp. at p. 1539.)
“Under the Purchase Contract, the Exchange Contractors sold all their San Joaquin
River water rights to the United States, except for ‘reserved water,’ water to which the
Exchange Contractors held vested rights. Simultaneously, under the Exchange Contract,
the Exchange Contractors agreed not to exercise their rights to reserved water, so long as
they received substitute water from the Federal Delta–Mendota Canal, or other sources
delivered to the Mendota Pool.” (Westlands Water Dist., supra, 864 F.Supp. at p. 1539,
fn. omitted.)
CVP’s Transportation of Water from Delta
While the Friant Division of the CVP operates on the east side of the Valley, the
CVP also has substantial infrastructure on the west side of the Valley. The CVP operates
a pumping plant that moves millions of acre-feet of water from the Bay-Delta (Delta) to
the Delta-Mendota Canal (DMC), which carries the water south along the western edge
of the San Joaquin Valley.2 (San Luis & Delta-Mendota Water Authority v. Jewell (9th

2 The DMC also has an inter-connection with the California Aqueduct west of the City of
Tracy and connects with the State Water Project (SWP) at the O’Neill Forebay.

3.
Cir. 2014) 747 F.3d 581, 594; State Water Resources Control Bd. Cases, supra, 136
Cal.App.4th at p. 692; In re Bay Delta etc. (2008) 43 Cal.4th 1143, 1154.) DMC waters
are pumped into the San Luis Reservoir for storage.3 When water is released from the
San Luis Reservoir back into the DMC, it can continue on to the Mendota Pool—a small
reservoir created by the Mendota Dam. At the Mendota Pool, the DMC waters replace
the natural flow of the San Joaquin River. (State Water Resources Control Bd. Cases,
supra, at p. 692.)
Coordination With SWP
The State of California has its own water project with reservoirs, dams, power
plants, pumping plants, canals and aqueducts (SWP). (Planning & Conservation League
v. Department of Water Resources (2000) 83 Cal.App.4th 892, 898–899.) In 1986, the
California Department and Water Resources and the United States Bureau of Reclamation
(Reclamation) signed a coordinated operating agreement. The coordinated operating
agreement defines each project’s responsibility to protect other beneficial uses of water
and defines the sharing of excess water between the projects.
II. The Project
The project at issue in this case is a proposed dam and reservoir connected to the
DMC, west of the City of Patterson. The proposed reservoir would provide 82,000 acre-
feet of storage. The project would also include three saddle dams, a spillway, inlet/outlet
works, and conveyance facilities (including a diversion/outfall facility on the DMC, and a
pumping plant).
The partners behind the project are DPWD and the Exchange Contractors (the
Project Partners). As noted above, the Exchange Contractors receive CVP waters
pursuant to the 1939 contracts (and subsequent agreements) with the United States. The

3 The San Luis Reservoir also stores water from the SWP delivered by the California
Aqueduct.

4.
Exchange Contractors have a contractual water allotment of 840,000 acre-feet during
noncritical years. In critical years, the allotment is reduced to 75 percent, or 650,000
acre-feet. The Exchange Contractors desire to stabilize their water supplies by storing
water allocated during noncritical years for use during critical years.
DPWD has its own water service contract with Reclamation through which it
purchases CVP waters. In some recent drought years, DPWD received no water at all.
The reservoir would store water delivered pursuant to the Project Partners’
contracts for delivery of waters from the DMC. The reservoir would also capture some
flows from the Del Puerto Creek. These are the only two sources of water anticipated to
fill the reservoir. If any other water sources would be used in the future, project-specific
environmental review would then be conducted.
Procedural History
In June 2019, DPWD issued a notice of preparation (NOP), generally describing
the project as “a reservoir located on Del Puerto Creek in the foothills of the Coast Range
Mountains west of Patterson, California and Interstate-5.” The reservoir would provide
85,000 acre-feet of water storage. The NOP also noted the project would involve
construction of a main dam, four saddle dams, a spillway, inlet/outlet works, conveyance
facilities, and electrical facilities; and would involve relocation of existing utilities.
A draft EIR (DEIR) was issued in December 2019, and notice was given that it
would be available for public review beginning December 12, 2019.
The final EIR (FEIR) was made available to the public and commenting agencies
on October 9, 2020. Pertinent details of the DEIR and FEIR are described below in
connection with the issues raised on appeal.
On October 21, 2020, the DPWD Board voted to certify the FEIR and approve the
project.
On November 20, 2020, the Sierra Club, California Native Plant Society, Center
for Biological Diversity, and Friends of the River (petitioners) filed a petition for writ of

5.
mandate in Stanislaus Superior Court. The petition sought to set aside the FEIR and the
approval of the project.
The court accepted briefing, including sealed briefing regarding petitioners’ claim
the FEIR failed to sufficiently analyze impacts to cultural resources, and heard oral
argument. On October 31, 2022, the court issued a ruling rejecting several of petitioners’
contentions, but granting the writ “as to failure to adequately address the relocation of
Del Puerto Canyon Road.” The court addressed the confidential cultural resources issues
in a separate minute order dated November 29, 2022, in which it ruled in favor of
petitioners.
Pursuant to a stipulation of the parties, the court issued an order on December 27,
2022, making alterations to the details of its October 31, 2022 ruling, but generally
reiterating the same substantive ruling.
DISCUSSION
I. The FEIR Was Not Required to Have a Different Project Description or Offer
Additional Analysis Concerning the Speculative Possibility Reclamation
Might Alter Delta Pumping Operations in the Future
A. Law
An EIR must describe the project under consideration, including its location and
“[a] general description of the project’s technical, economic, and environmental
characteristics .…” (Cal. Code Regs., tit. 14, § 15124, subds. (a), (c).)
An EIR must also identify and describe both direct and indirect environmental
impacts of the project. (Cal. Code Regs., tit. 14, § 15126.2, subd. (a).) This includes
both direct physical changes to the environment caused by the project and reasonably
foreseeable indirect physical changes that may be caused by the project. (Cal. Code
Regs., tit. 14, § 15064, subd. (d).) However, this does not include indirect impacts that
are speculative.

6.
B. Additional Background
The FEIR concluded that the proposed operation of the project would not affect
CVP or SWP pumping operations at the Delta. The FEIR added that the project could
provide Reclamation additional flexibility to increase pumping if it so chose, as a result
of increased storage capacity and increased flexibility to alter when water would be
pumped to Project Partners. The FEIR noted that “[a]ny such modification of Delta
pumping by Reclamation would be evaluated by Reclamation in a separate NEPA[4]
document if such pumping is determined to be outside existing certified environmental
documentation and/or operating agreements.” (Italics added.)
C. Analysis
Sierra Club contends the FEIR’s project description failed to disclose how the
project will affect diversions from the Delta. This, in turn, purportedly also rendered the
impacts analysis insufficient. Project Partners respond that the project will not affect
diversions from the Delta.
Reclamation increasing (or otherwise altering) Delta outflows is not the project at
issue here. The project is construction of a reservoir. And it is the environmental impacts
of the project that must be analyzed, not those of some other project that may materialize
in the future.
We acknowledge that EIR’s must usually consider both direct and indirect
impacts. However, indirect impacts can literally reverberate into the future indefinitely.
As these branches of possibilities grow exponentially into the unknown future, it quickly
becomes unhelpful and infeasible to analyze or even identify speculative possibilities.
Thus, when indirect impacts are attenuated to the level of speculation, they need not be
evaluated.

4 National Environmental Policy Act of 1969 (NEPA; 42 U.S.C. § 4321 et seq.).

7.
“Courts have made clear that ‘CEQA[5] does not require evaluation of speculative
impacts.’” (League to Save Lake Tahoe v. County of Placer (2022) 75 Cal.App.5th 63,
139.) While an EIR must examine even the potential for a project to impact the
environment, that “does not mean … that a potential impact, no matter how speculative,
must be considered in an EIR.” (Save Round Valley Alliance v. County of Inyo (2007)
157 Cal.App.4th 1437, 1451 (Save Round Valley Alliance).)
Specifically, the mere fact that some other future action has been proposed does
not necessarily require its inclusion in the EIR. (See Gray v. County of Madera (2008)
167 Cal.App.4th 1099, 1127.) Indeed, where future developments are unspecified and
uncertain, the EIR is not required to speculate as to future environmental consequences.
(Ibid.) “It has long been recognized that premature attempts to evaluate effects that are
uncertain to occur or whose severity cannot reliably be measured is ‘a needlessly
wasteful drain of the public fisc.’” (Citizens for a Sustainable Treasure Island v. City and
County of San Francisco (2014) 227 Cal.App.4th 1036, 1061.) “Evaluation of future
environmental effects must await the future decisions that could cause the effects.”
(Topanga Beach Renters Assn. v. Department of General Services (1976) 58 Cal.App.3d
188, 196.)
Consequently, across a variety of CEQA contexts, courts have declined to
invalidate an EIR for failing to discuss the potential environmental impacts of
speculative, hypothetical future responsive actions by third parties.
For example, in Save Round Valley Alliance, the proposed project was to subdivide
74 acres into twenty-seven 2.5-acre parcels for development into single family
residences. The challengers argued that the EIR should have analyzed what would
happen if the future lot owners chose to build two residences on each site. The
challengers alleged the failure to consider this possibility caused the EIR to persistently

