Conner Bros. Construction Company, Inc. v. Pete Geren, SECRETARY OF THE ARMY

2008-1188Court of Appeals for the Federal Circuit31 de dez. de 2008

Abrir fonte

Texto completo

United States Court of Appeals for the Federal Circuit
2008-1188
CONNER BROS. CONSTRUCTION COMPANY, INC.,
Appellant,
v.
Pete Geren, SECRETARY OF THE ARMY,
Appellee.
Joseph C. Staak, Smith, Currie & Hancock LLP, of Atlanta, Georgia, argued for
appellant.
Lauren S. Moore, Trial Attorney, Commercial Litigation Branch, Civil Division,
United States Department of Justice, of Washington, DC, argued for appellee. With her
on the brief were Gregory G. Katsas, Assistant Attorney General, Jeanne E. Davidson,
Director, and Donald E. Kinner, Assistant Director. Of counsel on the brief was Henry R.
Richmond, Deputy District Counsel, United States Army Corps of Engineers, of Savannah,
Georgia.
Appealed from: Armed Services Board of Contract Appeals
Administrative Judge Alexander Younger

-- 1 of 21 --

United States Court of Appeals for the Federal Circuit
2008-1188
CONNER BROS. CONSTRUCTION COMPANY, INC.,
Appellant,
v.
Pete Geren, SECRETARY OF THE ARMY,
Appellee.
Appeal from the Armed Services Board of Contract Appeals
in no. 54109, Administrative Judge Alexander Younger.
___________________________
DECIDED: December 31, 2008
___________________________
Before BRYSON, GAJARSA, and DYK, Circuit Judges.
BRYSON, Circuit Judge.
Conner Bros. Construction Company, Inc., a construction contractor doing work
for the Army Corps of Engineers, sought delay damages after it was denied access to
its construction site on a military base for 41 days following the terrorist attacks of
September 11, 2001. The Armed Services Board of Contract Appeals denied Conner’s
claim on the ground that the sovereign acts doctrine shielded the Army from liability.
We agree with the Board that the order excluding Conner from the base was a
sovereign act that precludes recovery of damages for the delay that resulted from that
act.

-- 2 of 21 --

2008-1188 2
I
On April 21, 2000, Conner contracted with the Corps of Engineers to construct an
Army Ranger regimental headquarters facility within the 75th Ranger regimental
compound at Fort Benning, Georgia. The Ranger compound is a segregated area
within Fort Benning that is under the operational control of the Ranger regimental
commander. The contract, which was for the construction of four buildings at two sites
within the compound, was administered by a Corps of Engineers project manager.
In response to the terrorist attacks against the United States on September 11,
2001, Fort Benning was placed at force protection condition Delta and shut down to
everyone except essential personnel. General (then Colonel) Joseph Votel, the
commander of the 75th Ranger regiment, also restricted access to the Ranger
compound to mission-essential personnel and ordered his staff to direct Conner to stop
work and vacate the compound immediately. Conner’s workforce left the compound by
2:00 p.m. on September 11, 2001, at which point its contract work was roughly 70-75%
complete. On September 17, 2001, Fort Benning lowered its force protection condition,
allowing contractors and other personnel to return to the base. However, the Ranger
compound continued to operate under condition Delta and remained subject to General
Votel’s order restricting access to mission-essential personnel, and Conner continued to
be excluded from its worksites within the compound.
In the immediate aftermath of the terrorist attacks, the Rangers prepared for
deployment to Afghanistan. They executed a “protracted low-level deployment”
whereby they departed in small groups so that their movements would not attract notice.
During that period, the Rangers occupied one of the partially constructed buildings on

