2026TLN00036•DO-DECISION AND ORDER ON THE MERITS NUMBER OF PAGES 20 JUDGE SWANK - Decision and Order Affirming the Certifying Officers Denial of Temporary Labor Certification — 2026TLN00036
DO-DECISION AND ORDER ON THE MERITS NUMBER OF PAGES 20 JUDGE SWANK - Decision and Order Affirming the Certifying Officers Denial of Temporary Labor Certification — 2026TLN00036
2026TLN00036Dol Oalj
Texto completo
UNITED STATES DEPARTMENT OF LABOR BOARD OF ALIEN LABOR CERTIFICATION APPEALS Washington, DC ______________ Issue Date: 07 April 2026 BALCA CASE No.: 2026-TLN-00036 ETA No.: H-400-26001-524410 In the Matter of: BECHTEL ENERGY CONSTRUCTION SERVICES, INC. Employer. Appearances: Jay C. Ruby, Esq. For the Employer Office of the Solicitor U.S. Department of Labor Washington, D.C. For the Certifying Officer Before: Drew A. Swank Administrative Law Judge DECISION AND ORDER AFFIRMING THE CERTIFYING OFFICER’S DENIAL OF TEMPORARY LABOR CERTIFICATION This case arises from the request for review of Bechtel Energy Services, Inc. (“Employer”) of the Certifying Officer’s (“CO”) February 24, 2026 Final Determination denying its application for temporary alien labor certification under the H-2B non-immigrant program. The H-2B program permits employers to hire foreign workers to perform temporary nonagricultural work within the United States on a one-time occurrence, seasonal, peakload, or intermittent basis, as defined by the United States Department of Homeland Security (DHS). See 8 U.S.C. § 1101(a)(15)(H)(ii)(b); 8 C.F.R. § 214.2(h)(6);1 20 C.F.R. § 655.6(b).2 Employers who seek to hire foreign workers under this 1 The definition of temporary need is governed by 8 C.F.R. § 214.2(h)(6)(ii)(B). Consolidated Appropriations Act, 2016, Pub. L. No. 114‐113, Division H, Title I, § 113 (2015). This definition has remained in place through subsequent appropriations legislation, including the current legislation. See Consolidated Appropriations Act, 2026, Pub. L. No. 119- 75, Division B, Title I, § 111 (2026). 2 On April 29, 2015, the Department of Labor (“DOL”) and the Department of Homeland Security jointly published an Interim Final Rule (“IFR”) amending the standards and procedures that govern the H-2B temporary labor certification program. See Temporary Non-Agricultural Employment of H-2B Aliens in the United States; Interim Final Rule, 80 Fed. Reg. 24,042 et seq. (Apr. 29, 2015). The rules provided in the IFR apply to applications “submitted on or after April 29, 2015, and that have a start date of need after October 1, 2015.” IFR, 20 C.F.R. §655.4(e). All citations to 20 C.F.R. Part 655 in this opinion and order are to the IFR.
- 2 -
program must apply for and receive labor certification from the United States Department of Labor
using a Form ETA-9142B, Application for Temporary Employment Certification (“Form 9142”). A
CO in the Office of Foreign Labor Certification (“OFLC”) of the Employment and Training
Administration reviews applications for temporary labor certification. Following the CO’s denial of
an application under 20 C.F.R. § 655.53, an employer may request review by the Board of Alien
Labor Certification Appeals (“BALCA” or “the Board”). 20 C.F.R. § 655.61(a).
BACKGROUND
On January 1, 2026, the Department of Labor’s Employment and Training Administration
(“ETA”) received an application for temporary labor certification from Employer requesting
certification for 275 Pipefitter Journeyman workers for the period of April 1, 2026 to December 31,
2026, under the SOC code of “Plumbers, Pipefitters, and Steamfitters.” AF 180-242.3 Employer
indicated that the nature of its temporary need is “peakload.” In regard to its statement of temporary
need, and its request for labor certification, Employer stated:
Bechtel Energy Construction, Inc. ("Bechtel") has a temporary need for 275 additional
Pipefitter Journeymen to work at its Rio Grande LNG project in the
Port Isabel, Texas (Brownsville) during its pipefitting phase of the project from April
1, 2026, to December 31, 2026. This temporary need is based upon a peakload need
as per Federal Regulations 8 CFR 214.2 (h)(6)(ii)(B)(3). Bechtel’s demand for
temporary supplemental pipefitter journeymen is based upon a short-term peakload
need to cover its peak pipefitting phase of the Rio Grand LNG project. Attached as
Exhibit 2 is a signed summarized payroll record for Bechtel energy construction
Services listing the number of permanent and temporary pipefitter journeymen, total
hours worked, and total earnings received monthly for the period of January 2023
through November 2025. Bechtel did not have any pipefitter journeyman workers
employed at the Rio Grande LNG terminal until August 2023 (starting with 4
pipefitters). The number rose to 65 pipefitters in December 2024 and is currently at
491 as of November 2025. Attached as Exhibit 3 is the staffing forecast curve for
pipefitters at the Rio Grande LNG project (RGLNG) and the number of pipefitters
needed will spike from approximately 1300 pipefitters starting in April 2026 to
approximately 1800 pipefitters in September 2026 and drop back below 1300
pipefitters after December 2026. The peakload need or demand for additional
temporary pipefitters to supplement Bechtel’s permanent cadre of pipefitters at the
RGLNG is approximately 500 pipefitters of which Bechtel will require 275
supplemental H-2B workers.
The forecasted headcount for Pipefitters takes into account U.S. worker Pipefitters to
be engaged for the majority of the Pipefitter workforce. However, the Rio Grande
LNG project is so unusually large that Bechtel will not be able to complete the peak
of the pipefitting phase without the additional 275 H-2B Pipefitter Journeymen.
