David Nebel D/B/A Nebel Electric v. David L. Lott and Julie A. Lott, Dubuque Bank and Trust, and Dubuque City of Housing Services Department

CourtListener 4373958Iowactapp8 de mar. de 2017

Abrir fonte

Texto completo

IN THE COURT OF APPEALS OF IOWA

No. 15-2035
Filed March 8, 2017

DAVID NEBEL d/b/a NEBEL ELECTRIC,
Plaintiff-Appellant,

vs.

DAVID L. LOTT and JULIE A. LOTT, DUBUQUE BANK AND TRUST, and
DUBUQUE CITY OF HOUSING SERVICES DEPARTMENT,
Defendants-Appellees.
________________________________________________________________

Appeal from the Iowa District Court for Dubuque County, Monica L.

Ackley, Judge.

Plaintiff appeals from the district court’s grant of a directed verdict against

him in his action to foreclose a mechanics’ lien. AFFIRMED IN PART AND

REVERSED IN PART.

Russel A. Neuwoehner of Lange & Neuwoehner, Dubuque, for appellant.

Susan M. Hess of Hammer Law Firm, P.L.C., Dubuque, for appellees

David and Julie Lott.

Edward F. Henry of Fuerste, Carew, Juergens, & Sudmeier, P.C.,

Dubuque, for appellee Dubuque Bank and Trust.

Considered by Vaitheswaran, P.J., and Potterfield and Bower, JJ.
2

POTTERFIELD, Judge.

David Nebel filed a petition to foreclose his mechanic’s lien on property

owned by the Lotts, maintaining the Lotts owed him $9283.69 for materials and

labor he provided doing electrical work on one of their rental properties.

Following a hearing on the petition, the district court granted the defendants’

motion for a directed verdict. On appeal, Nebel maintains the district court

applied the wrong statute and, as a result, the defendants’ motion for directed

verdict was improperly granted. Nebel also challenges the district court’s award

of attorney fees to the defendants.

“An action to enforce a mechanic’s lien is in equity and our review is de

novo.” Giese Constr. Co. v. Randa, 524 N.W.2d 427, 430 (Iowa Ct. App. 1994);

see also Iowa Code § 572.26 (2011) (“An action to enforce a mechanic’s lien

shall be by equitable proceedings, and no other cause of action shall be joined

therewith.”). “In mechanic’s lien cases, involving as they do numerous charges

and counter charges which depend entirely on the credibility of the parties, we

have frequently held the trial court is in a more advantageous position than we to

put credence where it belongs.” Sulzberger Excavating, Inc. v. Glass, 351

N.W.2d 188, 191–92 (Iowa Ct. App. 1984) (citation omitted).

Here, the court found that Nebel had failed to comply with the statute

controlling the perfection of a mechanics lien, pursuant to Iowa Code section

572.8 (2013), and thus determined his petition to foreclose the lien failed.

However, it is undisputed the court applied the wrong statute. Nebel filed his

mechanic’s lien in February 2012. In 2012, our legislature made a number of

significant changes to the controlling statutes, but those changes were explicitly
3

stated to take effect on January 1, 2013. See 2012 Iowa Acts ch. 1105 §§ 4, 27.

Thus, Iowa Code section 572.8 (2011) controls here. That section provides:

1. A person shall perfect a mechanic’s lien by filing with the
clerk of the district court of the county in which the building, land, or
improvement to be charged with the lien is situated a verified
statement of account of the demand due the person, after allowing
all credits, setting forth.
a. The date which such material was first furnished or labor
first performed, and the date on which the last of the material was
furnished or the last of the labor was performed.
b. The legal description of the property to be charged with
the lien.
c. The name and last known mailing address of the owner of
the property.
2. Upon the filing of the lien, the clerk of court shall mail a
copy of the lien to the owner. If the statement of the lien consists of
more than one page, the clerk may omit such pages as consist
solely of an accounting of the material furnished or labor performed.
In this case, the clerk shall attach a notification that pages of
accounting were omitted and may be inspected in the clerk’s office.

Iowa Code § 572.8.

Additionally, section 572.10 mandates what a plaintiff must do to perfect a

lien “beyond ninety days after the date which the last of the material was

furnished or the last of the labor was performed.” If more than ninety days has

lapsed, the contractor must “fil[e] a claim with the clerk of the district court and

giv[e] written notice thereof to the owner.” Id. § 572.10.

Considering the 2011 statute, we do not believe the district court’s grant of

a directed verdict for failure to comply with the statute was appropriate. On its

face, the lien comports with section 572.8 (2011). It states Nebel began

performing work and providing materials on February 14, 2011, and that he

stopped on February 2, 2012. See id. § 572.8(1)(a). It also contains a legal

description of the property on which he completed the work and a mailing
4

address for the Lotts. See id. § 572.8(1)(b), (c). Nebel did not provide written

notice of the lien to the Lotts; however written notice is only necessary to perfect

the lien if the lien is filed more than ninety days after materials and labor are

completed. See id. § 572.10.

At the hearing in September 2015, it became clear that February 2, 2012,

was not the last date on which material was provided or work performed.

According to the testimony of the electrical inspector for the City of Dubuque, he

had conducted an inspection of the electrical work at the property at the request

of Nebel. Afterward, Nebel voided his permit—sometime at the end of 2011—

likely on December 15, 2011.1 Nebel testified his last date on the project was on

the date he voided the permit; he relied on the inspector’s testimony for the exact

date. When asked if she could name the last date Nebel was on the job site,

Julie Lott testified she did not know because she had moved to Florida on August

18, 2011, and she did not return to the site until April 2012, at which point the

project had already been finished and the lien already filed.2 Based on the

record before us, there is nothing to suggest that Nebel’s last date on the site

was before November 18, 2011.3 Thus, Nebel was not required to provide

written notice to the Lott’s to perfect the lien. See id. § 572.10.

