Ventura County Citizens Against Mega Gas v. City of Camarillo CA2/6

CourtListener 10782981Calctapp2 de fev. de 2026

Abrir fonte

Texto completo

Filed 2/2/26 Ventura County Citizens Against Mega Gas v. City of Camarillo CA2/6
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion
has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

SECOND APPELLATE DISTRICT

DIVISION SIX

VENTURA COUNTY 2d Civ. No. B344843
CITIZENS AGAINST MEGA (Super. Ct. No.
GAS, 2024CUWM022213)
(Ventura County)
Plaintiff and Appellant,

v.

CITY OF CAMARILLO et al.,

Defendants and
Respondents.

COSTCO WHOLESALE
CORPORATION,

Real Party in Interest.

The City of Camarillo and its city council (collectively, the
City) approved Costco Wholesale Corporation’s (Costco)
application to build a retail store and gasoline fueling station (the
project). Ventura County Citizens Against Mega Gas (VCCAMG)
appeals from the denial of a petition for writ of mandate. It
contends the City violated the California Environmental Quality
Act (Pub. Resources Code,1 § 21000 et seq.; CEQA) when it issued
a second subsequent mitigated negative declaration (SSMND)
instead of an environmental impact report (EIR). It contends the
City did not properly consider or mitigate substantial changes in
the project and in the surrounding area since approval of prior
versions of the project. We affirm.
FACTUAL AND PROCEDURAL HISTORY
In 2007, the City approved development of a commercial
center in Camarillo. The project included a maximum building
area of 499,000 square feet including multi-tenant retail,
restaurant, and office space. It also included 2,411 parking
spaces. The City adopted a general plan amendment, zoning
amendments, a commercial planned development permit (CPD),
conditional use permit (CUP), and a mitigated negative
declaration (MND).2
Approval of the original project was subject to 224
conditions. Traffic impacts were analyzed and on-site and off-site
improvements were required to accommodate traffic associated
with the project, including payment of a traffic mitigation fee.
Mitigation conditions included a $651,222 payment to the

1 Undesignated statutory references are to the Public
Resources Code.

2 A “mitigated negative declaration” is prepared when the
initial study about the project identifies potentially significant
effects on the environment, but the applicant agrees to conditions
that would avoid the effects or mitigate them to a point that does
not have a significant effect on the environment. (§ 21064.5.)

2
transportation demand management fund to reduce emissions of
reactive organic compounds (ROC) and nitrogen oxides (NOx).
Air quality mitigation conditions included “fugitive dust control
measures” during excavation and reduction of air pollution
emissions, including limiting truck idling time, alternate fuel for
construction equipment if cost effective, and minimizing use of
construction equipment and vehicles during smog season.
In 2011, the City approved an addendum to the MND. The
site layout was changed to increase the building area for an
anchor tenant (Lowe’s) to 155,628 square feet and to add a
drive-through restaurant. The overall maximum building space
remained at 499,000 square feet. The number of parking spaces
was reduced to 2,074. Approval was subject to 255 conditions,
including continuation of the previous air quality requirements, a
traffic mitigation fee, and funds for local transit.
In 2016, the City adopted a subsequent mitigated negative
declaration (SMND) reflecting changes in the layout and building
elevations. It included a small increase to 157,801 square feet for
the anchor tenant. The maximum total building development
remained at 499,000 square feet. The mitigation conditions
remained the same as the 2011 addendum.
The project as approved in 2007, 2011, and 2016 was not
built. But in 2022, Costco applied to modify the project to build a
163,177 square foot retail warehouse and freestanding fuel
facility with 16 dispensers (32 fueling positions).
Following a public hearing, the City’s planning commission
approved the project, including modification of the CPD,
approving a CUP, and adopting the SSMND. The SSMND was
prepared by Cadence Environmental Consultants (Cadence) and
was 3,366 pages long. It analyzes 18 categories of environmental

