Key legal question
Whether the relocation of the farm road near the Oberfeld property had to be included in the preliminary project of the land consolidation.
Extracted holding
The preliminary project did not originally include the road relocation, but this did not prevent a later, substantively justified slight relocation.
Extracted reasoning
The preliminary project is a planning instrument binding the authorities only as to the spatial measures it contains. Given the lengthy nature of land consolidation proceedings, the authorities must retain the necessary discretion. A minor deviation that is objectively justified falls within that discretion.