UNITED STATES DISTRICT COURT
SOUTHERN DISTRICT OF CALIFORNIA
UNITED STATES OF AMERICA,
Plaintiff,
v.
CITY OF SAN DIEGO, et al.,
Defendants.
__________________________________
AND RELATED CROSS-ACTION.
Case No.: 23cv0541-LL-VET
ORDER GRANTING UNITED
STATES’ MOTION FOR PARTIAL
SUMMARY JUDGMENT ON
RECOVERY OF RESPONSE COSTS
FROM THE CITY OF SAN DIEGO
UNDER CERCLA
[ECF No. 154]
Before the Court is Plaintiff United States of America’s (“United States”) motion
for partial summary judgment on the recovery of response costs from Defendant City of
San Diego’s (“City”) under the Comprehensive Environmental Response, Compensation,
and Liability Act (“CERCLA”). ECF No. 154 (“Motion”). The matter is fully briefed, and
the Court deems it suitable for determination on the papers and without oral argument
pursuant to Civil Local Rule 7.1. For the reasons below, the Court GRANTS the United
States’ Motion.
/ / /
/ / /
/ / /
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 1 of 11
2
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
I. 	BACKGROUND
A. Factual Background
The United States filed the instant cost recovery action under CERCLA to recover
$17,131,016.38 in response costs the United States incurred in connection with the Navy
Boat Channel Site (“Site”) at the former San Diego Naval Training Center. United States’
Statement of Undisputed Material Facts1 (hereinafter “SOF”) ¶ 1, ECF No. 154-2.
Specifically, the United States Navy (“Navy”) incurred at least $15,944,926.65 through
July 31, 2023, and the United States Department of Justice (“DOJ”) incurred at least
$1,186,089.73 through October 31, 2024. Id. The response costs include contracts that the
Navy entered into with contractors such as Bechtel Environmental, Inc. to perform
remedial investigation activities and Parsons Government Services to develop the remedial
design and implement the remedial action. Id. ¶ 3. The DOJ also incurred direct and indirect
costs associated with the enforcement-related legal services it has provided to the Navy for
the Site. Id. ¶ 4. On December 27, 2016, the United States sent the City a written demand
for payment of all response costs incurred and to be incurred. Id. ¶ 5.
B. Procedural Background
On March 27, 2023, the United States commenced the underlying action to seek
reimbursement for the costs the Navy incurred in connection with the cleanup of the
Site. ECF No. 1. In April 2024, the United States settled with defendants San Diego Unified
Port District (“Port District”) and San Diego County Regional Airport Authority (“Airport
Authority”) for $2,412,029.89, plus interest. ECF No. 65. On June 18, 2024, the Court
approved the consent decree and entered a final judgment between those parties, thereby
leaving the City as the only remaining defendant in this case. ECF Nos. 67–69.
On August 28, 2025, this Court granted United States’ motion for partial summary
1 The City failed to respond to the United States’ Statement of Undisputed Facts and instead
inserted its own unrelated facts. Because the City failed to dispute the United States’ facts,
the Court will deem those facts undisputed. See Civil Chamber Rules at 5–6.
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 2 of 11
3
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
judgment on the City’s prima facie liability under CERCLA § 107(a) for cost recovery but
denied it on the City’s future liability under § 113(g)(2) for declaratory judgment. ECF No.
190. The United States filed the instant motion to recover $17,131,016.38 in response costs.
II. 	LEGAL STANDARD
“The court shall grant summary judgment if the movant shows that there is no
genuine dispute as to any material fact and the movant is entitled to judgment as a matter
of law.” Fed. R. Civ. P. 56(a). A fact is “material” when it “might affect the outcome of
the suit under the governing law,” and a dispute over a material fact is “genuine” when
“the evidence is such that a reasonable jury could return a verdict for the nonmoving party.”
Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). “The mere existence of a
scintilla of evidence . . . will be insufficient; there must be evidence on which the jury
could reasonably find for [the opposing party].” Id. at 252.
The moving party bears the initial burden of identifying those parts of the pleadings
and record “which it believes demonstrate the absence of a genuine issue of material fact.”