Because Nebel has complied with the statutory requirements to perfect

the lien, we consider the merits of Nebel’s petition to foreclose the lien.

1
Once the permit was voided, Nebel could not legally complete any additional work on
the project.
2
According to Julie, after she moved to Florida in August, her husband stayed behind to
oversee the completion of the project. David Lott did not testify at the hearing.
3
November 18, 2011, is ninety days before the mechanic’s lien was filed, on February
16, 2012.
5

“The burden of proof is upon the mechanic’s lien claimant.” Sulzberger,

351 N.W.2d at 192. “To be entitled to a mechanic’s lien, there must be an

express contract or such a state of facts as will give rise to an implied contract.”

Id. “If there is no express agreement as to the amount of compensation paid[,]

the law implies a promise to pay a reasonable compensation.” Id.

Here, Nebel testified that there was no written contract for the work to be

completed but that he had an agreement with the Lotts that they would pay him

for “time and material” to complete the necessary electrical work on their “six-

plex.” When asked if there was a discussion with the Lotts about his hourly rate,

Nebel testified, “I can’t remember. I’m pretty sure I went through with it, but I

can’t—I can’t tell you exactly what it was at that time.” He later testified that he

believed his rate in 2011 was “$65.00 an hour,” journeymen received “35 or 40”

dollars per hour, and “helpers” get “20, 25” dollars per hour.

Cancelled checks from the Lotts establish that Nebel was paid $20,493.00

over the life of the project.4 Nebel’s lien is for an additional $9283.69. In

reviewing the receipts Nebel provided for the purchased materials—considering

even those receipts that do not explicitly show the purchases were made for the

Lotts’ project—Nebel spent approximately $11,200 on materials. That leaves

approximately $9,300 that was paid to Nebel for labor. At the hearing on the

petition to foreclose, Nebel provided no breakdown (or even an estimate) of

hours of work that were completed on the project in either written form or in his

testimony. Here, we have no definitive hourly rate, no idea of numbers of hour

4
Nebel also completed work on another project for the Lotts. There are two cancelled
checks for that project totaling $5550, which we do not consider in the total paid to Nebel
for purposes of the lien.
6

worked, and no idea which workers—Nebel himself, journeyman, or helpers—

completed the work Nebel testified was done before he quit the job (before the

project was complete). Without more information, it is impossible for us to say

that Nebel is owed the $9283 based on either an express contract between him

and the Lotts or because it is reasonable compensation for the work completed.

Nebel has failed to satisfy his burden, and we decline to foreclose the

mechanic’s lien.

Next, we consider Nebel’s claim that the district court’s award of

“reasonable attorney fees” to the defendants was in error. In its denial of Nebel’s

petition to foreclose the lien, the court stated, “Reasonable attorney fees

pursuant to Iowa Code chapter 572 are awarded to Defendants. Certification of

attorney’s fee shall be filed by affidavit.” Following a hearing to determine the

appropriate amount of fees, the court ordered Nebel to pay the total of the

defendants’ fees—$6870—pursuant to section 572.32.

While we applied the 2011 code in determining what Nebel was required

to do to perfect the lien, his petition to foreclose the lien was not filed in court until

2014. Thus, the 2014 Iowa Code applies to the court action.5

Iowa Code section 572.32 (2014) provides:

1. In a court action to enforce a mechanic's lien, a prevailing
plaintiff may be awarded reasonable attorney fees.
2. In a court action to challenge a mechanic's lien posted on
a residential construction property, if the person challenging the lien

5
Since 2014, the Iowa Code has been published annually, as opposed to every other
year. See 2014 Acts ch. 1141, § 39 (amending Iowa Code section 2B.12, stating the
“legislative services agency shall publish an annual edition of the Iowa Code as soon as
possible, after the final adjournment of a regular or specially session of a general
assemble,” and removing the agency’s ability to publish a Code Supplement in lieu of
the Iowa Code).
7

prevails, the court may award reasonable attorney fees and actual
damages. If the court determines that the mechanic’s lien was
posted in bad faith or the supporting affidavit was materially false,
the court shall award the owner reasonable attorney fees plus an
amount not less than five hundred dollars or the amount of the lien,
whichever is less.

(Emphasis added.) “Residential construction” is further defined as “construction

on single-family or two family dwellings occupied or used, or intended to be

occupied or used, primarily for residential purposes, and includes real property

pursuant to chapter 499B.” Iowa Code § 572.1(10).

Neither subsection applies in this instance. Section 572.32 only allows the

award of attorney fees for a prevailing plaintiff or for a prevailing defendant if the

lien was filed on “residential construction” property. Here, the record is replete

with references to this property being a six-plex—six separate units meant to

house six individuals or families.6 “Because an award of attorney fees are a

derogation of the common law, attorney fees ‘are generally not recoverable as

damages in the absence of a statute or a provision in a contract.” Branstad v.

State ex rel. Nat. Res. Comm’n, 871 N.W.2d 291, 294 (Iowa 2015) (citation

omitted). “The statutory authorization must be express and ‘must come clearly

within the terms of the statute.’” Id. (citation omitted).

We reverse the district court’s award of attorney fees to the defendants.

Additionally, we deny the defendants’ request for appellate attorney fees.

AFFIRMED IN PART AND REVERSED IN PART.

6
We note the defendants would not be able to recover attorney fees under Iowa Code
section 572.32(2) (2011) either. Before the statute was amended in 2012, it limited
attorney fees to prevailing parties challenging a lien “filed on an owner-occupied
dwelling.” Iowa Code § 572.32(2). As noted above, this property was a rental property,
and there is nothing in the record that suggests that the Lotts lived in the six-plex.