3
impacts, including air quality, wildfire, energy, transportation,
biological resources, hazardous materials, population, and
housing. The planning commission found “there are no
environmental impacts that cannot be adequately mitigated.”
Mitigation conditions in the SSMND included a timetable for
implementing each measure and for monitoring compliance.
VCCAMG appealed to the city council. (§ 21151, subd. (c).)
The council held a public hearing and reviewed the project de
novo. A Cadence representative stated the addition of a gas
station was “not minor,” but an SSMND rather than an EIR was
appropriate because the mitigation conditions would reduce
environmental impacts to a less than significant level. He said
that if an EIR were prepared, it would add “a few more sections”
but would not provide the City with any new information. The
council denied the appeal and adopted the SSMND.
VCCAMG filed a petition for writ of mandate requesting
the City order an EIR. The trial court denied the petition.
(§ 21168; Code Civ. Proc., § 1094.5.)3
DISCUSSION
VCCAMG contends the City erred in approving Costco’s
project based on the SSMND rather than an EIR in violation of
CEQA. We are not persuaded. As discussed below, substantial
evidence does not support a fair argument that changed
circumstances would produce new significant environmental
effects that would not be effectively remediated by the SSMND

3 The court also dismissed VCCAMG’s claim for declaratory
relief as “not appropriate to review an administrative decision.”
(State of California v. Superior Court (1974) 12 Cal.3d 237, 249.)

4
mitigation conditions. (CEQA Guidelines,4 § 15162, subd. (a)(1)
& (2); Friends of College of San Mateo Gardens v. San Mateo
County Community College Dist. (2017) 11 Cal.App.5th 596, 607
(Friends II).)
“An appellate court’s review of the administrative record
for legal error and substantial evidence in a CEQA case, as in
other mandamus cases, is the same as the trial court’s: The
appellate court reviews the agency’s action, not the trial court’s
decision; in that sense appellate judicial review under CEQA is
de novo.” (Vineyard Area Citizens for Responsible Growth, Inc. v.
City of Rancho Cordova (2007) 40 Cal.4th 412, 427.) We
“independently determin[e] whether the administrative record
demonstrates any legal error by the [City] and whether it
contains substantial evidence to support the [City’s] factual
determinations.” (Ibid.)
VCCAMG has the burden to show substantial evidence that
changed circumstances required preparation of an EIR. (Citizens
for a Megaplex-Free Alameda v. City of Alameda (2007) 149
Cal.App.4th 91, 112.) “ ‘The event of a change in a project is not
an occasion to revisit environmental concerns laid to rest in the
original analysis. Only changed circumstances . . . are at issue.’ ”
(Friends of College of San Mateo Gardens v. San Mateo County
Community College Dist. (2016) 1 Cal.5th 937, 949 (Friends I).)
Therefore, here we review only the incremental effects of Costco’s
project compared to the earlier projects. (Temecula Band of
Luiseño Mission Indians v. Rancho Cal. Water Dist. (1996) 43
Cal.App.4th 425, 438.)

4 The Natural Resources Agency’s CEQA Guidelines are
contained in California Code of Regulations, title 14, section
15000 et seq.

5
Forfeiture
The City and Costco contend that VCCAMG forfeited
challenges regarding wildfire risk, traffic, and biological
resources by failing to raise them in the administrative
proceedings and/or trial court. We disagree. These issues were
preserved because they were raised below “by any person”
(§ 21177, subd. (a)) and “ ‘fairly apprise[d] the agency of the
substance of the objection so that it ha[d] an opportunity to
evaluate and respond to it.’ ” (Arcadians for Environmental
Preservation v. City of Arcadia (2023) 88 Cal.App.5th 418, 431.)
Regarding the risk of wildfires, the City sent a letter to
Costco requesting more information regarding several topics,
including the risk of fire from the proximity of electric vehicle
charging stations to fuel pumps. Wildfire risk was also raised in
the mandamus petition. Traffic concerns were discussed in a
letter from VCCAMG to the City, and in the mandamus petition.
Biological resources, specifically bird populations, were discussed
in a letter to the City from the Audubon Society. VCCAMG also
challenged the effect of the project on wildlife and birds in its
letter to the City and in the mandamus petition.
But we will not consider contentions raised for the first
time in VCCAMG’s reply brief, i.e., risks of a fueling station
under an airport flight path, ignition/explosion risk of
underground fuel tanks, untimely consideration of diesel truck
idling, and the adequacy of the 0.25-mile radius for evaluation of
air quality effects. (In re Groundwater Cases (2007) 154
Cal.App.4th 659, 693.)
CEQA framework
A lead agency must prepare an EIR before approving a
project “which may have a significant effect on the environment.”

