11-504

us-hi-regs-official-797dd31e6b24180255ea1da0afc5165943da3da57e7a74a2f89c61ee51ec9f3d11-504Regulation

HAWAII 	ADMINISTRATIVE 	RULES
TITLE 	11
DEPARTMENT OF 	HEALTH
CHAPTER 	504
ASBESTOS ABATEMENT 	CERTIFICATION 	PROGRAM
Subchapter 	1 	General 	Provisions
§11-504-1
§11-504-2
§11-504-3
§11-504-4
§11-504-5
§11-504-6
§11-504-7
§11-504-8
§11-504-9
§11-504-10
§11-504-11
§11-504-12
§11-504-13
§11-504-14
§11-504-15
§11-504-16
§11-504-17
§11-504-18
§11-504-19
§11-504-20
Purpose 	and 	scope
Definitions
References
Certification 	requirements
Interim certification
Certification 	application
Action 	on 	application
Denial 	of 	application
Suspension, 	revocation, 	or modification of
certification
Expiration 	of 	certification
Renewal 	of 	certification
Reciprocity
Summary 	of 	requirements 	for 	abatement
entities
Notification 	of 	abatement 	projects
Emergency abatement 	projects
Retention 	of 	records
Required 	records
Documents 	to 	be 	retained 	on-site
Summary of 	requirements 	for 	laboratories
and 	analysts
Reserved
504-1
Subchapter 	2 	Certification of 	Workers 	and
Contractor/Supervisors
§11-504-21
§11-504-22
§11-504-23
§11-504-24
§11-504-25
§11-504-26
§11-504-27
§11-504-28
§11-504-29
§11-504-30
General 	requirements 	for 	certification
Worker
Contractor/Supervisor
Reserved
Reserved
Reserved
Reserved
Reserved
Reserved
Reserved
Subchapter 	3 	Certification of 	Inspectors,
Management 	Planners, 	Project
Designers, 	and 	Project 	Monitors
§11-504-31
§11-504-32
§11-504-33
§11-504-34
§11-504-35
§11-504-36
§11-504-37
§11-504-38
§11-504-39
§11-504-40
Definitions
General 	requirements
Inspector
Management 	planner
Project 	designer
Project 	monitor
Reserved
Reserved
Reserved
Reserved
Subchapter 	4 	Accreditation 	of 	Training 	Courses
§11-504-41
§11-504-42
§11-504-43
§11-504-44
§11-504-45
§11-504-46
§11-504-47
General 	requirements
Interim accreditation
Application 	for 	training 	course
accreditation
Denial 	of 	application
Complete 	accreditation
Suspension, 	revocation, 	and 	modification
of 	accreditation
Letters 	of 	accreditation
504-2
§11-504-48
§11-504-49
§11-504-50
§11-504-51
§11-504-52
§11-504-53
§11-504-54
§11-504-55
§11-504-56
§11-504-57
Expiration 	of 	accreditation
Renewal 	of 	accreditation
Reciprocity
Retroactive 	accreditation
§11-504-2
Initial 	course 	contents 	and 	requirements
Refresher 	course 	contents 	and 	requirements
Examinations
Course 	certificates
Record-keeping 	requirements 	for 	training
courses
Instructor 	qualifications 	for 	training
courses
SUBCHAPTER 	1
General 	Provisions
§11-504-1 	Purpose 	and 	scope. 	These 	rules 	require
the 	certification of 	persons 	or 	companies 	who 	perform
activities 	at 	facilities 	for 	the 	evaluation 	or 	control
of 	material 	which 	contains 	asbestos. 	These 	rules 	also
set 	forth 	requirements 	for 	work 	practices 	and 	the
accreditation 	of 	asbestos 	training.
[Eff FEB 	15 	2001 	] 	(Auth: 	HRS 	§342P) 	(Imp: 	40 	CFR
Part 	763, 	Appendix 	C)
§11-504-2 	Definitions.
11 AAR 11 	means 	the 	Asbestos
11 AAT 11 	means 	the 	Asbestos
program.
As 	used 	in 	this 	chapter:
Analyst's 	Registry.
Analytical 	Testing
"Abatement 	activity" 	means 	any 	activity 	involving
job 	set 	up, 	removal, 	encapsulation, 	enclosure,
renovation, 	repair, 	demolition, 	construction,
alteration, 	or maintenance 	of 	asbestos-containing
material.
"Abatement 	entity" 	means 	any person 	having 	one 	or
more 	employees 	or members 	involved 	in 	any 	abatement
project.
"Abatement 	project" 	means 	any 	abatement 	activity
which 	can 	be 	predicted 	and 	in which 	the 	total 	amount 	of
504-3
§11-504-2
friable 	ACBM 	disturbed 	will 	exceed 	three 	linear 	feet 	on
pipes 	or 	three 	square 	feet 	on 	surfaces 	or generate 	more
than 	0.5 	cubic 	feet 	of 	debris.
"Agent" 	means 	any person who 	works 	on 	an 	abatement
project 	for 	an 	abatement 	entity, 	who 	is 	not 	an 	employee
of 	the 	entity 	(e.g., 	sub-abatement 	entity).
"ACBM" 	means 	asbestos-containing 	building
material.
"ACM" 	means 	asbestos-containing 	material.
"AIHA" 	means 	American 	Industrial 	Hygiene
Association.
"Analyst" 	means 	any person who 	analyzes 	bulk 	or
air 	samples 	to 	determine 	asbestos 	content 	or 	airborne
fiber 	content, 	respectively.
"Analytical 	service" 	means 	any 	facility 	which
analyzes 	bulk 	or 	air 	samples 	for 	asbestos 	content 	or
fiber 	counting.
"Asbestos" 	means 	the 	asbestiform varieties 	of:
chrysotile 	(serpentine), 	crocidolite 	(riebeckite),
amosite 	(cummingtonite-grunerite), 	anthophyllite,
tremolite, 	and 	actinolite.
"Asbestos-containing material" 	means 	material 	that
contains 	any 	type 	of 	asbestos 	in 	an 	amount 	greater 	than
one 	per 	cent 	by 	area, 	either 	alone 	or mixed 	with 	other
fibrous 	or 	non-fibrous 	materials.
"Containment" 	means 	the 	isolation 	of 	an 	asbestos
removal 	area 	from 	the 	outside 	air 	by use 	of 	physical
barriers.
