ANTHRACITE STRIP MINING AND CONSERVATION ACT
Act of Jun. 27, 1947, P.L. 1095, No. 472 Cl. 52
AN ACT
Providing for the regulation of mining of anthracite coal by the
open pit or strip mining method and for the conservation and
improvement of lands affected directly or indirectly by such
mining; requiring operators to be licensed, to pay license
fees, to secure permits to engage in strip mining and to file
bonds conditioned for compliance with this act; requiring
backfilling of stripping pits and leveling and planting lands
affected to prevent erosion and the pollution of waters and
to protect public health, safety and welfare; conferring
powers and imposing duties upon the Department of Mines and
Mineral Industries; providing for appeals, and imposing
penalties, and making appropriations. (Title amended Aug. 13,
1963, P.L.781, No.393)
Compiler's Note: Section 16(a)(3) of Act 317 of 1931
provided that Act 472 is repealed insofar as it is
inconsistent with Act 147.
The General Assembly of the Commonwealth of Pennsylvania
hereby enacts as follows:
Section 1. This act is an exercise of the police power to
provide for the improvement and conservation of lands affected
by the mining of anthracite coal by the open pit or strip mining
method; to prevent the combustion of such coal and the pollution
of rivers and streams and improve the use and enjoyment of such
lands; to preserve the value of such lands for taxation to
decrease and prevent soil erosion and aid in the protection of
game and wild life; and generally to provide for the public
safety, health and general welfare.
Section 2. Short Title.--This act shall be known and may be
cited as the "Anthracite Strip Mining and Conservation Act."
(2 amended Aug. 13, 1963, P.L.781, No.393)
Section 3. Definitions.--The following words and phrases,
unless a different meaning is plainly required by the context,
shall have the following meanings:
"Anthracite."--The hard coal mined in the northeasterly part
of the Commonwealth of Pennsylvania commonly known as the
Anthracite Region.
"Strip Mining."--The mining or recovery of coal by removing
the material which overlies the coal bed in its natural or
previously mined condition.
"Stripping pit."--Any trench, cut, hole or pit formed by the
removal of the surface or coal as a result of strip mining.
"Operation."--A stripping pit located within the boundaries
of a mine inspection district as outlined by the Pennsylvania
Department of Mines and Mineral Industries: Provided, That in
all cases where a single stripping pit extends across a mine
inspection district line such pit will not be considered as two
operations because of being located in two mine inspection
districts.
"Operator."--A person, partnership, association or
corporation engaged in strip mining of anthracite coal as a
principal, or who is or becomes the owner of the coal recovered
as the result of such strip mining.
"Spoil banks."--The material of whatever nature removed and
deposited on the surface that the underlying coal may be
recovered.
"Department."--The Department of Mines and Mineral Industries
of the Commonwealth of Pennsylvania.
"Secretary."--The Secretary of Mines and Mineral Industries.
"Abandoned."--An operation where no coal has been produced or
overburden removed for a period of six (6) months, verified by
monthly reports submitted to the department by the operator and
by inspections made by mine inspectors, unless an operator
within thirty (30) days after receipt of notification by the
secretary terming an operation abandoned submits sufficient
evidence to the secretary that the operation is in fact not
abandoned.
"Degree."--When used in this act, shall mean inclination from
the horizontal and in each case shall be subject to a tolerance
of five (5) degrees.
"Landowner."--The person, partnership, association or
corporation, private, municipal or otherwise, in which the legal
title to the land is vested.
"Overburden."--The material or strata overlying a seam or
seams of anthracite coal in its natural state.
"Area of land affected."--The area of land from which the
overburden is removed, except that in stripping pits not more
than one hundred (100) feet in depth the area shall include that
occupied by the spoil piles.
"Deep mining."--Such mining as is presently or has previously
been carried on by means of slope, tunnel, drift or shaft
without the removal of the overburden.