6
(§ 21151, subd. (a); Friends I, supra, 1 Cal.5th at p. 943.) But
when “[t]he initial study shows that there is no substantial
evidence, in light of the whole record before the agency, that the
project may have a significant effect on the environment,” an
agency shall prepare a “negative declaration” rather than an EIR.
(CEQA Guidelines, §§ 15070, subd. (a), 15063, subd. (b)(2), 15371;
§ 21064.)
But if “the initial study has identified potentially
significant effects on the environment,” and the applicant agrees
to “revisions in the project plans or proposals” that “would avoid
the effects or mitigate the effects to a point where clearly no
significant effect on the environment would occur,” an agency
shall prepare an MND. (§ 21064.5; CEQA Guidelines, § 15070,
subd. (b); Friends II, supra, 11 Cal.App.5th at p. 604.)
Subsequent changes
The CEQA Guidelines include a subsequent review
provision that applies following adoption of an EIR, a negative
declaration, or an MND. (CEQA Guidelines, § 15162; Friends II,
supra, 11 Cal.App.5th at p. 604; see § 21166.) An EIR shall not
be prepared unless substantial evidence establishes that
“[s]ubstantial changes are proposed in the project [or in the
circumstances under which the project is undertaken] which will
require major revisions of the previous . . . negative declaration
due to the involvement of new significant environmental effects
or a substantial increase in the severity of previously identified
significant effects,” or, in some cases, based on new information
that “could not have been known with the exercise of reasonable
diligence.” (CEQA Guidelines, § 15162, subd. (a).)
“An agency that proposes project changes thus must
determine whether the previous environmental document retains

7
any relevance in light of the proposed changes and, if so, whether
major revisions to the previous environmental document are
nevertheless required due to the involvement of new, previously
unstudied significant environmental impacts.” (Friends I, supra,
1 Cal.5th at p. 944.) “[W]hether ‘the original environmental
document’ . . . ‘retains some informational value’ . . . is a
‘predominantly factual question.’ ” (Friends II, supra, 11
Cal.App.5th at p. 604.) We review this determination for
substantial evidence. (Id. at p. 605.)
Here, preparation of the SSMND included review of the
environmental evaluations in the 2007 MND and 2016 SMND.
To determine whether the City properly relied on these prior
environmental reviews when adopting the SSMND rather than
preparing an EIR, we first determine whether “substantial
evidence supports an agency’s decision to proceed under CEQA’s
subsequent review provisions.” (Friends I, supra, 1 Cal.5th at
p. 953.) “We expect occasions when a court finds no substantial
evidence to support an agency’s decision to proceed under CEQA’s
subsequent review provisions will be rare, and rightly so; ‘a court
should tread with extraordinary care’ before reversing an
agency’s determination, whether implicit or explicit, that its
initial environmental document retains some relevance to the
decisionmaking process.” (Ibid.)
Substantial evidence here supports the City’s decision to
consider prior environmental reviews because they remained
relevant. For example, the City noted that the 2007 MND
concluded the project would not have a substantial adverse effect
on any sensitive species. The City also relied on the 2016
SMND’s conclusion that the project “would not change the
location, type, or amount of development originally evaluated”