"Contractor/Supervisor" 	means 	any 	abatement 	worker
who 	has 	been 	certified by 	the 	department 	under 	these
rules 	to 	ensure 	that 	abatement 	projects 	are 	conducted
in 	accordance 	with 	Federal 	and 	State 	requirements.
"Demolition" 	means 	the 	wrecking, 	taking 	out, 	or
intentional 	burning 	of 	any 	load 	supporting 	structural
member 	of 	a 	facility 	together 	with 	any 	related 	handling
operations.
"Department" 	means 	the 	department 	of 	health, 	State
of 	Hawaii.
"Director" 	means 	the 	director 	of 	the 	department 	of
health, 	State 	of 	Hawaii, 	or 	the 	director's 	duly
authorized 	agent.
504-4
§11-504-2
"Emergency abatement" 	means 	any 	abatement 	activity
requiring 	immediate 	action, 	due 	to 	public 	health 	or
safety 	reasons, 	which was 	not 	planned 	but 	results 	from
a 	sudden, 	unexpected 	event. 	This 	includes 	abatement
required 	by non-routine 	failures 	of 	equipment.
"EPA" 	means 	the 	United 	States 	Environmental
Protection Agency.
"EPA guidance 	document" 	means 	EPA 	560/5-85-024
Guidance 	for 	Controlling Asbestos-Containing 	Materials
in 	Buildings, 	1985.
"Facility" 	means 	any 	institutional, 	commercial,
public, 	industrial, 	or 	residential 	structure,
installation, 	or 	building 	(including 	any 	structure,
installation, 	or 	building 	containing 	condominiums 	or
individual 	dwelling 	units 	operated 	as 	a 	residential
cooperative, 	but 	excluding 	residences 	or 	residential
cooperatives 	that 	have 	four 	or 	fewer 	total 	dwelling
units); 	any 	ship; 	and 	any 	active 	or 	inactive 	waste
disposal 	site. 	For 	purposes 	of 	this 	definition, 	any
building, 	structure, 	or 	installation 	that 	contains 	a
loft 	used 	as 	a 	dwelling 	is 	not 	considered 	a 	residential
structure, 	installation, 	or 	building. 	Any 	structure,
installation, 	or 	building 	that 	was 	previously 	subject
to 	federal 	requirements 	pursuant 	to 	40 	CFR 	Part 	61,
Subpart 	M, 	is 	not 	excluded, 	regardless 	of 	its 	current
use 	or 	function.
"Friable 	asbestos-containing 	material" 	means 	any
material 	containing 	more 	than 	one 	percent 	asbestos
which 	has 	been 	applied 	on 	ceilings, 	walls, 	structural
members, 	piping, 	duct 	work, 	or 	any 	other 	part 	of 	a
building, 	which when 	dry, 	may 	be 	crumbled, 	pulverized,
or 	reduced 	to 	powder 	by hand 	pressure. 	The 	term
includes 	non-friable 	asbestos-containing 	material 	after
such previously non-friable 	material 	becomes 	damaged 	to
the 	extent 	that 	when 	dry 	it 	may be 	crumbled,
pulverized, 	or 	reduced 	to 	powder by 	hand pressure.
"Friable 	asbestos-containing 	building material"
means 	any 	friable 	asbestos-containing 	material 	that 	is
in 	or 	on 	interior 	structural 	members 	or 	other 	parts 	of
a 	school 	or 	public 	and 	commercial 	building.
"HIOSH" 	means 	Hawaii 	Occupational 	Safety and
Health.
504-5
§11-504-2
11 Inspector 11 	means 	a 	person who 	is 	certified by 	the
department 	to 	determine 	the 	presence, 	location, 	and
condition 	of 	asbestos-containing 	building material.
Excluded 	from 	being 	certified 	are 	Federal, 	state 	or
regulatory 	inspectors 	conducting 	compliance
inspections.
11 Instructor 11 	means 	any 	qualified person 	approved
by 	the 	department 	who 	provides 	instruction 	and 	training
in 	the 	person's 	area 	of 	expertise.
11 Management 	planner 11 	or 11 Asbestos 	management
planner 11 	means 	any 	person who 	is 	certified 	by 	the
department 	to 	use 	data 	gathered by 	a 	certified
inspector 	to 	assess 	the 	current 	or 	potential 	hazard
posed by 	asbestos-containing 	material, 	to 	determine 	the
appropriate 	response 	actions, 	and 	to 	develop 	a 	schedule
for 	implementing 	these 	response 	actions.
11 NIOSH 11 	means 	the 	National 	Institute 	of
Occupational 	Safety and 	Health.
11 NIOSH Method 	7400 11 	means 	the 	Fibers, 	Method 	7400
of 	the 	National 	Institute 	of 	Occupational 	Safety 	and
Health 	for 	the 	quantitative 	measure 	of 	airborne
asbestos 	as 	determined by phase 	contrast 	microscopy
(PCM) 	analysis.
11 NIST 11 	means 	the 	National 	Institute 	for 	Standards
and 	Technology.
11 NVLAP 11 	means 	the 	National 	Voluntary Laboratory
Accreditation 	Program, 	administered 	by 	the 	National
Institute 	of 	Science 	and 	Technology.
11 OSHA 11 	means 	the 	United 	States 	Occupational 	Safety
and 	Health Administration.
11 Person 11 	means 	any 	individual, 	partnership, 	firm,
association, 	public 	or 	private 	corporation, 	federal
agency, 	the 	state 	or 	any 	of 	its 	political 	subdivisions,
trust, 	estate, 	or 	any 	legal 	entity
11 PAT 11 	means 	the 	Proficiency Analytical 	Testing
Program.
11 Project 	designer 11 	means 	a 	person who 	is 	certified
by 	the 	department 	to 	determine 	how 	asbestos 	abatement
work 	should be 	conducted.
11 Project 	monitor 11 	means 	a 	person who 	is 	certified
by 	the 	department 	to 	monitor 	abatement 	projects 	and
collect 	air 	clearance 	samples.
504-6
§11-504-2
11 Removal 11 	means 	the 	stripping 	of 	any 	asbestos-
containing materials 	from 	surfaces 	or 	components 	of 	a
facility.
"Renovation" 	means 	the 	alteration 	of 	one 	or more
facility 	or 	structural 	components.
"Repair" 	means 	returning 	damaged ACBM 	to 	an
undamaged 	condition 	or 	to 	an 	intact 	state 	so 	as 	to
prevent 	fiber 	release.
