Filed 2/10/17
CERTIFIED FOR PUBLICATION
COURT OF APPEAL, FOURTH APPELLATE DISTRICT
DIVISION ONE
STATE OF CALIFORNIA
WILLIAM BLANCHETTE et al., D070545
Petitioners, (Imperial County
Super. Ct. No. ECU9103)
v.
THE SUPERIOR COURT OF IMPERIAL
COUNTY,
Respondent;
GHA ENTERPRISES et al.,
Real Parties in Interest.
ORIGINAL PROCEEDINGS in mandate. L. Brooks Anderholt, Judge. Petition
granted.
JCL Law Firm and Jean-Claude Lapuyade for Petitioners.
No appearance for Respondent.
Wood Smith Henning & Berman and Brenda Nicole Radmacher for Real Parties
in Interest.
In this construction defect case we are called upon to interpret the notice and time
requirements of the Right to Repair Act (the act), Civil Code1 section 895 et seq. As we
explain, the goal of the act is to resolve, if possible, construction defect claims without
resort to litigation. In brief, the act requires that, before initiating litigation, construction
defect claimants must give a builder notice of alleged defects and if a builder wishes, an
opportunity to inspect and repair the noticed defects. The act requires that a claimant's
notice set forth the defects "in reasonable detail" sufficient to determine the nature and
location of the alleged defects. (§ 910.) A builder receiving the notice has 14 days in
which to acknowledge receipt of the claim and 14 additional days in which, if the builder
wishes, to inspect the premises; within 30 days after completing an inspection, a builder
may make an offer to repair the claimed defects. The act requires that its time limits and
other requirements be strictly construed. (§ 930, subd. (a).)
Here, we grant petitioner William Blanchette's petition for a writ of mandate and
direct that the trial court vacate its order staying proceedings pending Blanchette's
compliance with the act. As we explain, Blanchette's compliance with the act was
relieved by virtue of real party GHA, Enterprises, Inc.'s (GHA)2 failure to timely
acknowledge receipt of Blanchette's notice of a claim. Contrary to GHA's argument, the
act's goal of promptly resolving claims without resort to litigation cannot be achieved by
permitting homebuilders to serve tardy responses to claims or to ignore them entirely.
1 All further statutory references are to the Civil Code.
2 Unless otherwise indicated, all references to GHA include real parties in interest
GHA Enterprises, Inc., Rumax Ranch, LLC, and GHA Holdings, Inc.
2
FACTUAL AND PROCEDURAL BACKGROUND
Blanchette is the owner of one of 28 homes constructed by GHA. No later than
February 2, 2016, Blanchette served GHA with notice of a claim, which set forth a
number of alleged defects in all 28 homes; Blanchette's notice used, almost verbatim, the
language section 896 employs in setting forth building standards, the violation of which,
give rise to actionable claims against homebuilders.3 Attached to the notice of claims
3 Section 896 establishes the following as building standards which support a
construction defect claim:
"(a) With respect to water issues:
(1) A door shall not allow unintended water to pass beyond, around, or through the door
or its designed or actual moisture barriers, if any.
(2) Windows, patio doors, deck doors, and their systems shall not allow water to pass
beyond, around, or through the window, patio door, or deck door or its designed or actual
moisture barriers, including, without limitation, internal barriers within the systems
themselves. For purposes of this paragraph, 'systems' include, without limitation,
windows, window assemblies, framing, substrate, flashings, and trim, if any.
(3) Windows, patio doors, deck doors, and their systems shall not allow excessive
condensation to enter the structure and cause damage to another component. For purposes
of this paragraph, 'systems' include, without limitation, windows, window assemblies,
framing, substrate, flashings, and trim, if any.
(4) Roofs, roofing systems, chimney caps, and ventilation components shall not allow
water to enter the structure or to pass beyond, around, or through the designed or actual
moisture barriers, including, without limitation, internal barriers located within the
systems themselves. For purposes of this paragraph, 'systems' include, without limitation,
framing, substrate, and sheathing, if any.
(5) Decks, deck systems, balconies, balcony systems, exterior stairs, and stair systems
shall not allow water to pass into the adjacent structure. For purposes of this paragraph,
'systems' include, without limitation, framing, substrate, flashing, and sheathing, if any.
(6) Decks, deck systems, balconies, balcony systems, exterior stairs, and stair systems
shall not allow unintended water to pass within the systems themselves and cause damage
to the systems. For purposes of this paragraph, 'systems' include, without limitation,
framing, substrate, flashing, and sheathing, if any.
