United States of America v. Andreas Enterprises LLC

1:26-cv-00012Mtd9 de fev. de 2026

Abrir fonte

Texto completo

Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 1 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 2 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 3 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 4 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 5 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 6 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 7 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 8 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 9 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 10 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 11 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 12 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 13 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 14 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 15 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 16 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 17 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 18 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 19 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 20 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 21 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 22 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 23 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 24 of 25
Case 1:26-cv-00012-SPW Document 4 Filed 02/09/26 Page 25 of 25

OCR transcription for search; preserved printed pages are authoritative

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 1 of 25

IN THE UNITED STATES DISTRICT COURT
FOR THE DISTRICT OF MONTANA

BILLINGS DIVISION
)
UNITED STATES OF AMERICA, )
)
)
) Case No. CV-26-12-BLG-SPW
Plaintiff, )
)
Vv. )
) STIPULATION and
) AGREED JUDGMENT
ANDREAS ENTERPRISES LLC, )
d/b/a ANDREAS PETROLEUM )
and LEE ANDREAS, )
)
Defendants. )
)

STIPULATION AND AGREED JUDGMENT

WHEREAS Plaintiff United States of America (“United States”), by
authority of the Attorney General of the United States and acting at the request of
the United States Coast Guard (“USCG”), the United States Department of the
Interior (“DOT”) and the National Park Service (“NPS”), filed a Complaint under
the System Unit Resources Protection Act (“SURPA”), 54 U.S.C. §§ 100721-

100725, and Section 1002 of the Oil Pollution Act (“OPA”), 33 U.S.C. § 2702
|

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 2 of 25

against Defendants Andreas Petroleum and Lee Andreas (collectively “Andreas” or

“Defendants”);

WHEREAS the United States sought in its Complaint recovery of all
damages available to it, including response costs and damages to System unit
resources as defined under SURPA, and removal costs and natural resource
damages as defined under OPA, within Yellowstone National Park (“Yellowstone”)
alleged to have resulted from an incident involving an Andreas Petroleum tractor
trailer, driven by Mr. Lee Andreas, that was hauling gasoline through the Park’s
Hayden Valley. Mr. Andreas lost control of the vehicle’s “pup” trailer which
overturned and spilled approximately 3,200 gallons of unleaded gasoline on and

alongside the roadway that follows the Yellowstone River;

WHEREAS the United States alleges that the incident caused NPS loss of
visitor use to the impacted area; that NPS and the Environmental Protection
Agency (“EPA”) incurred removal costs responding to and cleaning up the area;
and the public lost use and enjoyment of Yellowstone. The United States believes
that the settlement embodied in this Stipulation represents a reasonable

compromise and is consistent with the goals of SURPA and OPA;

WHEREAS the United States also sought in its Complaint recovery of

damages available to the United States arising under its natural resource trusteeship

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 3of 25

for alleged damage to natural resources, belonging to, managed by, controlled by

or appertaining to the United States;

WHEREAS Defendants neither admit nor deny the alleged violations of law

stated in the Complaint or the NOV;

WHEREAS the Parties have agreed that settlement of this matter is in the
public interest and that entry of this Order without further litigation constitutes the

most appropriate means of resolving this matter;

WHEREAS the United States has reviewed the financial information
provided by Andreas, including income, net worth, tax returns, statements of cash
flows, assets and liabilities, W-2s, and living expenses, and has determined that
Defendants possess limited financial ability to pay for damages to natural
resources, response costs, and removal costs incurred and to be incurred from the

Andreas Petroleum Spill beyond the amounts specified in this Stipulation; and

NOW THEREFORE, before the taking of any testimony, without
adjudication or admission of any issue of fact or law, and upon consent and
agreement of the Parties to this Stipulation, it is hereby AGREED, STIPULATED,

and ORDERED:

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 4of 25

I. JURISDICTION AND VENUE
1. | This Court possesses jurisdiction over the subject matter of this action
under 54 U.S.C. § 100723 (SURPA), 33 U.S.C. § 2717(b) (OPA), 28 U.S.C. §§
1331 (federal question), and 1345 (United States as a Plaintiff). For purposes of
this Stipulation, or any action to enforce this Stipulation, the Parties consent to the
Court’s jurisdiction over this Stipulation and any such action and over the Parties,
and consent to venue in this judicial district.
II. PARTIES BOUND
2. The obligations of this Stipulation apply to and are binding upon the
United States and upon the Defendants and their successors. Any change in
Defendants’ ownership or corporate status shall not alter its obligations hereunder.
All of Defendants’ obligations to perform acts or pay money pursuant to this
Stipulation and Agreed Judgment are set out in Sections IV, V and X below.
Ill. DEFINITIONS
3. Unless otherwise provided in this Stipulation, terms used in this
Stipulation that are defined in SURPA and OPA or in the regulations promulgated
under OPA shall have the meaning assigned to them in SURPA and OPA or in such
regulations. Whenever terms listed below are used in this Stipulation or its
appendices, the following definitions shall apply solely for the purposes of this

Stipulation:

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page5 of 25

A. “Affected Area” shall mean the spill site is located approximately 4
miles north/northwest of Yellowstone Lake on the Grand Loop Road near the
Cascade Picnic Area.

B. “Andreas Petroleum Spill” shall mean the August 27, 2020, incident
involving the overturned Andreas Petroleum tractor trailer and resulting spill of
approximately 3,200 gallons of unleaded gasoline.

C. “Complaint” shall mean the complaint filed by the United States in
this civil action.

D. “Day” or “day” shall mean a calendar day. In computing any period
of time under this Stipulation, where the last day would fall on a Saturday, Sunday,
or federal holiday, the period shall run until the close of business of the next
working day.

E. “DOI” shall mean the United States Department of the Interior and its
successor departments, agencies, or instrumentalities.

F,. “DOJ” shall mean the United States Department of Justice and its
successor departments, agencies, or instrumentalities.

G. “Effective Date” shall mean the date upon which the approval of this
Stipulation is signed by the Court and recorded on the Court’s docket.

4. “Government-Approved Remedy Plan” shall mean the United States,

and Wyoming-approved detailed design plan, including but not limited to, the

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 6 of 25

installation, removal and monitoring of permeable reactive barriers and other
actions in response to the Andreas Petroleum Spill. A copy of the Government-
Approved Remedy Plan is attached as Appendix A to this Stipulation.

H. “Kuntz Environmental Services” or “Kuntz” shall mean the contractor
responsible for work to be performed under the Government-Approved Remedy
Plan.

I. “NPS” shall mean the United States National Park Service and its
successor departments, agencies, or instrumentalities.

J. “Paragraph” shall mean a portion of this Stipulation identified by an
Arabic numeral or an upper or lower case letter.

K. “Parties” shall mean the United States and Defendants.

L. “Section” shall mean a portion of this Stipulation identified by a
Roman numeral.

M. “Stipulation” shall mean this Stipulation and Agreed Judgment.

N. “System unit resource” shall mean any living or non-living resources
located within the boundaries of a System unit as defined by SURPA. 54 U.S.C. §
100722(a).

O. “United States” shall mean the United States of America, including

the USCG, DOI and NPS.

Case 1:26-cv-00012-SPW' Document4 Filed 02/09/26 Page 7 of 25

P. “Wyoming” shall mean the State of Wyoming, including the Wyoming
Department of Environmental Quality.
IV. PAYMENT AND DISBURSEMENT OF FUNDS
5. Under this Stipulation, Defendants shall pay the sum of $3,500,000.00
for response costs and damages related to the Andreas Petroleum Spill. The funds
shall be distributed as follows:

a. Payment for United States’ Past Response Costs and Damages:

Not later than 45 Days after the Effective Date, Defendants shall pay $745,113.00
to the United States. Of this amount, the United States will disburse $545,113.00
to the USCG, National Pollution Funds Center for removal costs associated with
EPA’s response action and $200,000.00 to the NPS for its past response costs
pertaining to the Andreas Petroleum Spill. Payment shall be in the form of an
Electronic Funds Transfer to the DOJ account, in accordance with instructions
provided to Defendants on or before the Effective Date by the Financial Litigation
Unit (“FLU”) of the United States Attorney’s Office for the District of Montana.
The payment instructions provided by the FLU will include a Consolidated Debt
Collection System number, which Defendants shall, along with the DOJ Case
Number 90-5-1-1-12621, use to identify all payments required to be made in
accordance with this Stipulation. The FLU will provide the payment instructions

to Western Justice Associates, PLLC to the attention of Jory Ruggiero at

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 8 of 25

jory@westernjusticelaw.com on behalf of Defendants. Defendants may change the
individual to receive payment instructions on its behalf by providing written notice
of such change to the United States in accordance with Section IX (Notice).

b. Payment for Implementation of the Government-Approved

Remedy Plan: Defendants shall pay the sum of $2,754,887.00 for implementation
of the Government-Approved Remedy Plan for cleanup of the Affected Area. The
total amount described under this Paragraph shall be disbursed exclusively for
implementation of the Government-Approved Remedy Plan in accordance with the
requirements under Section V (Defendants’ Clean up and Restoration Obligations).
6. Defendants to date have expended $1,119,246.75 of the sum described
in Paragraph 5.b for implementation of the Government-Approved Remedy Plan.
7. Not later than 45 days after the Effective Date, the unpaid balance of
the sum under Paragraph S.b. totaling $1,635,640.25 shall be deposited in an
interest-bearing trust account that is mutually agreed-upon by the Parties
(“Remedy Plan Trust Account”). The account shall be administered by a trustee,
appointed by Defendants, who is an attorney licensed to practice law in Montana
or a bank or trust company authorized to do business in Montana under the laws of
Montana or the United States. The funds shall be managed by Defendants and all
such funds, plus accrued interest, shall be applied toward the cost of implementing

the Government-Approved Remedy Plan and this Stipulation, including any

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 9 of 25

reasonable expenses of the trustee incurred in communicating with the United
States and Wyoming, addressing disputes and overseeing distribution of the funds
in order to implement the Government-Approved Remedy Plan, until fully
expended or swept by NPS in accordance with Paragraph 14.
Vv. DEFENDANTS’ CLEAN UP AND RESTORATION OBLIGATIONS
8. Defendants have contracted with Kuntz Environmental Services to
implement the Government-Approved Remedy Plan. A copy of the contract
between Defendants and Kuntz (“Kuntz Contract”) is attached as Appendix B to
this Stipulation. The Parties agree that the Government-Approved Remedy Plan
will be implemented according to the Kuntz Contract. The Kuntz Contract may be
amended only by written agreement of the NPS, Wyoming, Defendants, and Kuntz.
9. | Defendants’ cleanup and restoration obligation shall be to pay Kuntz’s
bills pursuant to the Invoice and Payments provisions in Section 11 of the Kuntz
Contract, unless otherwise mutually agreed by NPS, Wyoming, Defendants and
Kuntz in writing. On or about the first of each month, the trustee will send NPS, in
accordance with Section IX (Notice), any bills received from Kuntz in the
preceding 30 days and any expenses of the trustee billed in the preceding 30 days.
10. Defendants shall have no obligation under this Stipulation, including
to fund the Government-Approved Remedy Plan or pay Kuntz, after the amount set

forth in Paragraph 5.b., plus any accrued interest, is expended or transferred to

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 10 of 25

NPS, pursuant to Paragraph 14. The United States and Wyoming shall have no
financial obligations regarding the implementation of the Government-Approved
Remedy Plan.

11. Before conducting work under the Government-Approved Remedy
Plan, Kuntz must apply for and receive a Special Use Permit (“SUP”) from NPS.
At all times, Kuntz must maintain a current and approved SUP to implement the
Government-Approved Remedy Plan and comply with the SUP.

12. Atthe conclusion of implementation of the Government-Approved
Remedy Plan, including any required period of monitored natural attenuation, any
funds described in Paragraph 5.b. that are dedicated to the Government-Approved
Remedy Plan that have not been paid out pursuant to Paragraph 7, shall be
deposited in the DOI Natural Resource Damage Assessment and Restoration Fund.
Such funds shall be used to fund additional natural resource restoration,
compensate for lost use, and reimburse any costs related to oversight and
administration of restoration planning and implementation.