"Small-scale, 	short 	duration" 	means 	activities
that 	involve 	removal 	of 	three 	square 	or 	linear 	feet 	or
less 	of 	friable 	material, 	such 	as 	surfacing 	or 	thermal
system 	insulation, 	or 	0.5 	cubic 	feet 	or 	less 	of 	friable
debris, 	and 	are 	tasks 	such 	as, 	but 	not 	limited 	to:
(1) 	Removal 	of 	asbestos-containing 	insulation 	on
pipes;
(2) 	Removal 	of 	asbestos-containing 	insulation 	on
beams 	or 	above 	ceilings;
(3) 	Replacement 	of 	an 	asbestos-containing 	gasket
on 	a 	valve;
(4) 	Installation 	or 	removal 	of 	drywall;
(5) 	Installation 	of 	electrical 	conduits 	through
or 	proximate 	to 	asbestos-containing
materials.
(6) 	Removal 	of 	asbestos-containing 	material 	only
if 	required 	in 	the 	performance 	of 	another
maintenance 	activity not 	intended 	as 	asbestos
abatement;
(7) 	Removal 	of 	asbestos-containing 	thermal 	system
insulation;
(8) 	Minor 	repairs 	to 	damaged 	thermal 	system
insulation which 	do 	not 	require 	removal,
(9) 	Repairs 	to 	a 	piece 	of 	asbestos-containing
wallboard;
(10) 	Repairs, 	involving 	encapsulation, 	enclosure,
or 	removal 	of 	friable 	ACM 	only 	if 	required 	in
the 	performance 	of 	emergency 	or 	routine
maintenance 	activity 	and 	not 	intended 	solely
as 	asbestos 	abatement.
11 Structure 11 	means 	a 	whole 	facility, 	building, 	or 	a
major 	portion 	thereof, 	such 	as 	a 	building 	wing.
11 TSCA 11 	means 	the 	U.S. 	Toxic 	Substance 	Control 	Act
15 	U.S.C. 	2601, 	et 	seq.
504-7
§11-504-2
"Worker" 	means 	any person who 	is 	certified
department 	to 	engage 	in 	abatement 	activities.
[Eff 	FEB 15 	2no1 	] (Auth: 	HRS 	§342P) 	(Imp:
Part 	763, 	Appendix 	C(A) 	and HRS 	§321-15)
by 	the
40 	CFR
§11-504-3 	References. 	The 	following 	references
contain 	detailed 	information 	on 	asbestos-related
regulations 	that 	are 	applicable 	to 	this 	chapter. 	The
user 	is 	responsible 	for 	obtaining 	updates 	and 	revisions
of 	the 	following 	documents:
(1) 	PL 	99-519, 	Toxic 	Substance 	Control 	Act, 	Title
II, 	Asbestos 	Hazard 	Emergency Response 	Act
(AHERA) ;
(2) 	40 	CFR, 	Part 	763, 	Asbestos 	Containing
Materials 	in 	Schools, 	Final 	Rule 	& Notice,
October 	30, 	1987;
(3) 	40 	CFR 	Part 	763 	Appendix A to 	Subpart 	E,
Interim Transmission Microscopy Analytical
Methods 	- 	Mandatory 	and 	Nonmandatory 	- 	and
mandatory 	Section 	to 	Determine 	Completion 	of
Response 	Actions, 	October 	30, 	1987;
(4) 	40 	CFR, 	Part 	763, 	Asbestos 	Model
Accreditation 	Plan 	[59 	CFR 	5236] 	(February 	3,
1994) ;
(5) 	40 	CFR, 	Part 	61, 	National 	Emission 	Standards
for 	Hazardous 	Air 	Pollutants 	(NESHAP) 	Subpart
A 	(General 	Provisions) 	and 	Subpart 	M
(National 	Asbestos 	Standards);
(6) 	OSHA 	29 	CFR 	1926.58, 	General 	Construction
Standard;
(7) 	OSHA 	29 	CFR 	1926.1101, 	Asbestos
(8) 	Chapter 	12-145, 	12-145.1, 	HIOSH 	Construction
Standards, 	Asbestos;
(9) 	Chapter 	12-206, 	HIOSH 	Health 	Standards,
Asbestos;
(10) 	Chapter 	16-77, 	subchapter 	19, 	DCCA Asbestos
Contractors; 	and
(11) 	Hawaii 	Revised 	Statutes, 	sections 	321-11(26),
3 2 1 - 13 ( a ) ( I ) 	and 	3 2 1 - 15 .
[Eff 	FEB 15 	2001 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763)
504-8
§11-504-7
§11-504-4 	Certification 	requirements. 	No 	person
shall 	engage 	in 	an 	abatement 	project 	as 	a 	worker,
contractor/supervisor, 	inspector, 	management 	planner,
project 	designer, 	project 	monitor, 	or 	training 	provider
without 	a 	valid 	and 	current 	certification 	from 	the
director. 	[Eff 	FEB 15 	2001 	] (Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-5 	Interim 	certification. 	(a) 	Persons
certified by 	another 	state 	or 	agency 	on 	the 	effective
date 	of 	these 	rules 	shall 	be 	certified on 	an 	interim
basis 	for 	a 	period 	of 	six months 	from 	the 	effective
date 	of 	these 	rules 	or 	until 	their 	current
certification expires, 	whichever 	comes 	first.
(b) 	All 	interim-approved persons 	must 	apply
within 	six months 	of 	the 	effective 	date 	of 	these 	rules
to 	become 	certified. 	[Eff 	FEB 	1 5 2001 	] 	(Auth: 	HRS
§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-6 	Certification 	application.