8
and would have “no new impacts on biological resources.” The
City reached the same conclusion regarding biological resources
for the current application, i.e., the “location, type, or maximum
amount of development” remained the same. Comparisons with
the 2007 and 2016 reports were also made regarding other topics,
including air quality and wildfire risks. Regarding traffic, the
SSMND analyzed data regarding average daily trips contained in
the 2007 and 2016 reports and updated this information based on
the new methodology regarding vehicle miles traveled.
The City also concluded the amount of development was
“within the project impact analysis” adopted in 2016. The total
maximum building footage did not change and the area for the
anchor tenant increased by less than 4 percent. Accordingly, the
City carried the prior mitigation conditions forward in the
SSMND. Because the 2007 and 2016 environmental reviews
analyzed data still relevant to Costco’s proposal, substantial
evidence supported consideration of those reviews.
Environmental effects
Having concluded the City properly considered the prior
environmental reviews, we turn to the question of whether an
EIR was required after the 2007 MND. VCCAMG contends an
EIR was required because a “fair argument” was made regarding
new significant environmental effects that were not effectively
remediated by the SSMND mitigation conditions. (Friends II,
supra, 11 Cal.App.5th at p. 607.) It contends that such effects
were shown regarding building size, addition of a fuel facility, air
quality, parking, wildfire risk, energy impacts, traffic, biological
resources, urban decay, and cumulative impacts. We conclude
that no EIR was required. After implementing mitigation
conditions, there is no substantial evidence of changes in the

9
project or in the surrounding community that would create “new
significant environmental effects or a substantial increase in the
severity of previously identified significant effects.” (CEQA
Guidelines, § 15162, subd. (a)(1) & (2).)
1. Building size
The proposed Costco building is 163,177 square feet,
slightly larger than the 157,801 square feet for the proposed
anchor tenant in the 2016 SMND. But the total maximum
building area for the project remained at 499,000 square feet.
The City reasonably concluded that this change did not establish
a new or more severe environmental effect. (§ 21166, subd. (a);
CEQA Guidelines, § 15162, subd. (a)(1); Concerned Dublin
Citizens v. City of Dublin (2013) 214 Cal.App.4th 1301, 1318
[shifting location of units within project not significant change];
Fund for Environmental Defense v. County of Orange (1988) 204
Cal.App.3d 1538, 1545 [7 percent increase in developed area not
significant].)
2. Fuel facility
VCCAMG contends an EIR was required because the
former environmental reviews did not include a fueling facility.
It claims that adding a fueling facility with 32 fueling positions
and underground tanks is a “fundamental” change with “great”
environmental impacts. But VCCAMG did not meet its burden to
show the addition of a fuel facility created new significant
environmental effects or a substantial increase in their severity.
(CEQA Guidelines, § 15162, subd. (a)(1).) “Opinions which state
‘nothing more than “it is reasonable to assume” that something
“potentially . . . may occur” ’ do not constitute substantial
evidence.” (Magan v. County of Kings (2002) 105 Cal.App.4th
468, 477.)

10
VCCAMG also expressed concern that excavation to bury
underground fuel tanks would release “fugitive dust” into the air,
and the fueling process and vehicle idling would pollute the air.
But as discussed below, the SSMND considered these air quality
impacts and imposed conditions to mitigate them.
3. Air quality
The City’s air quality analysis was conducted pursuant to
Ventura County Air Pollution Control District (VCAPCD)
methodology. The analysis would have been identical for an EIR.
The SSMND updated pollution data from the 2007 analysis by
including an evaluation of air quality impacts.
The SSMND continued the mitigation conditions of the
2007 MND and 2016 SMND to control fugitive dust during
construction including: watering areas to be excavated and
excavated material; enclosing, covering, or stabilizing material
stockpiles; and daily sweeping of adjacent streets. The City
concluded these conditions would reduce the fugitive dust impact
to a less than significant level.
The SSMND noted that unlike the previous proposals, the
operation of the fueling facility would produce toxic air
contaminants (TACs). But they were calculated as below
VCAPCD thresholds of significance. The report concluded that
carbon monoxide emissions would be less than significant
because no intersections near the project were classified as
“congested” where carbon monoxide would concentrate.
VCCAMG does not cite any contrary evidence.
VCCAMG has not shown that the City failed to consider
new residential housing near the project, including senior
apartments. The City evaluated “health impacts to off-site
receptors, including nearby residential and worker receptor