5 California Environmental Quality Act (CEQA; Pub. Resources Code, § 21000 et seq.).

8.
understate the project’s environmental impacts. The court rejected this argument,
observing that whether second units would be built “depends initially upon the desires of
future lot owners, who are unknown.” (Save Round Valley Alliance, supra, 157
Cal.App.4th. at p. 1450.) The court continued, “even if the building of some second units
might be foreseeable, it is impossible to predict how many units will be built, the size of
such units, on which lots they might be built, their location within a lot, the visibility of a
second unit from outside the subdivision, or how such units might impact the
environment.” (Id at p. 1450.)
In Marin Mun. Water Dist. v. KG Land California Corp. (1991) 235 Cal.App.3d
1652, the project was a water district’s moratorium on new water service connections.
The trial court concluded the EIR was deficient in several respects, including that it failed
to “analyze adequately the potentially significant adverse secondary environmental
effects of the moratorium .…” (Id. at p. 1659.) Specifically, it was acknowledged that
after five or six years, the moratorium would create “increased pressure for growth and
development in areas outside the District’s service area.” (Id at pp. 1662–1663.)
However, the nature and extent of future development and its environmental impacts
would depend on what the local agencies in those jurisdictions permitted. The court
affirmed the water district’s conclusion “that the potential environmental impact of
possible future development elsewhere was simply too speculative to evaluate .…” (Id.
at p. 1663.)
In Yerba Buena Neighborhood Consortium, LLC v. Regents of University of
California (2023) 95 Cal.App.5th 779, the project was a plan to make substantial changes
to one of UCSF’s campuses, including new buildings. (Id. at p. 788.) Challengers to the
EIR asserted it should have analyzed indirect impacts the project would have on vehicle
miles traveled. (Id at p. 807.) The court rejected that challenge, observing it relied “on
the speculative assumption that implementation of the [project] will lead to the transit
system being overwhelmed and [that] transit users will resort to private automobiles

9.
instead.” (Ibid.) In other words, the challengers were improperly demanding that the
EIR address speculative environmental effects that would be caused by third parties
changing their conduct in response to the project.
Analogous here, challengers assert a third party (i.e., Reclamation) will alter its
behavior (i.e., increase/alter pumping) after construction of the project, causing
environmental impacts that should have been analyzed in the EIR. However, it is
speculation to assume the alleged increase of capacity in San Luis Reservoir or the
increased flexibility of pumping schedules would lead to Reclamation increasing Delta
outflows. It is simply unknown how operations at the Delta may change in the future due
to the actions of third parties. (See Planning & Conservation League v. Department of
Water Resources (2024) 98 Cal.App.5th 726, 755-756.) It was not incumbent on the
FEIR to speculate that Reclamation might choose to alter its behavior based on the
project and then to analyze the environmental impacts of that speculative possibility.
As an aside, we observe that even if Reclamation did choose to increase pumping
from the Delta at some point in the future, that action would either (1) be within limits set
by existing approvals, which have already satisfied any applicable environmental review
requirements or (2) exceed existing approvals, which would almost certainly necessitate
federal and/or state environmental review at that point. The FEIR explains as much:
“Any … modification of Delta pumping by Reclamation would be evaluated by
Reclamation in a separate NEPA document if such pumping is determined to be outside
existing certified environmental documentation and/or operating agreements.”
Piecemealing
Sierra Club claims the FEIR’s approach fails to account for the whole of the
action, and instead chops up a single project into “bite-size pieces.”
“Improper piecemealing occurs ‘when the purpose of the reviewed project is to be
the first step toward future development’ or ‘when the reviewed project legally compels
or practically presumes completion of another action.’ [Citation.] By contrast, an EIR

10.
need not analyze ‘specific future action that is merely contemplated or a gleam in a
planner’s eye.’” (East Sacramento Partnerships for a Livable City v. City of Sacramento
(2016) 5 Cal.App.5th 281, 293 (East Sacramento Partnerships).)
In order to accept Sierra Club’s contention, we would have to conclude that the
construction/operation of Del Puerto Canyon Reservoir and Reclamation’s increase of
Delta outflows are, in fact, a single project disguised as two. Or, in other words, that the
FEIR made a “calculated selection of [a] truncated project concept .…” (County of Inyo
v. City of Los Angeles (1977) 71 Cal.App.3d 185, 200.) That is not what occurred here.
While there is a theoretical possibility that Reclamation could export additional water, in
no way does the construction of the reservoir “‘compel[]’” or “‘practically presume[]’”
an increase in Reclamation’s pumping at the Delta. Instead, Sierra Club has “‘merely
contemplated’” (East Sacramento Partnerships, supra, 5 Cal.App.5th at p. 293) that
Reclamation could hypothetically engage in such action. Building a reservoir and
increasing pumping at the Delta are not a single project.
Contradictory Statements
Sierra Club asserts that the FEIR’s claim the project will not affect Delta pumping
operations is “illogical” because the project was intended to enable DPWD “‘to accept
water when excess is available that would otherwise be lost due to lack of means to
store’” the water. But Sierra Club fails to sufficiently explain how these two concepts are
necessarily illogical or contradictory. In theory at least, water could be “lost” to the
Project Partners because they lack sufficient storage to accept delivery at the time it is
available, resulting in that water instead being stored in San Luis Reservoir or given to
other south-of-the-Delta users, without any increase in Delta pumping.
The fact remains that the FEIR clearly concludes that the project will not affect
CVP or SWP Delta pumping operations. In this way, the present case is quite
distinguishable from San Joaquin Raptor Rescue Center v. County of Merced (2007) 149
Cal.App.4th 645 (Raptor), on which Sierra Club relies. In that case, the EIR insisted in

11.
several places that the mine expansion project would not result in an increase in mine
production. Elsewhere, however, the EIR indicated that the mine might sometimes
operate at a new peak capacity of 500,000 tons per year, more than double the prior four-
year average production of 240,000 tons per year. (Id. at pp. 655–656 & fn. 4.) This was
an inherent and irreconcilable conflict in that case’s EIR.
Nor is this case like Communities for a Better Environment v. City of Richmond
(2010) 184 Cal.App.4th 70. That case involved a project to renovate a crude oil refinery.
The court held the project’s EIR was misleading because it “claim[ed] that the Project is
designed to allow more flexibility in refining future crude supplies that the EIR describes
as ‘increasingly heavier,’ but on the other hand, denie[d] that the Project will enable the
[r]efinery to process heavier crude.” (Id. at p. 83.) Additionally, the project proponent’s
filings with the United States Securities and Exchange Commission clearly indicated the
project was intended to “‘increase the flexibility to process lower API-gravity crude
oils .…’” (Id. at pp. 83–84.) Here, there is no analogous indication that the FEIR was
incorrect or misleading when it stated the project will not cause increased pumping from
the Delta.
Baseline
Sierra Club also contends the FEIR used the wrong baseline. “An EIR must
include a description of the physical environmental conditions in the vicinity of the
project. This environmental setting will normally constitute the baseline physical
conditions by which a lead agency determines whether an impact is significant.…” (Cal.
Code Regs., tit. 14, § 15125, subd. (a).) “An existing conditions baseline shall not
include hypothetical conditions, such as those that might be allowed, but have never
actually occurred, under existing permits or plans, as the baseline.” (Id., subd. (a)(3).)
Specifically, Sierra Club contends the FEIR erred in omitting environmental
impacts of increased pumping “solely because the CVP would continue to operate within
existing permit limits regardless of Project approval.” But that is not why the FEIR omits

12.
environmental impacts of increased pumping in the Delta. The FEIR omits that analysis
because the project will not cause increased pumping from the Delta, and therefore the
project will not cause the environmental impacts that might result from said increased
pumping. Increased pumping would be caused by Reclamation’s decision to do so, not
construction of the proposed reservoir.
III. The EIR Fails to Adequately Analyze Potential Impacts to Downstream
Terrestrial Species
Petitioners next contend the FEIR fails to analyze potential impacts to downstream
terrestrial species.
A. Law
An EIR must discuss significant environmental impacts of the project. (Cal. Code
Regs., tit. 14, § 15126.) An EIR must also briefly discuss effects of a project that were
determined not to be significant. (Id., § 15128.) Certain impacts on wildlife and/or their
habitat are required to be found significant. (Id., § 15065, subd. (a)(1).)
“‘[A] reviewing court must determine whether the discussion of a potentially
significant effect is sufficient or insufficient, i.e., whether the EIR comports with its
intended function of including “‘“detail sufficient to enable those who did not participate
in its preparation to understand and to consider meaningfully the issues raised by the
proposed project.”’”’” (Natural Resources Defense Council, Inc. v. City of Los Angeles
(2023) 98 Cal.App.5th 1176, 1204.) “The inquiry presents a mixed question of law and
fact. As such, it is generally subject to independent review.” (Sierra Club v. County of
Fresno (2018) 6 Cal.5th 502, 516 (Sierra Club).)
B. Analysis
As noted, Sierra Club contends the FEIR fails to properly discuss potential
impacts to downstream terrestrial species. We agree. While the FEIR analyzes adjacent
issues—e.g., impacts to downstream aquatic species and impacts to terrestrial species
that are not downstream—it does not analyze impacts to downstream terrestrial species.