(3 amended Aug. 13, 1963, P.L.781, No.393)
Section 4. (a) It shall be unlawful for any person to
proceed to mine coal, commonly known as anthracite, by the strip
mining method as an operator within this Commonwealth without
first obtaining a license as a strip mining operator from the
Department of Mines and Mineral Industries. Applications for
licensure as strip mining operators shall be made in writing to
the department upon forms prepared and furnished by the
department, and shall contain such information as to the
applicant as the department shall require, and when the
application is made by a corporation, partnership or
association, the names of its officers, directors and principal
owners. The application for licensure shall be accompanied by a
fee of three hundred dollars ($300). It shall be the duty of all
persons licensed as strip mining operators to renew such license
annually, and pay for each such license renewal the sum of three
hundred dollars ($300). The application for renewal of a license
as a strip mining operator shall be made, annually, on or before
January 1 of the next succeeding year.
Penalty.--Any person who proceeds to mine coal, commonly
known as anthracite, by the strip mining method as an operator
without having applied for and received a license as herein
provided, shall be guilty of a misdemeanor, and, upon
conviction, shall be sentenced to pay a fine of not less than
five thousand dollars ($5,000) and not exceeding ten thousand
dollars ($10,000), or undergo imprisonment not exceeding six
months, or both. The fine shall be payable to the Commonwealth.
(b) The department shall not issue any new strip mining
operator's license or renew any existing strip mining operator's
license to any person or operator if it finds, after
investigation, that the applicant for licensure or renewal has
previously failed and continues to fail to comply with any of
the provisions of this act as hereby amended. Where the
applicant is a corporation, partnership or association, the
department shall not issue such license or renewal if, after
investigation, it finds that any principal owner or partner of
such corporation, partnership or association, has previously
failed and continues to fail to comply with any of the
provisions of this act, or if any principal owner or partner is
or has been a principal owner or partner of any other
corporation, partnership or association, which has previously
failed and continues to fail to comply with any of the
provisions of this act as hereby amended.
(4 amended Aug. 13, 1963, P.L.781, No.393)
Section 5. (a) Before any person licensed as a strip mining
operator shall hereafter proceed to mine coal, commonly known as
anthracite, by the strip mining method, he shall apply to the
Department of Mines and Mineral Industries on a form prepared
and furnished by the department for a permit for each separate
operation.
(b) As a part of each application for a permit, the operator
shall furnish, in duplicate, a map or plan of mining and
restoration on a scale of not less than four hundred (400) feet
to the inch, showing the location and extent of the proposed
stripping pit with respect to the land lines of adjoining
properties, together with the location of any public highway,
dwelling house or stream of water. The map of the proposed
stripping pit shall be accompanied by cross-sections at
intervals not to exceed five hundred (500) feet. Such cross-
sections shall include the following information: tidal
elevations of the surface, top of the coal seam, bottom of strip
mine pit; the cross-sections shall provide surface elevations
for a distance of not less than three hundred (300) feet beyond
the outlines of the proposed stripping pit; there shall be
located on the cross-section the outline of the proposed
stripping pit and the approximate area of the placement of the
overburden. The operator shall furnish a detailed proposal
showing the manner, time and distance for backfilling. The
operator shall be required to furnish the department with new
maps and cross-sections at the end of each year of operation.
(c) Any permit issued by the department as required by this
act shall permit the operation of the pit for a period of one
(1) year from the date of issue unless sooner suspended by the
secretary.
(5 amended Aug. 13, 1963, P.L.781, No.393)
Section 5.1. Any mine inspector directed by the department
shall have the right to enter upon and inspect all stripping
operations for the purpose of determining conditions of safety
and for compliance with the provisions of this act and all rules
and regulations promulgated pursuant thereto. Should an operator
fail to comply with the requirements of this act or any rules or
regulations promulgated pursuant thereto, the mine inspector
shall report the matter to the secretary who shall immediately
notify the operator by registered mail of such failure. Unless
the operator complies with the act and such rules and
regulations within thirty (30) days from the receipt of such
notice, the secretary may, after hearing and final
determination, suspend the open pit mining operator's license of
the operator and issue a cease and desist order requiring the
operator to immediately cease open pit mining within this
Commonwealth until such time as it is determined by the
secretary that the operator is in full compliance. A mine
inspector shall have the authority to order the immediate
stopping of any operation that is started by an unlicensed
operator or without the operator thereof having first obtained a
permit as required by this act or in any case where safety
regulations are being violated.