11
populations” within 0.25 miles of the project, including north of
Highway 101. The health risk to nearby residents, including
sensitive residents, was calculated as below the VCAPCD
significance thresholds. While VCAPCD classifies “retirement
homes” as “sensitive receptors,” VCCAMG has not shown that
this definition would encompass the senior apartments near the
project.
The SSMND also concluded that construction of the project
would generate more than 25 pounds of ROC and/or NOx. Based
on the City’s CEQA Guidelines, this would constitute a
potentially significant impact. But mitigation conditions,
including limiting truck and equipment idling time, alternate
fuels for construction equipment, and limiting vehicle and
equipment use during smog season, would reduce emissions from
heavy-duty construction equipment with the same impact as the
2016 SMND.
Emissions from operating the project were also mitigated
by a $651,222 contribution to the transportation demand
management fund, “which would mitigate its air quality impacts
to a less than significant level.” Payments to such funds are a
valid mitigation condition. (See Save our Peninsula Committee v.
Monterey County Bd. of Supervisors (2001) 87 Cal.App.4th 99,
139–140 [traffic impact fee].) The contribution amount was
calculated using the VCAPCD methodology, i.e., pounds of
emissions over the threshold amount for a four-year period,
multiplied by the cost per unit of pollutant reduced. VCCAMG
has not shown that the amount calculated was not “ ‘roughly
proportional’ to the impacts of the project.” (CEQA Guidelines,
§ 15126.4, subd. (a)(4)(B).)
VCAPCD submitted a memorandum that included several

12
“comments” about the project. It did not oppose payments to
off-site mitigation fund programs. And it also “recommend[ed]”
the City consider “all feasible on-site mitigation.” Among
potential on-site measures were “reducing [the] number of fuel
pumps or staging area capacity.” But VCAPCD did not dispute
the conclusion that the mitigation conditions adopted would
reduce the air quality impact to below significant levels.
The City adopted all of VCAPCD’s suggestions except
reducing the number of fuel pumps and compressed work
schedules. As requested by VCAPCD, the City “consider[ed]”
these suggestions. Costco’s traffic expert advised the planning
commission that the number of pumps does not directly influence
the number of Costco members or their gas consumption, and
that experience at other Costco locations showed 32 fueling
positions reduced vehicle queues and idling time. Costco
explained that compressed work schedules were not feasible
because employees must work onsite. The City’s decision to not
implement some of VCAPCD’s suggested options does not
constitute a “disagreement among expert opinion” that would
require preparation of an EIR. (See CEQA Guidelines, § 15064,
subd. (g).)
4. Parking
Based on the square footage of the retail uses, a minimum
of 788 parking spaces were required. The current application
included 901 parking spaces. The SSMND found the project
consistent with a City policy to provide sufficient on-site parking
to discourage parking on residential streets.
VCCAMG contends the trial court “ignored th[e] evidence”
that providing extra parking spaces would cause “increased
impervious surface, heat island effects, greenhouse gas