13.
The study area of the FEIR’s section on terrestrial biological resources was: “the
footprints of the proposed project infrastructure, the maximum inundation area, areas
where utilities may need to be relocated, any areas of potential disturbance related to
constructing the proposed project, and a 300 foot buffer around these areas .…” In other
words, the study included areas that will be disturbed by construction, the areas that will
be inundated by water, and a 300-foot buffer. It does not reference downstream Del
Puerto Creek, the flows of which will be impacted to some extent by the project (at least
in terms of annual volume). Thus, this portion of the FEIR does consider impacts to
terrestrial biological resources, but only those in the study area and not those
downstream.
In contrast, the FEIR’s section on impacts to fish does consider whether there will
be downstream impacts. In responding to Sierra Club’s contentions, Project Partners
emphasize this analysis, which concluded that the operation of the project would ensure
that major flow events would be released downstream of the proposed dam in order to
mimic the natural patterns of flow variability. Specifically, it observes that,

“Under proposed project operations, major flow events in Del Puerto
Creek would continue to be released downstream of the proposed dam as
part of the environmental commitments of the project. These
environmental flow requirements include operation of the dam to bypass
major flow events in a pattern that preserves key components of the peak
flow events (Section 2.3.1, Reservoir Operations). This is consistent with
the ‘functional flow’ approach of managing flows in regulated rivers to
mimic the natural patterns of flow variability that drive the geomorphic and
ecological processes supporting native aquatic species (Yarnell et al.
2015).” (Italics added.)
However, this analysis expressly refers to aquatic species. So while it considers
impacts to downstream species, it does so for aquatic rather than terrestrial species.
Similarly, the Project Partners emphasize pages 2405–2405 of the administrative record,
but that section also quite clearly applies to impacts on fish and aquatic species. What is

14.
missing is analysis of whether there will be impacts to species that are both downstream
and terrestrial.
It may very well be the case that the project’s efforts to mimic natural patterns of
flow variability will result in the project having no impacts to downstream terrestrial
species. That is a scientific matter on which we offer no input.6 What matters in the
present action is that the FEIR does not expressly conclude as much. As a result, it fails
as an informational document to adequately consider a potentially significant
environmental impact.
IV. Substantial Evidence Supports the Agency’s Methodology in Studying
Biological Resources
Sierra Club argues that many of the “biological resources surveys conducted
during EIR preparation produced little information because they were poorly timed” (e.g.,
wet vs. dry years) and were not sufficiently comprehensive.
A. Standard of Review
“It is well established an agency has discretion in selecting the methodology to be
used in evaluating environmental impact, subject to review for substantial evidence.”
(South of Market Community Action Network v. City and County of San Francisco (2019)
33 Cal.App.5th 321, 337.) The substantial evidence standard “applies to challenges to
the scope of an EIR’s analysis of a topic, the methodology used for studying an impact
and the reliability or accuracy of the data upon which the EIR relied because these types
of challenges involve factual questions.” (Bakersfield Citizens for Local Control v. City
of Bakersfield (2004) 124 Cal.App.4th 1184, 1198.)

6 If the FEIR had made such a conclusion with respect to downstream terrestrial species,
we would review it under the deferential substantial evidence standard. However, since the
FEIR omits such analysis/conclusions, it is an issue of law.

15.
However, Sierra Club insists,

“[this] is not a dispute over methodology, but instead, whether the EIR
provided an adequate analysis to inform, which is a question of law.
[Citation.] Both [California Native Plant Society] and [Department of Fish
and Wildlife] identified the need to properly conduct surveys to make an
impact determination. [Citation.] As DPWD’s inclusive surveys were
reconnaissance level (protocol-level) and/or done at the improper time, the
EIR fails to provide an informed understanding of a critical aspect of the
Project’s environmental impacts.”
While Sierra Club posits this is not a “dispute over methodology,” it immediately
goes on to describe a dispute over methodology.7 Specifically, whether the FEIR is
insufficient because the studies were reconnaissance-level rather than protocol-level or
whether they were “done at the improper time.” Consequently, we review the Sierra
Club’s contention under the substantial evidence standard.
B. Additional Background
Wildlife surveys and an aquatic resources delineation was conducted in the spring
and summer of 2019. Biologists conducted botanical surveys in the fall of 2019, and
again in the spring of 2020.
Biologists conducted a general habitat evaluation “to determine whether suitable
habitat exists for special-status plant and animal species” from May through July 2019.
In addition to wildlife observations made during field surveys, motion-activated trail
cameras were placed near the mouth of Del Puerto Canyon in June 2019. Prior to the
field surveys, biologists reviewed databases to evaluate whether special-status species or
sensitive biological resources could occur in the study area. During the botanical surveys
and aquatic resources delineation survey, 297 plant species were observed.

7 Sierra Club also contends that Sierra Club is the controlling authority on the standard of
review issue. But even that case was quite clear that “a decision to use a particular methodology
and reject another is amenable to substantial evidence review .…” (Sierra Club, supra, 6 Cal.5th
at p. 514.)

16.
It was determined that five special-status plant species occur or have been reported
from the study area. The FEIR acknowledged that the project could result in direct,
substantial impacts to these species.
It was also determined that 22 special-status wildlife species may occur in the
study area or could be affected by the project.
C. Analysis
Sierra Club observes that springtime plant surveys were conducted during a dry
year. They point to the FEIR’s observation that two special-status species that could have
been present were not found in the study area, possibly due to the fact that recent rainfall
was 14 percent of normal, which could have caused the species not to produce seedlings.
But every study or survey could be made better in some way. A one-year study could
have been a two-year study. A two-year study could have been a three-year study. That
is, “[a] project opponent or reviewing court can always imagine some additional study or
analysis that might provide helpful information.” (Laurel Heights Improvement Assn. v.
Regents of University of California (1988) 47 Cal.3d 376, 415 (Laurel Heights).) But just
because further study would be helpful does not mean it is necessary. (Ibid.) Biologists
conducted botanical surveys in the fall of 2019, and again in the spring of 2020, and those
surveys identified several species in the study area. While they did not find the two
species referenced by Sierra Club, the FEIR appropriately acknowledged that the lack of
observation did not exclude the possibility they were present given the lower-than-
average rainfall. Indeed, the FEIR even presumed the two species were extant in the
study area despite not being observed. We conclude Sierra Club has failed to show these
botanical studies were insufficient.
Sierra Club similarly observes that wildlife surveys were conducted in “dry
months” and not “wet months,” even though the project might affect amphibians. Sierra
Club cites nothing in the record establishing that amphibians cannot be adequately
observed during the dry months of the year—an unstated but necessary premise to its

17.
claim the surveys were insufficient. This relatively undeveloped contention cannot be
sustained on substantial evidence review.
Sierra Club also criticizes the use of reconnaissance-level studies rather than
protocol-level studies. The FEIR explained its use of reconnaissance-level field studies
as follows,

“reconnaissance level field studies were conducted to evaluate the presence
of sensitive plants and wildlife. The evaluation of impacts on biological
resources was not exclusively done through the use of databases and maps
though these resources were employed to assist in characterization of
habitats and identification of species that have been previously found in the
project area. This is standard practice for evaluation of potential project
effects in CEQA documents because protocol-level surveys can take
multiple seasons to complete and the results of surveys are typically valid
for a limited period of time and thus may no longer be valid by the time
construction begins. Protocol level surveys would be conducted during the
appropriate season and in accordance with accepted methods prior to the
start of construction, and preconstruction surveys would be conducted
during the appropriate time frame as described in the mitigation measures
presented in the Draft EIR prior to initial ground disturbing activities
associated with project construction. The mitigation measures in the Draft
EIR include commitments to conduct protocol-level surveys for sensitive
plant species, vernal pool branchiopods, California tiger salamander,
California red-legged frog, foothill yellow-legged frog, Swainson’s hawk
and San Joaquin kit fox. Because protocol level surveys have not been
conducted, the EIR assumes presence of species where suitable habitat is
present.”
Sierra Club criticizes this approach because the fact that a particular survey costs
money is not a justification for omitting the information. But that was not the
justification. The EIR stated that protocol-level studies were not yet included because
they “are typically valid for a limited period of time and thus may no longer be valid by
the time construction begins.” Consequently, Sierra Club is incorrect to assert that the
FEIR “provides zero justification” for the lack of protocol-level surveys.

