99-30767•Gulf South Machine, Inc v. American Standard Inc; Union Switch and Signal, Inc.
99-30767Court of Appeals for the Fifth Circuit28 de set. de 2000
* Chief Judge of the United States District Court for the
Southern District of Texas, sitting by designation.
** Pursuant to 5TH CIR. R. 47.5, the court has determined
that this opinion should not be published and is not precedent
except under the limited circumstances set forth in 5TH CIR. R.
47.5.4.
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
No. 99-30767
GULF SOUTH MACHINE, INC; ET AL
Plaintiffs
GULF SOUTH MACHINE, INC
Plaintiff -Counter Defendant - Appellant - Cross
Appellee
v.
AMERICAN STANDARD INC; UNION SWITCH AND SIGNAL, INC.
Defendants - Counter Claimants - Appellees - Cross
Appellants
--------------------
Appeal from the United States District Court
for the Eastern District of Louisiana, New Orleans
USDC No. 97-CV-65-R
--------------------
September 22, 2000
Before KING, Chief Judge, PARKER, Circuit Judge, and KAZEN*,
District Judge.
PER CURIAM**:
The district court was correct in concluding that no genuine
issue of material fact existed as to whether the arrangement
between Gulf South Machine, Inc and Union Switch & Signal Inc.
amounted to a partnership agreement, and we affirm the court’s
grant of summary judgment on that point for essentially the
-- 1 of 2 --
No. 99-30767
-2-
reasons given by the district court in its Order and Reasons
entered July 2, 1998. The district court also correctly
concluded that the contractual standard for determining whether
Gulf South would earn the proposed $200,000 incentive bonus was
not ambiguous, thereby obviating the need for a jury instruction
relating to an ambiguous contract. The testimony on the value of
the equipment presented by Union Switch’s appraiser was
undermined on cross-examination and by the testimony of one of
Gulf South’s witnesses, and on this record the value that the
jury arrived at is supported by sufficient evidence. Finally,
the district court was correct in concluding that Gulf South’s
duty to mitigate damages was breached when it withheld service of
the complaint for nearly five years, resulting in a delay of
almost eight years between the accrual of the cause of action and
notification of Union Switch of the suit, and in limiting the
recovery of prejudgment interest accordingly.
The judgment of the district court is AFFIRMED.