Instalment payment of court advance and default warning

LC120002Tribunal Superior17 de jul. de 2012Granted

Abrir fonte

Extraído pela Omnilex

Resumo Omnilex

The Obergericht, II. Zivilkammer, granted the applicant permission to pay a CHF 3,000 court advance in four monthly instalments of CHF 750, starting on 16 August 2012. It further specified the default warning: if even one instalment is missed, the instalment arrangement falls away and a single short grace period under Art. 101 ZPO is to be granted.

Sumário Omnilex

Art. 98 ZPO, Art. 101 ZPO; instalment payment of a court advance and formulation of the default warning. The court may allow payment of an advance in instalments and may define the consequences of default in advance. If the judgment ties the instalment plan to a warning, the warning must make clear that a single missed instalment causes the instalment arrangement to lapse and triggers one short grace period; repeated extensions are excluded (consid. 3c by analogy).

Texto completo

Art. 98 ZPO, Art. 101 Abs. 3 ZPO. Ratenzahlung des Vorschusses und Nachfrist. Mögliche Formulierung der Säumnisandrohung.

Es wird verfügt: 1. Der Gesuchstellerin wird bewilligt, den ihr auferlegten Kostenvorschuss von Fr. 3'000.-- in Raten von je Fr. 750.-- zu zahlen, und zwar jeweils am 16. jeden Monats oder am folgenden Werktag, beginnend mit dem 16. August 2012. Bei Säumnis mit auch nur einer Rate fiele die Bewilligung von Ratenzahlungen dahin und würde eine einmalige kurze Nachfrist im Sinne von Art. 101 Abs. 2 ZPO angesetzt. 2. (...) Obergericht, II. Zivilkammer Verfügung vom 17. Juli 2012 Geschäfts-Nr.: LC120002-O/Z07

-> vgl. auch NP110002 vom 27. September 2011 E. 3c

Palavras-chave

court advanceinstalment paymentdefault warninggrace periodcivil procedure

Extraído pela Omnilex

Questão jurídica principal

Whether the applicant may pay the CHF 3,000 court advance in monthly instalments of CHF 750.

Decisão extraída

Yes. The applicant was permitted to pay the advance in four instalments of CHF 750 each, due on the 16th of each month, starting 16 August 2012.

Fundamentação extraída

The court exercised its power under the Code of Civil Procedure to allow instalment payment of the advance.

Questão jurídica principal

How the default warning must be formulated if one instalment is missed.

Decisão extraída

If even one instalment is missed, the instalment arrangement lapses and a single short grace period under Art. 101 para. 2 ZPO is to be set.

Fundamentação extraída

The court specified the consequence of default in a way consistent with Art. 101 ZPO and clarified that the warning should provide only one short additional period.