3 References to the appeal file will be abbreviated with an “AF” followed by the page number.- 3 - Bechtel has a temporary need which meets the criteria of establishing a temporary need as set forth in Federal regulations 8 CFR 214.2 (h)(6)(ii)(B)(3) … Bechtel regularly employs permanent Journeyman Pipefitters but has a short-term demand of 9 months (completion of the pipefitting phase at the Rio Grande LNG project) - an event of short duration. The need for additional pipefitters is above and beyond even an established engineering/construction firm would normally experience. Bechtel will not have a need for the supplemental H-2B Journeyman Pipefitters in Brownsville, TX after December 31, 2026. Thus, the supplemental Journeyman Pipefitters will not become part of Bechtel's regular, year-round staff. Bechtel's need is clearly not a "permanent need" for temporary services or labor because there is a definite duration of less than one year. AF 186. The CO issued a Notice of Deficiency (“NOD”) on January 11, 2021, listing two deficiencies in the Employer’s application. AF 171-179. The CO noted the first deficiency as the Employer’s failure to “establish the job opportunity as temporary in nature.” 20 C.F.R. §§ 656.6(a) and (b). The CO explained that “an employer must establish that its need for non-agricultural services or labor is temporary, regardless of whether the underlying job is permanent or temporary.” AF 176. The CO noted that an employer’s need is considered temporary if it is justified to the CO as one of the following: (1) a one-time occurrence; (2) a seasonal need; (3) a peak load need; or (4) an intermittent need; as defined by DHS (Department of Homeland Security) regulations. The CO stated that employment is of a temporary nature when the employer needs a worker for a limited period of time, noting that the DHS regulation the employer must establish that the need for the employee will end in the near definable future. The CO further stated that the Department of Labor has consistently viewed temporary need as defined in the DHS regulation as lasting no more than ten months, except in the case of a one-time occurrence which pursuant to the regulation may last up to three years. The regulation states regarding the length of temporary need, “that period of time will be limited to one year or less, but in the case of a one-time event could last up to 3 years.’’ 8 CFR § 214.2(h) (6)(ii)(B) (emphasis added). The CO noted that in this case, the employer has requested 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026 based on a peakload need. The CO noted that, in order to establish a peakload need, the Employer must establish that it regularly employs permanent workers to perform the services or labor at the place of employment, that it needs to temporarily supplement its permanent staff at the place of employment due to a seasonal or short-term demand, and that the temporary additions to staff will not become part of the Employer’s regular operation. The CO stated that statements and supplemental documentation provided by the Employer indicate that its temporary need is based on a specific Rio Grande LNG project. However, the CO noted that it appears that the Employer is in the business of soliciting and securing contracts on an ongoing and continuing basis. Therefore, the CO determined it is reasonable to expect that the employer will continue to be in the business of continually performing similar services as required. Further the CO noted it is unknown what other projects requiring pipefitter journeyman workers the employer has worked on
- 4 - in the past, is currently working on, and is contracted to work on in the future therefore making it difficult to determine how its single project has caused a temporary peakload need for the workers requested during the requested period of April 1, 2026 to December 31, 2026. The CO also noted that Employer indicates that the “completion of the pipefitting phase at the Rio Grande LNG project” is an event of short duration which causes it to experience a short-term demand of 9 months. However, the CO pointed out that the nature of the contract/project that the Employer will be performing does not necessarily define the nature of the employer’s need, noting that most contracts are for a limited duration. Therefore, the CO found that it remains unclear what seasonal or short-term demand leads to the Employer experiencing a peakload temporary need. Accordingly, the CO determined that further explanation and documentation was required to establish the Employer’s need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026. Specifically, the CO requested the following: 1. A statement describing the employer’s business history, activities (i.e. primary products of services), and schedule of operations throughout the year; 2. A summary listing of all projects in the area of intended employment for the 2024 and 2025 calendar years. The summary should include start and end dates of each project, worksite addresses and the number of Pipefitter Journeyman workers employed for each project; 3. An explanation of how a single contract (or contracts) represents a peakload need when the employer is in the business of securing contracts for services on an ongoing basis. This must include an explanation with supporting documentation of how the employer determined it would not receive other contracts requiring additional Pipefitter Journeyman workers during different peakload periods in the future; 4. Contracts for all the identified projects in the employer’s summary that indicate the worksite/project. The contracts must also include a description of the work to be performed and signatures of all appropriate parties; 5. Updated summarized monthly payroll reports for the complete 2025 calendar year that identify, for each month and separately for full-time permanent and temporary employment in the requested occupation Pipefitter Journeyman workers, the total number of workers or staff employed, total hours worked, and total earnings received and such documentation must be signed by the Employer attesting that the information was compiled from the Employer’s actual accounting records or system; 6. An explanation of the data in the submitted payroll documentation. In addition, the CO requested other evidence and documentation that similarly serves to justify the dates of need being requested. AF 177-178. In regard to the second deficiency – Failure to establish temporary need for the number of workers requested, the CO cited 20 C.F.R. §§ 655.11(e)(3)-(4), 655.1(a)(1) and 655.6. The CO determined that Employer had not sufficiently demonstrated that the number of workers requested on the application is true and accurate, and represents bona fide job opportunities. The CO stated: [T]he Department needs to know how many bona fide job opportunities are available so that it can determine whether ‘there are not sufficient U.S. workers who are
- 5 - qualified and who will be available to perform the temporary services.’ 20 CFR 655.1(a)(1); 8 USC 1101(a)(15)(H)(ii)(b); 8 USC 1184(c)(1). Temporary need, including the number of workers, is adjudicated during the processing of applications. 20 CFR § 655.11(j). AF 178. Specifically, the CO stated that the Employer did not provide documentation such as contracts that confirm the need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026. Again, the CO requested further explanation and supporting documentation including contracts, letters of intent, etc. that specify the number of workers and dates of need. In addition, the CO requested updated summarized monthly payroll reports for the complete 2025 calendar year that “identify for each month, and separately for full-time permanent and temporary employment in the requested occupation, as well as the total number of workers, total hours worked, and total earnings received,” as well as an explanation of the data in the submitted payroll records and other documentation supporting and justifying the number of workers requested. AF 179. Employer submitted its response to the Notice of Deficiency on February 5, 2026. Employer’s response included a cover letter and multiple exhibits in support of its position. AF 54-170. In its response letter Employer elaborated on its business noting that it was founded in 1898 and was ranked, in 2022, as the second largest construction company in the United States, and that it has over 50,000 employees as of May 2025. It further noted that Bechtel’s Energy unit (which Bechtel Energy Construction is part of) designs and builds liquefied natural gas (LNG), oil, pipeline, petrochemicals, natural gas, and water treatment facilities. Employer notes that since its founding it has built approximately 50,000 miles of pipeline systems, more than 50 major oil and gas field developments and over 380 major chemical and petrochemical projects. It also constructs and tests tanks for LNG storage and has built a third of the world’s LNG liquefaction capacity. Employer asserts that it is “heavily involved in the Liquefied Natural Gas industry, both in the U.S. and globally” and is known for its work on large-scale LNG projects including liquefaction plants and export terminals and has partnered with various companies like Cheniere Energy, Woodside Energy, and NextDecade on major LNG initiatives. Employer also provided information about the Rio Grande LNG (RGLNG) project which is a natural gas and export terminal situated on a 984-acre site on the banks of the Brownsville ship channel, noting that it is the largest privately funded LNG project in Texas. Employer states that the first phase of the RGLNG project consists of three liquefaction trains, two storage tanks and one marine berth. Employer attached as Exhibit 1, a summation of its activity in the Rio Grande Valley for 2024 and 2025. The Employer noted that the only project Bechtel Energy Construction Services has in the area of intended employment (Port Isabel/Brownsville TX MSA) is the Rio Grande LNG project for 2024 to the present. It stated that it attached as Exhibit 2, the contract for the construction for trains 4 and 5 of the RGLNG project. Employer discussed the regulatory definition of peakload need asserting that some peakload needs are recurring annually at the same time, but some peakload needs are unpredictable in nature, even if they are recurring. Accordingly, Employer argues that a single contract can create a short 0F