Celotex Corp. v. Catrett, 477 U.S. 317, 323 (1986). If a movant carries this burden of
production, then the non-movant must designate “specific facts showing that there is a
genuine issue for trial.” Id. at 324. In judging the evidence at the summary judgment stage,
the court does not make credibility determinations or weigh conflicting evidence. T.W.
Elec. Serv., Inc. v. Pac. Elec. Contractors Ass’n, 809 F.2d 626, 630 (9th Cir. 1987). Rather,
it draws all inferences in the light most favorable to the nonmoving party. Id. at 630–31.
However, 	“[c]onclusory, 	speculative 	testimony 	in 	affidavits 	and 	moving 	papers 	is
insufficient to raise genuine issues of fact and defeat summary judgment.” Soremekun v.
Thrifty Payless, Inc., 509 F.3d 978, 984 (9th Cir. 2007). Nor is it our task “to scour the
record in search of a genuine issue of triable fact;” we may “rely on the nonmoving party
to identify with reasonable particularity the evidence that precludes summary judgment.”
Keenan v. Allan, 91 F.3d 1275, 1279 (9th Cir. 1996).
/ / /
/ / /
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 3 of 11
4
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
III. 	DISCUSSION
A. National Contingency Plan
Section 107(a)(4)(A) of CERCLA allows the United States to recover “all costs of
removal or remedial action incurred by the United States Government . . . not inconsistent
with the national contingency plan.” 42 U.S.C. § 9607(a)(A)(4). The national contingency
plan (“NCP”), promulgated by the EPA as required by CERCLA § 105, 42 U.S.C. § 9605,
“provide[s] the organizational structure and procedures for preparing for and responding
to . . . releases of hazardous substances, pollutants, and contaminants.” 40 C.F.R. § 300.1.
It outlines “specific steps parties must take in choosing a remedial action plan and cleaning
up hazardous waste.” Carson Harbor Vill. v. Cnty. of Los Angeles, 433 F.3d 1260, 1265
(9th Cir. 2006); see also Washington State Dep’t of Transp. v. Washington Natural Gas
Co., Pacificorp, 59 F.3d 793, 799 (9th Cir.1995) (stating that the NCP “identifies methods
for investigating the environmental and health problems resulting from a release or
threatened release and criteria for determining the appropriate extent of response activities”
(citation omitted)). “The NCP is designed to make the party seeking response costs choose
a cost-effective course of action to protect the public health and the environment.”
Washington State, 59 F.3d at 802.
“[W]hen the United States government . . . is seeking recovery of response
costs, consistency with the NCP is presumed.” Washington State, 59 F.3d at 799–800
(citing United States v. Hardage, 982 F.2d 1436, 1442 (10th Cir. 1992)). Therefore, the
objecting party has the burden of proving inconsistency with the NCP. Washington State,
59 F.3d at 800. To prove that the costs of the United States government’s response action
was inconsistent with the NCP, the objecting party must prove that the government’s
selection of the response action was “arbitrary and capricious or otherwise not in
accordance with law.” 42 U.S.C. § 9613(j)(2); Washington State, 59 F.3d at 802.
Given that the United States established a prima facie case under CERCLA § 107(a)
(see ECF No. 190), the burden is now on the City to show that the Navy’s selection of the
response action was arbitrary and capricious or otherwise not in accordance with law. The
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 4 of 11
5
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
City failed to do so.
B. The United States Properly Documented Its Costs
Under the NCP, the lead agency is required to complete and maintain documentation
to support cost recovery actions:
During all phases of response, the lead agency shall complete and
maintain 	documentation 	to 	support 	all actions 	taken 	under
the NCP and to form the basis for cost recovery. In general,
documentation shall be sufficient to provide the source and
circumstances of the release, the identity of responsible parties,
the response action taken, accurate accounting of federal, state,
or private party costs incurred for response actions, and impacts
and potential impacts to the public health and welfare and the
environment.