-- 3 of 21 --

2008-1188 3
Conner’s worksite. General Votel testified that he decided to shut down Conner’s
construction activities in order to maintain operational security by preventing information
leaks while the Rangers prepared to deploy. He explained that because Conner’s work
was the “biggest thing happening on the installation,” Conner’s activities put its
employees and subcontractors in a unique position to observe sensitive deployment
activities.
Conner was excluded from the compound until September 27, 2001, when it was
allowed to return to one of its worksites. It was permitted access to its other site on
October 15, 2001, and it resumed work there on October 21, 2001. Conner
subsequently sought additional time to complete the project and $137,744 in delay
damages attributable to 35 of the 41 days during which it was shut down—that is, for
the period between September 17, 2001, when other contractors were permitted back
on the compound, and October 21, 2001, when Conner returned to work. The
contracting officer granted Conner the requested additional time to complete the project
but denied the monetary claim. Conner appealed that decision to the Board.
After conducting a three-day hearing, the Board denied Conner’s appeal. As an
affirmative defense, the Corps of Engineers asserted that the exclusion of Conner from
the construction site constituted a sovereign act that precluded Conner from recovering
damages for the delay. Conner argued that it was the sole target of the shutdown
order, as it was the only contractor ordered to leave the compound. For that reason,
Conner argued, the shutdown order was not a “public and general” act, and the
government therefore could not invoke the “sovereign acts doctrine” as a defense to
liability for breach of contract. The Board, however, found that the exclusion order was

-- 4 of 21 --

2008-1188 4
a sovereign act because it stemmed from the government’s war-making powers, was
merely incidental to the accomplishment of a broader governmental objective relating to
national security, and was not directed principally at Conner’s contract rights. The
Board also rejected Conner’s arguments that it was entitled to relief under the contract’s
“Changes” and “Suspension of Work” clauses. Conner now appeals to this court.
II
The sovereign acts doctrine provides that “the United States when sued as a
contractor cannot be held liable for an obstruction to the performance of the particular
contract resulting from its public and general acts as a sovereign.” Horowitz v. United
States, 267 U.S. 458, 461 (1925). The doctrine is an affirmative defense that is an
inherent part of every government contract. Hughes Commc’ns Galaxy, Inc. v. United
States, 998 F.2d 953, 958 (Fed. Cir. 1993). It is based on the government’s dual roles
as contractor and sovereign, and it is designed to balance “the Government’s need for
freedom to legislate with its obligation to honor its contracts.” United States v. Winstar
Corp., 518 U.S. 839, 896 (1996) (principal opinion of Souter, J.).
The doctrine is rooted in three early Court of Claims cases. In Deming v. United
States, 1 Ct. Cl. 190 (1865), a supplier who had contracted to provide rations to the
Marine Corps sued for damages when the enactment of the Legal Tender Act resulted
in the imposition of additional duties on some articles making up the rations, thereby
raising the contractor’s costs. The Court of Claims explained that “[a] contract between
the government and a private party cannot be specially affected by the enactment of a
general law” and held that the imposition of the duty constituted a sovereign act that did
not form the basis for governmental liability for breach of contract. Id. at 191 (emphasis

-- 5 of 21 --

2008-1188 5
in original). In what has become the iconic statement of the sovereign acts doctrine, the
court wrote: “The United States as a contractor are not responsible for the United States
as a lawgiver.” Id.
In Jones v. United States, 1 Ct. Cl. 383 (1865), the Court of Claims extended the
rule of Deming from legislative to executive acts. The court rejected a suit brought by
surveyors working for the Commissioner of Indian Affairs when their performance was
hindered by the withdrawal of U.S. troops from Indian territories. As in Deming, the
court emphasized that “the United States as a contractor cannot be held liable directly
or indirectly for the public acts of the United States as a sovereign.” Id. at 385.
Finally, in Wilson v. United States, 11 Ct. Cl. 513 (1875), the plaintiff contracted
to deliver mules to the Quartermaster-General during the Civil War. When the plaintiff
attempted to deliver the mules in Washington, D.C., which was in danger of capture by
Confederate forces, the contractor was refused entry to the city under orders from the
military governor of Washington barring any person not in the military service from
entering the city without signed permission from a commanding general. After the
plaintiff was turned away, Confederate soldiers confiscated some of the plaintiff’s mules.
The plaintiff then sued the United States to obtain compensation for the loss.
Reaffirming the principles of Deming and Jones, the court invoked the sovereign acts
doctrine to hold the government free from liability. The court explained that the
exclusion order “was general, applying to all persons, and affecting the claimant
precisely as though he had contracted with any private corporation.” Id. at 521.
The Supreme Court addressed the sovereign acts doctrine for the first time in
Horowitz v. United States, 267 U.S. 458 (1925). In that case, the Court explicitly