- 6 - term demand for workers and future possible contracts are not dispositive that an employer does not have recurring peakload needs. Employer states the following in regard to its alleged peakload need: What appears to be critical for proving a peakload need is that the employer regularly employs permanent workers to perform the services or labor and that it needs to supplement its permanent staff at the place of employment on a temporary basis due to a seasonal or short-term demand and that the temporary additions to staff will not become a part of the petitioner's regular operation. In addition, the employer should only need H-2B workers [ ] for a limited period, meaning that the need will end in the near, definable future. Bechtel Energy Construction regularly employs permanent Pipefitter Journeyman workers (as evidenced by the summarized payroll record and given its 127-year history including the construction of the Hoover Dam) and the contract to complete the Rio Grande LNG project has a near, definable future- and the pipefitting phase is only a portion of the construction. AF 61. Employer attached certain selected pages of its contract with Rio Grande LNG Train 5, LLC (Next Decade) as its Exhibit 2. Employer notes that the contract contains provisions about the scope of work to be performed by contractor Bechtel including supplying “a sufficient number of workers including Pipefitters.” AF 62. Employer notes that the project has a definitive end (substantial completion date) including the pipefitting phase, and if Bechtel Energy does not comply with the substantial completion, it is liable for liquidated damages. Employer also states that the work to be performed will entail piping requiring Pipefitter Journeymen. Employer attached Exhibits 7-9 which are copies of the NextDecade and Bechtel websites listing Bechtel as a contractor. Other documents attached to the Employer’s response include an updated signed summarized payroll report for the 2025 calendar year (Exhibit 3), a staffing forecast curve (Exhibit 4), slides explaining its alleged peakload need (Exhibit 5), affidavit attesting to how figures for the staffing forecast curve were derived, and an article from the Rio Grande Guardian Business Journal regarding the hiring of workers for the Rio Grande LNG project (Exhibit 10). Employer also addressed the second deficiency noted by the CO regarding a bona fide need for the number of workers requested. Employer noted that it attached its updated signed summarized payroll report for the 2025 calendar year, noting permanent and temporary employees at the Rio Grande LNG project as Exhibit 3. Employer states that its peakload need does not begin until April 2026 and therefore it does not have any temporary Pipefitter Journeyman workers to date, but that it will need them. It indicated that it does regularly employ permanent Pipefitter Journeyman workers. Employer states that it started with 4 pipefitters in August 2023, rising to 65 in December 2024 and currently has 482. It notes that the number of pipefitters needed will spike from approximately 1300 pipefitters in April 2026 to 1800 in September 2026 and drop below 1300 pipefitters after December 2026. Employer asserts that its peakload need or demand for additional temporary pipefitters to supplement Bechtel’s permanent cadre of pipefitters at the LNG project is approximately more than 500 pipefitters of which Bechtel will require 275 supplemental H-2B workers. Employer cited its attached Exhibits 4 – 6 in support of its position.
- 7 - On March 19, 2026, the CO issued a Final Determination-Denial to the Employer, finding that the two previously noted deficiencies remained. AF 36-53. In regard to the first deficiency (Employer’s failure to justify the nature of temporary need), the CO acknowledged the information submitted by the Employer but determined that the information did not overcome the deficiency. The CO cited statements in the Employer’s response in which it elaborated on its business history and its explanation as to why it believed its work on the RGLNG project represents a temporary peakload need for workers. The CO noted that Employer explained that it designs and builds liquified natural gas (LNG), oil, pipeline, petrochemical, natural gas, and water treatment facilities, including building a third of the world’s LNG liquefaction capacity and that it is heavily involved in the U.S. and globally as a leading engineering, procurement and construction company. The CO noted that the Employer describes its peakload need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026, as an event of short duration due to the pipefitting phase of the Rio Grande project peaking in September 2026 after which it begins to decrease. However, the CO noted that the Employer’s filing history and the documentation provided show that the Rio Grande LNG is a multiyear project requiring Pipefitter Journeyman workers that is not projected to be completed until 2029. The CO further noted that within the context of the Employer’s business operations it remains unclear how this specific phase of the Rio Grande LNG project creates a temporary need when the Employer has established that it is heavily involved in the liquefied natural gas industry. Accordingly, the CO found that it appears the Employer’s need is ongoing and not specific to a season or short-term demand. AF 44-45. The CO stated that this fact is further demonstrated by the Employer’s application filing history, noting that the Employer previously filed application, H-400-25184-150662, for 275 Pipefitter Journeyman workers for the same worksite for August 1, 2025, through March 15, 2027, based on a one-time occurrence temporary need. Although that application was denied, Employer had provided some additional insight into the overall Rio Grande LNG project. The CO pointed out that Employer had explained that it required 275 Pipefitter Journeyman workers for “Phases 1” of the project until March 15, 2027. A staffing forecast was also provided with the previous application showing the overall scope of the Rio Grande LNG (RGLNG) staffing forecast for pipefitters with an earlier phase ending in 2026 and trains 4 and 5 extending into 2029. The CO noted the following inconsistency in the Employer’s statements and documentation provided in its two applications: When looking at the scope of information provided with the previous and current applications for the Rio Grande LNG project, the presence of a peakload in demand for Pipefitter Journeyman workers from April 1, 2026, to December 31, 2026, appears to isolate a nine-month period within a minimum three-year project to fit within the definition of a peakload temporary need. It is unclear how in its previous application, the employer required 275 Pipefitter Journeyman workers until March 15, 2027, but now only requires them until December 31, 2026. The employer’s current explanation of the need for the 275 workers in its Explanation of Temporary Need slide presentation provided in its NOD response cites that 275 “Temporary Foreign Workers are requested to prevent a staffing shortfall at a critical point in the project life cycle.” The current staffing forecast showing 1,783 total Pipefitter Journeyman workers required at the purported peak in September of 2026, the 275 workers requested from April 1, 2026, to December 31, 2026, appears to be an arbitrary labor
- 8 - need during an overall project lasting over three years requiring well over 1,000 Pipefitter Journeyman workers. AF 46-47. The CO also determined that Employer did not provide further explanation for how these calculations were made, nor did Employer provide historical data or other supporting documentation to substantiate the employer's forecasted data. Accordingly, the CO determined that the Employer failed to justify how it calculated a need to temporarily supplement its permanent staff during this specific period. The CO also concluded that the Employer’s need for Pipefitter Journeymen will continue to vary depending on the timing and scope of the individual contracts that it secures. Accordingly the CO pointed out that the terms and scope of the contracts alone do not establish that the Employer’s underlying need is temporary in nature. The CO noted that Employer was instructed to provide a summary listing of all projects in the area of intended employment for the 2024 and 2025 calendar years and this summary was to include start and end dates of each project, worksite addresses and the number of Pipefitter Journeyman workers employed for each project. In response to this request the Employer stated that the Rio Grande project for trains 4 and 5 is the only project within the normal commuting distance of Port Isabel/Brownsville, TX. CO determined however that it found that the Rio Grande LNG project for trains 4 and 5 is not a singular project but rather a portion of an ongoing construction project for which Employer has employed Pipefitter Journeyman workers since August of 2023 as shown on its payroll report which has steadily increased since that date. Based on the documentation provided in its previous and current applications show that the project is anticipated to last into 2029 for trains 4 and 5 alone, with trains 6 -8 in development and per Employer’s representations, sufficient space exists at the site for development of tup to 10 liquefactions trains. Accordingly, the CO determined it can be reasonably expected that the need to complete future contractual obligations lie beyond the requested period of need. Further even if the Employer’s need is limited to work on the specific part of the larger project (trains 4 and 5) and the Employer will not secure any additional contracts on the Rio Grande project, the CO still concluded that the Employer’s true need “goes beyond the intended limited temporary duration of the H-2B program.” The CO concluded that the Employer’s need is in fact permanent and ongoing as it will continue to secure other contracts in the liquefied natural gas industry necessitating Pipefitter Journey man workers. Thus, the CO concluded that Employer failed to establish how its need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026 is temporary in nature under one of the regulatory standards found in the definition of temporary need. The CO noted that the employer’s statements throughout its NOD response do not refute that the Rio Grande LNG project is a large project spanning many years. Its discussion of its peakload temporary need only focuses on one moment in time during the overall project for which it has isolated an estimated temporary peakload in work volume for Pipefitter Journeyman workers. However, even when looking at this isolated period of time within the multiyear project, the CO found it is unclear how the employer determined the peak in work volume for Pipefitter Journeyman workers which it alleges occurs during the estimated dates requested, and not before or after. In this regard the CO noted that the partial contract that was provided shows no completion dates and therefore does not support the period of peakload need alleged.