40 C.F.R. § 300.160(a)(1). Proving that costs are unreasonable, excessive, or unnecessary
does not show inconsistency with the NCP. See Hardage, 982 F.2d at 1443 (rejecting
defendant’s argument that an individual cost is excessive or unreasonable demonstrates
inconsistency with the NCP); United States v. Northeastern Pharm. & Chem. Co., 810 F.2d
726, 748 (8th Cir. 1986) (“CERCLA does not refer to ‘all reasonable costs’ but simply to
‘all costs.’”); United States v. Iron Mountain Mines, Inc., 812 F. Supp. 1528, 1542–43
(E.D. Cal. 1992) (“Because the statute provides that all costs may be recovered, courts have
rejected the defense of failure to mitigate damages.”).
Generally, response costs include, inter alia, the costs of investigations, clean-up,
sampling, testing, security fencing and other measures to limit access, and enforcement
activities. See 42 U.S.C. § 9601(25); Cadillac Fairview/California, Inc. v. Dow Chem. Co.,
840 F.2d 691, 695 (9th Cir. 1988); Wickland Oil Terminals v. Asarco, Inc., 792 F.2d 887,
892 (9th Cir. 1986). The United States may also recover overhead or indirect costs. See
Iron Mountain, 812 F. Supp. at 1543.
1. Navy Costs
The United States seeks $15,944,926.65 in direct costs the Navy incurred for site
investigations and remedial actions performed by various Navy contractors through July
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 5 of 11
6
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
31, 2023. Mot. at 5. The United States claims that this amount is the difference between
$16,118,872.24 (the total Navy contractor costs) and $173,945.59 (a portion of the total
amount that the City’s cost accounting expert, Mr. Jason Kubota, challenges). Id. at 6. The
City does not argue that the United States should not be entitled to this amount. See
generally Opp’n.
The United States did not deduct $2,721,794.92 that Mr. Kubota also challenges
because it claims that Mr. Kubota’s opinion was “uninformed and grounded in a basic
misunderstanding of the types of documents that support the Navy’s incurrence and
payment of costs to its various contractors.” Mot. at 10. Based on the evidence submitted
by the United States, this Court agrees.
Mr. Kubota claims that $2,721,794.92 is not recoverable because no invoice or proof
of payment was provided by the United States or cited by United States’ cost accounting
expert Mr. Wiley R. Wright. Kubota Report, ECF No. 154-3 at 39–46; Kubota Tr. 26:12–
28:9, ECF No. 154-3 at 98. For example, Mr. Kubota states that for the $556,574.90 that
was incurred for Contract No. N68711-92-D-4670, Task Order 0092 from Bechtel
National, Inc., “no invoices under this contract/task order were provided by the US, cited
by Mr. Wright, or found in our search of the US’ production.” However, Mr. Wright stated
in his report that a contractor close out package, which was produced by the United States
as USN_0532936, included all the invoices for that specific task order. ECF No. 154-4 at
47. In fact, Mr. Wright listed every single invoice number in his schedules that were
attached at the end of his report. See id. at 43–59.
When asked about these closeout packages, Mr. Kubota replied that “The origins of
[] these pages and what they mean was not clear to me.” See Kubota Tr. 38:3–40:7, ECF
No. 154-3 at 99. Mr. Kubota further testified that he did not understand that the closeout
packages were prepared and submitted by the contractors even though the contractor’s
name and logo were prominently displayed on the documents. Kubota Tr. 40:5–41:18, ECF
No. 154-3 at 99. “Where the record taken as a whole could not lead a rational trier of fact
to find for the nonmoving party, there is no ‘genuine issue for trial.’” Matsushita Elec.
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 6 of 11
7
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Industrial Co., Ltd. v. Zenith Radio Corp. (1986) 475 US 574, 586-87. Here, Mr. Kubota
cannot feign ignorance to create a discrepancy of $2.7 million when the evidence states
otherwise. “The very object of summary judgment is to separate real and genuine issues
from those that are formal or pretended, so that only the former may subject the moving
party to the burden of trial.” Radobenko v. Automated Equip. Corp., 520 F.2d 540, 544 (9th
Cir. 1975) (fact that there were inconsistencies between deposition given by plaintiff under
oath and affidavit which he filed in opposition to motion for summary judgment did not
create genuine issues of material fact precluding summary judgment); see also Anderson,
477 U.S. at 247–48 (“the mere existence of some alleged factual dispute between the parties
will not defeat 	an otherwise properly supported 	motion 	for summary judgment”);
Accordingly, the Court finds that Mr. Kubota’s misunderstanding or failure to investigate
these closeout packages, especially after Mr. Wright cited to specific documents, does not
create a genuine dispute of material fact.