18.
V. The FEIR Did Not Improperly Defer or Inadequately Discuss Mitigation
Measures
Sierra Club contends the FEIR improperly defers mitigation of impacts on special-
status plants, foothill yellow-legged frogs, San Joaquin kit foxes, American badgers,
riparian and wetlands habitat, and oak woodland habitat. Specifically, Sierra Club asserts
the FEIR failed to give a reason for deferral and did not set standards of performance.
A. Law
An EIR must describe feasible measures that could minimize significant adverse
impacts. (Cal. Code Regs., tit. 14, § 15126.4, subd. (a)(1).) These are referred to as
“mitigation measures.” The general description of mitigation measures may not be
deferred and must be included in the EIR. “[T]he specific details of a mitigation
measure, however, may be developed after project approval when it is impractical or
infeasible to include those details during the project’s environmental review provided that
the agency (1) commits itself to the mitigation, (2) adopts specific performance standards
the mitigation will achieve, and (3) identifies the type(s) of potential action(s) that can
feasibly achieve that performance standard and that will [be] considered, analyzed, and
potentially incorporated in the mitigation measure.…” (Id., subd. (a)(1)(B).)
B. Additional Background
Vernal Pool Branchiopods
Vernal pool fairy shrimp and vernal pool tadpole shrimp were not observed in the
study area. However, habitat suitable for vernal shrimp was observed. The construction
and operation of the project would result in the permanent loss of up to 1.4 acres of such
habitat. That loss would have a substantial adverse effect on federally listed vernal pool
branchiopods and was therefore determined to be a significant environmental impact.
To mitigate this significant impact, the FEIR described what it called Mitigation
Measure BIO-TERR-1c as follows:

“At least one year prior to impacting any of the potential vernal pool
branchiopod habitat, a biologist with a 10(a)(1)(A) recovery permit for

19.
vernal pool branchiopods shall conduct protocol level surveys for federally
listed vernal pool branchiopods following the [United States Fish and
Wildlife Service’s] 2015 Survey Guidelines for the Listed Large
Branchiopods. These surveys require the completion of one dry season
survey and one wet season survey. If no federally listed branchiopods are
present no further mitigation would be required other than requirements
under federal and state laws protecting wetlands. If federally listed
branchiopods are determined to be present and are located in permanent
disturbance areas then the Project Partners shall compensate for the loss of
federally listed vernal pool branchiopod habitat through the purchase of
credits from a [United States Fish and Wildlife Service] approved
mitigation bank at a conservation acreage of 2:1 protection and 1:1
restoration.”
The FEIR concluded this mitigation measure would reduce the environmental
impact to less than significant because lost habitat would be replaced.
Foothill Yellow-legged Frog
The FEIR also concluded that the project would cause the permanent loss of
habitat for the foothill yellow-legged frog, more favorable conditions for its predators,
behavior disruption caused by lighting, and injuries/mortality from maintenance activities
and associated traffic. The FEIR determined the loss of habitat and direct
injury/mortality constituted a significant environmental impact.

The EIR described Mitigation Measure BIO-TERR-1h as follows,

“If surveys determine that foothill yellow-legged frog is not present
in Del Puerto Creek no further mitigation is necessary. If foothill yellow-
legged fro[g] is present, the habitat permanently impacted due to the
proposed project shall be fully mitigated by either purchasing property
and/or a conservation easement that contains stream habitat of similar
quality and quantity and that is currently occupied by foothill yellow-
legged frog and/or represents an area that has been historically occupied
and where successful recolonization is likely (e.g., known occupation in
nearby watershed or tributary). A final mitigation plan shall be developed
and approved by [California Department of Fish and Wildlife]. The plan
shall include measures for the long-term management of these lands for the
benefit of foothill yellow-legged frog and include adaptive management
measures.”

20.
The FEIR concluded that this measure, combined with others described in the
FEIR, would reduce the project’s impacts on the foothill yellow-legged frogs to less than
significant.
San Joaquin Kit Foxes
The FEIR stated that the contiguous habitat in the project footprint was likely too
small to support occupancy of San Joaquin kit foxes. However, it was unknown where
and how frequently kit foxes would disperse through the study area. Researchers did
locate an entry in the California Natural Diversity Database from the mouth of Del Puerto
Canyon and two additional entries reported road mortalities along Interstate 5.
The project would result in the permanent loss of up to 197 acres and would cause
temporary disturbance to 82 acres of potential kit fox habitat. Operational and
construction activities could cause injury or mortality to kit foxes.
In response, the FEIR presented Mitigation Measure BIO-TERR-1o, which
provided for a preconstruction survey to be completed no less than 14, and no more than
30 days before the beginning of ground disturbance. The biologist conducting the survey
was required to systematically canvass the area with transects spaced 30–100 feet apart to
ensure 100 percent visual observation of the area. If dens were located, they were to be
classified as being in one of four defined categories. If dens are located, avoidance
buffers will be applied based on the classification of the den.
American Badger
The FEIR found the project would have a substantial adverse effect on the
American badger, including permanent loss of up to 973 acres, and temporary effects on
up to 530 acres, of potential habitat. The project would also disrupt normal behaviors,
potentially cause injury and/or mortality of the American badger.
The FEIR presented Mitigation Measure BIO-TERR-1q, which included a
preconstruction survey by a biologist no more than 30 days before ground disturbance.
The biologist will conduct den searches with transects of between 30–100 feet, ensuring

21.
100 percent visual coverage of the area. If unoccupied dens are located in the work area,
the biologist would either receive permission from the Department of Fish and Wildlife to
temporarily block the burrow entrance to prevent badger usage during construction or, if
necessary, would collapse the den by hand. If occupied dens are located in the work area,
the biologist would consult with the Department of Fish and Wildlife regarding the best
practice to encourage the badger to move to alternate dens outside work areas. This
Mitigation Measure, along with others, was determined to reduce the impacts of the
American badger to less than significant.
Riparian Habitat
The FEIR concluded the project’s construction and operation would result in the
permanent removal of over 16 acres of riparian woodland and 19 acres of riparian
wetlands.
The EIR presented Mitigation Measure BIO-TERR-2, as follows,

“Riparian habitat shall be created or acquired and permanently
protected to compensate for project effects to ensure no net loss of riparian
habitat functions and values. Land that could be acquired could include
acres upstream of the reservoir or elsewhere that satisfied appropriate
compensation ratios. Compensation ratios shall be based on site-specific
information and determined through coordination with state and federal
agencies [(California Department of Fish and Wildlife, United States Fish
and Wildlife Service, United States Army Corp of Engineers, State Water
Resources Control Board]). The compensation shall be at a minimum 1:1
ratio (1 acre restored or created for every 1 acre filled) and may be a
combination of offsite restoration/creation and mitigation credits. A
restoration and monitoring plan shall be developed and implemented
concurrently with project construction. The plan shall describe how
riparian habitat will be created and monitored, including funding
mechanisms and appropriate long-term management measures, and agency
reporting requirements.”
The FEIR concluded the mitigation measure would reduce impacts on riparian
habitat to less than significant.

22.
Wetlands
The FEIR stated that the proposed project would result in the permanent loss of
over 32 acres of riparian wetlands, seeps, seasonal wetlands, and ponds, which
constituted a significant environmental impact.
Like the mitigation measure for riparian habitat, Mitigation Measure BIO-TERR-3
for wetlands provided for creation or acquisition of suitable wetland habitat to
compensate for project effects. The minimum compensation ratio was set at 1:1. The
compensation could be a combination of offsite restoration/creation and mitigation
credits. A restoration and monitoring plan would be developed and implemented, which
would describe how wetland habitat will be created and monitored.
Blue Oak Woodlands
The FEIR observed that the project would result in a loss of 39 acres of blue oak
woodlands. The FEIR presented Mitigation Measure BIO-TERR-5 whereby one acre of
oak woodland would be preserved, managed and monitored for every acre of oak
woodland loss as a result of project implementation. A management plan would be
developed for the newly preserved oak woodland.
C. Analysis
Sierra Club contends these portions of the FEIR impermissibly defer formulation
of mitigation for the Project’s impacts on foothill yellow-legged frogs, San Joaquin kit
foxes, etc. It criticizes the FEIR for relying on “unknown provisions of undeveloped
plans” as mitigation measures. However, the mitigation measures are the purchasing of
mitigation bank credits, substitute property, conservation easements, etc. It is the creation
of management plans for the purchased properties, easements, etc. that is deferred to a
later date—not plans governing the actual construction/implementation of the project.
It would be infeasible to do otherwise. Whether off-site mitigation is even needed
is dependent on pre-construction surveys that have not yet occurred. And even
presuming such mitigation will be required, the size of offsetting land/easements to

23.
satisfy the stated compensation ratios is presently unknown. Consequently, it is unknown
whether and/or how much land/credits will need to be purchased. This also means that
the location of the offsetting land/easements is likewise unknown. As a result, a
description of the mitigation/management plans for said properties is not currently
feasible. For example, how could the FEIR be expected to set forth the details of a plan
to manage offsite land for the benefit of foothill yellow-legged frogs when the location,
size, terrain, etc. of that land is unknown. Such a plan would obviously have at least
some site-specific aspects and therefore cannot be set forth unless and until a site is
selected.
The fact is, the cited mitigation measures commit the project proponents to
acquisition of credits/land/easements in specific ratios to resources impacted by the
project as determined by pre-construction surveys. This is definite enough to constitute a
valid mitigation measure. This conclusion is not altered by the fact that the specifics of
how the offsetting land/easements themselves will be managed are not described and are
instead deferred for future formulation. The aspects of the mitigation measures that are
presently formulated are sufficiently definite.
We find Rialto Citizens for Responsible Growth v. City of Rialto (2012) 208
Cal.App.4th 899 (Rialto) to be instructive. In that case, the EIR provided that a
mammalogist would conduct a habitat assessment in the future and, if certain endangered
kangaroo rats were found, the project proponent would consult with United States Fish
and Wildlife and/or the City of Rialto “‘to determine the appropriate off-site mitigation,
which requires that mitigation/compensation for the loss of the kangaroo rats be approved
through Section 10(a) consultation pursuant to the [federal Endangered Species Act of
1973 (16 U.S.C. § 1531 et seq.)], as well as specific measures, including, but not limited
to, avoidance, minimization and purchase of suitable off-site habitat, as well as
monitoring and funding for the maintenance of the site.’” (Id. at p. 943, italics added.)

