CourtListener 10024679•City of Irvine v. Kingston Kohr, LLC CA4/3
City of Irvine v. Kingston Kohr, LLC CA4/3
CourtListener 10024679Calctapp30 de jul. de 2024
Texto completo
Filed 7/30/24 City of Irvine v. Kingston Kohr, LLC CA4/3
NOT TO BE PUBLISHED IN OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FOURTH APPELLATE DISTRICT
DIVISION THREE
CITY OF IRVINE,
Plaintiff and Respondent, G061805, G061821, G061858
v. (Super. Ct. No. 30-2022-
01261652)
KINGSTON KOHR, LLC,
OPINION
Defendant and Appellant.
Consolidated appeal from orders of the Superior Court of Orange
County, Sandy N. Leal, Judge. Affirmed. Appellant’s motion to augment the
record. Granted.
Carney Mehr and Kendra Carney Mehr for Defendant and
Appellant.
Rutan & Tucker and Noam Duzman for Plaintiff and Respondent.
This consolidated appeal stems from a nuisance abatement action
initiated by the City of Irvine (the City) after a fire destroyed the roof of a
26,000 square foot industrial building owned by appellant Kingston Kohr, LLC
(Owner), leaving the concrete tilt-up walls at risk of collapse. Owner appeals
from three related orders issued by the trial court: the inspection and
abatement warrant that authorized the City to enter Owner’s property (the
Property) and demolish the building (the warrant, or the abatement warrant),
an extension of the warrant, and the denial of Owner’s motion to quash the
warrant. Owner does not dispute the building was a nuisance subject to
abatement and that it elected to demolish, rather than repair, the structure.
Nevertheless, Owner contends the City deprived it of due process by obtaining
the abatement warrant without showing (1) it gave Owner the opportunity to
demolish the building itself and (2) Owner was unable or unwilling to do so.
We affirm. The trial court’s orders are supported by substantial
evidence that the City complied with Owner’s due process rights before seeking
the warrant to demolish Owner’s building. The City gave Owner notice and an
opportunity to be heard and a reasonable opportunity to elect to repair its
building before the City proceeded with demolition. We disagree with Owner’s
contention that, once it elected not to repair the building, it had a due process
right to conduct the demolition itself to control or minimize demolition costs.
In any event, substantial evidence supports the conclusion that the City
attempted to give Owner that opportunity and did not act unreasonably in
imposing conditions on the issuance of a demolition permit to Owner.
2
PROCEDURAL HISTORY
I.
THE CITY’S FIRST ABATEMENT WARRANT
A fire occurred at the Property on February 2, 2020, damaging the
roof of the industrial building located on it. Two years later, on March 8,
2022, the City first applied to the trial court for a nuisance abatement
warrant pursuant to Code of Civil Procedure section 1822.50 et seq., seeking
1
authority to demolish the building. The City’s ex parte application was
supported by a declaration from the City’s chief building official/building and
safety manager and supporting exhibits. The court granted the application
and issued the abatement warrant on March 8, 2022, with an effective date of
March 10, 2022. The warrant was valid for 14 days. The City later applied to
the court and obtained an extension of the warrant to April 6, 2022.
On March 30, 2022, Owner sought an ex parte order quashing the
warrant. Owner contended it “has never disputed the fire-damaged structure
is a danger and must be abated [and that Owner has] only reasonably
requested additional time to do so.” Among other things, Owner argued the
warrant should be quashed because the City failed to show Owner was unable
or unwilling to do the abatement itself and the declaration submitted by the
City in support of the application omitted material facts and was misleading.
The City requested additional time to oppose Owner’s motion. The court set a
hearing on Owner’s motion to quash for April 11, 2022.
1
Appellant’s unopposed motion to augment the record on appeal with
pleadings and other records filed with the trial court is granted pursuant to
California Rules of Court, rule 8.155(a)(1)(A).
3
Shortly before the hearing, the parties filed a stipulation in which
Owner agreed to take its motion to quash off calendar without prejudice to the
City’s ability to renew its application for an inspection and abatement warrant
(with five business days’ notice to Owner) and to oppose the arguments made
by Owner in its motion to quash. The court entered the stipulation as an
order on April 11, 2022, and took Owner’s motion to quash the warrant off
calendar. The first abatement warrant expired by its own terms.
II.
THE CITY’S SECOND APPLICATION FOR ABATEMENT WARRANT
AND OWNER’S MOTION TO QUASH
Approximately seven weeks later, on May 24, 2022, the City filed
a second application with the trial court for an inspection and abatement
warrant, again seeking approval to abate the nuisance on the Property by
demolishing the building. Like the City’s prior application, the second
application was supported by a declaration (with exhibits) from the City’s
chief building official/building and safety manager. This time, however,
Owner was given notice and the matter was scheduled for a hearing.
Although Owner did not dispute the building was a danger and should be
demolished, it filed an opposition to the City’s second application, also
supported by declarations and exhibits. On July 14, 2022, the court heard
testimony from Owner’s managing member, as well as oral argument from
counsel for both parties.
The following is a summary of the evidence before the trial court
in connection with the City’s second application, Owner’s opposition thereto,
and Owner’s motion to quash. Because Owner elected to proceed on appeal
without submitting a record of the July 14 evidentiary hearing and oral
4
argument, either in the form of a reporter’s transcript or substitute therefor,
this summary does not reflect the testimony given by Owner’s managing
member.