Applications 	shall 	be 	made 	on 	forms 	provided by 	the
director. 	The 	department 	may 	require 	further
information 	to 	better 	determine 	whether 	an 	application
should 	be 	approved 	or 	denied. 	If 	the 	department
requests 	further 	information 	from 	an 	applicant, 	and
does 	not 	receive 	that 	information within 	sixty 	days,
the 	application 	shall 	be 	considered 	incomplete 	and
shall 	be 	denied. 	[Eff 	FEB 	1 5 2001 	] 	(Auth: 	HRS
§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-7 	Action 	on 	application. 	The 	director
shall 	approve 	or 	deny 	a 	completed 	application 	within
one 	hundred 	eighty 	days 	after 	submittal. 	The 	failure
of 	the 	director 	to 	act 	within 	the 	one 	hundred 	eighty-
day 	period 	shall 	be 	deemed 	an 	approval 	of 	the
application. 	[Eff 	FEB 	15 	2001 	] 	(Auth: 	HRS 	§342P-
41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix C)
504-9
;
§11-504-8
§11-504-8 	Denial 	of 	application. 	The 	director
may 	deny an 	application 	for 	certification 	of 	any
applicant 	who 	fails 	to 	meet 	the 	standards 	established
by 	these 	rules, 	including:
(1) 	Failure 	to 	demonstrate 	the 	ability 	to 	comply
fully 	with 	applicable 	requirements,
procedures, 	and 	standards 	set 	forth 	in 	these
rules;
(2) 	Past 	history 	of 	incompetence 	or 	negligence 	on
the 	part 	of 	the 	applicant 	or 	the 	applicant's
employees 	or 	agents;
(3) 	Submission 	of 	false 	information 	on 	an
application;
(4) 	Failure 	to 	submit 	the 	required 	information or
documentation 	with 	the 	application; 	or
(5) 	Past 	violations 	of 	federal 	asbestos
regulations 	or 	state 	asbestos 	rules.
[Eff 	FEB 	15 	2001 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-9 	Suspension, 	revocation, 	or 	modification
of 	certification. 	The 	director 	may 	suspend, 	revoke, 	or
modify 	any 	certification 	issued 	under 	these 	rules 	if,
after 	according 	the 	certificate 	holder 	an 	opportunity
for 	a 	hearing 	in 	accordance 	with 	chapter 	91, 	HRS, 	the
director 	determines 	that 	the 	person has 	not 	complied
with 	applicable 	procedures 	and 	standards 	or 	for 	any
reason 	given 	in 	section 	11-504-8. 	At 	a 	minimum, 	the
standards 	shall 	include:
(1) 	The 	person 	has 	failed 	to 	meet 	the 	standards
set 	forth 	in 	this 	chapter;
(2) 	The 	person 	has 	performed work 	requiring
certification 	at 	a 	job 	site 	without 	being 	in
physical 	possession 	of 	a 	copy 	of 	his 	or 	her
current 	certificate;
(3) 	The 	person 	has 	provided his 	or 	her 	own
certificate 	or 	permitted 	the 	duplication 	of
it 	for 	use 	by 	another;
(4) 	The 	person has 	performed work 	for 	which
certification 	has 	not 	been 	received;
504-10
§11-504-12
(5) 	The 	person has 	obtained 	certification 	from 	a
training 	provider 	that 	is 	not 	accredited 	to
offer 	training 	for 	the 	particular 	discipline;
or
(6) 	The 	person has 	violated other 	asbestos
regula,t.~s 	id~~~stered 	by 	the 	State.
[Eff 	f tt.5 	1;:) 	LUU l 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-10 	Expiration 	of 	certification.
Certification 	shall 	expire 	one 	year 	from 	the 	day 	on
which 	the 	training 	course 	was 	successfully 	completed,
unless 	certification was 	suspended or 	revoked 	sooner.
[Eff 	FEB 15 	200 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C)
§11-504-11 	Renewal 	of 	certification. 	(a) 	Any
application 	for 	renewal 	of 	certification 	shall 	contain
all 	the 	information 	requested 	by 	these 	rules 	without
reference 	to 	previously 	submitted material.
(b) 	Evidence 	of 	successful 	completion 	of 	an
accredited 	annual 	refresher 	course, 	specific 	to 	each
discipline, 	shall 	be 	provided with 	the 	renewal
application. 	[Eff 	FEB 	1 5 2001 	] 	(Auth: 	HRS 	§342P-
41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-12 	Reciprocity. 	(a) 	Each 	applicant 	for
certification who 	is 	licensed, 	certified, 	or 	permitted
for 	the 	appropriate 	asbestos 	abatement 	activity,
consulting 	service, 	or 	analytical 	service 	in 	another
state 	may petition 	the 	department 	on 	a 	form 	provided by
the 	department 	to 	grant 	certification without
repetition 	of 	the 	training 	requirements.
(b) 	The 	department 	may 	grant 	certification 	if 	the
applicant 	has 	met 	licensing, 	certification, 	or
permitting 	requirements 	in 	another 	state 	and 	these
504-11
§11-504-12
requirements 	are 	equal 	to 	or 	more 	stringent
requirements 	for 	certification 	in 	the 	State
[Eff 	f£8 15 	2001 	] 	(Auth: 	HRS 	§342P-41)
CFR 	Part 	763, 	Appehdix 	C)
than 	the
of 	Hawaii
(Imp: 	40
§11-504-13 	Summary of 	requirements 	for 	abatement
entities. 	(a) 	All 	abatement 	entities 	shall 	register
with 	the 	department 	prior 	to 	performing 	any 	abatement
project 	on 	facilities. 	Applications 	for 	registration
shall 	be 	made 	on 	forms 	provided by 	the 	director 	which
shall 	contain 	the 	following 	information:
(1) 	Name 	and 	address 	of 	business 	owner;
(2) 	Name 	of 	operations 	manager; 	and
(3) 	Names 	and 	State 	certification numbers 	for 	all
(b)
abatement
abatement
( 1)
( 2)
( 3)
( 4)
( 5)
(6)
(7)
employees 	performing 	asbestos 	work.
The 	following 	is 	a 	list 	of 	requirements 	that
entities 	shall 	comply with when 	performing
projects 	in 	the 	State 	of 	Hawaii:
Be 	registered with 	the 	department 	prior 	to
performing 	any work 	regulated 	by 	this
chapter;
Ensure 	that 	proper 	notification 	of 	any
proposed 	abatement 	project 	is 	sent 	in 	writing
to 	the 	department 	in 	accordance 	with 	sections
11-501-7 	and 	11-504-14;
Ensure 	that 	records 	of 	all 	abatement 	projects
which 	it 	performs 	are 	maintained 	and 	retained
in 	accordance 	with 	section 	11-504-17;
Ensure 	that 	an 	abatement
contractor/supervisor 	remains 	on-site
whenever 	any 	abatement 	activity 	is 	being
carried 	out 	as 	part 	of 	an 	abatement 	project;
Submit 	evidence 	to 	the 	director 	upon 	request
that 	all 	abatement 	workers 	and 	abatement
contractor/supervisors 	in 	its 	employment 	have
been 	properly 	trained 	and 	certified 	in
accordance 	with 	section 	11-504-22 	and 	23;
Ensure 	that 	all 	abatement 	projects 	shall 	be
performed 	as 	designed 	by 	a 	project 	designer;
If 	a 	supplied 	air 	system 	is 	used 	for
abatement 	activities, 	provide 	the 	director
504-12
§11-504-16
with 	access 	to 	the 	system 	for 	on-site
inspections;
(8) 	Ensure 	that 	the 	person who 	is 	responsible 	for
supervising 	the 	abatement 	project 	meets 	the
requirements 	set 	forth 	in 	section 	11-504-23;
and
(9) 	Ensure 	that 	all 	persons 	participating 	in
abatement 	projects 	have 	completed 	an
accredited 	initial 	training 	course 	as
specified 	in 	section 	11-504-52, 	or 	a
refresher 	training 	course 	in 	accordance 	with
section 	11-504-53 	within 	one 	year 	of 	their
last 	accredited 	training 	course, 	and 	that
their 	certification 	is 	current.