24.
The court concluded the mitigation measure was “sufficiently definite to ensure that
potential impacts to the … kangaroo rats will be mitigated.” (Id at p. 946.)
Rialto is closer to the present case than Raptor, relied on by Sierra Club. In that
case, the EIR deferred formulation of plans for managing the project itself in a way to
avoid/mitigate impacts in the first instance. (Raptor, supra, 149 Cal.App.4th. at pp. 668–
670.) The Raptor court held that such plans were improperly deferred. (Id. at p. 671.)
Here, the mitigation measure is the purchase of off-site credits/land, and it is the
formulation of management plans for those yet-to-be-acquired, off-site properties that is
deferred, not plans to manage the construction/project itself. Because there are clear
standards for the mitigating purchases (e.g., defined ratios, requirement of “full”
mitigation, etc.), the plans for managing the purchased land/easement themselves are
“specific details” that could be deferred. (See Cal. Code Regs., tit. 14, § 15126.4,
subd. (a)(1)(B).)
Sierra Club next contends the FEIR fails to prove that these mitigation measures
are achievable, since there is not an endless supply of mitigation bank credits or special-
status wildlife habitat for sale. But the fact that a mitigation measure involves finite
resources—and nearly all of them do—does not mean the FEIR must affirmatively prove
those resources exist. We are aware of no such requirement in CEQA, and it would be
surprising to have such a requirement. For example, if a measure mitigating traffic
impacts called for construction of an interchange, the EIR is not required to prove or
explain that there is enough asphalt in the world to build it. Here, the mitigation
measures involve the purchase of mitigation bank credits and/or off-site land
purchases/easements. These are common mitigation measures and, absent a comment
raising the issue in a manner requiring a response, we will not presume an inadequate
supply so as to require explanation in the FEIR.

25.
Using the mitigation of the foothill yellow-legged frog as an example, Sierra Club
contends it is unclear how much off-site mitigation will be necessitated if the species is
located in pre-construction surveys:

“Since the EIR projects potentially significant impacts to 31 acres of
aquatic habitat and 16 acres of riparian habitat [citation], will that amount
of compensatory mitigation be required if frogs are located in pre-
construction protocol-level surveys? Or some other amount? The EIR is
silent on this issue, a deficiency that infects multiple mitigation measures.”
But the EIR is not silent on the issue. Rather, it provides that if frogs are found, the
habitat permanently impacted by the proposed project shall be fully mitigated through
purchases of property/conservation easements. The word “fully” makes clear that off-site
mitigation would be at least equivalent to 31 acres of aquatic habitat and 16 acres of
riparian habitat.
VI. The FEIR’s Statement of Purpose Was Sufficient
Sierra Club argues the FEIR used an impermissibly narrow statement of purpose.
Specifically, the FEIR “fails to identify a reasonable basis for its imposition of a[n]
80,000 [acre feet storage] requirement.”
A. Law
An EIR must contain a “statement of the objectives sought by the proposed
project.” (Cal. Code Regs., tit. 14, § 15124, subd. (b).) The statement should include
“the underlying purpose of the project.” (Ibid.) A clearly written statement helps the lead
agency develop a reasonable range of alternatives to evaluate in the EIR. (Ibid.)
However, “CEQA does not restrict an agency’s discretion to identify and pursue a
particular project designed to meet a particular set of objectives. CEQA simply requires
the agency to thereafter prepare and certify a legally adequate EIR .…” (California Oak
Foundation v. Regents of University of California (2010) 188 Cal.App.4th 227, 276–277.)
By definition, it is the project proponent who determines what project they are proposing.
Consequently, project objectives can be quite narrow. For example, a proponent who

26.
wants to build a waterfront resort can insist its proposed project be waterfront, and not
inland. (See In re Bay-Delta etc., supra, 43 Cal.4th at p. 1166.) The issue arises when
the objective is “artificially” narrow. (Ibid.)
B. Analysis
As noted above, CEQA is not concerned with narrow project objectives unless
they are artificially narrow. In other words, when the purported project objectives are
insincere attempts to avoid true consideration of a reasonable range of alternatives rather
than accurately express the true underlying intent motivating the project proponents.
There is no such indication here.
The FEIR’s stated project objectives were the following:

1. Increase south of Delta water storage capacity in California’s Central
Valley by 80,000 acre feet;

2. Provide local water storage in proximity to the DMC and to users;

3. Improve water supply reliability;

4. Increase peak irrigation season water supplies;

5. Improve the ability to manage regional surface water and groundwater
resources;

6. Improve regional self-reliance and economic benefit from agricultural
production, jobs, and industry multipliers;

7. Develop a cost-effective project that provides water at an affordable cost
to landowners; and

8. Avoid displacement of homes and businesses.
Sierra Club contends the FEIR fails to identify a reasonable basis for a project
with 80,000 acre feet of storage capacity because the Project Partners only need 70,000
acre feet. But the FEIR did provide a reasonable basis when it stated,

“In addition to the up to 50,000 [acre feet] storage need identified by
the Exchange Contractors and the 20,000 [acre feet] demand for storage
identified by DPWD, the Project Partners are working to obtain federal

27.
funding and accommodate federal benefits that would be commensurate
with the funding. The Bureau of Reclamation would have an opportunity to
participate in the project for South of Delta benefits providing new water
supply and up to 20,000 [acre feet of storage] for wildlife refuges.”
Sierra Club has failed to show the stated project objective of providing 80,000 acre
feet of storage capacity south of the Delta was artificially narrow. Consequently, we see
no error in its usage to eliminate alternatives from detailed consideration. Moreover, we
note that the FEIR did consider an alternative that was smaller in terms of capacity: a
reservoir with half of the storage capacity (i.e., 40,000 acre feet).
Sierra Club further contends that the objective to create 80,000 acre feet of storage
does not explain the choice of constructing a reservoir instead of using smaller and/or
groundwater recharge projects.8 But creating 80,000 acre feet of storage was only one of
eight objectives. Among the other objectives were improving the reliability of the water
supply, increasing water supply during peak irrigation season, and improved management
of regional water resources. And as the FEIR explained, “Groundwater storage facilities
cannot bank large volumes of water in a short period of time and similarly groundwater
extraction cannot occur rapidly enough to meet seasonal demands in the same way that is
possible with a surface storage facility.” In other words, a reservoir satisfies other project
objectives in a way that groundwater recharge projects would not.9
Sierra Club argues that the fact the project met all eight objectives indicates that,
to some extent, the project’s approval was a foregone conclusion based on artificially
narrow project objectives. But the fact that a project meets all of the stated objectives is

8 We do note that groundwater projects are also being pursued, including recharge and
recovery projects at Orestimba Creek and Los Banos Creek.
9 Sierra Club observes that the FEIR does not state how often it is necessary to store and
release water in a rapid manner. But we see no reason to require that.
Nor do we find relevant Sierra Club’s discussion of the downsides to reservoirs. Every
project has drawbacks and benefits. CEQA’s concern is adequate environmental analysis and
disclosure.

28.
only an issue if those objectives are artificially narrow. If, instead, the objectives are
properly stated, then it is quite reasonable and even expected that a project would meet all
of the objectives formulated by its own proponents.
VII. The FEIR Considered an Adequate Range of Alternatives
Siera Club also challenges the FEIR’s discussion of alternatives.
A. Law
“An EIR shall describe a range of reasonable alternatives to the project, or to the
location of the project, which would feasibly attain most of the basic objectives of the
project but would avoid or substantially lessen any of the significant effects of the
project, and evaluate the comparative merits of the alternatives. An EIR need not
consider every conceivable alternative to a project. Rather it must consider a reasonable
range of potentially feasible alternatives that will foster informed decisionmaking and
public participation. An EIR is not required to consider alternatives which are infeasible.
The lead agency is responsible for selecting a range of project alternatives for
examination and must publicly disclose its reasoning for selecting those alternatives.
There is no ironclad rule governing the nature or scope of the alternatives to be discussed
other than the rule of reason.” (Cal. Code Regs., tit. 14, § 15126.6, subd. (a).)
“Among the factors that may be used to eliminate alternatives from detailed
consideration in an EIR are: (i) failure to meet most of the basic project objectives,
(ii) infeasibility, or (iii) inability to avoid significant environmental impacts.” (Cal. Code
Regs., tit. 14, § 15126.6, subd. (c).) “[T]he EIR need examine in detail only the
[alternatives] that the lead agency determines could feasibly attain most of the basic
objectives of the project.” (Id., subd. (f).)
B. Background
In table 4-6 of the FEIR, 11 potential alternative sites are ranked on four criteria:
capacity to surface area, capacity to dam embankment volume, capacity to dam height

