1
UNITED STATES DISTRICT COURT
WESTERN DISTRICT OF TEXAS
AUSTIN DIVISION
Sharon Fleming,
Plaintiff
v.
Ulta Salon, Cosmetics & Fragrance, Inc.;
Gateway Square, LLC; Washington Prime
Management Associates, LLC; and
WPG Texas Properties, LLC,
Defendants
§
§
§
§
§
§
§
§
Case No. 1:24-cv-00660-DAE
ORDER
Before the Court are Plaintiff’s Motion for Entry of Amended Docket Control Order and to
Extend Deadlines (Dkt. 34) and First Amended Motion to Extend Motion for Summary Judgment
Response[ ] Deadline (Dkt. 35), both filed January 27, 2026; Defendants Gateway Square LLC
and Washington Prime Management Associates, LLC’s Response to both motions, filed
February 5, 2026 (Dkt. 36); and Defendant Ulta Salon, Cosmetics & Fragrance, Inc.’s Response
to Plaintiff’s motion to extend deadlines, also filed February 5, 2026 (Dkt. 37).1 Plaintiff did not
file a reply brief in support of either of her motions.
Plaintiff filed this case in state district court in Travis County, Texas on March 14, 2024, and
it was removed to this Court on June 13, 2024. Dkt. 1. On October 21, 2024, the Court issued an
agreed scheduling order setting April 21, 2025 as the deadline for Plaintiff’s expert designation
and July 21, 2025 as the deadline to complete discovery. Dkt. 10 ¶¶ 5, 7.
Plaintiff’s pending motion is her third over the past eleven months seeking more time for her
expert to inspect the premises at issue. Dkts. 17, 22, 34. By Text Order entered April 22, 2025, the
District Court granted Plaintiff a 63-day extension of the expert deadline, until June 23, 2025.
1 The Honorable David A. Ezra referred the motions to this Magistrate Judge for disposition, pursuant to
28 U.S.C. § 636(b)(1)(A), Federal Rule of Civil Procedure 72, and Rule 1(c) of Appendix C of the Local
Rules of the United States District Court for the Western District of Texas. Dkt. 38 at 2.
Case 1:24-cv-00660-DAE Document 40 Filed 03/10/26 Page 1 of 3
2
But the site inspection never happened. Plaintiff offers no explanation for the yearlong delay,
making only the conclusory allegations that her expert “has not been allowed access to conduct
his examination” and Defendants refuse to provide workable dates. Dkt. 34 at 3; Dkt. 35 at 2.
In response, Defendants submit evidence that they attempted to accommodate Plaintiff but she
delayed inspection requests until near the end of each deadline and sought relief from the Court
rather than continuing to work to reach agreement. Plaintiff offers no rebuttal to this evidence.
Under Rule 16(b)(4), a scheduling order may be modified after a deadline has passed “only for
good cause and with the judge’s consent.” The Court first considers Plaintiff’s explanation for her
failure to timely move to modify the scheduling order.
To satisfy the Rule 16(b)(4) good cause standard, the movant must show that the deadlines
could not have reasonably been met despite the diligence of the party needing the extension. S & W
Enters., L.L.C. v. SouthTrust Bank of Ala., NA, 315 F.3d 533, 535 (5th Cir. 2003). Diligence is the
most important factor. BigCommerce, Inc. v. S&O Inc., No. 1:24-cv-00121-SH, 2025 WL 882701,
at *2 (W.D. Tex. Mar. 3, 2025) (“The most important factor bearing on the ‘good cause’ inquiry
under Rule 16(b)(4) is whether the party seeking to modify the scheduling order can show that it
has been diligent in pressing its claims but despite its diligence could not reasonably have met the
scheduling deadline.”) (citation omitted).
The Court finds that Plaintiff has not acted with diligence in seeking expert discovery. Her
repeated delays in requesting inspection and lack of explanation for the long delays weigh heavily
against reopening discovery.
Plaintiff obliquely addresses the second good cause factor, the importance of the modification,
by asserting that her expert will evaluate the subject premises for “the unreasonably dangerous
condition it posed to Plaintiff on the date of this incident” and Defendants’ claim of “exceptions
Case 1:24-cv-00660-DAE Document 40 Filed 03/10/26 Page 2 of 3
3
such as necessary use and distractions.” Dkt. 35 at 3. Ulta responds that the inspection will have
no bearing on the merits of its motion for summary judgment predicated on its lack of control of
the property. Dkt. 37 at 3. Gateway Square and Washington Prime Management respond that
Plaintiff has already visited the property and produced photographs of the scene, which were
included in their first motion for summary judgment. Dkt. 24 at 2; Dkt. 24-1; Dkt. 36 at 1 n.1.
The Court finds that because the inspection may bear on the issues presented, the second factor
favors reopening discovery. The Court also finds, however, that Plaintiff’s extreme delay and lack
of diligence in pursuing inspection under the first factor outweigh the importance of the
modification and preclude a finding of good cause.2
Because Plaintiff has not shown good cause to reopen expert discovery, her Motion for Entry
of Amended Docket Control Order and To Extend Deadlines (Dkt. 34) and First Amended Motion
to Extend Motion for Summary Judgment Response[ ] Deadline (Dkt. 35) are DENIED.
IT IS FURTHER ORDERED that the Clerk remove this case from this Magistrate Judge’s
docket and return it to the docket of the Honorable David A. Ezra.
SIGNED on March 10, 2026.
SUSAN HIGHTOWER
UNITED STATES MAGISTRATE JUDGE
2 Plaintiff does not address the remaining two good cause factors: potential prejudice in allowing the
modification and availability of a continuance to cure such prejudice. Gibson v. United States, No. 1:18-
CV-626-RP, 2021 WL 6617723, at *1 (W.D. Tex. Mar. 15, 2021).
Case 1:24-cv-00660-DAE Document 40 Filed 03/10/26 Page 3 of 3