Back to law

Art. 42c

814.201WPOFederal Council OrdinanceJan 1, 1999Original source
  1. In the case of installations which according to the plan require measures to remediate the bed load budget, the cantons shall prepare a study on the nature and extent of the required measures.
  2. Based on the study, the cantonal authority shall in accordance with paragraph 1 order the remediation measures. In the case of hydropower plants, the bed load must wherever possible be made to pass through the installation.
  3. Before it decides on the remediation project in the case of hydropower plants, it shall consult the FOEN. The FOEN shall examine with a view to an application under Article 30 paragraph 1 EnO1whether the criteria of Annex 3 number 2 EnO are met.2
  4. The persons responsible for hydropower plants shall verify the effectiveness of the measures taken in accordance with instructions from the cantonal authority.

Footnotes

  1. SR 730.01

  2. Second sentence amended by Annex 7 No II 2 of the Energy Ordinance of 1 Nov. 2017, in force since 1 Jan. 2018 (AS 2017 6889).

0 commentaries

No commentaries are available for this article yet.