[Eff 	FEB 1 5 2001 	(Auth: 	HRS 	§342P-42)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C; 	and HRS
§342P-42)
§11-504-14 	Notification 	of 	abatement 	projects.
An 	abatement 	entity 	intending 	to 	engage 	in 	any
abatement 	project 	involving 	the 	removal 	of 	at 	least 	160
square 	feet, 	260 	linear 	feet, 	or 	35 	cubic 	feet 	of
friable 	asbestos 	from 	a 	facility 	shall 	notify 	the
department 	pursuant 	to 	section 	11-501-7.
[Eff 	FEB 	1 5 2001 ] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-15 	Emergency 	abatement 	projects. 	An
abatement 	entity 	shall 	contact 	the 	department 	by phone
prior 	to 	beginning 	an 	emergency 	abatement 	project, 	and
written 	notification 	shall 	be 	postmarked 	no 	more 	than
twentY.-four 	hours 	after 	beginning 	the 	project.
[Eff 	FEB 15 	2001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C)
§11-504-16 	Retention 	of 	records. 	Each 	registered
abatement 	entity 	shall 	maintain 	records 	and 	retain
documents 	in 	accordance 	with 	section 	11-504-17 	of 	all
abatement 	projects 	which 	it 	performs 	and 	shall 	make
504-13
§11-504-16
these 	records 	and documents 	available 	to 	the 	department
upon 	request. 	The 	abatement 	entity 	shall 	retain 	the
records 	for 	no 	less 	than 	thirty years 	after 	completion
of 	the 	abatement 	project. 	[Eff FEB 1 5 2001 	] 	(Auth:
HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-17 	Required 	records. 	The 	abatement
entity 	shall 	record 	the 	following 	information 	for 	each
abatement 	project:
(1) 	The 	results 	of 	bulk 	sampling 	analysis 	of
suspect 	material 	to 	be 	disturbed 	that 	is 	not
assumed 	to 	be 	asbestos-containing, 	including
the 	name 	and 	certificate 	number 	of 	the
analytic 	service 	used;
(2) 	The 	location 	and 	work plan 	of 	the 	project 	and
estimated 	amount 	of 	asbestos 	involved 	in 	the
project;
(3) 	The 	scheduled 	and 	actual 	starting 	and
completion 	dates. 	If 	the 	actual 	completion
date 	differs 	from 	that 	originally 	scheduled,
a 	statement 	of 	reasons 	for 	the 	difference
shall 	be 	included;
(4) 	Documentation of 	compliance 	with 	all
asbestos-related 	regulatory 	requirements;
(5) 	Copies 	of 	all 	asbestos-related 	correspondence
with 	regulatory 	agencies 	concerning 	the
project 	(i.e., 	building 	or 	demolition
permits, 	notices 	of 	violation, 	etc.);
(6) 	The 	name 	and 	address 	of 	the 	authorized
asbestos 	disposal 	facility 	to 	which 	the
asbestos-containing 	materials 	were 	taken,
documentation 	of 	the 	amount 	of 	asbestos
received 	for 	disposal, 	and 	confirmation 	of
asbestos 	received 	for 	disposal, 	and
confirmation 	of 	proper 	disposal;
(7) 	The 	methodology 	and 	results 	of 	all 	air
sampling 	conducted 	during 	the 	abatement
process, 	the 	name 	and 	certificate 	number 	of
the 	project 	monitor 	hired 	to 	perform 	such
sampling, 	and 	the 	name 	and 	registration
504-14
§11-504-18
number 	of 	the 	analytical 	service 	employed 	to
analyze 	such 	samples;
(8) 	A complete 	list 	of 	workers,
contractor/supervisors, 	and 	other 	employees
or 	agents 	participating 	in 	the 	abatement
project, 	along 	with 	a 	copy 	of 	their 	current
certificate; 	and
(9) 	Descriptions, 	including 	dates 	and 	times, 	of
unplanned 	exposures 	to 	asbestos 	and 	work-site
accidents. 	[Eff 	FEB } 5 2001 	] 	(Auth: 	HRS
§342P-42) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix
C)
§11-504-18 	Documents 	to 	be 	retained 	on-site. 	The
following 	documents 	shall 	be 	retained 	on-site 	for 	the
duration 	of 	the 	abatement 	project:
(1) 	A current 	copy of 	chapters 	501 	through 	504;
(2) 	Documentation 	of 	the 	adequacy 	of 	compressed
air 	systems 	and 	respiratory protection
systems 	including 	a 	list 	of 	compatible
components 	and 	specifications 	of 	the 	types
and maximum number 	of 	respirators 	that 	may 	be
used with 	the 	system;
(3) 	Copies 	of 	the 	procedures 	for 	the 	use 	of 	the
decontamination 	enclosure 	system or 	any 	other
procedures 	which 	have 	been 	established 	to
prevent 	contamination 	of 	areas 	outside 	the
work 	area;
(4) 	Copies 	of 	procedures 	to 	be 	followed 	during
medical 	emergencies, 	including phone 	numbers
of 	the 	nearest 	hospital 	or 	other 	emergency
facility, 	which 	shall 	be 	posted by 	the
nearest 	telephone;
(5) 	Copies 	of 	certificates 	held 	by all 	abatement
workers 	and 	abatement 	contractor/supervisors
actively 	engaged 	in 	the 	abatement 	project;
(6) 	Certification 	of 	the 	project 	designer 	who
wrote 	procedures 	for 	the 	job;
(7) 	Copies 	of 	bulk 	sampling 	results, 	including
inspector 	and 	laboratory names 	for 	all
504-15
§11-504-18
suspect 	material 	to 	be 	disturbed 	that 	is 	not
assumed 	to 	be 	asbestos-containing; 	and
(8) 	Records 	of 	all 	air 	sampling 	as 	required 	in
section 	12-145-5. 	[Eff FEB 15 	2n,11 	]
(Auth: 	HRS 	§342P-42) 	(Imp: 	40 	CF'R 	Part
763, 	Appendix 	C)
§11-504-19 	Summary 	of 	requirements 	for
laboratories 	and 	analysts. 	(a) 	All 	laboratories 	or
analysts, 	or 	both must 	annually 	register 	with 	the
department 	in 	order 	to 	provide 	analysis 	on 	samples 	from
regulated 	facilities. 	All 	applications 	for
registration 	shall 	be 	made 	on 	forms 	provided 	by 	the
department 	which 	shall 	contain 	the 	following
information:
(1) 	Name 	and 	address 	of 	business 	owner;
(2) 	Name 	and 	address 	of 	the 	laboratory;
(3) 	Results 	of 	most 	recent 	quarterly 	test 	by
AIHA;
(4) 	Names 	of 	all 	analysts 	employed 	in 	the
laboratory;
(b) 	All 	analysts 	performing 	asbestos 	analysis 	on
samples 	from 	regulated 	facilities 	shall 	have 	completed
the 	NIOSH 	582 	course 	in 	asbestos 	analysis 	or 	its
equivalent.