29.
and distance to the DMC. The sites were given a cumulative score based on how they did
on all four factors.
The proposed project site, Del Puerto Canyon received the best cumulative score.
The site with the second-best cumulative score, Lone Tree Creek, was rejected for further
consideration because it would have a surface area of 2,900 acres (i.e., more than three
times larger than the project footprint). The site with the third-best cumulative score,
Little Salado Creek/Crow Creek, was rejected because its dam would be 4.5 miles from
the DMC, resulting in a substantially longer conveyance facility, with commensurate
increases in energy usage and greenhouse emissions. In addition, multiple commenters
during the scoping period urged consideration of the Ingram Canyon site, which had the
fourth-best cumulative score. As a result, the Ingram Canyon site was selected as the
alternative site that would be considered in detail.
C. Analysis
Sierra Club cites Habitat & Watershed Caretakers v. City of Santa Cruz (2013)
213 Cal.App.4th 1277 (Habitat) for the proposition that an EIR fails to analyze a
reasonable range of alternatives if it “fail[s] to consider any alternatives that would avoid
some of the significant environmental impacts of the project.”10 (Habitat, supra, at
p. 1303.) Sierra Club contends the FEIR fails “for this exact reason” because the FEIR
concludes the alternatives it considered were environmentally inferior to the project. But
there is an incongruity between the legal principle Sierra Club cites and the alleged
deficiency in the FEIR. An alternative that avoids some of the significant impacts of the
project is not necessarily the same as an alternative that is, on balance, environmentally
superior to the project. That is, an alternative might avoid some of the significant impacts
of the project yet still be, on the whole, environmentally inferior to the project. And

10 This quotation is actually the court describing one of the parties’ contentions, not
describing its own holding. (See Habitat, supra, 213 Cal.App.4th at p. 1303.)

30.
CEQA does not require that an EIR consider alternatives that are wholistically
environmentally superior to the project, but instead requires consideration of alternatives
that “avoid or substantially lessen one or more of the significant effects.” (Cal. Code
Regs., tit. 14, § 15126.6, subd. (c), italics added; see id., subd. (a) [“would avoid or
substantially lessen any of the significant effects of the project”], italics added.) The
FEIR did that here. For example, the Ingram Canyon alternative would substantially
lessen the significant environmental impacts caused by the project’s
relocation/construction of new or expanded water, wastewater treatment or stormwater
drainage, electric power, natural gas, or telecommunications facilities. While the EIR
ultimately concluded the Ingram Canyon alternative was inferior to the project on the
whole, that does not change the fact that the alternative would have “substantially
lessened” one or more of the significant effects of the project.
VIII. The FEIR’s Discussion of Alternatives Was Sufficient
Finally, Sierra Club argues the FEIR fails to provide sufficient information
regarding the alternatives it did consider. They point to the alternative reservoir sites of
Lone Tree Creek and Little Salado Creek/Crow Creek.
A. Law
The EIR’s analysis of alternatives must “include sufficient information about each
alternative to allow meaningful evaluation, analysis, and comparison with the proposed
project.” (Cal. Code Regs., tit. 14, § 15126.6, subd. (d).) “[T]he analysis must be
specific enough to permit informed decision making and public participation.” (Laurel
Heights, supra, 47 Cal.3d at p. 406.) “The need for thorough discussion and analysis is
not to be construed unreasonably, however, to serve as an easy way of defeating projects.
‘Absolute perfection is not required; what is required is the production of information
sufficient to permit a reasonable choice of alternatives so far as environmental aspects are
concerned.… [¶] When the alternatives have been set forth in this manner, an EIR does
not become vulnerable because it fails to consider in detail each and every conceivable

31.
variation of the alternatives stated.’ [Citations.] As with the range of alternatives that
must be discussed, the level of analysis is subject to a rule of reason.” (Id at pp. 406–
407.)
“If an alternative would cause one or more significant effects in addition to those
that would be caused by the project as proposed, the significant effects of the alternative
shall be discussed, but in less detail than the significant effects of the project as
proposed.” (Cal. Code Regs., tit. 14, § 15126.6, subd. (d), italics added.)
B. Analysis
Sierra Club faults the FEIR for not going into more detail in its analysis of the
Lone Tree Creek and Little Salado Creek/Crow Creek site alternatives. But as long as an
EIR considers in sufficient detail a reasonable range of alternatives, it may eliminate
other alternatives from detailed consideration. (Cal. Code Regs., tit. 14, § 15126.6,
subd. (c).) Here, the two alternative sites were eliminated from detailed consideration, so
it is not surprising nor improper for the analysis to be truncated. The FEIR quite
reasonably assumed that alternatives with triple the footprint or substantially longer
conveyance facilities were not deserving of further detailed consideration when another
alternative site, Ingram Canyon, was being analyzed in further detail.
Sierra Club points to the FEIR’s statement that the Ingram Canyon alternative
would have greater impacts on air quality, and argues the “basis for this claim is far from
clear.” Not so, the basis is clear:

“A dam at Ingram Canyon would entail construction of a slightly
larger embankment. Information from preliminary screening reports
estimated that the Ingram Canyon dam would have a volume of 7.2 million
cubic yards (CY) as compared to an initial estimate of 6.2 million CY for
the proposed Del Puerto Canyon dam (note that this number will be refined
as design progresses). The Ingram Canyon conveyance facility would also
be substantially longer than the conveyance facility for the Del Puerto
Canyon site (2.2 miles as compared to 0.9 miles). Because of the extent of
construction required, the Ingram Canyon site would not reduce emissions
of criteria pollutants during construction. As noted on page 4-13 of the

32.
Draft EIR, ‘This alternative would generate significant NOx emissions, and
it is uncertain whether emissions would be fully mitigable.’” (Italics
added.)
Additionally, the FEIR explained that the Ingram Canyon site would require
almost 95 gigawatt hours per year compared to the project’s over 40 gigawatt hours per
year, due to increased conveyance facility length and pumping to a higher elevation.
IX. A Challenge to the Sufficiency of the EIR’s Discussion of an Alternative’s
NOx Emissions is Not Cognizable
Finally, Sierra Club contends there is insufficient explanation for how the EIR can
conclude mitigation measures will result in the project not creating significant NOx
emissions, while being uncertain whether the emissions of the Ingram Canyon alternative
are fully mitigatable. Project Partners contend this assertion is not cognizable because
Sierra Club failed to exhaust its administrative remedies.
A. Law
“‘CEQA prohibits a petitioner or appellant from alleging noncompliance with the
requirements of CEQA unless the alleged grounds for noncompliance were presented to
the public agency either orally or in writing by any person during the public comment
period or during the hearing on project approval. [Citations.] When a ground of
noncompliance with CEQA was not raised during the comment period or during the
public hearing on project approval, the right to raise the issue in a subsequent legal action
is waived. The petitioner bears the burden of demonstrating that the issues raised in the
judicial proceeding were first raised at the administrative level. [Citation.] “[T]he
objections must be sufficiently specific so that the agency has the opportunity to evaluate
and respond to them.” [Citation.] This requirement is known as the exhaustion doctrine.
[Citation.] The rationale behind this rule is that the public agency should have the
opportunity to receive and respond to articulated factual issues and legal theories before
its actions are subjected to judicial review.’” (Planning & Conservation League v.

33.
Castaic Lake Water Agency (2009) 180 Cal.App.4th 210, 250 (Castaic Lake Water
Agency).)
B. Analysis
Project Partners have contended that Sierra Club failed to exhaust its
administrative remedies on this issue. Sierra Club has not pointed us to anywhere in the
record where this issue was raised. Consequently, Sierra Club failed to carry their
“‘burden of demonstrating that the issue[] raised in th[is] judicial proceeding w[as] first
raised at the administrative level.’” (Castaic Lake Water Agency, supra, 10 Cal.App.4th
at p. 250.)
X. The FEIR Adequately Addressed the Planned Relocation of Del Puerto
Canyon Road
Project Partners, as cross-appellants, contend the court erred in concluding the
FEIR did not adequately address the planned relocation of Del Puerto Canyon Road.
Sierra Club responds that the Project Partners improperly segments the project by
excluding the future relocation of Del Puerto Canyon Road.
A. Law
“Improper piecemealing occurs ‘when the purpose of the reviewed project is to be
the first step toward future development’ or ‘when the reviewed project legally compels
or practically presumes completion of another action.’ [Citation.] By contrast, an EIR
need not analyze ‘specific future action that is merely contemplated or a gleam in a
planner’s eye.’” (East Sacramento Partnerships 5 Cal.App.5th at p. 293.)
B. Background
The proposed reservoir will inundate a portion of Del Canyon Road, requiring that
portion be relocated. While the FEIR described the proposed alignment of the relocated
road, it noted that “[t]he roadway alignment has been developed at a conceptual level and
is subject to refinement during design. Any alignment revision would be evaluated to
determine if supplemental environmental documentation is required.” The proposed new

34.
alignment would essentially follow the shoreline of the new reservoir, including a large
number of horizontal curves with relatively small radii.
The FEIR identified Stanislaus County as the agency responsible for approving the
proposed relocation of Del Puerto Canyon Road. The FEIR proceeded to evaluate the
potential environmental impacts of the road relocation.
A management consultant submitted a comment on the draft EIR on behalf of the
Stanislaus County Environmental Review Committee on January 27, 2020. The
comment stated, in part,