(5.1 added Aug. 13, 1963, P.L.781, No.393)
Section 6. The operator shall file with the Department of
Mines and Mineral Industries a bond for each operation on a form
to be prescribed and furnished by the department payable to the
Commonwealth and conditioned that the operator shall faithfully
perform all the requirements of this act. The bond shall be in
the amount of not less than five hundred dollars ($500) per acre
nor more than one thousand dollars ($1,000) per acre based upon
the number of acres of land in such operation which the operator
estimates will be the area of land affected by strip mining
during one (1) year immediately following the date of the permit
issued by the department. If following an examination of the
maps and cross-sections submitted the secretary deems it
necessary to increase the amount of bond in excess of five
hundred dollars ($500) per acre, he shall stipulate the amount
of bond per acre required: Provided, That no bond shall be for
an amount less than five thousand dollars ($5,000). Liability
under the bond shall be for the duration of strip mining at each
operation and for a period of five years thereafter, unless
released prior thereto, in the manner hereinafter provided by
this act.
Such bond shall be signed by the operator and a corporate
surety licensed to do business in the Commonwealth: Provided,
however, That in lieu of a surety bond the operator may file a
collateral bond secured by cash in the form of a certified or
cashier's check or negotiable bonds of the United States
Government or the Commonwealth of Pennsylvania, the Pennsylvania
Turnpike Commission, the General State Authority, the State
Public School Building Authority, or any municipality within the
Commonwealth. The cash deposited or the market value of such
securities shall be equal at least to the amount of the required
bond and shall be held upon the same terms and conditions.
The Secretary of Mines and Mineral Industries shall, upon
receipt of any such deposit of cash or securities, immediately
deposit the same with the State Treasurer, whose duty it shall
be to receive and hold the same in the name of the Commonwealth
for the purpose for which such deposit is made. The State
Treasurer shall at all times be responsible for the safe-keeping
of such deposits.
Any operator making such deposits shall be entitled to
receive from the State Treasurer, on written order of the
Secretary of Mines and Mineral Industries, the whole or any
portion of any securities so deposited, upon depositing with the
department, in lieu thereof, a surety bond or other negotiable
securities of the classes herein specified having a market value
at least equal to the sum required for a bond as aforesaid.
The operator shall also be entitled upon request to receive
from the State Treasurer the interest or income from said
securities deposited as aforesaid as the same become due and
payable: Provided, however, That where securities deposited, as
aforesaid, mature or are called, the State Treasurer, at the
request of the operator, shall convert such securities into
other acceptable securities designated by the operator.
(6 amended Aug. 13, 1963, P.L.781, No.393)
Section 7. Upon application by the operator, the permit
shall be renewed from year to year so as to cover the number of
acres embraced in the original permit which have not been
stripped, and upon filing the required bond for such additional
land and such additional material as would have been required
for the additional land had it been included in the original
application for a permit, an amended permit shall be issued to
the operator to cover acres which are not included in the
original permit and which the operator estimates will be the
area of land affected during the following year.
(7 amended Aug. 13, 1963, P.L.781, No.393)
Section 8. Within thirty (30) days after the close of the
year for which the permit was issued, and likewise after the
close of each subsequent year, the operator, if he continues to
engage in strip mining, shall file with the Department of Mines
and Mineral Industries a new bond covering such new acres as he
may estimate will be affected during the following year. The
bond shall be at the rate of five hundred dollars ($500) per
acre, unless it has been determined by the secretary that a bond
in excess of five hundred dollars ($500) per acre is required.