(7) Foundation systems and slabs shall not allow water or vapor to enter into the structure
so as to cause damage to another building component.
3
(8) Foundation systems and slabs shall not allow water or vapor to enter into the structure
so as to limit the installation of the type of flooring materials typically used for the
particular application.
(9) Hardscape, including paths and patios, irrigation systems, landscaping systems, and
drainage systems, that are installed as part of the original construction, shall not be
installed in such a way as to cause water or soil erosion to enter into or come in contact
with the structure so as to cause damage to another building component.
(10) Stucco, exterior siding, exterior walls, including, without limitation, exterior
framing, and other exterior wall finishes and fixtures and the systems of those
components and fixtures, including, but not limited to, pot shelves, horizontal surfaces,
columns, and plant-ons, shall be installed in such a way so as not to allow unintended
water to pass into the structure or to pass beyond, around, or through the designed or
actual moisture barriers of the system, including any internal barriers located within the
system itself. For purposes of this paragraph, 'systems' include, without limitation,
framing, substrate, flashings, trim, wall assemblies, and internal wall cavities, if any.
(11) Stucco, exterior siding, and exterior walls shall not allow excessive condensation to
enter the structure and cause damage to another component. For purposes of this
paragraph, 'systems' include, without limitation, framing, substrate, flashings, trim, wall
assemblies, and internal wall cavities, if any.
(12) Retaining and site walls and their associated drainage systems shall not allow
unintended water to pass beyond, around, or through its designed or actual moisture
barriers including, without limitation, any internal barriers, so as to cause damage. This
standard does not apply to those portions of any wall or drainage system that are designed
to have water flow beyond, around, or through them.
(13) Retaining walls and site walls, and their associated drainage systems, shall only
allow water to flow beyond, around, or through the areas designated by design.
(14) The lines and components of the plumbing system, sewer system, and utility systems
shall not leak.
(15) Plumbing lines, sewer lines, and utility lines shall not corrode so as to impede the
useful life of the systems.
(16) Sewer systems shall be installed in such a way as to allow the designated amount of
sewage to flow through the system.
(17) Showers, baths, and related waterproofing systems shall not leak water into the
interior of walls, flooring systems, or the interior of other components.
(18) The waterproofing system behind or under ceramic tile and tile countertops shall not
allow water into the interior of walls, flooring systems, or other components so as to
cause damage. Ceramic tile systems shall be designed and installed so as to deflect
intended water to the waterproofing system.
(b) With respect to structural issues:
(1) Foundations, load bearing components, and slabs, shall not contain significant cracks
or significant vertical displacement.
4
(2) Foundations, load bearing components, and slabs shall not cause the structure, in
whole or in part, to be structurally unsafe.
(3) Foundations, load bearing components, and slabs, and underlying soils shall be
constructed so as to materially comply with the design criteria set by applicable
government building codes, regulations, and ordinances for chemical deterioration or
corrosion resistance in effect at the time of original construction.
(4) A structure shall be constructed so as to materially comply with the design criteria for
earthquake and wind load resistance, as set forth in the applicable government building
codes, regulations, and ordinances in effect at the time of original construction.
(c) With respect to soil issues:
(1) Soils and engineered retaining walls shall not cause, in whole or in part, damage to
the structure built upon the soil or engineered retaining wall.
(2) Soils and engineered retaining walls shall not cause, in whole or in part, the structure
to be structurally unsafe.
(3) Soils shall not cause, in whole or in part, the land upon which no structure is built to
become unusable for the purpose represented at the time of original sale by the builder or
for the purpose for which that land is commonly used.
(d) With respect to fire protection issues:
(1) A structure shall be constructed so as to materially comply with the design criteria of
the applicable government building codes, regulations, and ordinances for fire protection
of the occupants in effect at the time of the original construction.
(2) Fireplaces, chimneys, chimney structures, and chimney termination caps shall be
constructed and installed in such a way so as not to cause an unreasonable risk of fire
outside the fireplace enclosure or chimney.
(3) Electrical and mechanical systems shall be constructed and installed in such a way so
as not to cause an unreasonable risk of fire.
(e) With respect to plumbing and sewer issues:
Plumbing and sewer systems shall be installed to operate properly and shall not
materially impair the use of the structure by its inhabitants. However, no action may be
brought for a violation of this subdivision more than four years after close of escrow.
(f) With respect to electrical system issues:
Electrical systems shall operate properly and shall not materially impair the use of the
structure by its inhabitants. However, no action shall be brought pursuant to this
subdivision more than four years from close of escrow.