-- 6 of 21 --

2008-1188 6
approved the formulation of the doctrine in the early Court of Claims cases. The plaintiff
in Horowitz contracted with the Ordnance Department to purchase silk, which he
intended to resell at a profit. Although the government had agreed to ship the
merchandise within a specified period, its delivery was delayed when the U.S. Railroad
Administration embargoed freight shipments of silk. By the time Horowitz received the
silk, the price of silk had fallen and Horowitz was forced to sell his silk at a loss. Finding
that the embargo was a public and general act, the Court denied Horowitz’s claim to
recover damages for the delay. Horowitz, 267 U.S. at 461. The Court explained:
The two characters which the government possesses as a contractor and
as a sovereign cannot be thus fused; nor can the United States while sued
in the one character be made liable in damages for their acts done in the
other. Whatever acts the government may do, be they legislative or
executive, so long as they be public and general, cannot be deemed
specially to alter, modify, obstruct or violate the particular contracts into
which it enters with private persons.
Id., quoting Jones, 1 Ct. Cl. at 384.
In addition to requiring that the governmental act be “public and general,” the
Court in Horowitz explained that private contractors who deal with the United States
should not be treated any more favorably than if they had contracted with a private
party. Thus, just as private contractors would not recover in the event of an intervening
sovereign act that disrupted contract expectations, the Court stated that the same
principle would apply to those contracting with the government. The Court wrote:
In this court the United States appear simply as contractors; and they are
to be held liable only within the same limits that any other defendant would
be in any other court. Though their sovereign acts performed for the
general good may work injury to some private contractors, such parties
gain nothing by having the United States as their defendants.

-- 7 of 21 --

2008-1188 7
Id.; see also Jones, 1 Ct. Cl. at 385 (“If the removal of troops from a district liable to
invasion will give the claimant damages for unforeseen expenses, when the other party
is a corporate body, then it will when the United States form the other party, but not
otherwise.”); Richard E. Speidel, Implied Duties of Cooperation and the Defense of
Sovereign Acts in Government Contracts, 51 Geo. L.J. 516, 539 (1963) (noting policy
that “a contractor who deals with the United States in its contractual capacity should
occupy no better risk position than if he were dealing with a private party”).
In United States v. Winstar Corp., 518 U.S. 839 (1996), the Supreme Court was
again presented with a case requiring it to address the meaning of a “public and general
act” for purposes of the sovereign acts doctrine. The issue in Winstar was whether the
government was liable for breach of contract resulting from Congress’s enactment of
the Financial Institutions Reform, Recovery, and Enforcement Act of 1989 (“FIRREA”).
Prior to the Act, the Federal Home Loan Bank Board had induced healthy financial
institutions to take over insolvent thrifts by promising favorable accounting treatment for
the acquired assets. Subsequently, however, Congress enacted FIRREA, which
eliminated those accounting benefits. The Supreme Court held that the legislative
elimination of the agreed-upon benefits constituted a breach by the United States of its
contractual obligations to the acquiring institutions for which the government was liable.
The Court in Winstar rejected the government’s argument that the legislation
constituted a sovereign act that provided a defense against claims of contract breach.
The principal opinion, authored by Justice Souter, explained that in order to place the
government on an equal footing with other contractors, “some line has to be drawn”
between situations in which the government’s act is “relatively free of Government self-