Following the fire, the City deemed the Property a danger to
public safety and red-tagged it as unsafe. A city inspector determined a
strong wind or moderate seismic event could cause the building to collapse.
The inspector also determined bracing was required on the surviving
structural walls to provide lateral support. On February 10, 2020, the City
issued a “Pre-Citation Correction Notice” to Owner, directing Owner to brace
all exterior walls no later than February 18, 2020. When Owner did not
comply, the City issued administrative citations on February 20 and February
25, 2020.
By March 27, 2020—almost two months after the fire—Owner had
neither contacted the City nor braced the walls, so the City obtained a bid to
install the bracing itself. On March 31, 2020, the city attorney sent a letter to
Owner entitled, “Notice of Violation.” The letter demanded Owner contact the
City and outlined the two options available to Owner to remediate the
Property: (1) repair the building, which would require bracing the tilt-up
panels within 15 days and then rebuilding within 120 days (by July 29, 2020),
or (2) demolish the building within 30 days of securing permits from the City,
after confirming no asbestos remediation was necessary. The notice of
violation warned Owner that failure to remediate the Property would result in
the City assessing its legal options, including “utilizing the City’s own and/or
retained forces to abate the violations . . . and/or taking any other legal steps
to address the violations at the Property.”
5
On April 4, 2020, Owner responded by e-mail to the notice of
violation. Owner said its goal was the “same as [the City’s] goal” but that it
2
had encountered roadblocks. Owner did not say whether it intended to
rebuild or demolish the building, and it offered no specific date by which it
would take action. Two days later, the city attorney responded by e-mail,
stating “time is of the essence,” asking the Owner to contact him to discuss the
matter, and warning the City might move forward to demolish the building at
Owner’s expense.
On April 9, 2020, a representative of Owner spoke with the city
attorney. The next day, Owner sent an e-mail to the city attorney describing
issues Owner had encountered in determining how to brace the building and
securing a contractor to do the work. Owner referred to a pending fire
investigation and to a concern it said had been raised by a contractor that
might affect that investigation. Owner asked the city attorney if bracing
could occur without removing the debris and said the bracing could be done
within 15 days if debris removal were not required. Owner represented it
would provide feedback to the City on remediation solutions by April 14, 2020.
Owner also asked for an extension of time to rebuild the structure should it
choose that option and indicated that, if the City were unwilling to grant an
extension, Owner would have to choose demolition, which in turn would
require the Owner to obtain the fire investigator’s input to devise a solution.
2
According to Owner, its failure to brace the building was caused by a lack of
insurance funds to perform the work. Owner’s insurance carrier initially
provided a contractor to perform the bracing work, but called off the work
when the carrier determined there was no coverage for the fire. That led to a
separate dispute between Owner and Owner’s tenant; Owner contended the
tenant was responsible for the fire.
6
Also on April 10, 2020, the City received a bid from a contractor to
brace the building in preparation for the possibility Owner would not meet the
deadlines in the notice of violation.
On April 16, 2020, having heard nothing further from Owner, the
city attorney sent an e-mail to Owner, stating “[t]he City is losing confidence
that you will be able to quickly repair the structure as required on your own
and it appears to us that we will have to abate it on your behalf.” The city
attorney asked for a conference call for the following day. Owner responded
the next day, stating it was available for a meeting that morning and that it
was “waiting on feedback from the general contractor and the structural
engineer to make plans for bracing inside [the building].” Owner asked the
city attorney to respond to Owner’s April 10 e-mail. The city attorney
responded with an e-mail confirming the conference call, attaching a copy of
the proposal the City obtained for the bracing work, and advising that Owner
would have to pay the contractor a full 100 percent retainer to begin the
bracing work.
On April 17, 2020, the city attorney sent another e-mail to Owner
confirming Owner must proceed immediately to brace the building, but
agreeing to extend the deadline by six months (to October 14, 2020) for Owner
to bring the building into full compliance. The e-mail gave the Owner 60 days
(to June 16, 2020) to secure all necessary permits for the remediation. The
city attorney reiterated that if Owner did not do the work expeditiously and in
good faith, the City would proceed with the abatement itself and file a lien
against the Property for the costs it incurred to do so.
On April 21, 2020, the city attorney inquired about the Owner’s
plan and timeline for bracing the panels. Owner responded it still had not
7
decided whether to elect bracing and rebuilding or demolition, but said in
light of the limited time the City was giving to Owner to rebuild, it might opt
for demolition.
On Friday, April 24, 2020, the city attorney e-mailed Owner
demanding that Owner communicate its decision to either brace and rebuild
or demolish by noon on Monday, April 27, 2020. Owner did not respond by
that deadline. Instead, Owner e-mailed the city attorney on April 30, 2020,
offering reasons why it missed the deadline and assuring the City it was
actively working on the issue. Owner asked the City for more flexibility with
the “rebuild timing.”
On May 1, 2020, the city attorney e-mailed Owner that the City
was moving forward to obtain city council approval to abate the Property, but
if Owner promptly submitted a permit application and plans for bracing and
obtaining permits, the City would reassess this course of action. The city
attorney stated the City required a structural plan for bracing the concrete
tilt-up panels, which “is not complicated at all,” and provided a basic outline of
the information a structural engineer would need to give the City to obtain a
permit for the bracing. The city attorney further explained that, according to
the City’s chief building official/building and safety manager, it should not
take the Owner more than one or two days to prepare the necessary plans.
Another five days passed, and when Owner did not respond, the
city attorney followed up with another e-mail on May 6, 2020. On May 8,
2020, Owner said it would respond later that day.