(g) With respect to issues regarding other areas of construction:
(1) Exterior pathways, driveways, hardscape, sidewalls, sidewalks, and patios installed by
the original builder shall not contain cracks that display significant vertical displacement
or that are excessive. However, no action shall be brought upon a violation of this
paragraph more than four years from close of escrow.
(2) Stucco, exterior siding, and other exterior wall finishes and fixtures, including, but not
limited to, pot shelves, horizontal surfaces, columns, and plant-ons, shall not contain
significant cracks or separations."
5
was a list of the names and addresses of each of the owners of the 28 homes in the
development.
GHA responded to Blanchette's notice of claims by letter dated February 23, 2016.
GHA asserted the construction defects set forth in Blanchette's claim were not alleged
Borrowing from the language of the statute Blanchette alleged:
"Each window, patio doors, deck doors, and their systems allows water to pass
beyond, around, or through the window, patio door, or deck door or its designed or
actual moisture barriers, including, without limitation, internal barriers within the
systems themselves.
"Decks, deck systems, balconies, balcony systems, exterior stairs, and stair systems
allow water to pass into the adjacent structure.
"Stucco, exterior siding, and exterior walls allow excessive condensation to enter the
structure and cause damage to other components, including but not limited to floor
coverings, baseboards, drywall, doorjambs and door thresholds.
"Foundations, load bearing components, and slabs, contain significant cracks or
significant vertical displacement.
"Soils are causing damage to the structure built upon the soil in the form of cracked
concrete, cracked stucco, crack[ed] foundations and cracked drywall.
"Fireplaces, chimneys, chimney structures, and chimney termination [caps] were
constructed and installed in such a way as to cause an unreasonable risk of fire outside
the fireplace enclosure and chimney.
"Electrical systems operate improperly and materially impair the use of the structure
by Claimant.
"Living space air-conditioning was not provided in a manner consistent with the size
and efficiency design criteria specified in Title 24 of the California Code of
Regulations.
"Ceramic tile and tile backing was installed in such a manner that the tile detaches
throughout the Property."
6
with reasonable detail, as required by section 910, subdivision (a); nonetheless GHA
offered to inspect the homes.
Blanchette responded to GHA on February 26, 2016. Blanchette asserted that
GHA's response was untimely and excused him and the other homeowners from any
obligations under the act.
Thereafter, Blanchette filed a construction defect class action complaint against
GHA in the trial court. GHA responded to the complaint by moving to stay the action
until Blanchette satisfied the prelitigation requirements of the act. Blanchette opposed
the motion on the grounds GHA had not timely responded to his notice of claims.
The trial court agreed with GHA that Blanchette's notice of claim lacked detail
sufficient to trigger GHA's obligations under the act. Accordingly, the trial court stayed
the action pending completion of the notice and inspection procedures required by the act
and ordered that Blanchette serve a new notice of claims to "identify each individual
claimant by address," to "provide a defect list for each subject property, which sets forth
[the] alleged defects," to "set forth the location, nature and severity of each alleged
defect," and to identify "the code section(s) [the claimants] contend each alleged defect
violates."
Blanchette filed a petition for a writ of mandate in which he challenged the trial
court's order. We issued an order to show cause.
7
DISCUSSION
I
Blanchette's petition raises a novel issue under the act: when must defects in a
notice of claim be raised by a builder? We also note that because the trial court enforced
its interpretation of the act by way of a pretrial stay, Blanchette has no adequate remedy
by way of appeal. The novel issue raised by Blanchette's petition and the absence of an
adequate remedy by way of appeal support writ review here. (See Omaha Indemnity Co.
v. Superior Court (1989) 209 Cal.App.3d 1266, 1273-1274.)
II
The act, its purposes, and provisions were in many important respects considered
by the court in Darling v. Superior Court (2012) 211 Cal.App.4th 69 (Darling). In
Darling, the court rejected a homeowner's contention the document production required
of homebuilders under the act (§ 912) could be initiated in the absence of the notice of
claims required by section 910. (Darling, at p. 84.) However, neither Darling nor any
other case which has come to our attention, has directly considered when defects in the
notice of claim must be asserted by a builder.
As the court in Darling noted, the prelitigation requirements of the act are set forth
in Chapter 4 of the act, commencing with section 910. (Darling, supra, 211 Cal.App.4th
at p. 82.) The purpose of Chapter 4, "is to give a builder the opportunity to resolve a
homeowner's construction defect claim in an expeditious and nonadverserial manner.
[Citation.]" (Ibid.; see also Stats. 2002, ch. 722, § 1(b) & (c), p. 4247 [Chapter 4
8
intended to provided for "prompt and fair resolution of construction defect claims" and
"procedures for early disposition of construction defects claims."].)