The bond shall not be less than five thousand dollars ($5,000)
and shall be accompanied by an annual report, upon a form
furnished by the department, setting forth the number of acres
of land affected during the preceding year and the number of
acres of land that will be affected during the ensuing year at
each operation: Provided, however, That any portion of a bond
covering an operation which may remain unencumbered at the end
of an operational year may be applied to acres of land which the
operator anticipates will be affected during the following year.
(8 amended Aug. 13, 1963, P.L.781, No.393)
Section 9. Upon receipt of such annual report, the Secretary
of Mines and Mineral Industries shall make an investigation of
the operation and shall charge the area of land actually
affected by strip mining during the year for which said report
is filed against the bond or deposit filed by the operator at
the established rate per acre of the area of land affected, but
in no case shall the bond or deposit retained by the Secretary
of Mines and Mineral Industries be less than five thousand
dollars ($5,000). Should the area of land actually affected
exceed the estimate made by the operator at the time of the
application for the permit, the operator shall file an
additional bond at the established rate per acre of the area of
land affected over and above his estimate: Provided, That an
additional bond need not be filed where the number of acres of
land actually affected multiplied by five hundred dollars ($500)
does not exceed the sum of five thousand dollars ($5,000),
except in those instances where the secretary has found it
necessary to increase the rate per acre. If the work
contemplated by the permit and bond be not completed, but the
area of land actually affected by strip mining during the year
is less than the estimate, the secretary shall issue a release
of the excess of the bond or deposit upon which liability has
not been charged, as aforesaid: Provided, That in no case shall
any bond or deposit be released or reduced to an amount less
than five thousand dollars ($5,000).
(9 amended Aug. 13, 1963, P.L.781, No.393)
Section 10. (10 repealed Sept. 2, 1961, P.L.1194, No.528)
Section 11. The operator shall be required to backfill
stripping pits in the following manner:
(1) All stripping pits not more than one hundred (100) feet
in depth shall be completely backfilled.
(2) All stripping pits shall be completely backfilled for a
distance of one hundred (100) feet from the right-of-way of any
public highway or two hundred and fifty (250) feet from any
occupied dwelling house, public building, school, church,
commercial or institutional building.
(3) In all stripping pits in excess of one hundred (100)
feet in depth and more than one hundred (100) feet beyond the
right-of-way of any public highway or more than two hundred and
fifty (250) feet beyond any occupied dwelling house, public
building, school, church, commercial or institutional building,
the amount of final backfill required shall be determined by the
Land Restoration Board as hereinafter constituted. Upon approval
of the plan of mining and restoration by said board, the
approved plan shall be included in and become a condition of the
permit which shall be effective and complied with until the
operation is completed or abandoned. The amount of final
backfill required for such stripping pits shall be determined by
said board concurrently with the issuing of a permit, and shall
be included in and become a condition of the permit and the
operator shall be required to backfill to the extent specified:
Provided, however, That alternative plans for reclamation
wherein the land can be used for suitable purposes may be
approved by the Land Restoration Board.
(4) Whenever reasonable and practicable, the department
shall require backfilling as the open pit mining progresses.
Within six months after the operation is completed or abandoned,
the operator shall have backfilled all pits in accordance with
the plan previously approved by the secretary, except in those
instances where the pit or pits are within one hundred (100)
feet of the right-of-way of any public highway or within two
hundred and fifty (250) feet of any occupied dwelling house,
public building, school, church, commercial or institutional
building, in which case, the department shall specify the time
within which the backfilling shall be completed in order to
protect the public safety. All backfilling shall be completed
before necessary backfilling equipment is removed from the
operation.
Provided, however, That any permit issued subsequent to the
effective date of this amending act shall not require
restoration or backfilling of any anthracite coal stripping pit
stripped, affected or created prior to the effective date of
this amending act to other than the requirements of legislation
applicable on the date of such prior stripping.
The permit shall also specify the distance to which the
bottom of the spoil banks made by the strip mining operation may
approach any stream of water having a well defined channel. Such
distances shall be fixed by the department at such number of
feet as in the judgment of the department, after consultation
with the Water and Power Resources Board, taking into
consideration the character of the overburden, is necessary to
protect the channel of the stream.