“As previously communicated through initial meetings, including the
September 16, 2019 meeting between Stanislaus County Public Works and
Project Partners, and ongoing discussions with the Project Partners, the
alignment shown on page 3.13-2 is not an alignment Stanislaus County
Department of Public Works (DPW) will support as the maintaining agency
for public highways. The Department of Public Works looks forward to
finalizing a new alignment with the Project Partners.”
The FEIR responded to the comment acknowledging the county did not
“support[]” the roadway alignment depicted in the draft EIR. The FEIR further
responded:

“The roadway alignment evaluated in the EIR would adequately replace the
existing road and the Draft EIR has fully evaluated the impacts of the
roadway alignment described in the Draft EIR; however, the Project
Partners have not foreclosed consideration of other options. [¶] The
Project Partners will continue working with County staff to develop an
acceptable alignment and understand that further environmental review
would be needed for a revised roadway alignment.”
The trial court ruled the FEIR did not adequately address the planned relocation of
Del Puerto Canyon Road because the roadway location was “unknown.”
C. Analysis
Sierra Club reads this portion of the FEIR as “acknowledg[ing] that the road
relocation identified and discussed in the EIR is not the location and alignment where the
road will be located.” Not so. After acknowledging the lack of support from the county,

35.
the EIR continued on to insist that the current alignment “would adequately replace the
existing road.” Even the FEIR saying the Project Partners had “not foreclosed
consideration of other options” and that environmental review of any such changes would
be needed, indicates that it is a possibility that different options could be pursued in the
future. In this way, the FEIR again signaled that the current alignment was the status quo.
Reading the FEIR this way, there is no piecemealing issue. The project proposed
relocation of a road and analyzed the relocation of the road. In other words, the analysis
of the proposed relocation was not deferred or piecemealed.11
Sierra Club insists the county “rejected” the proposed alignment. But a
correspondence from a county committee saying another county department will not
support the alignment is not the same as the county rejecting the proposed alignment. A
county acts on the alignments of its roads through its board of supervisors. (Sts. & Hy.
Code, § 940.) Anything short of that, including lack of support from a county
department, is not an actual rejection by the approving agency. Of course, opposition
from a county’s public works department does not bode well for the Project Partners,
because it seems as a practical matter that many supervisors vote in accordance with their
staff recommendations on these sorts of issues.12 But the unlikelihood of a proposed
project receiving ultimate approval does not erase an EIR’s environmental analysis of it.
The fact remains that the environmental analysis of the road realignment was presented in
the FEIR and was not segmented or deferred to a later date. The trial court erred in
concluding otherwise.

11 Given these case-specific circumstances, we find the cases cited by the parties unhelpful.
12 If, due to rejection by the board of supervisors or for some other reason, the Project
Partners ultimately seek approval for a different alignment than the one analyzed in the FEIR,
they may very well be required to do a subsequent or supplemental EIR to study the new
alignment. (See Pub. Resources Code, § 21166.) The FEIR acknowledges as much.

36.
XI. The Court Abused Its Discretion in Denying Project Partners’ Motion to
Vacate
The Exchange Contractors, as appellants, challenge the court’s denial of their
motion to vacate a ruling concerning cultural resources.
A. Background
The FEIR considered the project’s impacts on cultural resources. The FEIR
observed that “[m]ost of the study area was previously studied in 1993 as part of the Del
Puerto Alternative Reservoir Site project (Bell et al. 1993). During this study,
approximately 640 acres of the current project was subject to an archaeological
pedestrian survey.” We will refer to this as the 1993 Bell Survey. The FEIR concluded
that “[b]ecause this survey was conducted over ten years ago and is not considered
current, an updated survey was warranted for the current investigation.” Accordingly, the
FEIR consultant’s primary environmental subconsultant ICF International (ICF)
conducted pedestrian archaeological surveys in May–July 2019. A total of 10
archaeological sites were located in the area.
ICF also conducted subsurface testing at five of the sites. ICF also conducted
records reviews and contacted Native American groups. Ultimately, 11 prehistoric
archaeological resources were documented.
A survey and evaluation of all the archaeological sites yielded one unique
archaeological resource: site P-50-344. That site was described as follows:

“Site P-50-344 is a prehistoric occupation site consisting of four
bedrock mortars and cupule features, an artifact surface scatter of lithic
debitage (stone chips and flakes from making stone tools), groundstone (a
stone tool for grinding) fragments, and one obsidian biface tool fragment
located along the slope and base of a hill overlooking Del Puerto Creek to
the south. Subsurface testing at the site identified a deposit of lithic
debitage, a bone awl fragment, burned faunal material, freshwater mussel
shell fragments and marine shell beads. The features and artifact deposit at
the site are indicative of habitation along Del Puerto Creek, containing
information important in prehistory, specifically to the prehistoric
inhabitants of the local area. Because the site contains information

37.
important in prehistory (Criterion 4), and retains enough integrity to convey
its significance, it appears eligible for listing in the [National Register of
Historic Places] and [California Register of Historical Resources]. The site
was evaluated in accordance with Section 15064.5 (a)(2)-(3) of CEQA
Guidelines and using criteria outlined in Section 5024.1 of the [Public
Resources Code] and is an Archaeological Resource for the purposes of
CEQA.”
The FEIR ultimately concluded that the project would have significant and
unavoidable impacts because it would destroy the site.
2020 ICF Report
ICF created a report inventorying and evaluating the cultural resources at the Del
Puerto Reservoir Project site, which we will refer to as the 2020 ICF Report.
Section 106 Report
Apart from CEQA, federal law requires that federally licensed or federally funded
undertakings must first consider “the effect of the undertaking on any historic property.”
(54 U.S.C. § 306108.) Because Reclamation might issue federal funding for the project,
the Project Partners underwent what is called the Section 106 cultural resources
consultation process. On February 3, 2020, the Project Partners’ consultant transmitted a
draft cultural report to Reclamation. We will refer to this report as the Section 106
Report. Reclamation provided feedback on the draft in May 2020. ICF sent a final
version of the Section 106 Report to Reclamation in September 2021.
The Section 106 Report and the 2020 ICF Report are substantially similar.
Preparation of Administrative Record
Sierra Club elected to prepare the administrative record in this case pursuant to
Public Resources Code section 21167.6, subdivision (b)(2). The Project Partners
provided documents to Sierra Club’s counsel, including “an abbreviated confidential
form” of the 1993 Bell Survey. Sierra Club’s counsel requested the full 1993 Bell
Survey, to which Project Partners’ counsel responded the document was likely
confidential. Project Partners’ counsel later added that neither the Project Partners nor its

38.
consultant possessed the 1993 Bell Survey. Sierra Club’s counsel indicated he would
likely seek an order from the court compelling disclosure of the document. In order to
avoid time-consuming law and motion proceedings, the Project Partners agreed to acquire
and provide Sierra Club’s counsel with the 1993 Bell Survey. However, the Project
Partners would not agree to certifying the administrative record with the 1993 Bell
Survey included unless the 2020 ICF Report was also included, because the FEIR
expressly relied on the latter and not the former in its cultural resources analysis.
Pursuant to a stipulation of the parties, the court ordered that the 1993 Bell Survey
and the 2020 ICF Report be kept confidential.
In a motion dated December 18, 2021, Sierra Club sought discovery of the files of
the FEIR consultant’s subcontractors and emails sent by Project Partners’ consultants (to
recipients other than employees of DPWD). On January 21, 2022, the court denied Sierra
Club’s request. The court determined that the files of the subcontractors to the FEIR
consultant were not part of the “‘public agency’s files on the project.’”
On February 14, 2022, the Project Partners certified the administrative record.
Both the 1993 Bell Survey and the 2020 ICF Report were included in the confidential
portion of the administrative record.
In early 2022, Sierra Club’s counsel informed Project Partners’ counsel that he was
considering filing a motion to strike the 2020 ICF Report from the administrative record.
However, Sierra Club’s counsel said he would not file the motion if Project Partners
stipulated that, at the time DPWD approved the project, neither the 1993 Bell Survey nor
the 2020 ICF Report were in the possession of DPWD or its FEIR consultant. In fact, the
2020 ICF Report had been in the possession of both DPWD and its FEIR consultant
before project approval. However, because Project Partners’ counsel misunderstood an
email he had previously received, he believed the proposed stipulation was correct and
signed it. According to Project Partners, the stipulation was not initially filed with the
court.