On May 9, 2020, Owner e-mailed the city attorney saying it would
likely elect to demolish the structure because the deadline imposed by the
City to rebuild was not feasible. Although Owner said it was waiting for a
8
contractor to respond and would make the decision “very soon,” the City heard
nothing from the Owner for another month.
On June 9, 2020, the Irvine City Council met and adopted
Resolution No. 20-45 (Resolution 20-45) declaring the Property a public
nuisance as defined in Civil Code section 3480 and Irvine Municipal Code
section 4-11-101 and giving the Owner the same options the city attorney had
conveyed to Owner in March 2020. Resolution 20-45 ordered “the owner of the
Property to abate the nuisance conditions by either (1) demolishing the entire
structure within 30 days or (2) bracing the concrete tilt-up panels and exterior
walls of the structure that were damaged within 7 days and then fully
rehabilitating the structure within 6 months.” Resolution 20-45 further
stated: “If the nuisances are not completely abated by the owner as directed
within the thirty-day period, the City shall cause the same to be abated by the
City personnel or private contract, . . . The owner of the premises shall be
liable to the City for all costs of the abatement, including administrative
costs.” Owner received notice of the city council hearing on proposed
Resolution 20-45 a few days prior to the June 9 hearing and submitted a
written comment. Owner knew Resolution 20-45 was adopted, as it
participated in the June 9 hearing online.
On July 8, 2020, one month after the City adopted Resolution 20-
45 declaring the Property a nuisance, Owner’s attorney prepared a letter to
the city attorney requesting another 30 days (to August 7, 2020) “to complete
abatement.” Owner claimed it needed the additional time because the
Property had to be preserved in its current condition due to Owner’s claimed
ongoing investigation regarding the cause of the fire. The letter stated Owner
9
“has hired a contractor to begin bracing the exterior walls of the structure
immediately to abate the property,” and bracing is a “necessary cost.”
Despite Owner’s representation it had a contractor in place to
begin bracing the walls immediately, the bracing did not happen. Instead, on
July 15, 2020, Owner attempted to contact the City’s chief building
official/building and safety manager to talk about the terms for bracing the
Property. The city attorney responded to Owner and referred Owner to his
May 1, 2020 e-mail, which had already outlined the requirements to obtain a
bracing permit.
On July 28, 2020, Owner’s attorney informed the City that Owner
would be unable to meet the City’s deadlines, based on the opinion of one or
more unidentified “contractors/engineers who specialize in restoration of fire-
damaged properties.”3 By this date, almost six months after the fire, Owner
still had not braced the Property or applied for a bracing permit.
Then, more than another month elapsed. On September 9, 2020,
the City and Owner entered into an “Extension of Time for Abatement
Agreement” (Agreement 1). Owner acknowledged in Agreement 1 the
deadlines and requirements imposed on it by the City as part of Resolution
20-45 and also acknowledged it had neither timely demolished the Property
nor performed the bracing work, despite having requested (and received) an
extension of time to remedy the violations on the Property. Pursuant to
Agreement 1, Owner agreed to complete the bracing work on the Property
within 28 calendar days—i.e., by October 7, 2020—including submitting plans
3
There is no evidence in the record from any contractor, engineer, or other
expert supporting Owner’s assertions that the City’s deadlines were
impossible to meet.
10
to the City and obtaining the requisite permits. In addition, in Agreement 1,
the City gave Owner yet another opportunity to elect whether to demolish the
building or rehabilitate it. Agreement 1 provided that if Owner elected to
demolish the building, it would have to submit plans, obtain building permits,
and complete the demolition within 120 days—by January 7, 2021. Owner
paid the City a $50,000 conditionally-refundable cash deposit pursuant to
Agreement 1 to “secure the faithful performance of [Agreement 1] and to pay
for the demolition of the Property in the event the Company for any reason
fails to comply with any of the . . . deadlines stated herein.”
On September 11, 2020, seven months after the fire, Owner
submitted plans to the City to brace the building, but it failed to submit the
necessary permit application and the City’s required plan check fee. During
the following week, the City reviewed Owner’s plans and reminded Owner it
had to submit a permit application and plan check fee. Owner submitted the
permit application and, after initially disputing the fee, paid the plan check
fee on September 18, 2020.
The City’s plan check engineer provided informal plan check
corrections to Owner’s engineer on September 21, 2020. But Owner’s engineer
responded that it was not the submitting party and asked the City to provide
its formal plan check review directly to Owner. The engineer told the City his
company had not been paid by Owner for its services on the project. In a
subsequent e-mail to the City’s principal plan check engineer, the engineer
noted “the building has been left in an unsafe condition, by the owner, for
many months.”
The City provided its formal plan check corrections to Owner the
next day, September 22, 2020. As part of those corrections, the City notified
11
Owner that if, as the plans indicated, it now proposed to brace the building
from the outside by tying the braces to the foundation of the adjacent building
(which Owner also owned), the adjacent building could not be occupied.
A week later, on September 29, 2020, Owner’s representative
contacted the City with questions about the plan review comments. Between
October 2 and October 6, 2020, Owner and the City corresponded regarding
the City’s determination that, if the building were braced from the outside as
Owner had proposed, the adjacent building would have to remain vacant.
Owner did not modify its bracing plans based on the City’s comments.