13
emissions, and conflicts with State ZEV policy.” We conclude this
contention is forfeited because VCCAMG does not direct us to any
such evidence in the record and cites only its own public comment
letter which does not mention these purported effects. (Cal.
Rules of Court, rule 8.204(a)(1)(C); L.O. v. Kilrain (2023) 96
Cal.App.5th 616, 619–620.)
5. Wildfire risk
The SSMND noted that the 2007 MND and 2016 SMND
did not evaluate wildfire risks as a separate topic, and the state
subsequently adopted thresholds of significance for wildfire
impacts. However, the MND and SMND included evaluation of
wildfire risks in their discussions of hazardous materials and
concluded the project would have no wildfire impact because it
was not adjacent to wildlands or located in a fire hazard zone.
Because the current application did “not change the location,
type, or maximum amount of development,” the SSMND
concluded that no new significant wildfire impacts were shown.
The SSMND also carried forward the 2007 and 2016 fire safety
measures, i.e., the building plans must incorporate fire
department recommendations for fire safety, and the fire
department must approve the plans. No error has been shown.
6. Energy impacts
CEQA requires “a discussion of the potential energy
impacts of proposed projects, with particular emphasis on
avoiding or reducing inefficient, wasteful and unnecessary
consumption of energy.” (CEQA Guidelines, appen. F, § I; see
§ 21100, subd. (b)(3); League to Save Lake Tahoe v. County of
Placer (2022) 75 Cal.App.5th 63, 164–168.)
The City concluded the project did not involve new
significant energy impacts. It reasoned that the construction

14
equipment and methods would be typical and not unusually
energy intensive. It also considered that the project would
comply with California’s Building Energy Efficiency Standards
(Cal. Code Regs., tit. 24, part 6, § 10-101 et seq.) and the
California Green Building Standards Code (Cal. Code Regs., tit.
24, part 11, § 101.1 et seq.). The City concluded the project was
not wasteful or inefficient, and did not consume unnecessary
energy. We conclude there was no error.
One method of conserving energy is “increasing reliance on
renewable energy sources,” with options including alternate or
renewable fuels or energy systems. (CEQA Guidelines, appen. F,
§§ I, II, subd. D.4.) The City considered a supplemental energy
analysis that quantified the project’s energy use during
construction and operation, and discussed renewable energy and
energy conservation measures. It found the building was
designed to accommodate future solar panel installation, and no
other on-site renewal energy sources were available.
The SSMND included conditions to reduce emissions,
including requiring solar or low-emission water heaters in the
commercial buildings, and construction of bus stops and shelters.
Conditions in the CPD and CUP included payment of a traffic
mitigation fee, measures to reduce equipment pollutant
emissions during construction, and a program to reduce mobile
emissions.
Costco also agreed “that the project will employ the
sustainable design features to reduce energy use described in the
Supplemental Energy Analysis . . . including entering into a
Retail Power Purchase Agreement (PPA) directly with a clean
energy retailer to provide 100 percent clean power.” This
agreement furthered use of renewable energy sources.

15
In summary, VCCAMG fails to establish new significant
environmental effects regarding energy use (CEQA Guidelines,
§ 15162, subd. (a)(1)), or that the City’s analysis of the issue was
insufficient.
7. Traffic
The SSMND concluded the project “would have different
trip generating characteristics than the [previously] approved
shopping center uses.” It therefore included a memorandum that
analyzed daily trip generation and vehicle miles traveled. The
City analyzed miles traveled by employees and new Costco
members, which was partially offset by the reduction in miles
traveled by Camarillo residents who would otherwise drive to
existing Costco stores. The SSMND concluded the Costco
proposal would result in 4,591 fewer daily vehicle miles traveled
than the previously approved 2016 project. VCCAMG has not
shown that the traffic effects would create “a substantial increase
in the severity of previously identified significant effects.” (CEQA
Guidelines, § 15162, subd. (a)(1).)
Because the traffic associated with the current application
was less than that of the previous proposal, it was unnecessary to
conduct a traffic survey to analyze whether an additional lane
should be added to Las Posas Road over the freeway. The City
properly concluded that a survey might be necessary in the future
if a proposal were made to develop the western portion of the
property. Because no such proposal had been made, and the City
did not give advance approval for such a proposal, the City did
not improperly approve the Costco project “before fully evaluating
its environmental effects.” (Save Tara v. City of West Hollywood
(2008) 45 Cal.4th 116, 142.)

