1.08 Time Limits for Review

1.08: Time Limits for Review

Each Submission for a Permit (or component thereof) is subject to a deadline by which the DEC must make a decision. i.e., take a final vote. Listed are the applicable time periods, measured from the date of the DOC. The time limits for Level One reviews may be extended by mutual written agreement of the Applicant and the Director. The time limits for Level Two reviews also may be extended by a written agreement of the Applicant and the DEC. In a Submission with more than one component, the longest time limit associated with one component shall apply to the entire Submission.

TABLE 3:TIME LIMITS FOR REVIEW

Level One ReviewTime Limits in Days

Lotting Plan14

Development Plan21

Engineering Adjustment 14

Building or Occupancy Permit 30

Other reviews authorized in the By-Laws, Article III, Section D21

Level Two Review(inclusive of the date of the DEC's vote)

Site Plan Review75

Subdivision Approval75

Wetlands63

Variances90

Reconsiderations - (measured from the date of request)45

Historic District Certificates of Appropriateness45