As for the missing proof of payment, Mr. Kubota continued his refusal to investigate.
When asked why he did not credit certain evidence of payment, Mr. Kubota explained that
he was “unclear” whether “DAY PD” referred to “days to pay” or “the date of payment.”
Kubota Tr. 91:7–92:25, ECF No. 154-3 at 105. Instead of asking for clarification from the
Navy or analyzing the data based on the two definitions he debated, Mr. Kubota decided
to completely disregard the evidence. Again, this type of speculative testimony is
insufficient to raise a genuine issue of material fact.
Next, the Court analyzes whether the Navy adequately documented its response
action and the costs incurred. Here, the United States submitted the Navy’s itemized cost
summary, which lists the names of the contractors, contract numbers, descriptions of the
work performed, total amount billed, and total amount claimed. See ECF No. 154-3 at 6–
7. Further, the tables following the cost summary list all of the contractor invoice numbers,
dates of the invoice, invoiced amounts, dates paid, and amounts claimed. Id. at 8–23.
Numerous courts have taken the same approach to assessing the adequacy of CERCLA
cost documentation. See, e.g., Cal. Dep’t of Toxic Services v. Neville Chem. Co., 213 F.
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 7 of 11
8
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
Supp. 2d 1134, 1140–41 (C.D. Cal. 2002) (contractor invoices sufficient to document
contract costs); Hardage, 982 F.2d at 1443 (10th Cir. 1992) (summaries of cost data
sufficient); United States v. Chromalloy American Corporation, 158 F.3d 345, 352 (5th
Cir.1998) (detailed cost summaries supporting its oversight expenses); United States v.
Chrysler 	Corp., 	168 	F. 	Supp. 	2d 	754, 	769, 	774 	(N.D. 	Ohio 	2001) 	(contractor
vouchers/invoices, invoice approval forms, and Treasury schedules).
Moreover, the Navy’s costs have been independently verified by the United States’
expert Mr. Wiley Wright, a Certified Public Accountant who ensured that each claimed
cost was incurred, paid, and properly documented. ECF No. 154-4, Exhibit A. Thus, this
Court finds that the evidence presented by the United States is sufficient to provide an
accurate accounting of the Navy’s response costs.
2. DOJ Costs
The United States seeks $1,186,089.73 as direct and indirect costs that the DOJ
incurred 	through 	October 	31, 	2024. 	Mot. 	at 	6–7. 	This 	is 	the 	difference 	between
$1,219,927.76 (the total DOJ enforcement costs) and $33,838.04 (the amount that the
City’s expert, Mr. Kubota, challenges). Id. at 6. Again, the City completely fails to argue
that the United States is not entitled to this amount. See generally Opp’n.
In CERCLA actions, the United States is entitled to all response costs, including
enforcement costs like attorney fees and litigation expenses incurred by the EPA and the
DOJ. See 42 U.S.C. § 9601(25); United States v. Chapman, 146 F.3d 1166, 1175 (9th Cir.
1998) (costs including legal work are recoverable); Neville, 213 F. Supp. 2d at 1137
(litigation and indirect costs recoverable).
Here, the United States submitted its expert witness William Kime’s declaration
which summarized the DOJ cost documentation for this case, including direct costs
incurred (e.g., employee payroll, travel, expert witness fees, deposition transcripts), other
litigation support expenses, and indirect costs. ECF No. 154-5 at 2–4, ¶¶ 9–20; at 9. His
declaration also included as exhibits DOJ employees’ time entries from November 4, 2022
to October 31, 2024; FY 2023 Year-end Closeout Accounting Memorandum (which
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 8 of 11
9
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
included EPA Billing Summary, Superfund Case Cost Summary, Superfund Cases Time
by Attorney/Paralegal, and Superfund Direct Costs for fiscal year 2023); and an audit of
the Superfund Activities in Environment Natural Resource Division for fiscal years 2021
and 2022. ECF No. 154-5 at 10–137. Accordingly, this Court finds that the evidence
presented by the United States is sufficient to provide an accurate accounting of the DOJ’s
response costs. See Chapman, 146 F.3d at 1171–72 (timesheets, cost estimates, and
accountant and attorney declarations were sufficient to show documentation consistent
with NCP).
