act-1994-0-142•Pennsylvania Act 1994-142 — PUBLIC WORKS CONTRACT REGULATION LAW - AMEND
Pennsylvania Act 1994-142 — PUBLIC WORKS CONTRACT REGULATION LAW - AMEND
act-1994-0-1421994 Pa. Act 142Law
Act text
PUBLIC WORKS CONTRACT REGULATION LAW - AMEND
Act of Dec. 12, 1994, P.L. 1042, No. 142 Cl. 62
Session of 1994
No. 1994-142
HB 1914
AN ACT
Amending the act of November 26, 1978 (P.L.1309, No.317),
entitled "An act regulating the awarding and execution of
certain public contracts; providing for contract provisions
relating to the retention, interest, and payment of funds
payable under the contracts; and repealing inconsistent
acts," further providing for prompt payment schedules and for
bidder lists.
The General Assembly of the Commonwealth of Pennsylvania
hereby enacts as follows:
Section 1. Section 1 of the act of November 26, 1978
(P.L.1309, No.317), referred to as the Public Works Contract
Regulation Law, is amended by adding definitions to read:
Section 1. Definitions.
The following words and phrases, when used in this section,
shall have the following meanings unless the context clearly
indicates otherwise:
* * *
"Contractor." A person who enters into a public contract
with a contracting body.
"Deficiency item." Work performed but which the design
professional, the contractor or the inspector will not certify
as being completed according to the public contract.
"Design professional." An architect licensed under the act
of December 14, 1982 (P.L.1227, No.281), known as the
"Architects Licensure Law," a professional engineer or
professional land surveyor licensed under the act of May 23,
1945 (P.L.913, No.367), known as the "Engineer, Land Surveyor
and Geologist Registration Law," or a landscape architect
licensed under the act of January 24, 1966 (1965 P.L.1527,
No.535), known as the "Landscape Architects' Registration Law."
"Inspector." The person authorized or engaged by the
contracting body to inspect the work performed and materials
furnished pursuant to a public contract to determine whether the
work completed is in compliance with the public contract.
"Local government unit." Any county, city, borough,
incorporated town, township, school district, vocational school
district, county institution, local authority or any joint or
cooperative body of local government units or any
instrumentality, authority or corporation thereof which has
authority to enter into a public contract.
* * *
"Subcontractor." A person who has contracted to furnish
labor or materials to or has performed labor for a contractor or
another subcontractor in connection with a public contract.
* * *
Section 2. Section 2 of the act is amended to read:
Section 2. Time for awarding contracts; list of bidders.
(a) Every public contract shall be awarded by the
contracting body to the lowest responsible bidder within 60 days
of the date of bid opening or all bids shall be rejected except
as otherwise provided in this section.
If the award is delayed by a required approval of another
government agency, the sale of bonds, the award of a grant or
grants, the contracting body shall reject all bids or award the
contract to the lowest responsible bidder within 120 days of the
date of bid opening.
Thirty-day extensions of the date for the award may be made
by the mutual written consent of the contracting body and the
lowest responsible bidder.
(b) All contracting bodies of the Commonwealth or any State-
aided institution shall be required to provide a list of the
bidders and their bid amount on each public contract within ten
working days of the bid opening to interested parties for a fee
to be determined by the contracting body to cover the cost of
developing such list. This requirement shall not apply to the
contracting bodies of any political subdivision or local
authority which has the authority to enter into a public
contract.
Section 3. The act is amended by adding sections to read:
Section 6.1. Performance by contractor or subcontractor.
(a) Performance by a contractor in accordance with the
provisions of a public contract shall entitle the contractor to
payment by the contracting body.
(b) Performance by a subcontractor in accordance with the
provisions of a contract shall entitle the subcontractor to
payment from the contractor with whom the subcontractor has
contracted.
Section 6.2. Contracting body's progress payment obligations.
(a) The contracting body shall pay the contractor or design
professional strictly in accordance with the public contract.
(b) If the public contract does not contain a term governing
the time for payment, the contractor or design professional
shall be entitled to make application for payment from the
contracting body for progress payments, and the contracting body
shall make payment less the applicable retainage amount as
authorized in section 5 to the contractor or design professional
within 45 calendar days of the date the application for payment
is received.
(c) Except as otherwise agreed by the parties, if any
progress payment less the applicable retainage amount as
authorized in section 5 is not made to a contractor or design
professional by the due date established in the contract or in
subsection (b), the contracting body shall pay to the contractor
or design professional, in addition to the amount due, interest
on the amount due, and the interest shall be computed at the
rate determined by the Secretary of Revenue for interest
payments on overdue taxes or the refund of taxes as provided in
sections 806 and 806.1 of the act of April 9, 1929 (P.L.343,
No.176), known as "The Fiscal Code," and any subsequent
amendments to those sections.
(d) In the event that the public contract does not contain a
grace period and if a contractor or design professional is not
paid by the payment date required by subsection (b), no interest
penalty payment required under this section shall be paid if
payment is made on or before the 15th calendar day after the
payment date required under this act.
Section 6.3. Contractors' and subcontractors' payment
obligations.
(a) Performance by a subcontractor in accordance with the
provisions of the contract shall entitle the subcontractor to
payment from the party with whom the subcontractor has
contracted. For purposes of this section, the contract between
the contractor and subcontractor is presumed to incorporate the
terms of the public contract.
(b) A contractor or subcontractor shall disclose to a
subcontractor, before a subcontract is executed, the due date
for receipt of progress payments from the contracting body.