Instead, Owner took the position the City had breached Agreement 1, which
provided: “City agrees to allow [Owner] to open the adjacent property . . . for
leasing and business operations immediately after [Owner] has completed
bracing of the Property.” Owner argued the City knew about Owner’s outside
bracing plan when it signed Agreement 1, so the City should allow Owner to
both brace the damaged building from the outside and occupy the adjacent
building. According to the City, Owner’s request to brace from outside using
the adjacent building would require a detailed analysis by Owner’s engineer to
demonstrate the adjacent building’s walls had sufficient strength and stiffness
to support the applicable loads. Owner failed to provide such an analysis.
Owner did not meet the deadlines set forth in Agreement 1 to
secure a bracing permit, complete the bracing work, or submit feasibility
plans from a licensed contractor regarding the possibility of rehabilitating the
building. Accordingly, on October 14, 2020, the city attorney sent a letter to
Owner declaring Owner in material breach of Agreement 1 and notifying
Owner it had forfeited the $50,000 deposit. The city attorney’s letter advised
Owner the City would move forward to either demolish or rehabilitate the
12
building itself. The city attorney stated Resolution 20-45 ordering abatement
“is now re-instated, and [Owner] must [immediately] cease any additional
work on the Property.”
On October 15, 2020, Owner’s attorney sent a letter to the City.
Owner disagreed it was in breach of Agreement 1 and asserted that the City’s
actions caused delay, including the City’s attempt to modify the terms of
Agreement 1 in a way that made it impossible for Owner to meet the City’s
deadlines. The city attorney responded on December 3, 2020, disputing
Owner’s assertions and stating Owner had refused to act in good faith.
On December 10, 2020, the City entered into a contract with a
third party to prepare demolition drawings to demolish the Property.
On December 15, 2020, Owner e-mailed the City’s director of
community development (the Director) that it was awaiting a response from
the City’s planner to an e-mail Owner had sent on October 6, 2020. In the
December 15 e- mail, Owner asked for help to allow it to “proceed with
abatement.” Owner stated demolition by the City is “really unnecessary, as
[Owner has] been ready to abate and [doesn’t] need the city to do this.” On
December 17, 2020, Owner’s representative spoke by telephone with the
Director. In an e-mail sent to Owner the same evening, the Director wrote:
“As I stated, the City is now moving forward with [the] selection of a
contractor for demolition of the property and that preparation work will
continue. On our phone call, you stated that the property owner is now
interested in demolishing the property as well. While I make no
commitments, we are willing to take a look at your plan and timeline for
demolition and evaluate it in the interest of finding the most expedient path
toward ensuring public safety.”
13
On December 18, 2020, Owner e-mailed the Director proposing a
timeframe of 45 to 73 days to complete demolition and asked, “[w]ould you like
me to start right away?” On December 21, 2020, the Director responded to
Owner that the building and safety team needed to evaluate the timeline and,
in light of the impending holidays, the Director would get back to Owner the
following week. The next day, Owner wrote to the Director stating, “I’m now
confident we are moving in a successful direction to swiftly abate the
building.” (Italics added.)
Owner followed up with the City again on December 30, 2020.
That day, the Director responded to Owner and stated the City was drawing
up an agreement that would allow Owner to perform the demolition itself
based on the timeline Owner had provided. The Director said the City was
attempting to reach Owner’s attorney to get the agreement drafted, but the
attorney was out of town until Monday. The Director said, “[t]he sooner he
hears back [from Owner’s attorney,] the sooner we can get the agreement in
place.”
On January 4, 2021, the City informed Owner’s attorney it would
accept the deadlines proposed by Owner but would nevertheless continue with
its own plans for demolition; in either event, the City advised Owner it
expected the building to be demolished by mid-February 2021. In an e-mail
put into evidence by Owner, Owner’s own attorney notified Owner that the
City’s agreement to allow Owner to conduct the demolition was contingent on
Owner’s agreement to reimburse the City for costs incurred in the process and
Owner’s attorney needed to draft a new agreement to reflect that requirement
“before you can move forward with demolition.” Owner’s attorney advised
Owner to “move at the speed of lightning and beat the City to the demolition
14
as soon as the parties have a new contract,” and further advised that “[i]f the
City sees you meeting each deadline as scheduled, they would be less inclined
to move forward with their demolition plans.” Owner’s counsel emphasized to
his client: “This is a parallel course of demolition, and to avoid duplicative
costs and efforts, you would have to beat the City out on all the plans to
demolish.”
Despite the admonition by Owner’s own attorney that Owner
should “move at the speed of lightning,” weeks went by. On or about January
28, 2021, the parties exchanged competing proposed agreements for
demolition of the Property by Owner (proposed Agreement 2). The City’s
proposed Agreement 2 confirmed Owner’s proposed schedule to complete the
demolition within 75 days was acceptable to the City, with the caveat that the
City would continue with its own demolition plan “to proceed alongside with
[Owner’s] scheduled demolition plan” to ensure the demolition would proceed
“expeditiously and without delay.” The City’s proposed Agreement 2 also
stated the City would issue Owner a permit for demolition—but only upon
Owner’s execution of proposed Agreement 2—and would agree not to interfere
with Owner’s demolition. As for the City’s costs for demolition, the City’s
proposal provided that the $50,000 deposit Owner had furnished to the City in
connection with Agreement 1 would be refunded to Owner after Owner had
completed the demolition on the terms in the Agreement, but that City could
deduct from the deposit any reasonable demolition costs the City “has
incurred or does incur in the future.” The City’s proposed Agreement 2 also
provided that, if Owner did not comply with the deadlines set forth in it, the
City could use the cash deposit to cover all reasonable costs associated with
the City undertaking the demolition; in the event the City’s reasonable costs
15
exceeded the amount of the cash deposit, Owner would pay the difference
within 90 days of invoice and, if unpaid, the City could record the unpaid
amount as a lien against the Property or assess it as a special assessment.