3. Prejudgment Interests
The United States also seeks prejudgment interest on Navy’s costs. Mot. at 7. The
City, again, does not dispute this. See generally Opp’n. CERCLA provides that “amounts
recoverable in an action under this section shall include interest,” and that “[s]uch interest
shall accrue from the later of (i) the date payment of a specified amount is demanded in
writing, or (ii) the date of the expenditure concerned.” 42 U.S.C. § 9607(a). Here, the
United States claims that it sent its written demand for payment on December 27, 2016 and
therefore the prejudgment interest must start from then. Mot. at 7. However, the statute
allows interest to accrue from the later of (1) the date of the written demand or (2) the date
of the expenditure. Since the Navy conducted the remedial action between late 2017 and
2019 (Pl.’s Amended Compl. ¶ 48, ECF No. 25), the interest will accrue from 2019, not
2016.
C. The Navy’s Response Cost Was Not Inconsistent with the NCP
As discussed earlier, when the United States is seeking response costs, consistency
with the NCP is presumed. Washington State, 59 F.3d at 799–800. To prove that the
Navy’s response cost was inconsistent with the NCP, the City must establish that the Navy
acted arbitrarily and capriciously in choosing a particular response action to respond to a
hazardous waste site. See 42 U.S.C. § 9613(j)(2); Washington State, 59 F.3d at 802. The
arbitrary and capricious standard is “highly deferential,” and the Court “may not substitute
its judgment for that of the agency.” Fireman’s Fund Ins. Co. v. City of Lodi, California,
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 9 of 11
10
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
302 F.3d 928, 949 (9th Cir. 2002).
The City does not claim that the Navy acted arbitrarily and capriciously. See
generally Opp’n. Thus, the Court finds that the City did not meet its burden of proving
inconsistency with the NCP by failing to make any argument that the Navy’s selection of
the response action was arbitrary and capricious, or otherwise not in accordance with law.
Therefore, the City failed to set forth a genuine dispute of material fact as to whether the
Navy’s action was inconsistent with the NCP, and thus, this Court GRANTS the United
States’ Motion. Accordingly, the United States is entitled to $17,131,016.38 in response
costs.2
D. City’s Argument
Instead of responding to the United States’ arguments, the City argues that the
United States cannot bring a CERCLA § 107 claim and that it can only seek to recover its
costs under CERCLA § 113 because the United States is a “potentially responsible party”
(“PRP”). Opp’n. at 4. The Court does not find these arguments relevant to the United
States’ Motion and declines to address them fully.
In short, CERCLA allows a party to bring a contribution claim under § 113 in two
circumstances: “during or following” being sued in a § 107 cost recovery action, and after
the party “has resolved its liability to the United States or a State . . . in an administrative
or judicially approved settlement.” 42 U.S.C. § 9613(f)(1), (3)(B); see also Whittaker Corp.
v. United States, 825 F.3d 1002, 1008 (9th Cir. 2016) (“[Section] 113(f) generally allows
a polluter to bring a contribution claim against other polluters if the polluter has been sued
in a § 107 cost recovery action or settled with the government.”). The Court agrees with
the 	United 	States 	that 	“because 	the 	United 	States 	meets 	neither 	of 	the 	statutory
requirements to bring a § 113 contribution claim, it cannot bring such a claim.” Reply at 4.
/ / /
2 The City’s concern about “double recovery” (Opp’n. at 9) will be addressed in the future
when the Court calculates how much of those costs the City will actually be liable for.
Case 3:23-cv-00541-LL-VET Doc 223 Filed 03/24/26 PgID.<pageID> Pg 10 of 11
11
23cv0541-LL-VET
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
IV. 	CONCLUSION
The United States has presented evidence documenting the costs it incurred in
responding to the release of hazardous substances. The City failed to raise any genuine
dispute of material fact regarding whether the Navy’s response cost was inconsistent with
the NCP. Therefore, the United States’ motion for summary judgment is GRANTED.
IT IS SO ORDERED.
Dated: March 24, 2026