Landlord’s obligation to keep the building’s passenger elevator operating

48 C 15468/10Tribunal de Primeira Instância28 de out. de 2011Direito do arrendamentoDeferido

Abrir fonte

Extraído pela Omnilex

Resumo Omnilex

The Düsseldorf District Court granted the plaintiff’s request for declaratory relief, finding the defendant obliged to keep the disputed passenger elevator in the building operating. It ordered the defendant to pay the costs of the proceedings. The judgment is provisionally enforceable; the defendant may avert enforcement by providing security equal to 120% of the enforceable amount, unless the plaintiff provides security in the same amount before enforcement.

Texto completo

Amtsgericht Düsseldorf — 48 C 15468/10 — Urteil

Entscheidungsdatum: 2011-10-28

Aktenzeichen: 48 C 15468/10

ECLI: ECLI:DE:AGD:2011:1028.48C15468.10.00

Dokumenttyp: Urteil

Spruchkörper: 48. Abteilung

Tenor

hat das Amtsgericht Düsseldorf

aufgrund der mündlichen Verhandlung vom 30.09.2011

durch die Richterin am Amtsgericht I

für Recht erkannt:

Es wird festgestellt, dass die Beklagte verpflichtet ist, den streitgegenständlichen Personenaufzug im Hause Lstr. 000 in 00000 E in Betrieb zu halten.

Die Kosten des Rechtsstreits werden der Beklagten auferlegt.

Dieses Urteil ist vorläufig vollstreckbar.

Die Beklagte darf die Zwangsvollstreckung gegen Sicherheitsleistung in Höhe von 120 % des zu vollstreckenden Betrags, wenn nicht die Klägerin vor der Vollstreckung Sicherheit in gleicher Höhe leistet.

Palavras-chave

tenancypassenger elevatorlandlord obligationsdeclaratory reliefcosts

The defendant is obliged to keep the passenger elevator in operation.

The defendant must bear the costs of the proceedings.

Continue sua pesquisa no ChatGPT ou Claude