Questão jurídica principal
Whether the building commission may reject objections without deciding the building permit at the same time.
Decisão extraída
As a rule, once objections against a building application are rejected, the building commission must decide the building permit immediately in the same procedure.
Fundamentação extraída
The practice of deciding the permit only after the objections have become final is impractical and, under the correct interpretation of the new building law, no longer permissible.