The District Court Düsseldorf considered the plaintiff’s claim following an oral hearing on 12 May 2009. It dismissed the claim and ordered the plaintiff to bear the costs of the proceedings. The judgment was declared provisionally enforceable. The plaintiff may avert enforcement by providing security equal to 110% of the amount enforceable under the judgment, unless the defendant provides security equal to 110% of the amount being enforced. The decision provides no details about the underlying claim or the court’s reasoning.
Entscheidungsdatum: 2009-05-12
Aktenzeichen: 40 C 11773/08
ECLI: ECLI:DE:AGD:2009:0512.40C11773.08.00
Dokumenttyp: Urteil
Spruchkörper: 40. Abteilung
hat das Amtsgericht Düsseldorf
auf die mündliche Verhandlung vom 12.05.2009
durch den Richter am Amtsgericht X
für Recht erkannt:
Die Klage wird abgewiesen.
Die Kosten des Rechtsstreits hat die Klägerin zu tragen.
Das Urteil ist vorläufig vollstreckbar. Die Klägerin darf die Vollstreckung durch Sicherheitsleistung in Höhe von 110 % des aufgrund des Urteils vollstreckbaren Betrages abwenden, wenn nicht die Beklagte vor der Vollstreckung Sicherheit in Höhe von 110% des jeweils zu vollstreckenden Betrages leistet.
The plaintiff's claim.
The claim was dismissed.
Allocation of the costs of the proceedings.
The plaintiff must bear the costs of the proceedings.
Provisional enforceability and security to avert enforcement.
The judgment is provisionally enforceable; the plaintiff may avert enforcement by providing security of 110% of the enforceable amount, unless the defendant first provides security of 110% of the amount to be enforced.