"Chapter 4 begins with section 910. Section 910 requires a homeowner to serve
notice of a construction defect claim to commence the prelitigation process, before
bringing a lawsuit. The statute provides in relevant part: 'Prior to filing an action against
any party alleged to have contributed to a violation of the standards set forth in Chapter 2
(commencing with Section 896), the claimant shall initiate the following prelitigation
procedures: [¶] (a) The claimant or his or her legal representative shall provide written
notice via certified mail, overnight mail, or personal delivery to the builder, in the
manner prescribed in this section, of the claimant's claim that the construction of his or
her residence violates any of the standards set forth in Chapter 2 (commencing with
Section 896). That notice shall provide the claimant's name, address, and preferred
method of contact, and shall state that the claimant alleges a violation pursuant to this
part against the builder, and shall describe the claim in reasonable detail sufficient to
determine the nature and location, to the extent known, of the claimed violation. In the
case of a group of homeowners or an association, the notice may identify the claimants
solely by address or other description sufficient to apprise the builder of the locations of
the subject residences. That document shall have the same force and effect as a notice of
commencement of a legal proceeding.
"Compliance with section 910 is a prerequisite to filing a lawsuit against a
residential builder for construction defects. [Citations.] " (Darling, supra, 211
Cal.App.4th at pp. 75-76.)
9
After a notice of claim has been served under section 910, a process expressly
designed to permit the parties to resolve claims without resort to litigation commences.
As the court in Darling set forth, following service of notice: "the builder must
acknowledge in writing its receipt of the notice of the claim within 14 days after the
claim is received (§ 913); the homeowner is released from the requirements of the chapter
if the builder does not acknowledge receipt of the notice, elects not to go through the
process, or fails to request an inspection in a timely manner (§ 915); the builder must
complete its initial inspection and testing within 14 days after it acknowledges its receipt
of the notice of the claim (§ 916); the builder may offer in writing to repair the violation
and compensate the homeowner for applicable damages '[w]ithin 30 days of the initial or,
if requested, second inspection or testing' (§ 917); the homeowner has 30 days after
receipt of the repair offer to authorize the builder to proceed with the repair or request
alternative contractors (§ 918); the offer to repair shall be accompanied by an offer to
mediate the dispute if the homeowner chooses (§ 919); if the builder fails to make an
offer to repair or otherwise strictly comply with Chapter 4 within the times specified, the
homeowner is released from the requirements of the chapter and may proceed with the
filing of an action, and the homeowner may file an action if the contractor performing the
repair does not complete the repair in the time or manner specified (§§ 920, 925); and the
repairs shall commence within 14 days after acceptance or selection of an alternative
contractor or within seven days of the mediation, or within five days of permit issuance,
and must be done 'with the utmost diligence' and be 'completed as soon as reasonably
possible.' (§ 921.)" (Darling, supra, 211 Cal.App.4th 77-78.)
10
Importantly, section 930 provides: "(a) The time periods and all other
requirements in this chapter are to be strictly construed, and, unless extended by the
mutual agreement of the parties in accordance with this chapter, shall govern the rights
and obligations under this title. If a builder fails to act in accordance with this section
within the timeframes mandated, unless extended by the mutual agreement of the parties
as evidenced by a postclaim written confirmation by the affected homeowner
demonstrating that he or she has knowingly and voluntarily extended the statutory
timeframe, the claimant may proceed with filing an action. If this occurs, the standards of
the other chapters of this title shall continue to apply to the action. [¶] (b) If the claimant
does not conform with the requirements of this chapter, the builder may bring a motion to
stay any subsequent court action or other proceeding until the requirements of this
chapter have been satisfied. The court, in its discretion, may award the prevailing party
on such a motion, his or her attorney's fees and costs in bringing or opposing the motion."
III
When we are called upon to interpret a statute we begin with its express terms and,
if ambiguity or conflict arise, we resolve them by reference to the statute's purpose. (See
Darling, supra, 211 Cal.App.4th at p. 69.) Section 913 is clear. It provides that
following service of a notice of claim, a builder must acknowledge receipt of the notice
within 14 days. Section 910 provides the notice of claim must state the name and address
of the claimant or claimants and that the claim or claimants allege a violation of building
standards set forth in the act. Here, Blanchette's notice of claim met the requirements of
section 910. It provided his name and address and a statement alleging violations of the
11
act's building standards. Section 915 is equally explicit: "[i]f a builder fails to
acknowledge receipt of the notice of a claim within the time specified . . . this chapter
does not apply and the homeowner is released from the requirements of this chapter and
may proceed with the filing of an action." (Italics added.) We are obligated to strictly
enforce section 913's time limits. (§ 930.)
