Questão jurídica principal
Whether the cantonal decision allowing a modified construction project mid-procedure was arbitrary under cantonal procedure rules.
Decisão extraída
The cantonal court was entitled to continue the procedure with the modified project because the changes responded to objections, did not unlawfully bypass participation rights, and served procedural economy.
Fundamentação extraída
The new project was sufficiently close to the original, the parties were heard, and a fresh public notice was issued; no arbitrariness resulted.