Michael W. Wynne, SECRETARY OF THE AIR FORCE v. Lockheed Martin Corporation

2008-1056Court of Appeals for the Federal Circuit7 de mar. de 2008

Abrir fonte

Texto completo

NOTE: This order is nonprecedential.
United States Court of Appeals for the Federal Circuit
2008-1056
Michael W. Wynne, SECRETARY OF THE AIR FORCE,
Appellant,
v.
LOCKHEED MARTIN CORPORATION,
Appellee.
Appeal from the Armed Services Board of Contract Appeals in no. 53822,
Administrative Judge Robert T. Peacock.
ON MOTION
Before PROST, Circuit Judge, FRIEDMAN, Senior Circuit Judge, and MOORE, Circuit
Judge.
PROST, Circuit Judge.
O R D E R
Lockheed Martin Corporation moves to dismiss for lack of jurisdiction the
Secretary of the Air Force’s appeal from a June 27, 2007 decision of the Armed
Services Board of Contract Appeals reversing the contracting officer's (CO) decision
and remanding the case to the parties to negotiate quantum. The Secretary opposes.
Pursuant to 28 U.S.C. § 1295(a)(10), our jurisdiction is limited to reviewing only
final decisions of the Board. Teledyne Continental Motors v. United States, 906 F.2d
1579, 1581 (Fed. Cir. 1990). “[A]n important focal point in ascertaining finality of a
board’s decision is the scope and extent of the contracting officer’s decision.” Teller
Envtl. Sys., Inc. v. United States, 802 F.2d 1385, 1389 (Fed. Cir. 1986).

-- 1 of 4 --

In his final decision, the CO presented a claim for a price adjustment of $32
million for increased costs to the government arising out of voluntary changes made by
Lockheed to its cost accounting practices, effective June 28, 1993 (collectively, the June
1993 changes). The $32 million claim constituted the total increased costs associated
with a variety of Lockheed’s contracts with the government. Included in the CO’s claim
was “approximately $14.8 million” for increased costs associated with a contract for the
engineering and manufacturing development of the Air Force’s F-22 fighter aircraft. The
F-22 contract was originally awarded to Lockheed in August 1991 but modified in
November 1993.
Lockheed agreed to pay approximately $17 million of the claim but appealed the
portion of the claim for increased costs associated with the F-22 contract to the Board.
Lockheed asserted that the Secretary was not entitled to increased costs for the F-22
contract associated with the June 1993 changes because such costs were subsumed in
the renegotiated price in the November 1993 modification agreement. On June 27,
2007, the Board issued its decision agreeing with Lockheed and sustaining its appeal.
Noting throughout its decision that the only issue being decided at that time was
entitlement, the Board remanded to the parties to negotiate quantum.
The Secretary appeals seeking review of the Board’s entitlement decision.
Lockheed contends, however, that the Board’s decision was not final and therefore not
reviewable at this time. In support of its motion Lockheed cites our decision in Teller. In
Teller, the contracting officer’s decision was adverse to the contractor on both
entitlement and quantum. Because both issues were before the Board and the Board
decided only entitlement and remanded any damages determination to the parties, we
2008-1056 2

-- 2 of 4 --

held in Teller that this court lacked jurisdiction over the appeal because there was no
final decision. Teller, 802 F.2d at 1390.
We agree with Lockheed that pursuant to the holding of Teller we lack jurisdiction
to review this appeal. Here, similar to Teller, the CO’s decision was adverse to
Lockheed on both entitlement and quantum. The CO determined that the government
was entitled to a total of $32 million, which included “approximately $14.8 million”
associated with the F-22 contract. In its decision, the Board specifically held that "the
precise dollar cost shifts associated with including or excluding the F-22 contract . . . are
uncertain." The Secretary disputes that statement and states in his opposition to the
motion to dismiss that "the board here determined that the Government [is] entitled to
no damages." The Secretary further states that "here, the board held that the amount of
damages recoverable upon the F-22 contract by the Government due [to] Lockheed's
Mid-Year Changes must necessarily be zero. Thus, there was nothing left to decide in
this case."
Nonetheless, the Board has not issued a final decision but has remanded to the
parties to determine quantum. If, as the government asserts, there is no quantum, the
parties should so inform the Board and the Board can issue a final decision. However,
as it now stands, the Board has stated that it has remanded an issue to the parties and
thus has not issued a final decision.
Accordingly,
IT IS ORDERED THAT:
(1) The motion to dismiss is granted.
2008-1056 3

-- 3 of 4 --

2008-1056 4
(2) Each side shall bear its own costs.
FOR THE COURT
March 7, 2008 /s/ Sharon Prost
Date Sharon Prost
Circuit Judge
cc: Stephen C. Tosini, Esq.
Terry L. Albertson, Esq.
s19
ISSUED AS A MANDATE: March 7, 2008

-- 4 of 4 --

Continue sua pesquisa no ChatGPT ou Claude

Conecte o Omnilex para pesquisar o corpus jurídico pelo seu assistente de IA.