13. No later than 30 Days after the Government-Approved Remedy Plan
has been completed, the funds described in Paragraph 5.b. are exhausted, or the
Remedy Plan Trust Account is swept by NPS in accordance with Paragraph 15,
Defendants shall send written notice to NPS in accordance with Section IX

(Notice) that the restoration obligations set out in Section V are completed in full

10

Case 1:26-cv-00012-SPW Document4_ Filed 02/09/26 Page 11 of 25

compliance with the requirements of this Stipulation. The notice of completion
shall include the Certification set forth in Section X (Certification).

14. No later than 60 Days after the date of NPS’s receipt of Defendants’
notice of completion under Paragraph 13, NPS shall evaluate the notice of
completion, and if NPS, after consultation with Wyoming, agree that Defendants
have met its obligations under this Stipulation, the United States will issue a
certification of completion of Defendants’ obligations under this Stipulation and
the United States will file notice of satisfaction of judgment.

15. NPS, after mutual agreement with Wyoming, reserves the right to
object to any aspect of Kuntz’s implementation of the Government-Approved
Remedy Plan. If NPS determines, after mutual agreement with Wyoming, that
Kuntz is not implementing the cleanup as provided in the Government-Approved
Remedy Plan or that Defendants’ trustee or Kuntz is not performing in a cost-
effective or timely manner, NPS, after mutual agreement with Wyoming, may
direct Defendants to pay any outstanding bills and expenses from the amount
designated in Paragraph 5.b and transfer the balance of the trust account to the DOI
Natural Resource Damage Assessment and Restoration Fund. Before directing
Defendants to transfer any balance of the trust account, the Parties will meet to
discuss any objections to Kuntz’s implementation of the Government-Approved

Remedy Plan or performance of the Defendants’ trustee and attempt to remedy

11

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 12 of 25

identified concerns in an effort to ensure that the Government-Approved Remedy
Plan is completed in a cost-effective and timely manner.

16. Funds transferred to the DOI Natural Resource Damage Assessment
and Restoration Fund pursuant to Paragraph 15 shall be used in accordance with 54
U.S.C. § 100724.

17. IfDefendants disagree with any mutual agreement reached between
NPS and Wyoming directing Defendants to transfer the balance of the trust account
to the DOI Natural Resource Damage Assessment and Restoration Fund under
Paragraph 15, Defendants may elect to invoke the dispute resolution procedures set

forth in Section VII (Dispute Resolution).

VI. FORCE MAJEURE

18. “Force majeure,” for purposes of this Stipulation, is defined as any
event arising from causes beyond the control of Defendants, of any entity
controlled by Defendants, or of Defendants’ contractors that delays or prevents the
performance of any obligation under this Stipulation despite Defendants’ best
efforts to fulfill the obligation. The requirement that Defendants exercise “best
efforts to fulfill the obligation” includes using best efforts to anticipate any
potential force majeure event and best efforts to address the effects of any potential

force majeure event.

12

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 13 of 25

19. Ifany event occurs or has occurred that may delay the performance of
any obligation under this Stipulation, whether or not caused by a force majeure
event, Defendants shall provide notice by telephone or email to NPS within 72
hours of when Defendants first knew that the event might cause a delay. Within
seven days thereafter, Defendants shall provide in writing to NPS an explanation
and description of the reasons for the delay; the anticipated duration of the delay;
all actions taken or to be taken to prevent or mitigate the delay; a schedule for
implementation of any measures to be taken to prevent or mitigate the delay or the
effect of the delay; Defendants’ rationale for attributing such delay to a force
majeure event if it intends to assert such a claim; and a statement as to whether
such event may cause or contribute to an endangerment to public health, welfare or
the environment. Defendants shall include with any notice all available
documentation supporting the claim that the delay was attributable to a force
majeure. Failure to comply with the above requirements shall preclude Defendants
from asserting any claim of force majeure for that event for the period of time of
such failure to comply, and for any additional delay caused by such failure.

