ECLI:EU:T:2010:480•Judgment of the General Court (Eighth Chamber) of 24 November 2010.#European Commission v Irish Electricity Generating Co. Ltd.#Arbitration clause - Contract concluded in the framework of a specific programme for research and technological development, including demonstration, in the field of non-nuclear energy (1994 to 1998) - Non-performance of the contract - Reimbursement of the sums advanced - Late-payment interest - Procedure by default.#Case T-323/09.

Open source

Judgment of the General Court (Eighth Chamber) of 24 November 2010.#European Commission v Irish Electricity Generating Co. Ltd.#Arbitration clause - Contract concluded in the framework of a specific programme for research and technological development, including demonstration, in the field of non-nuclear energy (1994 to 1998) - Non-performance of the contract - Reimbursement of the sums advanced - Late-payment interest - Procedure by default.#Case T-323/09.

ECLI:EU:T:2010:480Eu Chamb 08 TNov 24, 2010

Open source

Full text

Subject of the case
Operative part

Subject of the case

Re:

APPLICATION under an arbitration clause seeking an order that Irish Electricity Generating Co. Ltd repay the sum of EUR 180 664.70 corresponding to part of the advances paid to it by the Commission under contract No WE/178/97/IE/GB, together with late-payment interest.

Operative part

Operative part

The Court:

1. Orders Irish Electricity Generating Co. Ltd to repay to the European Commission the sum of EUR 180 664.70, together with late-payment interest:

– at the rate of 5.56% per annum from 25 August 2003 to the date of the present judgment;

– at the annual rate applied under Irish law, that is to say, currently section 26 of the Debtors (Ireland) Act, 1840, as amended, up to a rate of 5.56% per annum from the date of the present judgment until full clearance of the debt;

2. Orders Irish Electricity Generating Co. Ltd to pay the costs.

Wondering how this text applies to your situation?

Free consultation, no commitment

Describe your situation. Our team will contact you by email about your consultation.

Continue your research in ChatGPT or Claude

Connect Omnilex to search the legal corpus from your AI assistant.