39.
The parties began filing merits briefing on the CEQA issues in April 2022. In a
sealed brief, Sierra Club argued the FEIR’s discussion of cultural resources was
insufficient. Project Partners filed a responsive brief, contending that Sierra Club ignored
the 2020 ICF Report and its contents. In a reply brief, Sierra Club argued that the 2020
ICF Report was not properly part of the administrative record because it was only in the
possession of ICF, and not the Project Partners or their EIR consultant. Sierra Club
contended that “[i]f the files were not before the agency, as they were not, then they
cannot constitute substantial evidence supporting the agency’s decision.” As explained
above, this assertion is actually incorrect; the 2020 ICF Report was in the possession of
the Project Partners and their FEIR consultant before project approval. However, through
no apparent fault of his own, Sierra Club’s counsel believed otherwise due to Project
Partners’ counsel’s mistaken assertion. The mistake still had not come to light when the
court ruled on the merits of the cultural resources issues on November 29, 2022.
In its ruling, the court observed that Sierra Club “does not contest that the [2020
ICF Report] is adequate,” but, instead, contended the report could not be relied upon.
The court rejected Sierra Club’s contention that the 2020 ICF Report was not part of the
administrative record. However, the court found it “critical[]” that the 2020 ICF Report
was not relied upon by the Project Partners, because it was provided “after the agency’s
decision.” Consequently, it ruled in favor of Sierra Club on the merits of the cultural
resources issue.
Project Partners’ counsel considered filing a motion to vacate this ruling and
accordingly contacted ICF, thinking they could explain why the 2020 ICF Report was not
provided to the Project Partners or their FEIR consultant before project approval. ICF
staffers responded that, in their recollection, they had provided the 2020 ICF Report to

40.
the FEIR consultant in early-mid 2020,13 which in turn provided the report to the Project
Partners days later. Through subsequent conversations, Project Partners’ counsel came to
realize his prior understanding of an October 21, 2021, email from the FEIR consultant
was mistaken. In that email, the consultant said he had “access to both reports,” which
Project Partners’ counsel had originally understood to mean the draft and final versions of
the Section 106 Report. But Project Partners’ counsel now understood that “both reports”
referred to the Section 106 Report and the 2020 ICF Report.
Project Partners filed a motion to vacate and amend the judgment pursuant to
Code of Civil Procedure sections 663 and 473, subdivision (b).14 The motion explained
the chronology of events through its memorandum of points and authorities and a
declaration from Project Partners’ counsel. Counsel explained his mistake and
apologized to the court. The motion urged the court to amend its prior ruling since it had
been based on the mistaken belief that Project Partners and their FEIR consultant were
not in possession of the 2020 ICF Report before project approval. Sierra Club opposed
the motion.
The court denied the motion. The ruling stated that the stipulation regarding the
2020 ICF Report had been provided in a dispute over whether Sierra Club’s prior counsel
could file an amicus brief. The court held that a party may not offer a fact for one
purpose to its advantage and then later ask the court to disclaim that fact. The ruling also
stated the court was “obligated” to accept stipulations as true (unless contrary to law or
policy).

13 Recall that the FEIR was made available to the public and commenting agencies on
October 9, 2020.
14 All further undesignated statutory references are to the Code of Civil Procedure.

41.
B. Law
Section 663 provides for a motion to set aside a judgment or decree when there
was an “[i]ncorrect or erroneous legal basis for the decision, not consistent with or not
supported by the facts .…” (Ibid.) Section 473, subdivision (b), permits a court to
“relieve a party or his or her legal representative from a judgment, dismissal, order, or
other proceeding taken against him or her through his or her mistake, inadvertence,
surprise, or excusable neglect.” (Ibid.)
We review the trial court’s rulings under these statutes for abuse of discretion.
(Conservatorship of Buchenau (2011) 196 Cal.App.4th 1031, 1038; e.g., National
Secretarial Service, Inc. v. Froehlich (1989) 210 Cal.App.3d 510, 524 [motion under
§ 663].) “‘Abuse of discretion is a deferential standard of review.’” (Cadiz Land Co.,
Inc. v. Rail Cycle (2000) 83 Cal.App.4th 74, 117.) “Although this standard is deferential,
a court abuses its discretion ‘“where no reasonable basis for the action is shown.”’” (Bui
v. Nguyen (2014) 230 Cal.App.4th 1357, 1367.)
“‘The discretion of a trial judge is not a whimsical, uncontrolled power, but a legal
discretion, which is subject to the limitations of legal principles governing the subject of
its action, and to reversal on appeal where no reasonable basis for the action is shown.’”
(Sargon Enterprises, Inc. v. University of Southern California (2012) 55 Cal.4th 747,
773.) “To determine if a court abused its discretion, we must thus consider ‘the legal
principles and policies that should have guided the court’s actions.’” (Ibid.)
“‘[T]he provisions of section 473 … are to be liberally construed and sound policy
favors the determination of actions on their merits.’” (Zamora v. Clayborn Contracting
Group, Inc. (2002) 28 Cal.4th 249, 256.)
C. Analysis
The basis provided for the court’s ruling is that the stipulation concerning the 2020
ICF Report was provided to the court pursuant to a dispute over whether Sierra Club’s
prior counsel could file an amicus brief. The court reasoned that it would be unfair to

42.
allow a party to offer a fact “for one purpose” and then disclaim the fact for another
purpose. However, the court’s factual premise was plainly incorrect. The stipulation was
not entered into pursuant to a dispute over amicus briefing. Instead, the stipulation was
offered to avert a motion to strike the 2020 ICF Report from the administrative record. In
other words, it was offered pursuant to the same issue the court presently faced.
The ruling also stated the court was “obligated” to accept stipulations as true
(unless contrary to law or policy). But the entire purpose of section 473, subdivision (b),
is to provide relief from what the law would otherwise require or permit in a given
situation. Observing that, without an excusable mistake, the law would provide for a
particular outcome is no explanation for why relief should not be granted where an
excusable mistake is present.
Consider a classic section 473, subdivision (b), scenario: an attorney requests
relief from a default entered after he or she failed to file a timely answer to a complaint.
It would not justify denial of relief to say that the law requires entry of default after the
time to answer expires. The question is not the propriety of the court’s initial action in
response to counsel’s mistake, but whether the attorney should be relieved from the
court’s admittedly proper action due to the attorney’s excusable neglect. In sum, the fact
that courts are obligated to accept stipulations as true does not explain why the court
would deny a section 473, subdivision (b), motion to obtain relief therefrom.
Sierra Club correctly observes that section 663, paragraph 1, only applies where
the decision has an “[i]ncorrect or erroneous legal basis,” not an incorrect factual basis.
(Ibid., italics added.) But section 473, subdivision (b), is not so limited. Under that
provision, “‘mistake’ justifying relief may be either a mistake of fact or a mistake of law.
‘A mistake of fact exists when a person understands the facts to be other than they
are; .…’” (H.D. Arnaiz, Ltd. v. County of San Joaquin (2002) 96 Cal.App.4th 1357,
1368.)

43.
In light of the insufficient explanations provided by the trial court, we consider
whether its approach was otherwise justified. We conclude it was not. Despite some of
the convoluted background, the simple fact is the 2020 ICF report was in the possession
of the Project Partners and their FEIR consultant prior to project approval.15 And, as the
trial court observed, Sierra Club does not effectively contest the sufficiency of the 2020
ICF report. We will not turn a blind eye to substantial evidence in the record merely
because counsel misdescribed it earlier in the case and sought to rectify the good-faith
error pursuant to a statute designed exactly for that purpose. We also question what
purpose it would serve to invalidate the FEIR on such grounds when everyone knows the
substantial evidence exists. What could such a writ effectively require of the Project
Partners that would not be a waste of time and resources?
For these reasons,16 we will reverse the trial court’s denial of Project Partners’
motion to vacate.

15 Sierra Club contends the 2020 ICF Report was not part of the administrative record
pursuant to the court’s January 21, 2022, discovery order regarding the internal files of
subcontractors. But the administrative record was certified on February 14, 2022, after the
January 21, 2022, order with the 2020 ICF Report included. As for the incorrect stipulation, we
conclude the court should have granted relief from it due to excusable mistake as explained
herein.
Sierra Club also posits that the Exchange Contractors failed to argue that the 2020 ICF
Report was a mandatory part of the record pursuant to Public Resources Code section 21167.6 as
part of their motion to vacate. But they did not need to make that argument because the 2020
ICF Report was already part of the administrative record.
Sierra Club cites the court’s November 29, 2022, ruling and says this court is “bound by
the facts” as the trial court found them in that order. But that order expressly states, “Respondent
contends that the ICF report provides substantial evidence supporting the EIR’s conclusions.
Petitioner’s claim that this should not be part of the administrative record fails .…” (Italics
added.)
16 Also for these reasons, we do not address the other grounds Project Partners advance in
defense of their motion to vacate.

44.
DISPOSITION
The court’s order denying the motion to vacate filed by DPWD and San Joaquin
River Exchange Contractors Water Authority is reversed. The court is directed to enter a
new and different order granting the motion consistent with the views expressed in this
opinion.
The judgment is reversed in part and the court is directed to enter a new and
different judgment consistent with this court’s holding that the FEIR was sufficient with
respect to the relocation of Del Puerto Canyon Road and cultural resources; and that the
FEIR was insufficient with respect to impacts on terrestrial species downstream from the
proposed reservoir.
The superior court is directed to issue a peremptory writ of mandate as soon as
practicable after it has filed the modified judgment.
The parties shall bear their own costs on appeal.

MEEHAN, J.
WE CONCUR:

DETJEN, Acting P. J.

FAIN, J.

 Judge of the Fresno Superior Court, assigned by the Chief Justice pursuant to article VI,
section 6 of the California Constitution.

45.