- 9 - The CO cited the preamble to the interim Final Rule jointly published by the Department of Homeland Security (DHS) and the Department of Labor (DOL) which addressed the duration of temporary need, noting that the rule precludes employers from mischaracterizing a permanent need as one that is temporary by filing consecutive applications for workers on a peakload basis. See 80 Fed. Reg 24055024056 (Apr. 29, 2015). Thus, the CO reiterated that the Employer’s business practice is contingent on soliciting, securing and fulfilling contracts, and that the terms and scope of one contract or project alone do not establish that the Employer’s underlying need is temporary in nature. The CO noted that per the Employer’s statements it is heavily involved in the LNG industry as a leading construction company and that it appears that its need for Pipefitter Journeymen is ongoing and part of its regular operations. Further the CO noted that although Employer has indicated that it has difficulty finding a sufficient number of workers, a labor shortage alone does not indicate that the underlying need for labor is temporary. The CO determined that the Employer did not establish that its need is due to a seasonal or short-term demand, as required to prove a peakload need, nor did it establish how its need is temporary in nature under any of the other regulatory standards as defined by the applicable regulations. Accordingly, the CO determined that the Employer failed to prove its temporary peakload need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026, and therefore did not overcome the stated deficiency. Likewise, the CO determined that Employer failed to establish a temporary need for the number of workers requested. The CO again acknowledged the Employer’s response letter and the submitted documentation but determined that the explanation and documentation submitted did not overcome the deficiency. The CO noted that the Employer was directed in the NOD to provide documentation supporting its need for the 275 Pipefitter Journeyman workers such as contracts, letters of intent, etc. that specified the number of workers and dates of need. The CO found that Employer failed to provide the requested information. Instead, it provided an internal project timeline and head count estimations. The CO noted Employer’s statement that the RGLNG project will require 1,783 pipefitters at peak and that it discussed the labor market challenges resulting in its estimation that 275 of those workers may be “fillable by temporary foreign workers.” However, the CO concluded that these statements presented only general figures with no insight as to how the number of workers was calculated based on the specific work required. Also, the portions of the contract provided shows that the project requires Pipefitter Journeyman workers but all expected start and completion dates for the project are redacted from view. The CO concluded that the Employer provided no objective basis for the Department to analyze its estimates. Therefore, the CO determined Employer failed to establish its need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026. Accordingly, the Employer did not overcome the deficiency. On March 10, 2026, Employer filed a request for Administrative Review. AF 1-35. In its request for review Employer argues that the CO’s denial is arbitrary and capricious and should be reversed. Employer states that the CO did not apply the regulatory standard for “peakload need” and did not address whether a peakload need can be recurring. The Employer asserts that a peakload need may be recurring and should not be conflated with a one-time occurrence need. Employer asserts that although it is in the business of securing contracts for services on an ongoing basis, this should not be a basis for denying its alleged peakload need. Employer states that a single contract or project
- 10 - can create a short-term demand for workers and future possible contracts are not dispositive that an employer does not have recurring peakload needs. AF 4-5. Employer asserts that it meets the definition of peakload need as it employs permanent workers to perform the services or labor and it needs to supplement its permanent staff at the place of employment on a temporary basis due to a seasonal or short-term demand. Employer also states that it will only need the H-2B workers for a limited period of time, thus its need will end in the near definable future. Employer claims that the requirements of peakload need as they apply to the Employer were not adequately discussed by the CO. Employer states that although it will have other contracts requiring additional workers during different peakload periods in the future, this does not preclude a peakload need because a peakload need can be recurring. Employer states that future projects are not determinative of whether an employer has a peakload need. Employer asserts that the CO failed to consider the notarized affidavit of David Todd, Workforce Planning & Development Manager for Bechtel Energy Construction Services which was supplied as Exhibit 6 in Bechtel's response to the notice of deficiency. Employer argues that Mr. Todd explains how the total of 275 temporary foreign Pipefitter Journeyman workers was derived, as well as the staffing forecast curve and his estimation of the staffing peak (from Exhibit 4 and 5). Employer states the following regarding Mr. Todd’s affidavit: Mr. Todd explains that the staffing peak (from Exhibit 4 and Exhibit 5) for Pipefitter Journeyman workers will be approximately 1,783 Pipefitters in Q3 2026 and that an estimated 33% of the total pipefitters needed will be non-local (travelers and subcontractors) totaling 588 non-local pipefitters. Mr. Todd expects that 50% of these 588 Pipefitter positions (minus 50 subcontractors already working at the project) need to be filled by 275 temporary foreign workers (and/or US workers hired during the H- 2B recruitment process). AF 6. Employer argues that the CO fails to address that the 1,783 Pipefitter Journeyman workers for 2026 is above and beyond what Employer can staff during the peak phase of the pipefitting phase. Employer also explains that the provided contract does not specify the number of workers needed and dates of need because such contracts often do not explicitly define the specific number of workers or exact manpower levels, focusing instead on the final result, project timeline and price. Employer