Questão jurídica principal
Whether the contractors proved entitlement to additional installation costs under the construction contract
Decisão extraída
The contractors did not prove the contractual overrun of crane installation time or the value of the alleged additional installation work.
Fundamentação extraída
The cantonal court's findings were based on evidence assessment and fact-finding, which cannot be challenged here as a misapplication of federal law; Art. 8 CC does not govern evidence appraisal.