(c) 	Bulk 	sample 	analysis 	requires 	participation
in 	a 	laboratory 	testing 	program, 	and 	air 	sample
analysis 	requires 	participation 	in 	either 	a 	laboratory
testing 	program or 	an 	individual 	analyst 	testing
program. 	All 	members 	of 	a 	participating 	laboratory
shall 	participate 	in 	the 	testing 	rounds 	and 	records 	of
the 	results 	shall 	be 	kept 	by 	the 	laboratory.
(d) 	Bulk samples 	shall 	be 	analyzed 	by 	polarized
light 	microscopy 	(PLM) 	in 	accordance 	with 	"Interim
method 	for 	the 	determination 	of 	asbestos 	in 	bulk
insulation 	samples", 	found 	in 	40 	CFR 	Part 	763, 	Appendix
E 	to 	Subpart 	E. 	The 	laboratory or 	analyst 	shall 	be
accredited 	in 	one 	of 	the 	following 	programs:
(1) 	The 	National 	Voluntary Laboratory
Accreditation 	Program 	(NVLAP), 	administered
by NIST; 	or
504-16
§11-504-21
(2) 	The 	Bulk Asbestos 	Quality Assurance 	(BAQA)
program administered 	by AIHA.
(e) 	Air 	clearance 	samples 	analyzed 	by
transmission 	electron microscopy 	(TEM) 	shall 	be
analyzed 	in 	accordance 	with 	"Interim 	transmission
electron microscopy 	analytical 	methods", 	found 	in 	40
CFR 	Part 	763 	Appendix A to 	Subpart 	E. 	The 	laboratory
or 	analyst 	shall 	be 	accredited with NVLAP.
(f) 	Air 	samples 	analyzed by phase 	contrast
microscopy 	(PCM) 	shall 	be 	performed 	by 	laboratories 	or
analysts 	that 	use 	the 	NIOSH 	7400 	method 	and 	participate
in 	one 	of 	the 	following 	programs:
(1) 	The 	laboratory 	Proficiency Analytical 	Testing
(PAT) 	program, 	administered 	by AIHA; 	or
(2) 	The 	Asbestos 	Analytical 	Testing 	(AAT)
program, 	administered by AIHA 	and 	registered
in 	the 	Asbestos 	Analysts 	Registry 	(AAR).
(g) 	Any 	changes 	in 	personnel 	or 	status 	with AIHA
or NIST 	shall 	require 	written 	notification 	to 	the
department 	tμq..t 	is 	received 	or postmarked within 	thirty
days. 	[Ef f 	t tB 	J 5 2001 	] 	(Auth: 	HRS 	§342P-42)
(Imp: 	40 	CFR 	Part 	763, 	Appendix C)
§11-504-20 	Reserved
SUBCHAPTER 	2
Certification of 	Workers 	and 	Contractor/Supervisors
§11-504-21 	General 	requirements 	for
certification. 	(a) 	No 	person 	shall 	perform 	any
abatement 	project 	without 	first 	being 	certified 	as 	a
worker 	or 	a 	contractor/supervisor by 	the 	department.
(b) 	No 	person 	shall 	engage 	in 	any 	on-site
supervision of 	a 	worker 	during 	an 	abatement 	project
without 	first 	being 	certified as 	a
contractor/supervisor.
(c) 	Any person 	seeking 	certification 	as 	a 	worker
504-17
§11-504-21
or 	contractor/supervisor 	shall 	apply 	for 	a 	certificate
in 	accordance 	with 	section 	11-504-6.
[Eff FEB 1 !i 	2nn1 	] 	(Auth: 	HRS 	§342P-41)
CFR 	Part 	76~, 	X~pendix 	C)
(Imp:
§11-504-22 	Workers. 	(a) 	A worker 	may 	provide
services 	that 	include 	the 	following:
(1) 	Perform 	abatement 	work as 	designed 	by 	a
certified project 	designer; 	and
(2) 	Perform 	small-scale, 	short 	duration 	or
emergency 	activities.
(b) 	The 	minimum 	requirements 	necessary 	for
certification as 	a 	worker 	include:
(1) 	Is 	at 	least 	eighteen years 	of 	age; 	and
40
(2) 	Has 	successfully 	completed 	an 	accredited
four-day, 	initial 	training 	course 	in
accordance 	with 	section 	ll-504-52(a) 	or 	any
associated 	refresher 	course 	in 	accordance
with 	section 	11-504-53.
[Eff 	FEB 15 	20 	1 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C(l) (B) (1))
§11-504-23 	Contractor/Supervisors. 	(a) 	A
contractor/supervisor may provide 	services 	that 	include
the 	following:
(1) 	Perform 	abatement 	work 	as 	described 	for
workers 	in 	accordance 	with 	ll-504-22(a);
(2) 	Ensure 	proper 	work practices 	are 	followed;
and
(3) 	Ensure 	that 	the 	abatement 	project 	is
performed 	in 	accordance 	with 	the
specification of 	the 	certified project
designer.