Nothing contained in this section shall be construed to
prohibit the relocation of any public road, in the manner
provided by law, or the change of the course or channel of any
stream, in the manner provided by law, upon permit issued by the
Water and Power Resources Board.
(11 amended Aug. 13, 1963, P.L.781, No.393)
Section 12. (12 repealed Aug. 13, 1963, P.L.781, No.393)
Section 13. In any case where a strip mining excavation,
after the same is abandoned, is likely to result in an
accumulation of water which in the opinion of the department may
constitute a hazard to present or future deep mining, or is
likely to break out of the excavation and cause a flood, the
department shall order the operator, before abandoning the
operation, to provide proper drainage for the excavation, if the
excavation can be drained reasonably by gravity flow.
Nothing contained in this section shall be construed to
require the draining of a strip mining excavation where the
accumulation of water therein, will not, in the opinion of the
department constitute a hazard, or where such water may furnish
means of recreation or a supply of water for domestic or
industrial uses.
Section 14. In all cases in which the Secretary of Mines and
Mineral Industries shall find as a fact that the planting of
such areas is reasonable, practicable and likely to succeed, the
peaks and ridges of such spoil banks shall be leveled and
rounded off to such an extent as will permit the planting of
trees, grasses, or grasses and trees or grasses and shrubs.
Within one (1) year after the strip mining operation on the
premises is terminated, the operator shall plant trees, grasses,
or grasses and trees or grasses and shrubs, upon the surface of
the spoil banks and the surface of backfills. Any operator,
however, may at his option pay to the Department of Mines and
Mineral Industries the sum of one hundred fifty dollars ($150)
per acre for each acre of such surface of spoil banks and
backfillings, and thereby shall be released from any duty to
plant as herein provided. The moneys so paid from time to time
shall be placed in a special fund in the hands of the Treasury
Department of the Commonwealth and shall be used by the
Department of Mines and Mineral Industries to pay the cost of
planting such trees, grasses or grasses and trees or grasses and
shrubs, and the supervision of such work and all other expenses
necessary for or connected with such planting, and are hereby
appropriated to the Department of Mines and Mineral Industries
for such purposes. Any moneys remaining unused after such
planting may be used for planting any other lands affected by
strip mining of anthracite coal. All planting, required by this
act to be done by the operator, shall be done subject to the
supervision and approval of the Secretary of Mines and Mineral
Industries. If, upon inspection, the Secretary of Mines and
Mineral Industries does not approve the planting, he shall
notify the operator in writing setting forth the objections and
after a hearing shall order the planting to be completed in
accordance with his final decision.
(14 amended Nov. 25, 1970, P.L.748, No.243)
Section 15. Within six (6) months after the backfilling and
other acts required by this act have been completed, the
operator shall file with the Department of Mines and Mineral
Industries a completion report on a form to be prescribed and
furnished by the secretary, identifying the operation and
stating the area of land affected by open pit mining and such
other information as may be required by the secretary before
releasing the bond of the operator.
The operator shall attach to the completion report a map of
the operation, certified by a registered professional engineer,
showing the boundary lines of the tract or tracts, tidal
elevations of the surface top of the coal seam and the bottom of
the strip mine pit, the access to the operation from the nearest
public highway, the area of land affected by open pit mining,
the locations preserved for deep mining and the proposed plans
in connection therewith.
(15 amended Sept. 2, 1961, P.L.1194, No.528)
Section 16. If and when the Secretary of Mines and Mineral
Industries shall find that the operator has completed the
backfilling and other acts as required by this act, and a report
is filed by the inspector certifying that it has been done in
the manner prescribed by this act, the Secretary of Mines and
Mineral Industries shall issue a release of the bond or of the
cash and securities deposited retaining one hundred dollars
($100) per acre affected until such time as the planting is
completed and certified to by the forester as being done in
workmanlike manner at which time the retained one hundred
dollars ($100) per acre shall be released. Upon the presentation
of such release, the State Treasurer shall immediately return to
the operator the amount of cash or securities specified in its
release.