notes that this is because “the contractor is given the flexibility to determine the best method to deliver a conforming project at the set price and time, allowing them to manage their own staffing.” AF 7. Accordingly, Employer indicates it uses “S-curve modeling” which can be adjusted to reflect changes etc. Id. Employer also argues that the CO erred in determining that a multiyear project cannot have a peakload need for a specific occupation. Employer states that future peakload or short-term demands do not preclude an employer from establishing a present peakload need or short-term demand. Employer asserts that the CO is incorrectly applying the standard for a one-time occurrence to a peakload need. Employer argues that the Department is arbitrarily assuming that Bechtel will not be able to cover future projects or contracts with its permanent cadre of Pipefitter Journeyman workers or other sources, noting that even if Bechtel could not, it would still be eligible to establish a future
- 11 - peakload need. Employer asserts that the CO did not adequately consider its staffing forecast that was provided and explained by its Workforce Planning & Development Manager, David Todd, in his affidavit. Employer asserts that the CO improperly considered its prior application which requested 275 Pipefitter Journeyman workers between August 1, 2025 through March 15, 2027 for Phase 1 of the Rio Grand LNG project on the basis of a one-time occurrence. Employer states that each application should be considered on a case-by-case basis and should be reviewed on its own merits. Further as the Employer’s one time occurrence application was denied, Employer was within its rights to submit a second application asserting a peakload need for workers. Employer also argues that the CO imposed an improper legal standard. Employer notes that the correct standard is preponderance of the evidence and therefore the CO should have only required the Employer to prove it is more likely than not that it would need the services of 275 Pipefitter Journeymen from April 1, 2026, to December 31, 2026, in connection with the peak of its pipefitting phase of the Rio Grande LNG project in Port Isabel, Texas (Brownsville). Employer asserts that it has met its burden.4 By Order issued on March 24, 2026, the CO and the Employer were given the opportunity to file briefs in support of their positions on or before April 2, 2026. Employer submitted its brief with its request for review. No brief was submitted by the CO. SCOPE OF REVIEW BALCA has a limited scope of review in H-2B cases. Specifically, BALCA may only consider the appeal file prepared by the CO, the legal briefs submitted by the parties, and the employer’s request for review, which may contain only legal argument and such evidence as was actually submitted to the CO before the date the CO’s determination was issued. 20 C.F.R. § 655.61(a). After considering this evidence, BALCA must take one of the following actions in deciding the case: (1) Affirm the CO’s determination; or (2) Reverse or modify the CO’s determination; or (3) Remand to the CO for further action. 20 C.F.R. § 655.61(e). STANDARD OF REVIEW Neither the Immigration and Nationality Act, nor the regulations applicable to H-2B temporary labor certifications, identify a specific standard of review pertaining to an Administrative Law Judge’s review of determinations by the CO in H-2B matters. BALCA has, fairly consistently, applied an arbitrary and capricious standard to its review of the CO’s determination in H-2B 4 Although Employer claims the CO applied an incorrect legal standard to its consideration of the Employer’s application, the undersigned finds no basis for this claim and as will be discussed below the CO properly determined that Employer failed to meet its burden of proving its entitlement to temporary labor certification based on the record in this case.
- 12 - temporary labor certification cases. See Brook Ledge Inc., 2016-TLN- 00033 at 5 (May 10, 2016) (BALCA panel acknowledging that it reviewed the CO’s determination under an arbitrary and capricious standard). BALCA must be satisfied that the CO has examined “the relevant data and [has] articulate[d] a satisfactory explanation for its action including a rational connection between the facts found and the choice made.” See Custom Retaining Walls, LLC 2023 TLN 00057 (April 10, 2023) quoting Motor Vehicle Mfrs. Ass’n, Inc. v. State Farm Mut. Auto Ins. Co., 463 U.S. 29, 43 (1983). In reviewing the CO’s explanation, BALCA must “consider whether the decision was based on a consideration of the relevant factors and whether there has been a clear error of judgment.” Id. ISSUES 1) Whether the Certifying Officer properly denied the Employer’s H-2B applications due to Employer’s failure to establish that its request for 275 Pipefitter Journeyman workers for the period of April 1, 2026, to December 31, 2026, was based upon a “temporary” employment need, according to the Employer’s stated standard of “peakload need.” 2) Whether the Certifying Officer properly denied the Employer’s temporary labor certification application due to Employer’s failure to meet its burden of establishing its temporary need for 275 Pipefitter Journeyman workers for the period of April 1, 2026 to December 31, 2026. DISCUSSION In order to obtain temporary labor certification for foreign workers under the H-2B program the Employer is required to establish that its need for the requested workers is “temporary.” Temporary need is defined by the DHS regulation at 8 C.F.R. §214.2(h)(6)(ii). This regulation states: (A) Definition. Temporary services or labor under the H-2B classification refers to any job in which the petitioner’s need for the duties to be performed by the employee(s) is temporary, whether or not the underlying job can be described as permanent or temporary. 8 C.F.R. §214.2(h)(6)(ii)(A). The DHS regulation further states in regard to the nature of petitioner’s need: Employment is of a temporary nature when the employer needs a worker for a limited period of time. The employer must establish that the need for the employee will end in the near, definable future. Generally, that period of time will be limited to one year or less, but in the case of a one-time event could last up to 3 years. The petitioner’s need for the services or labor shall be a one-time occurrence, a seasonal need, a peakload need, or an intermittent need. 8 C.F.R. §214.2(h)(6)(ii)(B).