20. IfNPS agrees that the delay or anticipated delay is attributable to a
force majeure event, the time for performance of the obligations under this
Stipulation that are affected by the force majeure event will be extended by NPS

for such time as is necessary to complete those obligations. An extension of the

13

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 14 of 25

time for performance of the obligations affected by the force majeure event shall
not, of itself, extend the time for performance of any other obligation.

21. IfNPS does not agree that the delay or anticipated delay has been or
will be caused by a force majeure event, NPS will notify Defendants in writing of
its decision.

22. If Defendants elect to invoke the dispute resolution procedures set
forth in Section VII, Defendants shall do so no later than 30 days after receipt of
NPS’s notice. In any such proceeding, Defendants shall have the burden of
demonstrating by a preponderance of the evidence that the delay or anticipated
delay has been or will be caused by a force majeure event, that the duration of the
delay or the extension sought was or will be warranted under the circumstances,
that best efforts were exercised to avoid and mitigate the effects of the delay, and
that Defendants complied with the requirements of Paragraphs 16 and 17. If
Defendants carry this burden, the delay at issue shall be deemed not to be a
violation by Defendants of the affected obligation of this Stipulation identified to
NPS and the Court.

VII. DISPUTE RESOLUTION

23. Unless otherwise expressly provided for in this Stipulation, the

dispute resolution procedures of this Section shall be the exclusive mechanism to

resolve disputes arising under or with respect to this Stipulation. Any Party’s

14

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 15 of 25

failure to seek resolution of a dispute under this Section shall preclude that Party
from raising any such issue as a defense to an action to enforce any obligation
arising under this Stipulation.

24. Informal Dispute Resolution. Any dispute subject to Dispute
Resolution under this Stipulation shall first be the subject of informal negotiations.
The dispute shall be considered to have arisen when one or more Parties send all
other Parties a written Notice of Dispute. Such Notice of Dispute shall state
clearly the matter in dispute. The period of informal negotiations shall not exceed
20 days from the date the dispute arises, unless that period is modified by written
agreement. If the Parties cannot resolve a dispute by informal negotiations, then
the position advanced by the United States shall be considered binding unless,
within 30 Days after the conclusion of the informal negotiation period, Defendants
invoke formal dispute resolution procedures as set forth below.

25. Formal Dispute Resolution. Defendants shall invoke formal dispute

resolution procedures, within the time period provided in the preceding Paragraph,
by sending DOJ a written Statement of Position regarding the matter in dispute.
The Statement of Position shall include, but need not be limited to, any factual
data, analysis, or opinion supporting the position of Defendants and any supporting

documentation relied upon by Defendants.

15

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 16 of 25

26. The United States will send Defendants its Statement of Position
within 45 days of receipt of the Statement of Position of Defendants. The United
States’s Statement of Position shall include but need not be limited to, any factual
data, analysis, or opinion supporting that position and any supporting
documentation relied upon by the United States. The United States’s Statement of
Position is binding on Defendants, unless Defendants file a motion for judicial
review of the dispute in accordance with the following Paragraph.

27. Judicial Dispute Resolution. Defendants may seek judicial review of

the dispute by filing with the Court and serving on the United States a motion
requesting judicial resolution of the dispute. The motion (a) must be filed within
Thirty (30) Days of receipt of the United States’ Statement of Position pursuant to
the preceding Paragraph; (b) may not raise any issue not raised in formal dispute
resolution pursuant to Paragraph 25 unless the United States raises a new issue of
law or fact in the Statement of Position; (c) shall contain a written statement of the
position of Defendants on the matter in dispute, including any supporting factual
data, analysis, opinion, or documentation, and (d) shall set forth the relief
requested and any schedule within which the dispute must be resolved for orderly

implementation of the Stipulation.

16

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 17 of 25

28. The United States shall respond to the motion of Defendants within
the time period allowed by the Local Rules of this Court. Defendants may file a
reply memorandum, to the extent permitted by the Local Rules.