16
8. Biological resources
The Ventura Audubon Society expressed concern about the
effect of the current application on bird populations and
contended a 2004 biological survey was outdated. The SSMND
concluded that “no new potential impacts to biological resources
were expected for the proposed project” because the project site is
not classified as “open space,” and ground cover at the site was
regularly controlled by goats brought in for that purpose.
VCCAMG fails to establish new significant environmental effects.
(CEQA Guidelines, § 15162, subd. (a)(1).)
Biologists also conducted an updated assessment of the
project in April 2022, which recommended completion of a
nesting bird survey before construction. If active nests were
found, a buffer zone would be maintained until the nests were no
longer active. The conditions of the CPD and CUP require (not
just recommend, as VCCAMG contends) performance of a nesting
bird survey before construction, reporting the findings to the
City, limitation of construction in a buffer zone around any active
nests, and weekly monitoring of nests by a qualified biologist
compliant with Fish and Game Code section 3503.5 and the
Migratory Bird Treaty Act (16 U.S.C. § 703 et seq.).
Preconstruction surveys and buffer zones are appropriate
mitigation conditions. (Save Panoche Valley v. San Benito
County (2013) 217 Cal.App.4th 503, 524.) VCCAMG has not
shown that these conditions fail to establish a “reporting or
monitoring program” or are not “fully enforceable through permit
conditions, agreements, or other measures.” (§ 21081.6, subds.
(a)(1), (b).)
9. Urban decay
VCCAMG contends the project would result in urban decay.

17
(Joshua Tree Downtown Business Alliance v. County of San
Bernardino (2016) 1 Cal.App.5th 677, 685 (Joshua Tree).) The
only evidence in support of this theory was the public comment of
a gas station/convenience store owner stating that the Costco fuel
station “could prove devastating to” his business and the
livelihoods of his employees. He did not say the project would
cause him to close his business. Nor does VCCAMG establish
that he made his comment as an “expert” that would constitute a
“disagreement among expert opinion” requiring preparation of an
EIR. (CEQA Guidelines, § 15064, subd. (g).) The record does not
establish that he was a qualified expert, with “ ‘special
knowledge, skill, experience, training, or education . . . on the
subject to which his testimony relates’ ” that is “ ‘[r]elated to a
subject that is sufficiently beyond common experience that the
opinion of an expert would assist the trier of fact.’ ” (Tesoro del
Valle Master Homeowners Assn. v. Griffin (2011) 200 Cal.App.4th
619, 639; Evid. Code, §§ 720, subd. (a), 801, subd. (a).) The
statements here were not expert testimony because they
“ ‘consist[ed] of inferences and conclusions which can be drawn as
easily and intelligently by the trier of fact as by the witness.’ ”
(Tesoro del Valle Master Homeowners Assn., at p. 639.)
An impact on a competing business does not necessarily
constitute urban decay. Economic effects of a project are not
treated as significant effects on the environment unless they
cause physical changes to the environment. (§ 21080, subd.
(e)(2); CEQA Guidelines, §§ 15064, subd. (e), 15131.) The fact
that “ ‘constructing big-box retail stores . . . may drive smaller
retailers out of business is not an effect covered by CEQA.
[Citation.] Only if the loss of businesses affects the physical
environment—for example, by causing or increasing urban