- 13 - In the current case, the Employer is applying for temporary labor certification for 275 Pipefitter Journeyman workers for the period of April 1, 2026 to December 31, 2026, on the basis of a peakload need. In order to prove a peakload need, the DHS regulation states, “[t]he petitioner must establish that it regularly employs permanent workers to perform the services or labor at the place of employment and that it needs to supplement its permanent staff at the place of employment on a temporary basis due to a seasonal or short-term demand and that the temporary additions to staff will not become a part of the petitioner’s regular operation.” 8 C.F.R. § 214.2(h)(6)(ii)(B)(2). An Employer must also demonstrate a bona fide need for the number of workers and period of need requested. 20 C.F.R. § 655.11(e)(3) and (4). See Roadrunner Drywall, 2017-TLN-00035, slip op. at 9-10 (May 4, 2017) (affirming denial where the employer’s temporary and permanent employee payroll data did not support its claimed number of workers or period of need). The Employer bears the burden of establishing why the job opportunity and number of workers requested reflect a temporary need within the meaning of the H-2B program. See, e.g., Alter and Son General Engineering, 2013-TLN-3 (Nov. 9, 2012) (affirming denial where the Employer did not provide an explanation regarding how its request fits within one of the regulatory standards of temporary need). In its statement of temporary need Employer alleges a temporary need for 275 Pipefitter Journeymen to work at the Rio Grande LNG project in the Port Isabel, Texas (Brownsville) during its pipefitting phase of the project from April 1, 2026, to December 31, 2026, on the basis of its peakload temporary need. Employer stated that it regularly employs permanent journeyman pipefitters but has a short-term demand of 9 months based on the completion of the pipefitting phase at the Rio Grande LNG project which it claims is an event of short duration. The CO issued a Notice of Deficiency on January 11, 2026 requesting further explanation and documentation to support the Employer’s temporary peakload need for the number of workers during the requested period of need. The CO noted that Employer indicates that the “completion of the pipefitting phase at the Rio Grande LNG project” is an event of short duration which causes it to experience a short-term demand of 9 months. The CO pointed out, in part, that the nature of the contract/project that the Employer will be performing does not necessarily define the nature of the employer’s need, noting that most contracts are for a limited duration. Therefore, the CO found that it remains unclear what seasonal or short-term demand leads to the Employer experiencing a peakload temporary need. Accordingly, the CO determined that further explanation and documentation was required to establish the Employer’s need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026. Employer responded to the Notice of Deficiency elaborating on its business, as well as its request for 275 Pipefitter Journeyman workers from April 1, 2026, to December 31, 2026, on the basis of its alleged peakload temporary need. Employer noted that its business was founded in 1898 and was ranked, in 2022, as the second largest construction company in the United States, and that it has over 50,000 employees as of May 2025. It further noted that Bechtel’s Energy unit (which Bechtel Energy Construction is part of) designs and builds liquefied natural gas (LNG), oil, pipeline, petrochemicals, natural gas, and water treatment facilities. Employer notes that since its founding it has built approximately 50,000 miles of pipeline systems, more than 50 major oil and gas field
- 14 - developments and over 380 major chemical and petrochemical projects. It also constructs and tests tanks for LNG storage and has built a third of the world’s LNG liquefaction capacity. Employer asserts that it is “heavily involved in the Liquefied Natural Gas industry, both in the U.S. and globally” and is known for its work on large-scale LNG projects including liquefaction plants and export terminals and has partnered with various companies like Cheniere Energy, Woodside Energy, and NextDecade on major LNG initiatives. AF 58. Employer also provided information about the Rio Grande LNG (RGLNG) project which is a natural gas and export terminal situated on a 984-acre site on the banks of the Brownsville ship channel, noting that it is the largest privately funded LNG project in Texas. Employer states that the first phase of the RGLNG project consists of three liquefaction trains, two storage tanks and one marine berth. Regarding the need for workers on this project Employer states that, [d]uring the life of the project, RGLNG will have many opportunities available to the Rio Grand Valley workforce and wider community. The workforce is anticipated to reach approximately 5,000 at peak construction. Bechtel will continuously be aggressive in recruiting U.S. skilled craft for the project although recruitment efforts thus far have indicated there will be a shortfall in skilled US craft to complete the project.” Id. The Employer noted that the only project Bechtel Energy Construction Services has in the area of intended employment (Port Isabel/Brownsville TX MSA) is the Rio Grande LNG project for 2024 to the present. Employer attached as Exhibit 1, a summation of its activity in the Rio Grande Valley for 2024 and 2025. This summation shows that Employer had 17 pipefitters working on the project on 1/1/24 rising to 125 pipefitters by the end of 2024. By the end of 2025 the number of pipefitters rose to 1,147. In its response the Employer argued that it met the regulatory definition of peakload need asserting that some peakload needs are recurring annually at the same time, but some peakload needs are unpredictable in nature, even if they are recurring. Accordingly, Employer argues that a single contract can create a short-term demand for workers and future possible contracts are not dispositive that an employer does not have recurring peakload needs. Employer attached certain selected pages of its contract with Rio Grande LNG Train 5, LLC (Next Decade) as its Exhibit 2. Employer notes that the contract contains provisions about the scope of work to be performed by contractor Bechtel including supplying “a sufficient number of workers including Pipefitters.” AF 62. Employer notes that the project has a definitive end (substantial completion date) including the pipefitting phase, and if Bechtel Energy does not comply with the substantial completion, it is liable for liquidated damages. Employer also states that the work to be performed will entail piping requiring Pipefitter Journeymen. Employer attached Exhibits 7-9 which are copies of the NextDecade and Bechtel websites listing Bechtel as a contractor. Other documents attached to the Employer’s response include an updated signed summarized payroll report for the 2025 calendar year (Exhibit 3), a staffing forecast curve (Exhibit 4), slides explaining its alleged peakload need (Exhibit 5), affidavit attesting to how figures for the staffing forecast curve were derived, and an article from the Rio Grande Guardian Business Journal regarding the hiring of workers for the Rio Grande LNG project (Exhibit 10). After thoroughly considering the record in this case, including Employer’s submitted evidence and arguments, as well as the CO’s Final determination set out in detail previously, I find that the CO did not act arbitrarily or capriciously in denying the Employer’s application in which it
- 15 - alleges a peakload need for 275 Pipefitter Journeyman workers from April 1, 2026, to December 31, 2026. In the Final Determination the CO acknowledged the information submitted by the Employer but determined that the information did not overcome the deficiency. The CO cited statements in the Employer’s response in which it elaborated on its business history and its explanation as to why it believed its work on the RGLNG project represents a temporary peakload need for workers. The CO noted that Employer explained that it designs and builds liquified natural gas (LNG), oil, pipeline, petrochemical, natural gas, and water treatment facilities, including building a third of the world’s LNG liquefaction capacity and that it is heavily involved in the U.S. and globally as a leading engineering, procurement and construction company. The CO noted that the Employer describes its peakload need for 275 Pipefitter Journeyman workers from April 1, 2026 to December 31, 2026, as an event of short duration due to the pipefitting phase of the Rio Grande project peaking in September 2026 after which it begins to decrease. The CO noted that the Employer’s filing history and the documentation provided show that the Rio Grande LNG project is a multiyear project requiring Pipefitter Journeyman workers that is not projected to be completed until 2029. The CO further noted that within the context of the Employer’s business operations it remains unclear how this specific phase of the Rio Grande LNG project creates a temporary need when the Employer has established that it is heavily involved in the liquefied natural gas industry. Accordingly, the CO found that it appears the Employer’s need