-- 8 of 21 --

2008-1188 8
interest,” and those in which the action is “tainted by a governmental object of self-
relief.” Winstar, 518 U.S. at 896. The government will not be held liable, Justice Souter
explained, “so long as the action’s impact upon public contracts is, as in Horowitz,
merely incidental to the accomplishment of a broader governmental objective.” Id. at
898. In contrast, the sovereign acts defense is unavailable “where a substantial part of
the impact of the Government’s action rendering performance impossible falls on its
own contractual obligations.” Id. The principal opinion concluded that FIRREA was not
a public and general act because “[t]he statute not only had the purpose of eliminating
the very accounting gimmicks that acquiring thrifts had been promised, but the specific
object of abrogating enough of the acquisition contracts as to make that consequence of
the legislation a focal point of the congressional debate.” Id. at 900.
Although the portion of the principal opinion addressed to the sovereign acts
doctrine had the support of only four (and as to some portions, only three) justices, this
court has treated that opinion as setting forth the core principles underlying the
sovereign acts doctrine. See Carabetta Enters., Inc. v. United States, 482 F.3d 1360,
1365 (Fed. Cir. 2007); Yankee Atomic Elec. Co. v. United States, 112 F.3d 1569, 1574-
77 (Fed. Cir. 1997). That approach probably best approximates the Supreme Court’s
position with respect to the doctrine. The dissenting justices in Winstar would have
given the doctrine broader sweep. Winstar, 518 U.S. at 933 (Rehnquist, C.J.,
dissenting) (a general regulatory action constitutes a “sovereign act” regardless of
whether the action was “free of governmental self-interest” or was “tainted” by a
governmental objective of “self-relief”). The concurring justices would have construed
the doctrine more narrowly, but still would regard it, along with the “unmistakability

-- 9 of 21 --

2008-1188 9
doctrine,” as reversing the normal presumption that a party will be liable for any
impossibility that is attributable to its own actions. Winstar, 518 U.S. at 920-21, 923-24
(Scalia, J., concurring in the judgment). In any event, we discern no indication in the
separate opinions in Winstar that the approach taken by the justices who subscribed to
those opinions would lead to a different result on the facts of this case than the result
reached by the Board.
In cases following Winstar, we have reiterated that the sovereign acts defense is
unavailable where the governmental action is specifically directed at nullifying contract
rights. See, e.g., City Line Joint Venture v. United States, 503 F.3d 1319, 1323 (Fed.
Cir. 2007) (legislation abrogating option of low-income apartment owners to prepay
mortgages was not a sovereign act because it was “aimed at the contract rights
themselves in order to nullify them,” quoting Cienega Gardens v. United States, 331
F.3d 1319, 1335 (Fed. Cir. 2003)); Centex Corp. v. United States, 395 F.3d 1283, 1308
(Fed. Cir. 2005) (legislation breaching agreements entitling financial institutions to take
tax deductions for specific losses was not a public and general act because it “was
specifically targeted at appropriating the benefits of a government contract”). Even
before Winstar, our precedent provided that the government could not use the
sovereign acts defense as a means to escape from contracts that it subsequently
concluded were unwise. See Everett Plywood Corp. v. United States, 651 F.2d 723,
731-32 (Ct. Cl. 1981).
In addition, when considering whether the alleged sovereign act is exclusively
directed to aborting performance of government contracts, courts addressing the
sovereign acts doctrine have looked to the extent to which the governmental action was