18
decay—will CEQA be engaged.’ ” (Joshua Tree, supra, 1
Cal.App.5th at p. 685.)
VCCAMG has presented no evidence that closing one gas
station would have effects such as “ ‘visible symptoms of physical
deterioration that invite vandalism, loitering, and graffiti that is
caused by a downward spiral of business closures and multiple
long term vacancies[,] . . . plywood-boarded doors and windows,
. . . dumping of refuse on site, overturned dumpsters, broken
parking barriers, broken glass littering the site, dead trees and
shrubbery together with weeds, lack of building maintenance,
abandonment of multiple buildings, homeless encampments, and
unsightly and dilapidated fencing.’ ” (Joshua Tree, supra, 1
Cal.App.5th at p. 685.)
VCCAMG contends “multiple residents” and “detailed
testimony” expressed concerns about such risks. But it has
forfeited this claim by failing to provide specific citations to the
record to support it. (Cal. Rules of Court, rule 8.204(a)(1)(C);
L.O. v. Kilrain, supra, 96 Cal.App.5th at pp. 619–620.) Moreover,
“ ‘[i]n the absence of a specific factual foundation in the record,
dire predictions by nonexperts regarding the consequences of a
project do not constitute substantial evidence.’ ” (East
Sacramento Partnerships for a Livable City v. City of Sacramento
(2016) 5 Cal.App.5th 281, 297.)
10. Cumulative impacts
VCCAMG contends the City failed to properly evaluate the
“project’s potentially significant exacerbating effects on existing
environmental hazards.” (California Building Industry Assn. v.
Bay Area Air Quality Management Dist. (2015) 62 Cal.4th 369,
388 (California Building Industry Assn.).) We are not persuaded.
A “vague claim of exacerbation, without any factual support, is

19
insufficient. . . . ‘ “Unsubstantiated opinions, concerns, and
suspicions about a project, though sincere and deeply felt, do not
rise to the level of substantial evidence.” ’ ” (East Sacramento
Partnerships for a Livable City v. City of Sacramento, supra, 5
Cal.App.5th at p. 297.)
The SSMND analyzed air quality impacts to nearby
residential developments and the area in general. It concluded
that VCAPCD guidelines do not “require an analysis of
cumulative impacts with existing facilities,” such as Highway 101
or other existing streets and highways.
Here, the air quality impacts from the project do not
exacerbate the pollution from Highway 101 any more than
pollution from any other source. Thus, it was unlike the example
given in California Building Industry Assn. where a project’s
construction activities could exacerbate an existing hazard by
dispersing a hazardous chemical currently dormant in the soil of
an abandoned gas station. (California Building Industry Assn.,
supra, 62 Cal.4th at p. 389.) Nor has VCCAMG “identified any
deficiencies or omissions in [the City’s] analysis” or shown that
“the project had impacts not contemplated” by the SSMND.
(Covina Residents for Responsible Development v. City of Covina
(2018) 21 Cal.App.5th 712, 731.)
Adoption of SSMND
An EIR is required only “if the project modification
introduces previously unstudied and potentially significant
environmental effects that cannot be avoided or mitigated
through further revisions to the project plans.” (Friends II,
supra, 11 Cal.App.5th at pp. 606–607, italics added.)
Here, the City updated the prior analyses with new data
and analysis on topics including air quality, wildfire, energy,

20
traffic, and biological resources. The SSMND adopted by the City
was supported by a wealth of statistics, calculations, maps, and
studies. In our view, the City properly determined that an
SSMND, circulated for public review, was the appropriate vehicle
to address changed circumstances because mitigation conditions
were sufficient to reduce the new impacts to a less than
significant level. (CEQA Guidelines, § 15070, subd. (b).)
VCCAMG has not shown a “disagreement among expert opinion”
that would require preparation of an EIR. (See CEQA
Guidelines, § 15064, subd. (g).) Thus, we conclude VCCAMG
failed to establish a “fair argument” (Friends II, supra, 11
Cal.App.5th at p. 607) that new significant environmental effects
were not effectively remediated by the SSMND mitigation
conditions.
DISPOSITION
The judgment is affirmed. Respondents and real party
shall recover their costs on appeal.
NOT TO BE PUBLISHED.

BALTODANO, J.

We concur:

YEGAN, Acting P. J. CODY, J.

21
Mark S. Borrell, Judge

Superior Court County of Ventura

______________________________

Finney Arnold, Tal C. Finney and Shaune B. Arnold for
Plaintiff and Appellant.
Burke Williams & Sorensen, Rachel H. Richman, Kevin D.
Siegel and Connon T. MacLean for Defendants and Respondents.
Armbruster Goldsmith & Delvac and Damon P. Mamalakis
for Real Party in Interest.