On February 1, 2021, Owner reached out to the City, including the
Director, asserting that the Director had agreed in December to allow Owner
to do the demolition itself and Owner had already started connecting with
contractors to update bids. Owner asked the City to hold off doing any
parallel work. Owner said it would have the project finished in 75 workdays
and that it was “ahead of schedule.” The Director responded that the City
would move ahead in parallel with the Owner’s preparation for demolition so
the City would be prepared to step in and promptly initiate the demolition in
the event Owner did not complete it in a timely fashion. The Director stated,
“we will need the signed [proposed Agreement 2] from you before we will issue
a demolition permit.” The Director also reminded Owner the City’s draft of
proposed Agreement 2 was still being reviewed by Owner’s attorney.
Owner did not sign proposed Agreement 2. Instead, Owner
prepared a revised draft of proposed Agreement 2 that deleted all references
to the City undertaking a parallel demolition. Owner’s proposed Agreement 2
provided the City could not assess and recoup costs from Owner for any work
done by the City in connection with demolition unless and until Owner failed
to comply with the 75-day deadline.
On February 5, 2021, a consultant retained by the City inspected
the Property and confirmed extensive damage to the building; indeed, the
inspector concluded the walls were so unstable the building might collapse.
The inspector notified the City that “[w]e consider this an emergency causing
life safety concern” and recommended temporary bracing be done to shore the
16
east wall. By that date, Owner had not provided a response to the City
regarding proposed Agreement 2 or the City’s required demolition schedule.
On February 8, 2021, approximately 40 days after Owner’s
December conversation with the Director in which Owner indicated it was
ready to immediately begin a swift demolition—and more than one year after
the fire—Owner applied for a demolition permit from the City. The City
reviewed the application and was prepared to issue a demolition permit but
would not do so because Owner refused to enter into the City’s proposed
Agreement 2. Owner and the City never entered into any version of proposed
Agreement 2.
From April to November 2021, the City solicited proposals for the
demolition of the Property. The City awarded a contract on December 28,
2021, to a third party to perform the demolition. It issued a purchase order
for the work on February 11, 2022, and sought its first nuisance abatement
warrant from the court shortly thereafter, on March 8, 2022.
III.
THE COURT’S RULINGS
On July 14, 2022, after hearing live testimony from Owner’s
representative and argument by both parties’ counsel, the trial court granted
the City’s application for an abatement warrant and denied Owner’s motion to
quash the abatement warrant. On July 27, 2022, and again on August 10,
2022, the City applied to the court for extensions of the warrant. Both
applications were supported by declarations from the City’s chief building
official/building and safety manager explaining the need for the extensions
17
and describing the partial work already performed. The court granted both
4
extensions.
The City completed demolition of the Property on or about August
5
16, 2022. It returned the warrant on August 30, 2022, and the trial court
approved the return on September 1, 2022.
After the building had been demolished, Owner filed a notice of
appeal of the trial court’s July 14, 2022 order issuing the abatement warrant,
a notice of appeal of the court’s July 19, 2022 order denying Owner’s motion to
quash the warrant, and a notice of appeal of the court’s July 27, 2022 order
extending the abatement warrant. We granted Owner’s unopposed motion to
consolidate the three separate appeals.
DISCUSSION
Owner contends the trial court erred by issuing and extending the
abatement warrant and denying Owner’s motion to quash the warrant
because the City failed to meet its burden of showing it complied with Owner’s
4
The trial court denied Owner’s ex parte application for reconsideration of
the order granting the abatement warrant. Owner did not properly appeal
that order. Although Owner attached the minute order denying
reconsideration to its notice of appeal of the July 27, 2022 order extending the
abatement warrant, it did not file a separate notice of appeal as to the order
denying reconsideration. Owner also did not either include the denial of
reconsideration in its list of issues presented on appeal or brief the issue. We
therefore consider the issue waived. (Guthrey v. State of California (1998) 63
Cal.App.4th 1108, 1115.) In any event, because Owner asked the trial court to
reconsider its order issuing the abatement warrant and we find no error in
that order, this appeal necessarily disposes of any argument Owner might
have asserted that the reconsideration motion should have been granted and
the abatement warrant recalled.
5
Owner did not seek a writ from this court or otherwise seek to stay either
the abatement warrant or the extensions of it.
18
due process rights prior to obtaining the warrant and demolishing Owner’s
building. Specifically, Owner contends it was ready, willing, and able to do
the demolition itself, but the City unreasonably conditioned the issuance of a
demolition permit on Owner agreeing to reimburse the City for costs
associated with a parallel demolition process Owner contends was
unnecessary. Owner argues it had a due process right to perform the
demolition itself. We reject Owner’s contentions.
I.
STANDARD OF REVIEW
“[A] judgment or order of the trial court is presumed correct and
prejudicial error must be affirmatively shown. [Citation.] ‘In the absence of a
contrary showing in the record, all presumptions in favor of the trial court’s
action will be made by the appellate court. “[I]f any matters could have been
presented to the court below which would have authorized the order
complained of, it will be presumed that such matters were presented.”’”
