Key legal question
Whether the plan-approval decision sufficiently examined noise protection and the requested 2 m barriers
Extracted holding
The federal department had not sufficiently examined the noise-protection objections; the matter had to be reconsidered in detailed planning.
Extracted reasoning
The authority itself acknowledged that the objections were not fully investigated and that further technical examination could still change the assessment. The approval was therefore unlawful on these points.