is ongoing and not specific to a season or short-term demand. AF 44-45. The CO stated that this fact is further demonstrated by the Employer’s application filing history, noting that the Employer previously filed application, H-400-25184-150662, for 275 Pipefitter Journeyman workers for the same worksite for August 1, 2025, through March 15, 2027, based on a one-time occurrence temporary need. Although that application was denied, Employer had provided some additional insight into the overall Rio Grande LNG project. The CO pointed out that Employer had explained in its previous application that it required 275 Pipefitter Journeyman workers for “Phases 1” of the project until March 15, 2027. A staffing forecast was also provided with the previous application, showing the overall scope of the Rio Grande LNG (RGLNG) staffing forecast for pipefitters with an earlier phase ending in 2026 and trains 4 and 5 extending into 2029. The CO noted the following inconsistency in the Employer’s statements and documentation provided in its two applications: When looking at the scope of information provided with the previous and current applications for the Rio Grande LNG project, the presence of a peakload in demand for Pipefitter Journeyman workers from April 1, 2026, to December 31, 2026, appears to isolate a nine-month period within a minimum three-year project to fit within the definition of a peakload temporary need. It is unclear how in its previous application, the employer required 275 Pipefitter Journeyman workers until March 15, 2027, but now only requires them until December 31, 2026. The employer’s current explanation of the need for the 275 workers in its Explanation of Temporary Need slide presentation provided in its NOD response cites that 275 “Temporary Foreign Workers are requested to prevent a staffing shortfall at a critical point in the project life cycle.” The current staffing forecast showing 1,783 total Pipefitter Journeyman workers required at the purported peak in September of 2026, the 275 workers requested from April 1, 2026, to December 31, 2026, appears to be an arbitrary labor
- 16 - need during an overall project lasting over three years requiring well over 1,000 Pipefitter Journeyman workers. AF 46-47. It is reasonable for the CO to consider the Employer’s filing history as well as other documentation provided in assessing whether the Employer’s request for temporary H-2B workers represents a temporary peakload need during the dates requested. BALCA has consistently upheld the CO’s practice of considering previous applications filed by an employer, as well as multiple applications filed for the same year, in assessing whether an employer’s need for labor is temporary and whether the requested dates of need accurately represent the Employer’s true temporary need for the dates and number of workers requested, according to the Employer’s chosen standard of need. See Hill N’ Dale Sales, 2016-TLN-00031 (Apr. 14, 2016 (Changing dates from prior applications suggested a permanent need); See also JAJ Hauling, LLC, 2016-TLN-00054 (ALJ July 18, 2016) (affirming denial of certification where fluctuation in application timeframe suggested that Employer’s need appeared to be “year-round need rather than seasonal”). In this case Employer argues in its request for review that the CO improperly considered its prior application which requested 275 Pipefitter Journeyman workers between August 1, 2025 through March 15, 2027 for Phase 1 of the Rio Grand LNG project, on the basis of a one-time occurrence. See Application # H-400-25184-150662. Employer is correct that each application must stand on its own merits and be judged on a case-by-case basis, and that an employer is within its rights to file a peakload application, notwithstanding the denial of its one-time occurrence application. However, as noted above, the CO typically looks to the other applications filed by an employer and does reasonably consider when inconsistent representations or documentation have been provided. Accordingly, the CO’s consideration of the Employer’s previous application, for the same number of workers on the same project, for dates of need that varied from the current application, was proper. The CO accurately noted that the Employer claimed a temporary need for 275 Pipefitter Journeyman workers between August 1, 2025 and March 15, 2027, based on a one-time occurrence temporary need in a prior application which was denied on November 20, 2025, after administrative review. See AF 244 – 277. Statements provided by the Employer supporting a continuous temporary need throughout that nearly 18-month period on a one-time occurrence basis are inconsistent with a temporary peak need for the same number of workers in the current application which alleges a nine- month temporary period between April 1, 2026 and December 2026. As noted by the CO it appears the Employer is attempting to carve out a temporary period that would fit within the H-2B regulations rather than accurately representing its true temporary need for the requested workers. BALCA has affirmed denials where the CO determined that an employer’s alleged need is not supported by documentation and appears to be crafted merely to meet perceived program requirements. See Kiewit Offshore Services, LTD., 2013-TLN-00020 (Jan. 15, 2013) (affirming denial where the employer’s documentation revealed that the employer’s alleged “peak load” need spanned at least a 19-month period). See also William Ashby Maltsberger d/b/a Maltsberger Ranch, 2016-TLC-00078, 86 (Sept. 28, 2016)(finding employer’s two labor certification applications, though separate, demonstrated a year-round need when combined, because of the overlapping nature of the dates of need and the similarities in job requirements and duties).
- 17 - The CO also reasonably determined that statements in the employer’s supporting documents call into question whether the Employer’s alleged need represents a temporary need according to one of the H-2B standards of need, or whether the alleged need is in fact an ongoing permanent need for labor that the Employer continues to experience based on the contracts and projects it secures and fulfills on an ongoing basis. Employer attempts to argue in its response to the NOD, as well as in its request for review, that a single contract can and should be the basis for a peakload need for workers so long as the employer meets other requirements of the peakload definition, such as the employment of permanent workers by the employer. However, the CO reasonably questioned the Employer’s temporary need as it determined that Employer in this case is in the business of securing and fulfilling contracts on an ongoing basis. The background provided by the Employer regarding its business supports this conclusion. Employer stated in its response that that it was founded in 1898 and was ranked, in 2022, as the second largest construction company in the United States, and that it has over 50,000 employees as of May 2025. It further noted that Bechtel’s Energy unit (which Bechtel Energy Construction is part of) designs and builds liquefied natural gas (LNG), oil, pipeline, petrochemicals, natural gas, and water treatment facilities. Employer notes that since its founding it has built approximately 50,000 miles of pipeline systems, more than 50 major oil and gas field developments and over 380 major chemical and petrochemical projects. It also constructs and tests tanks for LNG storage and has built a third of the world’s LNG liquefaction capacity. Employer asserts that it is “heavily involved in the Liquefied Natural Gas industry, both in the U.S. and globally” and is known for its work on large-scale LNG projects including liquefaction plants and export terminals and has partnered with various companies like Cheniere Energy, Woodside Energy, and NextDecade on major LNG initiatives. There is nothing in these statements that would lead one to believe the alleged period of peakload need represents Employer’s temporary need for workers, rather than an ongoing permanent need for labor, in the grand scheme of the Employer’s business, or even as pointed out be the CO, during the span of work required at the Rio Grande LNG project which apparently began in 2024 and appears to be ongoing with further expansions of work planned in the future. The CO stated, Within the greater context of the employer’s business operations it remains unclear how this specific phase of the Rio Grande LNG project creates a temporary need when the employer has established that it is heavily involved in liquefied natural gas (LNG) industry. Therefore it appears the employer’s need is ongoing and not specific to a season or short-term demand. AF 44-45. Employer admits that it does not allege a seasonal need but rather one based on a “short term” demand based on a contract for work on the RGLNG. However, as the CO points out the limited contract provisions that were offered as an Exhibit do not reflect either the number of pipefitters required or the period of time, in which the Employer is required to complete the pipefitter portion of the contract. Accordingly, the contract provisions do not provide support for Employer’s assertion regarding either the alleged peakload period or the number of workers requested.