(b) 	The 	minimum 	requirements 	necessary 	for
certification as 	a 	contractor/supervisor 	include:
(1) 	Is 	at 	least 	eighteen years 	of 	age; 	and
(2) 	Fulfills 	one 	of 	the 	following 	sets 	of
requirements:
(A) 	Has 	six months 	of 	experience 	working
within 	containment 	and 	has 	either
504-18
§11-504-29
successfully 	completed a 	five-day,
initial 	contractor/supervisor 	training
course 	in 	accordance 	with 	11-504-52(b)
or 	a 	refresher 	course 	in 	accordance 	with
11-504-53. 	The 	abatement 	entity 	shall
submit 	evidence 	of 	these 	requirements 	to
the 	department, 	including 	a 	summary of
past 	contracts 	and 	abatement 	projects
completed; 	or
(B) 	Three 	years 	of 	experience 	in 	general
construction 	and 	either 	successful
completion 	of 	an 	accredited
contractor/supervisor 	training 	course 	in
accordance 	with 	subsection 	11-504-52(b)
or 	any 	associated 	refresher 	training
course 	in 	accordance 	with 	section 	11-
504-53. 	The 	asbestos 	abatement 	entity
shall 	submit 	evidence 	of 	this 	training
and 	experience 	to 	the 	department,
including 	a 	summary of 	past 	contracts
and 	abatement 	projects 	completed.
[Eff FEB 	1 5 2001 	] 	(Auth: 	HRS 	§342P-
41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix
C(l)(B)(2))
§11-504-24 	Reserved
§11-504-25 	Reserved
§11-504-26 	Reserved
§11-504-27 	Reserved
§11-504-28 	Reserved
§11-504-29 	Reserved
504-19
§11-504-30
§11-504-30 	Reserved
SUBCHAPTER 	3
Inspectors, 	Management 	Planners, 	Project 	Designers, 	and
Project 	Monitors
§11-504-31 	Definitions. 	As 	used 	in 	this
subchapter:
"Engineering" 	means 	any 	service 	or 	creative 	work,
the 	adequate 	performance 	of 	which 	requires 	engineering
education, 	training, 	State 	licensing, 	and 	experience 	in
the 	application 	of 	special 	knowledge 	of 	the
mathematical, 	physical, 	and 	engineering 	sciences. 	This
includes 	consultation, 	investigation, 	evaluation,
planning, 	and 	design 	of 	engineering works 	and 	systems,
planning 	the 	use 	of 	land 	and water, 	and 	accomplishing
engineering 	surveys. 	Such 	services 	or 	work may 	be
either 	for 	public 	or 	private 	purposes, 	and 	may 	be
performed 	in 	connection with 	any 	utilities, 	structures,
buildings, 	machines, 	equipment, 	processes, 	work
systems, 	projects, 	and 	equipment 	systems 	of 	a
mechanical, 	electrical, 	hydraulic, 	pneumatic, 	or
thermal 	nature, 	insofar 	as 	they 	involve 	safeguarding
life, 	health, 	or 	property.
"Industrial 	hygiene" 	means 	the 	recognition 	of
environmental 	factors 	and 	stresses 	associated 	with work
and 	work 	operations 	and 	the 	understanding 	of 	their
effects 	on people 	and 	their 	well-being 	in 	the 	workplace
and 	the 	community; 	the 	evaluation, 	through 	training 	and
experience, 	and 	with 	the 	aid of 	quantitative
measurement 	techniques, 	of 	the 	magnitude 	of 	these
factors 	and 	stresses 	in 	terms 	of 	ability 	to 	impair 	a
person's 	health 	and 	well-being; 	and 	the 	prescription 	of
methods 	to 	control 	or 	reduce 	such 	factors 	and 	stresses
when 	necessary 	to 	alleviate 	their 	effects.
[Eff 	f[B 	15 	2001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C and HRS 	§321-15)
504-20
§11-504-33
§11-504-32 	General 	requirements. 	(a) 	No 	person
shall 	provide 	any 	of 	the 	services 	in 	this 	subchapter
without 	first 	being 	certified by 	the 	department 	to
provide 	such 	services.
(b) 	Any person 	seeking 	certification 	as 	an
inspector, 	management 	planner, 	project 	designer 	or
project 	monitor 	shall 	apply 	for 	certification 	in
accordance 	with 	section 	11-504-6.
(c) 	All 	certified persons 	shall 	keep 	a 	copy 	of
their 	certificate 	at 	the 	location where 	they 	are
conducting 	the 	abatement 	work. 	[Eff 	FEB 	} 5 2001
(Auth: 	HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix
C)
§11-504-33 	Inspector. 	(a) 	A person 	certified 	as
an 	inspector may provide 	services 	that 	include 	the
following:
(1) 	Collect 	bulk 	samples 	from 	suspect 	asbestos-
containing 	material;
(2) 	Evaluate 	the 	condition 	of 	asbestos-containing
materials 	in 	buildings;
(3) 	Inspect 	buildings 	for 	the 	presence 	of
asbestos-containing 	materials;
(4) 	Formulate 	plans 	for 	bulk 	sampling 	strategies;
and
(5) 	Determine 	whether 	suspect 	asbestos-containing
materials 	are 	friable 	or 	non-friable.
(b) 	The 	minimum 	requirements 	necessary 	for
certification 	as 	an 	inspector 	are:
(1) 	Possession 	of 	at 	least 	two 	years 	of 	full-time
college 	education 	from 	an 	accredited 	college
or 	university, 	successful 	completion 	of 	an
inspector 	initial 	training 	course, 	and 	any
associated 	annual 	refresher 	courses
accredited 	by 	the 	department;
(2) 	Possession 	of 	a 	high 	school 	diploma 	or
General 	Equivalency Diploma, 	two 	years 	of
experience 	in 	engineering 	or 	industrial
hygiene, 	successful 	completion 	of 	an
inspector 	initial 	training 	course, 	and 	any
504-21
§11-504-33
associated 	annual 	refresher 	training 	courses
accredited 	by 	the 	department; 	or
(3) 	Possession 	of 	a 	high 	school 	diploma 	or
General 	Equivalency Diploma, 	one 	year 	of
experience 	in 	abatement 	activities,
successful 	completion 	of 	an 	inspector 	initial
training 	course, 	and 	any 	associated 	annual
refresher 	courses 	accredited 	by 	the
department. 	[Ef f 	FEB 	l 5 2on1 	J 	(Auth =
HRS 	§342P-41) 	(Imp: 	40 	CFR Part 	763,
Appendix 	C(l) (B) (3) 	and 	(1) (E) (1))
§11-504-34 	Management 	planner. 	(a) 	A person
certified 	as 	a 	management 	planner may provide 	services
that 	include 	the 	following:
(1) 	Utilize 	information gathered by 	certified
inspectors 	to 	assess 	the 	potential 	hazards 	of
asbestos-containing 	materials;
(2) 	Develop 	abatement 	response 	actions,
management 	plans, 	or 	operation 	and
maintenance 	plans;
(3) 	Select 	and 	recommend 	abatement 	actions 	to
mitigate 	the 	health 	hazards 	posed 	by
asbestos-containing 	materials 	in 	facilities;
and
(4) 	Provide 	advice 	to 	clients 	on 	the 	selection
and 	use 	of 	personal 	protective 	equipment.