(Foust v. San Jose Construction Co., Inc. (2011) 198 Cal.App.4th 181, 187.) To
overcome this presumption, appellants must provide an adequate record that
demonstrates error. (Maria P. v. Riles (1987) 43 Cal.3d 1281, 1295.) Where,
as here, an appellant fails to provide the reviewing court with pertinent
reporter’s transcripts (or a suitable substitute), we presume the evidence
supports the trial court’s rulings unless error appears on the face of the
record. (Cal. Rules of Court, rule 8.163; National Secretarial Service, Inc. v.
Froehlich (1989) 210 Cal.App.3d 510, 521–522.)6
6
Owner failed to provide a complete record on appeal, including all the
evidence the trial court considered in ruling on the City’s application for the
abatement warrant. The hearing on the City’s application included live
19
On appeal, we review factual issues underlying the trial court’s
abatement warrant under the substantial evidence standard. (Clary v. City of
Crescent City (2017) 11 Cal.App.5th 274, 284; People v. Wheeler (1973) 30
Cal.App.3d 282, 292.) Under that test, the power of this court begins and ends
with a determination whether there is any substantial evidence in the record,
contradicted or uncontradicted, that supports the trial court’s findings, and
“[w]hen two or more inferences can be reasonably deduced from those facts,
the reviewing court has no power to substitute its deductions for those of the
fact finder.” (Associated Builders & Contractors, Inc. v. San Francisco
Airports Com. (1999) 21 Cal.4th 352, 374.) Issues concerning the application
of statutory authority present questions of law subject to independent review
of the trial court’s rulings. (Stratton v. First Nat. Life Ins. Co. (1989) 210
Cal.App.3d 1071, 1083–1084.) Legal issues, including the scope of due process
rights, are reviewed de novo. (People v. Aguilera (2020) 50 Cal.App.5th 894,
909; see Clark v. City of Hermosa Beach (1996) 48 Cal.App.4th 1152, 1169 [the
ultimate determination of whether administrative proceedings were
fundamentally fair is a question of law].)
testimony from Owner’s agent. Without a reporter’s transcript, we are unable
to review all evidence before the trial court. (See Cal. Rules of Court, rule
8.120(b) [“If an appellant intends to raise any issue that requires
consideration of the oral proceedings in the superior court, the record on
appeal must include a record of these oral proceedings”].) Generally,
appellants in ordinary civil appeals must provide a reporter’s transcript at
their own expense. (City of Rohnert Park v. Superior Court (1983) 146
Cal.App.3d 420, 430–431.)
20
II.
APPEALABILITY
We first address whether the orders appealed from are in fact
appealable. We conclude they are. Although the challenged orders are not
among those included in the list of appealable judgments and orders set forth
in section 904.1 of the Code of Civil Procedure, an order is appealable if it is
essentially a final judgment against a party growing out of a matter collateral
to the main proceeding, which either directs the appellant to pay money or
directs some action be taken by or against the appellant. (Koshak v. Malek
(2011) 200 Cal.App.4th 1540, 1545–1546.) In the peculiar procedural posture
of the underlying proceeding, the only issue before the trial court was whether
to issue the abatement warrant and authorize the demolition. Once issued,
the court’s order was final. We therefore find the interrelated orders are
appealable.
III.
MOOTNESS
Because the Owner’s fire-damaged building has been demolished,
the only issue remaining between the parties is whether the City can proceed
to assess and recoup its costs of abatement against Owner. We invited the
parties to submit supplemental briefing on the issue of mootness and this
court’s discretion to hear the appeal. In that supplemental briefing, both
parties agreed this appeal is Owner’s only avenue to challenge the validity of
the abatement warrant pursuant to which the City will seek to recoup its
abatement costs. We therefore exercise our discretion to decide the validity of
the abatement warrant and the extension of it. (See Cucamongans United for
Reasonable Expansion v. City of Rancho Cucamonga (2000) 82 Cal.App.4th
21
473, 479–480 [appellate court has discretion to decide moot appeal when,
among other things, there may be a recurrence of the controversy between the
parties, or a material question remains for the court’s determination].)
IV.
ANALYSIS
A. Nuisance Abatement Law
A city’s legislative body may, by ordinance, declare what
constitutes a nuisance. (Gov. Code, § 38771.) There are three remedies
available to a public agency when a public nuisance exists: (1) a criminal
proceeding; (2) a civil action for an injunction, appointment of a receiver, or
damages; or (3) abatement. (Civ. Code, § 3491.) With limited circumstances
not relevant here, a public entity is free to choose any of the three options.
(Flahive v. City of Dana Point (1999) 72 Cal.App.4th 241, 244.) Public
authorities may demolish a building or other structure if necessary to abate a
public nuisance. (City of Bakersfield v. Miller (1966) 64 Cal.2d 93, 103.) But
absent consent or exigent circumstances, government officials must obtain a
warrant before entering private property to abate a nuisance. (Gleaves v.
Waters (1985) 175 Cal.App.3d 413, 419.)
The abatement warrant in this case was issued pursuant to
section 1822.50 et seq. of the Code of Civil Procedure, which governs
inspection warrants but has been extended by the common law to apply to
abatement warrants. (Flahive v. City of Dana Point, supra, 72 Cal.App.4th at
p. 246, fn. 8.). Under section 1822.51, an inspection warrant will issue only
“upon cause, unless some other provision of state or federal law makes
another standard applicable. An inspection warrant shall be supported by an
affidavit, particularly describing the place, dwelling, structure, premises, or
22
vehicle to be inspected and the purpose for which the inspection is made.”