(16 amended Aug. 13, 1963, P.L.781, No.393)
Section 17. If the operator fails or refuses to comply with
the requirements of the act as to any area for which liability
has been provided in the bond, the Secretary of Mines and
Mineral Industries shall declare such portion of the bond
forfeited, and shall certify the same to the Department of
Justice, which department shall proceed to sue out and collect
the amount of liability forfeited thereon; and where the
operator has deposited cash or securities in lieu of bond, the
Secretary of Mines and Mineral Industries shall declare such
portion of the deposit forfeited and shall direct the State
Treasurer to pay said moneys into a special fund for the use of
the department, or to proceed to sell said securities to the
extent forfeited and pay the proceeds thereof into the said
special fund. Such moneys or securities so forfeited and
collected shall be used by the Secretary of Mines and Mineral
Industries to pay the cost of backfilling and other acts
required by this act, and the cost of planting as required by
section 14 of this act.
(17 amended Sept. 2, 1961, P.L.1194, No.528)
Section 18. In the event that an operator or owner desires
to conduct deep mining upon the premises affected by strip
mining, the said operator or owner may make this fact known to
the secretary with the request that the backfilling of pits and
the planting, as may be necessary to permit deep mining, be
deferred during the period of such deep mining. In such case the
secretary may defer the backfilling and planting. The deep
mining shall be started within six (6) months after the recovery
of coal by strip mining is completed. If such request is made by
the owner, he shall secure by bond the backfilling of such pit
and the planting after the deep mining operation has been
completed; if the request is made by the operator, the bond
filed under section 6 of this act shall stand as security for
such backfilling and planting.
(18 amended Sept. 2, 1961, P.L.1194, No.528)
Section 19. Any operator, or any other person who shall be
aggrieved by any administrative regulation, directive or order
of the Secretary of Mines and Mineral Industries, the Land
Restoration Board, or any other administrative agency making
application of the provisions of this act, may file a petition
in the court of common pleas of the county where the land is
located, alleging therein the action complained of and praying
for remedy thereof and the said court shall proceed therein by
rule or rules upon the proper administrative officer, body or
authority to show cause why the petitioner should not have the
remedy prayed for by his, her or its petition. The court in such
proceedings shall make such procedural orders as may be
necessary for facilitating and expediting hearings and
disposition of the matters complained of. Every such petition
shall specify the petitioner's objection to the action of the
administrative officer, body or authority and such officer, body
or authority on or before the return day of the rule shall make
answer thereto. Such petition shall be heard by the said court
of common pleas de novo. From the decision of the said court of
common pleas, an appeal may be taken by either party to the
Superior or Supreme Court of Pennsylvania as in other cases.
Such rights to a hearing and to appeal shall also be enjoyed by
the duly authorized officials of the political subdivision or
subdivisions in which the land is located.
(19 amended Aug. 13, 1963, P.L.781, No.393)
Section 20. The use of explosives for the purpose of
blasting in connection with strip mining in the neighborhood of
any public highway, stream of water, dwelling house, public
building, school, church, commercial or institutional building
or pipe line shall be done in accordance with regulations
promulgated by and under the supervision of the Department of
Mines and Mineral Industries.
(20 amended Sept. 2, 1961, P.L.1194, No.528)
Section 20.1. There is hereby created within the department
a Land Restoration Board to be composed of the Secretary of
Mines and Mineral Industries who shall be chairman of the board,
a conservationist, a representative of the anthracite industry
and a registered professional engineer, each of whom shall be
appointed by the Governor for terms of four years to coincide
with the Governor's own term of office, or until his successor
has been appointed and has qualified, and of the Deputy
Secretary of Mines and Mineral Industries assigned to anthracite
operations.
(20.1 added Aug. 13, 1963, P.L.781, No.393)
Section 20.2. There is hereby created within the department
a Bureau of Anthracite Conservation and Reclamation and the
secretary shall appoint and fix the compensation of a director
of said bureau to be known as the Director of Anthracite
Conservation and Reclamation.