-- 10 of 21 --

2008-1188 10
directed to relieving the government of its contractual obligations. As Justice Souter
stated in Winstar, “The greater the Government’s self-interest, . . . the more suspect
becomes the claim that its private contracting partners ought to bear the financial
burden of the Government’s own improvidence . . . .” Winstar, 518 U.S. at 898
(principal opinion of Souter, J.). The Court of Federal Claims applied that principle in
Casitas Municipal Water District v. United States, 72 Fed. Cl. 746 (2006), aff’d in part,
543 F.3d 1276 (Fed. Cir. 2008). In that case, the United States agreed to construct and
operate a water reclamation project in exchange for a commitment from the Casitas
Municipal Water District to repay the construction and operation costs. Almost 40 years
after construction of the project, the National Marine Fisheries Service listed the West
Coast Steelhead Trout as an endangered species and subsequently issued a biological
opinion pursuant to the Endangered Species Act requiring Casitas to construct a fish
passage facility and adhere to new operating criteria to assist trout migration. When the
water district sued the government for breach of contract, the court held that the
biological opinion was a sovereign act because “no economic advantage accrued to the
United States, as a contracting party, as a result of” its issuance. 72 Fed. Cl. at 755.
Another factor relevant to the “public and general” inquiry is whether the
governmental action applies exclusively to the contractor or more broadly to include
other parties not in a contractual relationship with the government. In the Yankee
Atomic case, an electric utility that purchased uranium enrichment services from the
government brought suit to recover costs it incurred pursuant to the Energy Policy Act of
1992, which required domestic utilities to pay a pro rata share of costs associated with
decontaminating and decommissioning former enrichment facilities. In concluding that

-- 11 of 21 --

2008-1188 11
the legislation constituted a sovereign act, we emphasized that “the special assessment
does not reach only those utility companies that previously contracted with the
Government; it also reaches those utilities that purchased the services through the
secondary market but had no contracts with the Government.” 112 F.3d at 1576
(emphasis in original). Thus, any governmental act that obstructs a government
contract is more likely to be regarded as incidental when the scope of the governmental
act is sufficiently broad to affect parties having no connection to the contract.
In light of these principles, we sustain the Board’s decision that the exclusion
order that temporarily shut down Conner’s performance was a sovereign act and that
the government is therefore not liable for delay damages under its contract with Conner.
As we explain in detail below, the exclusion order was not directed at relieving the
government of its contractual obligations; to the contrary, any effect on Conner was
incidental to a broader governmental objective relating to national security.
III
Conner’s primary contention on appeal is that General Votel’s exclusion order
cannot be a public and general act, because the order was specifically directed at
Conner’s performance of its contract. This argument is predicated on Conner’s
assertion that General Votel issued two separate directives: one restricting the Ranger
compound to mission-essential personnel, and the other specifically excluding Conner
from the compound. In fact, however, the two orders are not as segregable as Conner
suggests. Instead, the decision to exclude Conner was simply an extension of the
broader access restrictions implemented to respond to the emergency created by the
terrorist attacks.

-- 12 of 21 --

2008-1188 12
The Board found, and Conner does not dispute, that the restriction of the Ranger
compound to mission-essential personnel and the refusal to admit Conner both served
the same governmental objective: maintaining operational security as the Rangers
prepared to deploy after the attacks of September 11, 2001. General Votel and his
deputy commander testified to their concern that Conner’s operation was a large-scale
project, that Conner’s workers were constantly moving about the compound, and that
the workers were well positioned to observe Ranger staging activities. The Rangers
also needed one of the partially completed facilities to prepare for their post-September
11 mission. Based on the evidence before it, the Board found that Conner was barred
from returning to the compound because of General Votel’s determination that Conner’s
activities on the compound presented risks and impediments to the accomplishment of
an important policy objective that was unrelated to the parties’ obligations under the
contract. The Board therefore concluded that Conner’s exclusion from the compound
was not directed at the contract, but was just a specific application of the general
exclusion order.
Conner contends that General Votel’s order was targeted at Conner’s contract
rights precisely because his order was predicated on concerns about Conner’s
presence in the compound. In so arguing, Conner seemingly takes issue with the
Board’s finding that in attempting to secure the Ranger compound and provide a facility
for the Rangers to prepare for deployment, General Votel had to make particularized
judgments as to which activities potentially interfered with that objective. Contrary to
Conner’s suggestion, the fact that the government made case-specific determinations
as to who was nonessential and whose presence interfered with the Rangers’