29. Standard of Review. Except as otherwise provided in this Stipulation,

in any dispute brought under Paragraph 27, Defendants shall bear the burden of
demonstrating that their position complies with this Stipulation. The United States
reserves the right to argue that its position is reviewable only on the administrative
record and must be upheld unless arbitrary and capricious or otherwise not in
accordance with law.

30. The invocation of dispute resolution procedures under this Section
shall not, by itself, extend, postpone, or affect in any way any obligation of
Defendants under this Stipulation, unless and until final resolution of the dispute so
provides.

VIII. EFFECT OF SETTLEMENT

31. This Stipulation and Agreed Judgment resolves the civil claims of the
United States for violations alleged in the Complaint filed in this action.

32. Nothing in this Stipulation shall be construed to create any rights in,
or grant any cause of action to, any person not a Party to this Stipulation. Nothing
in this Stipulation shall limit, enlarge, or otherwise affect, the private rights or

claims of any person not a Party to this Stipulation, except as may be determined

17

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 18 of 25

otherwise by a court of competent jurisdiction. Each of the Parties expressly
reserves any and all rights (including, but no limited to, any right to contribution),
defenses, claims, demands, and causes of action which each Party may have with
respect to any matter, transaction, or occurrence relating in any way to the Andreas
Petroleum Spill against any person not a Party hereto. Nothing in this Stipulation
diminishes the right of the United States to pursue any such persons to obtain
additional natural resource damages, response costs, removal costs, or response
actions.

33. General Reservations by the United States. The United States
reserves, and this Stipulation is without prejudice to, all rights against Defendants
with respect to all matters not expressly included in Paragraph 31.
Notwithstanding any other provisions of this Stipulation, this agreement does not
constitute resolution of Defendants’ potential liability for the following:

a. Claims based on failure by Defendants to meet a requirement of
this Stipulation;

b. Any potential claims against Defendants for criminal liability
associated with the Andreas Petroleum Spill;

C. Claims against Defendants for natural resource damages that do

not arise out of the Andreas Petroleum Spill or related remedial actions.

18

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 19 of 25

34. This Stipulation shall not preclude the United States from instituting a
separate or ancillary action to enforce the terms of this Stipulation.

35. Covenants by Defendants. Defendants hereby covenant not to sue and

agree not to assert any claims or causes of action against the United States and
their employees, agents, contractors, departments, agencies, administrations and
bureaus, related to damages arising from the Andreas Petroleum Spill, including,
without limitation, any potential or pending claims against the National Pollution
Funds Center relating to the Andreas Petroleum Spill. This Paragraph does not
preclude Defendants from filing a motion for judicial review under Section VI
(Dispute Resolution).
IX. NOTICE

36. Unless otherwise specified in this Stipulation, whenever notifications,
submissions, or communications are required by this Stipulation, they shall be
made in writing and sent by mail or email, with a preference for email, addressed
as follows:

As to DOJ by email (preferred): eescdcopy.enrd@usdoj.gov
Re: DJ # 90-5-1-1-12621

As to DOJ by mail: EES Case Management Unit
Environment and Natural Resources
Division
U.S. Department of Justice
P.O. Box 7611
Washington, D.C. 20044-7611
Re: DJ # 90-5-1-1-12621

19

Case 1:26-cv-00012-SPW Document 4

As to DOI:

As to NPS:

As to USCG:

Filed 02/09/26 Page 20 of 25

Clare E. Cragan
Attorney-Advisor

Rocky Mountain Region
Office of the Solicitor
Department of the Interior
Clare.cragan@sol.doi.gov

Karen Battle Sanborn

Acting Branch Manager

Damage Assessment Case Officer
National Damage Assessment Office
Karen_Battle-Sanborn@nps.gov

Tim Reid
Chief, Yellowstone Center for
Resources

Tim_Reid@NPS.gov

Dave Dubay

U.S. Coast Guard — National Pollution
Funds Center

2703 Martin Luther King Jr. Ave. SE
(6906-03)

Washington, D.C., 20593-7605
David.M.Dubay2@uscg.mil

As to Defendants and Remedy Plan Trust
Account Trustee (via both email and mail):