Notwithstanding any other provisions of this act, if a
contractor or a subcontractor fails to accurately disclose the
due date to a subcontractor, the contractor or subcontractor
shall be obligated to pay the subcontractor as though the due
dates established in subsection (c) were met by the contracting
body. This subsection shall not apply to a change in due dates
because of conditions outside of the contractor's control,
including, but not limited to, design changes, change orders or
delays in construction due to weather conditions.
(c) When a subcontractor has performed in accordance with
the provisions of the contract, a contractor shall pay to the
subcontractor and each subcontractor shall in turn pay to its
subcontractors the full or proportional amount received for each
such subcontractor's work and material, based on work completed
or services provided under the subcontract, 14 days after
receipt of a progress payment. Payment shall be made under this
section unless it is being withheld under section 6.4.
(d) If any progress payment is not made to a subcontractor
by the due date established in the contract or in subsection
(c), the contractor shall pay to the subcontractor, in addition
to the amount due, interest as computed in section 6.2(c).
(e) In the event that the contract does not contain a grace
period and if a subcontractor is not paid by the payment date
required by subsection (c), no interest penalty payment required
under this section shall be paid if payment is made on or before
the 15th calendar day after the payment date required under this
act.
Section 6.4. Withholding of payment for good faith claims.
(a) The contracting body may withhold payment for deficiency
items according to terms of the public contract. The contracting
body shall pay the contractor according to the provisions of
this act for all other items which appear on the application for
payment and have been satisfactorily completed. The contractor
may withhold payment from any subcontractor responsible for a
deficiency item. The contractor shall pay any subcontractor
according to the provisions of this act for any item which
appears on the application for payment and has been
satisfactorily completed.
(b) If a contracting body withholds payment from a
contractor for a deficiency item, it shall notify the contractor
of the deficiency item within the time period specified in the
contract or fifteen calendar days of the date that the
application for payment is received. If a contractor withholds
payment from a subcontractor for a deficiency item, it must
notify the subcontractor or supplier and the contracting body of
the reason within 15 calendar days of the date after receipt of
the notice of the deficiency item from the owner.
Section 6.5. Penalty and attorney fees.
(a) If arbitration or a claim with the Board of Claims or a
court of competent jurisdiction is commenced to recover payment
due under this act and it is determined that the contracting
body, contractor or subcontractor has failed to comply with the
payment of terms of this act, the arbitrator, the Board of
Claims or the court may award, in addition to all other damages
due, a penalty equal to 1% per month of the amount that was
withheld in bad faith. An amount shall be deemed to have been
withheld in bad faith to the extent that the withholding was
arbitrary or vexatious. An amount shall not be deemed to have
been withheld in bad faith to the extent it was withheld
pursuant to section 6.4.
(b) Notwithstanding any agreement to the contrary, the
prevailing party in any proceeding to recover any payment under
this act may be awarded a reasonable attorney fee in an amount
to be determined by the board of claims, court or arbitrator,
together with expenses, if it is determined that the contracting
body, contractor or subcontractor acted in bad faith. An amount
shall be deemed to have been withheld in bad faith to the extent
that the withholding was arbitrary or vexatious.
Section 6.6. Public contracts involving Federal aid.
If any provision of this act conflicts with a Federal statute
or regulation or with conditions attached to the receipt of
Federal aid, this act shall not operate to prevent receipt of
the Federal aid in accordance with any Federal statute or
regulation.
Section 6.7. Certain provisions unenforceable.
A provision in the public contract making it subject to the
laws of another state or requiring that any litigation,
arbitration or other dispute resolution process on the contract
occurs in another state shall be unenforceable.
Section 6.8. Applicability.
(a) This act shall apply to public contracts entered into on
or after the effective date of this act.
(b) (1) Section 6.2 shall not apply when the State
government unit's nonpayment on a particular project is
caused by the failure of the General Assembly to enact a
budget for the fiscal year of payment.
(2) Section 6.2 shall not apply when a local government
unit's nonpayment on a particular project is caused by
failure of the Federal or State government to pay funds due
and payable to the local government unit.
(3) Section 6.2 shall not apply when a contracting
body's nonpayment on a particular project is caused by the
failure of the General Assembly to enact an operating budget
for the fiscal year of payment or a capital budget for the
capital project or by failure of the Federal, State or local
government to pay funds designated or to be designated for
the specific project.
(4) Nothing in this act shall be construed to require
payment of interest penalties by the Federal or State
government if the municipality is liable for such interest.
(c) This act shall not apply to any of the following:
(1) A municipality determined to be distressed under the
act of July 10, 1987 (P.L.246, No.47), known as the
"Municipalities Financial Recovery Act."
(2) A school district which has been determined to be a
distressed school district under section 691 of the act of
March 10, 1949 (P.L.30, No.14), known as the "Public School
Code of 1949."
(3) A city of the first class that has entered into the
Intergovernmental Cooperation Agreement under the act of June
5, 1991 (P.L.9, No.6), known as the "Pennsylvania
Intergovernmental Cooperation Authority Act for Cities of the
First Class," for so long as any deficit-reducing bonds
issued by the authority pursuant to section 301(b)(1) of that
act are outstanding and payable.
(4) Any corporate entity or school district as defined
in the "Pennsylvania Intergovernmental Cooperation Authority
Act for Cities of the First Class."
Section 6.9. Claims by innocent parties.
(a) The contracting body shall have no obligation to any
third parties for any claim.
(b) Once a contractor has made payment to the subcontractor
according to the provisions of this act, future claims for
payment against the contractor or the contractor's surety by
parties owed payment from the subcontractor which has been paid
shall be barred.
Section 4. This act shall take effect in 60 days.
APPROVED--The 12th day of December, A. D. 1994.
ROBERT P. CASEY