(Code Civ. Proc., § 1822.51.) Cause is deemed to exist “if . . . there is reason to
believe that a condition of nonconformity exists with respect to the particular
place, dwelling, structure, [or] premises.” (Id., § 1822.52.)
“Before issuing an inspection warrant, the judge may examine on
oath the applicant and any other witness, and shall satisfy himself of the
existence of grounds for granting such application.” (Code Civ. Proc.,
§ 1822.53.) “An inspection warrant shall be effective for the time specified
therein, but not for a period of more than 14 days, unless extended or renewed
by the judge who signed and issued the original warrant . . . .” (Id.,
§ 1822.55.) The municipality has the burden of proving the existence of the
nuisance and the necessity for its abatement. (Leppo v. City of Petaluma
(1971) 20 Cal.App.3d 711, 718.) An inspection warrant must be executed and
returned to the judge who issued it within the time specified in the warrant or
within the extended or renewed time. (Code Civ. Proc., § 1822.55.)
Because destruction of property is a drastic remedy, it is
necessarily a remedy of last resort. (Hawthorne Savings & Loan Assn. v. City
of Signal Hill (1993) 19 Cal.App.4th 148, 161 (Hawthorne).) “The official duty
of the city in a case in which they seek to abate a nuisance is to afford the
property owner a due process hearing which consists of an opportunity to be
heard [to determine whether the property constitutes a public nuisance]
[citation] and a determination upon competent sworn testimony.” (Leppo v.
City of Petaluma, supra, 20 Cal.App.3d at p. 717.) Except in limited
circumstances, the government may only demolish a building where “‘in
fairness and in justice there is no other way reasonably to correct the
nuisance.’” (Id. at p. 718.) Due process requires that a city give the property
23
owner an opportunity to correct the defects or repair the structure prior to
demolition. (D & M Financial Corp. v. City of Long Beach (2006) 136
Cal.App.4th 165, 174–175 (D & M); Hawthorne, supra, at pp. 158–160, 162.)
B. Owner’s Due Process Challenge to the Abatement Warrant
As an initial matter, we underscore that Owner does not dispute
the existence of a nuisance on the Property or contend it did not receive notice
and an opportunity to be heard regarding whether the structure constituted a
nuisance. Owner also does not dispute it received notice the City intended to
demolish the structure if Owner did not take action itself to abate the
nuisance, and that the City gave it a reasonable opportunity to elect to brace
and repair the Property in lieu of demolition. Owner acknowledges it opted to
demolish the Property, rather than repair it, and notified the City of its
decision.7
Nevertheless, Owner asserts the City deprived it of due process
after Owner had been given notice and an opportunity to be heard and elected
not to repair the structure. Owner’s due process argument rests on the theory
that, once it elected demolition over repair, it continued to have a due process
right to perform the demolition itself in order to minimize or reduce the costs
of demolition. We find no deprivation of due process.
First, none of the California cases on which Owner relies supports
Owner’s argument that due process extends beyond a property owner’s right
to notice and an opportunity to be heard, and the right to repair its property
7
Although Owner suggests it felt pressured to choose demolition because the
City’s timeline for bracing and repair was not feasible, Owner does not
challenge the need for demolition or dispute that it ultimately elected
demolition over repair.
24
prior to demolition (i.e., the ability to show that other less drastic means exist
to abate the nuisance). In D & M, supra, 136 Cal.App.4th 165, the court
explained a property owner has a due process right to receive notice that the
municipality intends to demolish a structure and the “opportunity to repair
defects at the property.” (Id. at pp. 170, 174, italics added.) Specifically, the
court explained: “When a city threatens demolition of structures, due process
also requires the city to give a property owner the opportunity to correct
defects or repair a structure constituting a nuisance before demolition.” (Id. at
pp. 175, 184, italics added; see City of Santa Monica v. Gonzalez (2008) 43
Cal.4th 905, 933–934 [California law requiring that a property owner be given
the choice of repairing or demolishing “merely prohibits an enforcement
agency from ordering an owner to demolish a substandard building without
first affording the owner the choice and a reasonable opportunity to repair the
building instead” (italics added)].) D & M does not support Owner’s
contention that once a property owner has elected not to repair the property
and instead agrees to demolition, the property owner has a due process right
to perform the demolition itself to control abatements costs.
Whether a property owner has a due process right to demolish its
own property also was not at issue in Hawthorne, supra, 19 Cal.App.4th 148.
Rather, the issue was whether the city had given the current property owner
“the opportunity to choose repair over demolition” and sufficient time to
evaluate whether to attempt to repair the property before demolition. (Id. at
pp. 160–161.) Unlike this case, the property owner in Hawthorne produced
evidence that its property could be repaired and that it was prepared to make
the repairs. (Id. at pp. 157–158.) The court held that “prior to ordering
demolition, the City had a constitutional and statutory duty to first afford
25
Hawthorne the choice of repairing or demolishing the buildings, a reasonable
time in which to make that choice and, if [the Owner] chose to repair, a
reasonable opportunity to do so.” (Id. at p. 158, italics added.) The court
characterized a property owner’s right as freedom “from an unconstitutional
taking of its property.” (Id. at p. 157.) Hawthorne did not decide that a
property owner who elects not to repair has a constitutional right to conduct
the demolition itself in order to control costs. Owner has failed to show that,
once a property owner has agreed to demolition and opted not to repair,
demolition by the City is a taking subject to constitutional scrutiny.