20

Valerie Wyman

Montana Business Law, PLLC
PO Box 11467

Bozeman, MT 59719
valerie@mtbusinessattorney.com

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 21 of 25

X. CERTIFICATION
37. Each certificate of completion submitted by Defendants pursuant to
this Stipulation shall be signed by an official of Defendants and include the
following certification:
I certify under penalty of law that this document and all attachments were
prepared under my direction or supervision in accordance with a system
designed to assure that qualified personnel properly gather and evaluate the
information submitted. Based on my inquiry of the person or persons who
manage the system, or those persons directly responsible for gathering the
information, the information submitted is, to the best of my knowledge and
belief, true, accurate, and complete. I have no personal knowledge that the
information submitted is other than true, accurate, and complete. I am aware
that there are significant penalties for submitting false information, including
the possibility of fine and imprisonment for knowing violations.

XI. RETENTION OF JURISDICTION; COSTS; HEADINGS;
INTEGRATION

38. This Court shall retain jurisdiction over both the subject matter of this
Stipulation and the Parties for the duration of the performance of this Stipulation
for the purpose of enforcing the terms and conditions of this Stipulation and to
resolve disputes arising hereunder as may be necessary or appropriate for the
construction or execution of this Stipulation.

39. The Parties shall bear their own costs of this action, including the
costs incurred in enforcing the terms of this Stipulation.

40. The headings of the Sections shall have no legal significance.

21

Case 1:26-cv-00012-SPW Document4 _ Filed 02/09/26 Page 22 of 25

41. This Stipulation constitutes the final, complete, and exclusive
understanding among the Parties with respect to the settlement embodied in this
Stipulation. The Parties acknowledge that there are no representations,
agreements, or understandings relating to the settlement other than those expressly
contained in this Stipulation.

XII. SIGNATORIES; SERVICE; SATISFACTION

42. Each undersigned representative of the United States and of
Defendants certifies that they are fully authorized to enter into the terms and
conditions of this Stipulation and to execute-and legally bind such Party to the
document. This Stipulation may be signed in counterparts and its validity may not
be challenged on that basis.

43. Defendants hereby agree that the person identified to receive Notice
under Section IX (Notice) is authorized to accept service by mail on behalf of
Defendants with respect to service of the Complaint, Stipulation, and any related
filings with the Court. Defendants hereby agree to accept service in that manner
and to waive the formal service requirements set forth in Rule 4 of the Federal
Rules of Civil Procedure and any applicable local rules of this Court, including but

not limited to service of a summons.

22

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 23 of 25.

XI. FINAL JUDGMENT

44. Upon the Effective Date, this Stipulation shall constitute a final
judgment between the United States and Defendants under Fed. R. Civ. P. 54 and
58.

XIV. APPENDICES

45. The following Appendices are attached to and are a part of this

Stipulation:
“Appendix A” is the Government-Approved Remedy Plan

“Appendix B” is the Kuntz Contract

Dated and entered this 9th day of February, 2026

Lew Pi b tts

‘UNITED STATES DISTRICT JUDGE

23

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 24 of 25

FOR THE UNITED STATES OF AMERICA:

ADAM R.F,. GUSTAFSON

Principal Deputy Assistant Attorney General
Environment and Natural Resources Division
U.S. Department of Justice

JEFFREY K. SANDS
Deputy Section Chief
Environment and Natural Resources Division
U.S. Department of J ustice
: Digitally signed by JONAH

JONAH BROWN
/ S / Date? 2026.02.05 13:28:47 -07'00°
JONAH P. BROWN
Trial Attorney
Environment and Natural Resources Division
Environmental Enforcement Section
U.S. Department of Justice
Washington, D.C. 20044-7611
Email: Jonah.brown@usdoj.gov

24

Case 1:26-cv-00012-SPW Document4 Filed 02/09/26 Page 25 of 25

FOR DEFENDANTS:

/S/ Lee Andreas
LEE ANDREAS

25

Continue sua pesquisa no ChatGPT ou Claude

Conecte o Omnilex para pesquisar o corpus jurídico pelo seu assistente de IA.