- 18 - Further, as the CO determined, the Employer is in the business of continually securing and fulfilling contracts on an ongoing basis and therefore a single contract alone does not support a temporary need. Although every contract may represent a temporary event the definition of temporary need under the H-2B program is concerned with the nature of the petitioner’s need rather than the underlying job. Per the definition of temporary labor, Temporary services or labor under the H-2B classification refers to any job in which the petitioner’s need for the duties to be performed by the employee(s) is temporary, whether or not the underlying job can be described as permanent or temporary. 8 C.F.R. § 214.2(h)(6)(ii)(A). Although a single contract may be one consideration in determining whether an employer has proven its temporary need, it is generally not sufficient by itself to establish a peakload need in the case of a business that routinely secures and completes contracts. That is because each contract that a business secures is temporary, but when those contracts are viewed as a series of contracts, they represent a continuous need for labor. BALCA has upheld the denial of certification in peakload cases which were based on a single contract. See Pronto Solutions Inc., 2025-TLN-00003 (October 18, 2024) (Finding that the existence of one contract for the requested dates does not, by itself, establish a temporary need since Employer works on contracted projects year-round). See also Falls Framing LLC, 2020-TLN-00007, slip op. at 7 (November 18, 2019) (finding that a single contract did not demonstrate a peakload need). The CO properly considered the evidence provided by the Employer in reaching the determination that Employer failed to prove a peakload need for the workers requested during the 9- month period of need requested, considering the Employer’s filing history, statements in its applications and the documentation proved including the limited contract provisions provided. See Munoz Enterprises, 2017-TLN-00016, slip op. at 7 (Jan. 19, 2017) (finding that a peakload need “depends on the amount of work the employer is contractually obligated to perform, when such work must be performed, whether the employer’s contractual obligations overlap, and how many permanent workers are employed by the employer”). Employer also asserts in its request for review that the CO did not consider the affidavit of David Todd, Workforce Planning & Development Manager for Bechtel Energy Construction Services, which was supplied as Exhibit 6 in Bechtel's response to the notice of deficiency. Employer states the following regarding Mr. Todd’s affidavit: Mr. Todd explains that the staffing peak (from Exhibit 4 and Exhibit 5) for Pipefitter Journeyman workers will be approximately 1,783 Pipefitters in Q3 2026 and that an estimated 33% of the total pipefitters needed will be non-local (travelers and subcontractors) totaling 588 non-local pipefitters. Mr. Todd expects that 50% of these 588 Pipefitter positions (minus 50 subcontractors already working at the project) need to be filled by 275 temporary foreign workers (and/or US workers hired during the H- 2B recruitment process).
- 19 - AF 6. I find the Employer’s claim that the affidavit was not considered lacks merit. The CO acknowledged the affidavit of Mr. Todd in the Final Determination, and specifically stated the following: The employer was instructed to provide documentation supporting the employer’s need for 275 Pipefitter Journeyman workers such as contracts, letters of intent, etc. that specified the number of workers and dates of need. The employer provided an internal project timeline and head count estimations, stating, “RGLNG will require 1,783 pipefitters at peak (Q3 2026),” and discusses the labor market challenges resulting in its estimation that 275 of those workers may be “fillable by temporary foreign workers.” However, these are general figures with no insight as to how the number of workers was calculated based on the specific work required. The employer also provided portions of its contract with NextDecade. The contract provided shows that the project does require Pipefitter Journeyman workers. However, all expected start and completion dates for the project are redacted from view. The employer provided no objective basis for the Department to analyze its estimates. Therefore, the Department is unable to confirm the need for 275 Pipefitter Journeyman workers from April 1, 2026, to December 31, 2026. AF 53. The undersigned finds that the CO considered the evidence submitted by the Employer as well as Employer’s claims but reasonably determined that the Employer provided estimates with little explanation as to how they were derived and no objective basis to verify the claims. BALCA has determined that a CO is not required to take an Employer at its word and may require supporting documentation for the Employer’s assertions regarding its temporary need and the number of workers requested. As noted by the CO, Employer has not provided objective evidence as to how its calculations were made. Thus there is no objective way to verify the information or the calculations regarding the number of workers required or the period of need requested. See Technical America, Inc. 2019-TLN-00139 (July 9, 2019) (Bare assertions without supporting evidence are insufficient to carry the employer’s burden of proof. See also AB Controls & Technology, 2013-TLN-00022 (Jan. 17, 2013). See North Country Wreaths, 2012-TLN-00043 (Aug. 9, 2012) slip op. at 6 (“it is the Employer’s burden to prove that the requested positions represent bona fide job opportunities, and the CO is not required to take the Employer at its word”). Accordingly, the CO’s denial of the Employer’s application for failure to establish its temporary need for the number of workers requested and the period of need is supported by the record. The CO also correctly determined that a labor shortage alone is insufficient to prove an employer’s temporary peakload need. See BMC West LLC, 2018-TLN-00099, at 11 (July 13, 2018) (“The presence of a labor shortage, [ ] does not support a finding that Employer’s need is temporary in nature. Rather, Employer bears the burden to establish ‘that it needs to supplement its permanent staff at the place of employment on a temporary basis due to a seasonal or short-term demand and that the temporary additions to staff will not become a part of the petitioner’s regular operation.’” quoting 8 C.F.R. § 214.2(h)(6)(ii)(B)(3))
- 20 - The DHS regulation which defines temporary need for purposes of the H-2B program provides as follows: Employment is of a temporary nature when the employer needs a worker for a limited period of time. The employer must establish that the need for the employee will end in the near, definable future. Generally, that period of time will be limited to one year or less, but in the case of a one-time event could last up to 3 years. The petitioner’s need for the services or labor shall be a one-time occurrence, a seasonal need, a peakload need, or an intermittent need. (emphasis added). (8 C.F.R. §214.2(h)(6)(ii)(B)). In this case, Employer has shown a need for labor, but has failed to show that its need will end in the near definable future. Employer has merely shown an ongoing need for labor and has not shown that it has a “seasonal or short-term demand” as required by the regulation defining “peakload” temporary need, which is the Employer’s stated standard of need. See 8 C.F.R. §214.2(h)(6)(ii)(B)(3). Based on the information submitted to the CO, and for the reasons stated above, the undersigned finds the CO reasonably determined that the Employer failed to meet its burden of showing its temporary peakload employment need for 275 Pipefitter Journeyman workers for the period of April 1, 2026 to December 31, 2026 and has also failed to demonstrate a bona fide need for the number of workers requested. ORDER Employer has failed to meet its burden of establishing its temporary employment need for 275 Pipefitter Journeyman workers for the period of April 1, 2026 to December 31, 2026. The CO’s denial of Employer’s application was not arbitrary or capricious and is supported by the record. Accordingly, the CO’s denial of Employer’s application for temporary labor certification is AFFIRMED. SO ORDERED. For the Board of Alien Labor Certification Appeals: DREW A. SWANK Administrative Law Judge