The Bureau of Anthracite Conservation and Reclamation shall
have the power and its duty shall be to administer all of the
laws of this Commonwealth governing and relating to the mining
of anthracite coal by the open pit or strip method and, subject
to the approval of the secretary, to exercise all the powers and
perform all the duties by law vested in and imposed upon said
secretary in relation to such open pit or strip mining.
(20.2 added Aug. 13, 1963, P.L.781, No.393)
Section 20.3. Except as herein provided, all coal stripping
operations coming within the provisions of this act shall be
under the exclusive jurisdiction of the department and shall be
conducted in compliance with such reasonable rules and
regulations as may be deemed necessary by the secretary for the
health and safety of those persons engaged in the work. The
secretary through the mine inspectors shall have the authority
and power to enforce the provisions of this act and the rules
and regulations promulgated thereunder by him.
(20.3 added Aug. 13, 1963, P.L.781, No.393)
Section 21. Any operator who proceeds to mine coal, commonly
known as "anthracite," by the strip mining method without having
received a permit, or without having received an amended permit
as herein provided, shall be guilty of a misdemeanor, and upon
conviction, shall be sentenced to pay a fine of not less than
five hundred dollars ($500.00) and not exceeding five thousand
dollars ($5,000.00), or undergo imprisonment not exceeding three
(3) months, or both. The fine shall be payable to the
Commonwealth.
(21 amended Aug. 13, 1963, P.L.781, No.393)
Section 21.1. All funds received by the Secretary of Mines
and Mineral Industries from registration fees, from forfeiture
of bonds, of cash deposits and securities, and from penalties
provided under the terms of this act, shall be held by the State
Treasurer in a special fund separate and apart from all other
moneys in the State Treasury, to be known as the "Anthracite
Coal Open Pit Mining Reclamation Fund," and shall be used by the
Secretary of Mines and Mineral Industries for the sole purpose
of administering the provisions of this act and for foresting or
reclaiming land affected by open pit mining of anthracite coal,
and for such purposes are hereby specifically appropriated to
the Department of Mines and Mineral Industries.
(21.1 added Aug. 13, 1963, P.L.781, No.393)
Section 22. All acts or provisions thereof inconsistent
herewith are hereby repealed: Provided, however, That the act of
assembly, approved the eighteenth day of June, Anno Domini, one
thousand nine hundred forty-one (Pamphlet Laws 133), entitled
"An act relating to coal stripping operations; providing for the
health and safety of persons employed therein and for the
inspection and regulation of such operations by the Department
of Mines; requiring certain information and reports, and
prescribing penalties," and the act of assembly, approved on the
twenty-fifth day of June, Anno Domini, one thousand nine hundred
thirty-seven (Pamphlet Laws 2275), entitled "An act to promote
safety for the traveling public on State highways; to extend the
responsibility for subsidence of such highways by the failure of
vertical and lateral support, and declaring said subsidence a
public nuisance; to provide for inspection of mine maps by the
Department of Highways, and the furnishing to said department of
copies of such mine maps in certain cases; to authorize entry by
the Department of Highways into mines in certain cases; and to
provide for notices to the Department of Highways of certain
mining operations under or adjacent to highways; and providing
penalties," and all other acts and provisions thereof, which
regulate the mining of anthracite coal shall not be repealed or
nullified by this act, but shall remain in full force and
effect. Nothing in this act shall be construed to abrogate or
modify the power and jurisdiction of the Department of Mines to
make rules and regulations and to administer the laws of the
Commonwealth applicable to open pit mining.
Section 23. This act shall become effective immediately upon
its final enactment: Provided, however, That any person,
partnership, association or corporation, which is engaged in
strip mining on the effective date of the act, shall be allowed
the period until the first day of September, one thousand nine
hundred forty-seven (1947) to file an application, secure a
permit and deposit a filing fee and bond with the Department of
Mines.