Key legal question
Whether reusable scaffold work qualifies for a construction lien under Art. 837(1)(3) CC
Extracted holding
No. Scaffold work only qualifies if the scaffold is specially made for a particular construction or otherwise becomes part of the work; a reusable system scaffold does not meet that requirement.
Extracted reasoning
The Court upheld the sachenrechtliche approach from prior case law. The lien protects work materially connected to the building or destined for such connection. Reusable scaffold work is directed at the scaffold itself, not the land parcel, and therefore lacks the required permanent physical connection.