This brings us to the portion of section 910 that requires a notice of claim
"describe the claim in reasonable detail sufficient to determine the nature and location, to
the extent known, of the claimed violation." (Italics added.) Unlike the 14-day time limit
set forth in section 913 and the express consequence for failing to meet that deadline set
forth in section 915, whether a claim provides sufficient detail and the extent of a
claimant's knowledge are matters that will vary from case to case.
Based upon our reading of the applicable statutes, we conclude that where, as here,
a claimant provides his or her name and address and a statement alleging violation of
building standards, service of the notice will trigger the 14-day response time set forth in
section 913. If a builder believes the notice is not sufficient to determine the nature and
location of the claimed violation, the builder may within that 14-day period, bring the
lack of specificity to the claimant's attention. However, the requirement for specificity is
not a ground upon which the developer may choose to ignore the notice of a defect and
the 14-day time period within which it must respond. The need for specificity is intended
to guide the parties to a resolution before a potential legal dispute.
12
We believe our interpretation is consistent with the purpose of the act, which is to
promote resolution of a homeowner's construction defect claims "in an expeditious and
nonadverserial manner. [Citation.]" (Darling, supra, 211 Cal.App.4th at p. 82, italics
added; see also Stats. 2002, ch. 722, § 1(b) & (c), p. 4247.) Given its variability and
inherently subjective nature the "reasonable detail" requirement of section 910, is a
matter that should be promptly resolved, if it can be, by the parties and before litigation
commences. Plainly, an interpretation which permits a builder to ignore the time limits
of section 913 and nonetheless preserve its objection to the lack of detail in a notice and
require that the trial court then resolve the issue after litigation has commenced, will only
delay rather than accelerate resolution of construction defect claims. Requiring prompt
objection as to the detail set forth in a notice of claim is thus far more consistent with the
purpose of the act than permitting a builder to ignore a notice of claim or serve a tardy
acknowledgement.
A builder who receives proper notice of a potential defect is therefore obliged to
respond within the 14-day period as prescribed by statute. If the builder believes there is
insufficient specificity, it is obliged to respond to that effect. Thereafter the parties
through discussion and inspection can together determine and resolve any potential defect
issues.
As we have explained, a developer who unilaterally concludes the level of
specificity in a notice is insufficient, and therefore concludes it need not respond within
13
the 14-day period prescribed by statute, acts at its peril if later, it wishes to employ the
inspection and settlement process otherwise mandated by the statute.
Our construction of the act strictly applies the time limits of the act, as required by
its terms, but gives builders more than adequate opportunity to vindicate their right to a
reasonable specification of defects.
Here, we agree the notice of claim was served but on its face, was insufficient. It
simply repeats the language of section 896. It did not provide the "reasonable detail
sufficient to determine the nature and location, to the extent known" of claimed
violations, as required by section 910. While at the early stages of giving notice of
potential defects, the statutory process does not require a homeowner provide anything
approaching an expert opinion as to the nature and extent of the defects, without some
information about the nature and location of the circumstances which the claimants
believe support their claims, builders cannot be expected to meaningfully engage in the
inspection and resolution process required by the statute. For example, if a claimant
sends notice that a water stain has developed on a wall, that notice would be sufficient to
alert the developer as to the subcontractor that may be required to inspect the claimant's
concern. If the claimant sends notice that a crack has developed in the ceiling, the
developer may wish to inspect first to determine which subcontractor should further
respond in order to determine the nature and cause of the claimant's concern.
On the other hand, the record here is also clear that GHA did not acknowledge
receipt of Blanchette's notice of claim within the 14-day period prescribed by section
913. Contrary to the trial court's ruling, GHA's failure to timely acknowledge
14
Blanchette's notice of claim and resolve the issue of specificity relieved Blanchette of any
further obligations under the act.
Because GHA did not timely acknowledge receipt of Blanchette's claim and set
forth its objections to the information provided in the claim, Blanchette was "released
from the requirements of [the act]." (§ 915.)
DISPOSITION
Let a writ issue commanding respondent to vacate its order granting the motion to
stay filed by real parties in interest and to enter a new and different order denying the
motion. The stay issued by this court on July 13, 2016, is dissolved. Blanchette to
recover costs he incurred in this writ proceeding.
BENKE, Acting P. J.
WE CONCUR:
NARES, J.
IRION, J.
15