-- 13 of 21 --

2008-1188 13
operations in the compound does not convert an otherwise public and general act into a
nongeneral one. Nor does the fact that General Votel specifically instructed his
subordinates to order Conner to vacate the compound on September 11, 2001, bolster
Conner’s assertion that its exclusion constituted an action distinct from the general
exclusion order.
Conner next makes the related claim that because it was the only contractor
barred from returning to work on the compound, while certain other contractors were
granted access, the exclusion order must necessarily be regarded as directed at
Conner’s contract rights. That argument suffers from several flaws. To begin with, the
exclusion order was not limited to Conner’s activities. The Board found that under the
access restrictions, “ordinary civilians, journalists, Department of the Army civilians, and
contractors not concerned with the Rangers would have been denied access to the
compound.” Thus, by analogy to Yankee Atomic, the access restrictions reached not
only parties having contracts with the government, but also parties with no government
contracts at all, including the public at large. See Yankee Atomic, 112 F.3d at 1576.
More generally, the public and general nature of an action does not turn on the
number of contracts it actually obstructed. While the legislation at issue in Winstar
affected financial institutions generally, that did not prevent the Supreme Court from
rejecting the sovereign acts defense, because the legislation specifically discharged the
government’s contractual obligations to the institutions that had agreed to acquire failing
thrifts. Conversely, governmental actions affecting a single contractor can be shielded
by the sovereign acts doctrine as long as the effect on the contractor’s contract rights is
incidental to a broader governmental objective. For example, in Casitas Municipal

-- 14 of 21 --

2008-1188 14
Water District v. United States, 543 F.3d 1276, 1288 (Fed. Cir. 2008), we affirmed the
application of the sovereign acts doctrine where a municipal water district was
specifically ordered to construct a fish passage facility and take other steps to protect an
endangered trout species. And in Orlando Helicopter Airways, Inc. v. Widnall, 51 F.3d
258, 262 (Fed. Cir. 1995), we upheld as a sovereign act a stop-work order issued by a
contracting officer after the Department of Justice had launched a criminal investigation
into alleged fraud by the contractor. The sovereign acts inquiry does not rest on a
mechanical determination of how many contractors are affected, but rather focuses on
the nature and scope of the governmental action.
The Board correctly concluded that this case is a far cry from the “change of
heart” cases in which the government unilaterally terminated a single contract after
deciding that performance would be unwise. See Everett Plywood Corp. v. United
States, 651 F.2d 723, 731-32 (Ct. Cl. 1981) (rejecting sovereign acts defense where
National Forest Service terminated a timber contract because of anticipated
environmental damage); Sun Oil Co. v. United States, 572 F.2d 786, 817 (Ct. Cl. 1978)
(rejecting sovereign acts defense where plaintiffs who obtained oil and gas leases from
the Department of Interior were denied permits to install drilling platforms). The Army
did not exclude Conner from the worksite because it was unhappy with Conner’s
performance, or because it was unhappy with the contract price, or because it decided
that it no longer wanted a new Ranger headquarters facility. Rather, General Votel
made a determination that excluding Conner directly served the government’s broader
objective of restricting access to the compound in order to minimize potential threats to
operational security and to facilitate deployment. The fact that Conner’s activities were

-- 15 of 21 --

2008-1188 15
conducted pursuant to a government contract does not mean that General Votel’s
decision that Conner was not a mission-essential contractor was directed at Conner’s
right to perform its contract to construct the Ranger headquarters.
The fact that other contractors were permitted back onto the Ranger compound
after September 17, 2001, also does not support Conner’s contention that its exclusion
resulted from a governmental act aimed at its contract rights. The Board noted that
dining facility and custodial services contractors, a Coca-Cola vendor, and cable
television personnel were all allowed on the compound while Conner was denied
access. The Board found, however, that although Conner was “treated differently from
non-construction contractors,” those other contractors were not situated similarly to
Conner. See Gothwaite v. United States, 102 Ct. Cl. 400, 401 (1944). Unlike Conner,
both the dining facility and custodial contractors were deemed to be mission-essential.
The Board found that the Rangers could not leave the compound for food, and that the
custodial workers were essential to ensure proper sanitation on the facility. In addition,
the admission of “mission-essential” personnel contemplated the admission of persons
who would not interfere with mission planning or security. The Board noted that, unlike
Conner’s workers, the food service and custodial contract employees were either
confined to limited areas within the compound or could be admitted with escorts,
thereby minimizing any potential operational disruptions or security breaches.
The government acknowledges that the Coca-Cola vendor and the cable
personnel who were admitted to the compound were not mission-essential. General
Votel admitted that their presence in the compound during the restricted access period
was inappropriate; in fact, he explained, their presence contravened his orders. But the