We are not persuaded by Owner’s reliance on Miles v. District of
Columbia (D.C. Cir. 1975) 510 F.2d 188 (Miles). Hawthorne is the only
California court that has cited Miles. In Hawthorne, the court reiterated the
general proposition that one of the constraints due process imposes on a
municipality’s ability to order a structure demolished is “‘that in fairness and
in justice there is no other way reasonably to correct the nuisance.’”
(Hawthorne, supra, 19 Cal.App.4th at p. 159.) Like D & M and Hawthorne,
Miles involved the issue of notice and a property owner’s right to repair—not
whether a property owner had the right to conduct the demolition itself. The
language in Miles quoted by the Hawthorne court (and relied upon here by
Owner) that a municipality must give the owner “‘ample opportunity to
demolish the building himself’” (Hawthorne, at p. 159) is not only dicta, but
dicta that relies only on a treatise. After citing Miles, the Hawthorne court
cited another out of state case it considered more analogous to the facts before
it, which, according to the Hawthorne court, held “demolition of the property
without giving the owner a reasonable opportunity to bring the building into
26
conformity with the housing code was a denial of due process.” (Hawthorne,
supra, at p. 159, italics added.)
Notably, in the residential context, California has codified the
property owner’s constitutional right to choose repair or demolition. (Health &
Saf. Code, § 17980, subd. (c)(1).) As explained in Hawthorne, supra, 19
Cal.App.4th, the law places “reasonable conditions on that choice in order to
protect the public interest in the abatement of substandard buildings. These
conditions include the requirements the owner exercise the choice to repair or
demolish in a timely manner and develop a ‘reasonable and feasible schedule
for expeditious repair.’ In addition, the repair work must be done on schedule.
If the owner fails to comply with these conditions, the municipality may itself
demolish or repair the buildings.” (Id. at p. 160, citing Health & Saf. Code,
former § 17980, subd. (b).)
Here, the City afforded Owner ample opportunities, over a
reasonable period of time, to elect to brace and repair the damaged structure,
and gave notice to Owner that the City intended to demolish the structure if
Owner failed to abate the nuisance. After months of professed indecision,
Owner chose not to attempt repair and, instead, agreed the Property should be
demolished. We therefore conclude that, “[u]nlike the situation in D & M
Financial, no violation of due process appears in this case because [Owner] was
provided ‘with notice, with the opportunity to be heard, and with the
opportunity to correct or repair the defect before demolition.’” (City of Santa
Monica v. Gonzalez, supra, 43 Cal.4th at p. 929.)
Even assuming the City had the burden, on its application for an
abatement warrant, to show that it gave Owner a reasonable opportunity to
conduct the demolition itself, there was substantial evidence before the trial
27
court that the City did so. Over a period of many months—and in the face of
dangerous conditions at the Property that posed serious public safety
concerns—the City repeatedly communicated with Owner, explained its
options, urged Owner to act promptly because time is of the essence, and
provided Owner information about the steps it would have to follow. The City
made clear more than once that if Owner did not work expeditiously and in
good faith, the City would step in and perform the demolition at Owner’s
expense. Despite all of the City’s exhortations, Owner was often slow to
respond or promised imminent responses or action but did not follow through.
The evidence supports a conclusion that Owner was dragging its feet (perhaps
to buy time to resolve its dispute over insurance coverage for the fire damage)
and being less than forthcoming with the City. In short, there is substantial
evidence the City gave Owner at least a reasonable opportunity to initiate
steps to conduct the demolition itself and Owner failed to do so. The City was
not obliged by due process principles to indefinitely allow Owner to dictate the
timetable for the abatement of the nuisance or delay the demolition until the
Owner decided it was ready to act.
There also was substantial evidence supporting a conclusion the
City acted reasonably in ultimately declining to issue the demolition permit to
Owner and insisting on pursuing a parallel demolition process in the event
Owner did not follow through on its professed intention to proceed with a
prompt demolition. In light of the months of delays, inactivity, excuses, and
unfulfilled promises by Owner and the continued public safety issues posed by
the condition of the Property, it was not unreasonable for the City to insist on
having a parallel plan in place that would enable it to immediately step in to
abate the nuisance if, at the end of the 75-day period in which Owner claimed
28
it would complete the demolition, Owner again had failed to perform. Courts
have found that delays and denials of permits by municipalities do not
constitute a violation of due process. (See Clark v. City of Hermosa Beach,
supra, 48 Cal.App.4th at p. 1185.) Moreover, there is substantial evidence that
by the time the City conditioned a demolition permit on Owner’s willingness to
enter into a second agreement, the City had already fully complied with
Owner’s due process rights by giving Owner the opportunity to choose whether
to repair or demolish the structure. The City was not required to do more.
In sum, the record before us shows the City provided Owner an
administrative hearing and more than a reasonable time to choose between
repairing or demolishing the Property. Once Owner elected demolition, the
City gave Owner ample time to abate the nuisance itself before the City
sought the abatement warrant and then took steps pursuant to the warrant to
demolish the damaged structure. Owner had actual notice of the City’s intent
to demolish the building at Owner’s expense if Owner did not take action to
repair or abate it itself, and Owner had more than a reasonable time within
which to challenge the City’s findings or act to abate the nuisance itself. The
City did not deprive Owner of its due process rights by refusing to allow it to
indefinitely delay and derail the necessary abatement process.
29
DISPOSITION
We affirm the trial court’s orders. Respondent shall recover costs
on appeal.
GOODING, J.
WE CONCUR:
O’LEARY, P. J.
DELANEY, J.
30