Key legal question
Whether the appeal against the interim refusal of suspensive effect was admissible under the public procurement exclusion rule and as an appeal against an interim decision.
Extracted holding
The appeal was admissible because the contract value exceeded the threshold and the case raised a legal question of fundamental importance; the appellant also faced irreparable legal harm.
Extracted reasoning
The Court held that the exclusion in Art. 83 lit. f BGG can also apply to interim decisions, but here the statutory conditions for access were met and the refusal of suspensive effect opened the way for a new award, causing irreparable disadvantage.