-- 16 of 21 --

2008-1188 16
Board found that the Coca-Cola and cable personnel, like the dining and custodial
contractors, were “qualitatively different” from Conner. Conner and its subcontractors
constituted a massive presence on the compound, moved around extensively, could
view the areas of the compound where the Rangers were preparing to deploy, and
could not feasibly be escorted. In that regard, the Coca-Cola and cable television
personnel were not situated similarly to Conner. Moreover, and more importantly, the
admission of the Coca-Cola and cable television personnel was a mistake, in that it
violated General Votel’s exclusion order. The fact that his order was disobeyed in those
instances does not affect the general nature of the exclusion order or show that the
government’s action targeted Conner’s contract rights. Based on the Board’s factual
findings we sustain the Board’s legal conclusion that the admission of non-construction
contractors in the period following September 17, 2001, did not bar the application of
the sovereign acts defense.
The Board’s conclusion that General Votel’s exclusion order was not directed at
Conner’s contract rights is further supported by the fact that the government gained no
economic advantage by refusing to admit Conner to the Ranger compound. See
Casitas, 72 Fed. Cl. at 755. The Corps of Engineers did not seek to shift its costs to
Conner, and it granted Conner contract extensions to compensate for the period in
which Conner was shut down. Because the government as contractor gained nothing
from barring Conner during the exclusion period, the exclusion order cannot be fairly
said to have been “tainted by the governmental object of self-relief.” See Winstar, 518
U.S. at 896 (principal opinion of Souter. J.). The broad reach of the exclusion order and
the absence of governmental self-interest indicate that the order was not specifically

-- 17 of 21 --

2008-1188 17
targeted at appropriating the benefits of a government contract and that any effect on
Conner’s contract rights was merely incidental to the achievement of a broader
governmental objective.
Granting Conner delay damages would also undercut one of the principal
rationales of the sovereign acts doctrine: that contractors dealing with the government
should not receive more favorable treatment than they would if contracting with a private
party. If Conner had contracted with a private company to construct a building
immediately outside Fort Benning, and the Army had temporarily excluded Conner from
its worksite after the attacks of September 11 in order to set up a security perimeter
around the base and to facilitate troop deployments, Conner would not have been able
to shift the costs resulting from the work stoppage to its private contracting partner
(absent a specific clause in the contract so providing). That being so, it would be
anomalous to grant Conner monetary damages in a parallel situation in which the only
difference is that the government, rather than a private party, was Conner’s contracting
partner.
In short, General Votel’s order excluding Conner from its worksite fits comfortably
within the category of actions that we have consistently upheld as sovereign acts. In
fact, the circumstances of this case closely parallel those in Wilson, where the
government contractor was refused entry into Washington, D.C., during the Civil War
pursuant to an exclusion order issued by the city’s military governor. Concluding that
the contractor’s exclusion was a sovereign act, the court in Wilson emphasized that the
order was, as here, issued by a military commander rather than a contracting agent and

-- 18 of 21 --

2008-1188 18
was “limited strictly to the public defense.” Wilson, 11 Ct. Cl. at 521.1 Like Wilson,
Conner suffered losses as a result of the exclusion order. As in Wilson, however, the
effect on Conner’s contract rights was incidental to the achievement of a broader
governmental objective relating to national security and therefore did not give rise to
governmental liability.
Conner further contends that even if the exclusion order constituted a public and
general act, the government cannot avoid liability because it failed to establish a
common-law impossibility defense. As explained in Winstar, even where the sovereign
acts doctrine applies, “the common-law doctrine of impossibility imposes additional
requirements before a party may avoid liability for breach.” Winstar, 518 U.S. at 904
(principal opinion of Souter, J.); see Carabetta, 482 F.3d at 1365. Thus, the
nonoccurrence of the act in question must have been a basic assumption of the
contract, and the government must not have assumed the risk that such an act would
occur. See Winstar, 518 U.S. at 905; Seaboard Lumber Co. v. United States, 308 F.3d
1283, 1294 (Fed. Cir. 2002). Conner argues that the government did in fact
contemplate that an emergency could result in a shutdown, and that by expressly
promising in the contract that Conner’s work would be performed in facilities that would
1 Conner is correct that the fact that the government may have had lawful
authority and valid reasons for taking an action is not sufficient to satisfy the “public and
general” requirement. Serving the public good is a necessary but insufficient condition
for asserting the sovereign acts defense. See Winstar, 518 U.S. at 903 (principal
opinion of Souter, J.) (noting that a purpose of advancing the public welfare cannot
“serve as a criterion of a ‘public and general’ sovereign act”). The key issue here—as in
all sovereign act cases—is not whether the government had the authority to exclude
Conner for national security purposes, but rather who should bear the cost of an action
that was admittedly in the public interest: a single contractor or the taxpayers at large.
The answer to that question turns on whether the governmental action was public and
general, not whether it served the public interest.

-- 19 of 21 --

2008-1188 19
be “unoccupied and vacant” during the course of construction, the government further
assumed the risk of any such occurrence, thereby precluding a valid impossibility
defense. We need not address the merits of this argument, however, because Conner
failed to raise it before the Board.
Conner attempts to avoid the consequences of its waiver of the “impossibility”
argument by noting that because the sovereign acts doctrine is an affirmative defense,
the government had the burden of establishing each element of the defense, including
the “impossibility” component. However, the sovereign acts doctrine was the
government’s sole defense to Conner’s liability claim and the focus of the argument
before the Board. In response to the government’s assertion of the defense, Conner
challenged the public and general nature of the exclusion order, disputed its
reasonableness, and questioned General Votel’s authority to shut down the construction
project. Conner did not, however, suggest that the elements of impossibility were not
satisfied. In particular, Conner did not suggest that the shutdown in response to a
national emergency was foreseeable or that the government assumed the risk of any
such occurrence. Having challenged the government’s assertion of the sovereign acts
defense before the Board, Conner was obliged to put forth all of its arguments against
the application of that defense. Because Conner failed to argue that the government
did not satisfy the “impossibility” requirement of the sovereign acts defense, it has
waived that argument for purposes of appeal.
IV
As an alternative ground for recovery, Conner contends that the Corps of
Engineers breached its implied duty to cooperate by failing to issue a suspension of

-- 20 of 21 --

2008-1188 20
work order after General Votel issued the exclusion order. As the Board found,
however, the contracting officer played no part in the decision to restrict access to the
Ranger compound. That decision was a sovereign act involving national security, and it
was unrelated to any interests of the government as contractor. The contracting officer
was under no obligation to issue a suspension of work order in response to an action
taken by the government in its sovereign capacity. Cf. Urban Plumbing & Heating Co.
v. United States, 408 F.2d 382, 392-93 (Ct. Cl. 1969) (finding that contracting officer
should have issued a suspension of work order where the government, acting in its
contractual capacity and for the convenience of the government as contractor, caused a
delay in performance). We therefore uphold the Board’s decision that Conner is not
entitled to recovery under the “suspension of work” clause of the contract, and we affirm
the Board’s ruling that Conner’s exclusion from the worksite qualified as a sovereign act
that relieved the government of liability for delay damages.
AFFIRMED.

-- 21 of 21 --

Continue sua pesquisa no ChatGPT ou Claude

Conecte o Omnilex para pesquisar o corpus jurídico pelo seu assistente de IA.