(b) 	The 	minimum 	requirements 	necessary 	for
certification 	as 	a 	management 	planner 	are:
(1) 	Possession 	of 	a 	bachelor's 	degree 	in 	project
planning, 	management, 	environmental 	sciences,
engineering, 	architecture, 	industrial
hygiene, 	occupational 	health, 	or 	a 	related
scientific 	field; 	six months 	of 	experience 	in
abatement 	activities, 	successful 	completion
of 	an 	inspector 	and management 	planner
initial 	training 	course, 	and 	any 	associated
annual 	refresher 	courses 	accredited 	by 	the
department;
(2) 	Possession 	of 	an 	associates 	degree 	in project
planning, 	management, 	environmental 	sciences,
504-22
§11-504-35
engineering, 	construction, 	architecture,
industrial 	hygiene, 	occupational 	health, 	or 	a
related 	scientific 	field, 	one 	year 	of
experience 	in 	abatement 	activities,
successful 	completion 	of 	an 	inspector 	and
management 	planner 	initial 	training 	course,
and 	any 	associated 	annual 	refresher 	courses
accredited by 	the 	department; 	or
(3) 	Possession 	of 	a 	high 	school 	diploma 	or
General 	Equivalency Diploma, 	three 	years 	of
experience 	in 	engineering 	or 	industrial
hygiene, 	one 	year 	of 	experience 	in 	abatement
activities, 	successful 	completion 	of 	an
inspector 	and 	management 	planner 	initial
training 	course, 	and 	any 	associated 	annual
refresher 	courses 	accredited 	b¥ 	the
department. 	[Ef f 	FEB 1 	200 ! 	] 	(Auth:
HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763,
Appendix 	C ( 1) ( B) ( 4 ) 	and 	( 1 ) ( E) ( 2 ) )
§11-504-35 	Project 	designer. 	(a) 	A person
certified as 	a 	project 	designer may provide 	services
that 	include 	the 	following:
(1) 	Provide 	the 	design, 	preparation, 	and
evaluation 	of 	abatement 	projects 	or 	abatement
project 	specifications;
(2) 	Prepare 	bidding 	documents, 	architectural
drawings, 	and 	schematic 	representation 	of
material 	locations; 	and
(3) 	Determine 	how 	the 	abatement 	should 	be
conducted.
(b) 	The 	minimum 	requirements 	necessary 	for
certification 	as 	a 	project 	designer 	are:
(1) 	Status 	as 	either 	an American 	Board 	of
Industrial 	Hygiene 	Certified 	Industrial
Hygienist, 	a 	licensed 	Professional 	Engineer,
or 	licensed Architect, 	six months 	of
experience 	in 	abatement 	projects, 	successful
completion 	of 	an 	accredited 	project 	designer
initial 	training 	course, 	and 	any 	associated
504-23
)
§11-504-35
annual 	refresher 	courses 	accredited 	by 	the
department;
(2) 	Possession 	of 	a 	bachelor's 	degree 	from 	an
accredited 	four-year 	college 	or 	university,
one 	year 	of 	experience 	in 	abatement 	projects,
successful 	completion 	of 	a 	project 	designer
initial 	course, 	and 	any 	associated 	annual
refresher 	courses 	accredited 	by 	the
department;
(3) 	Possession 	of 	an 	associates 	degree 	in project
planning, 	management, 	environmental 	sciences,
engineering, 	construction, 	architecture,
industrial 	hygiene, 	occupational 	health, 	or 	a
related 	scientific 	field, 	three 	years 	of
experience 	in 	abatement 	projects, 	the
successful 	completion 	of 	a 	project 	designer
initial 	training 	course, 	and 	any 	associated
annual 	refresher 	courses 	accredited 	by 	the
department; 	or
(4) 	Possession 	of 	a 	high 	school 	diploma 	or
General 	Equivalency Diploma, 	four 	years 	of
experience 	in 	engineering 	or 	industrial
hygiene; 	one 	year 	of 	experience 	in 	abatement
projects, 	successful 	completion 	of 	a 	project
designer 	initial 	training 	course, 	and any
associated 	annual 	refresher 	courses
accredited by 	the 	department.
[Eff 	FEB J 5 2001 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C(l) (B) (5)
and 	( 1 ) ( E) ( 3 ) )
§11-504-36 	Project 	monitor. 	Project 	monitors 	are
required pursuant 	to 	section 	11-502-9 	but 	are 	not
required 	for 	all 	abatement 	projects. 	(a) 	A person
certified 	as 	a 	project 	monitor may provide 	services
that 	include 	the 	following:
(1) 	Recommend 	to 	the 	building 	owner 	abatement
options 	to 	mitigate 	the 	health 	hazard posed
by 	the 	asbestos-containing 	materials 	in
buildings;
504-24
§11-504-36
(2) 	Collect 	air 	samples 	for 	the 	purpose 	of 	area
and 	clearance 	monitoring 	at 	abatement 	project
sites 	provided 	that 	the 	monitor 	is 	not 	an
employee 	of 	the 	abatement 	entity performing
the 	abatement, 	unless 	the 	project 	is
conducted 	solely by 	in-house 	employees;
(3) 	Provide 	advice 	to 	the 	building 	owner 	on
selection and 	use 	of 	personal 	protective
equipment;
(4) 	Oversee 	abatement 	projects 	carried 	out 	by
abatement 	entities;
(5) 	Perform visual 	inspections 	of 	completed
abatement 	projects 	to 	determine 	if 	the
project 	meets 	completion 	requirements; 	and
(6) 	Serve 	as 	a 	building 	owner 	representative 	to
ensure 	that 	abatement 	is 	done 	correctly.
(b) 	The 	minimum 	requirements 	necessary 	for
certification 	as 	a 	project 	monitor 	are:
(1) 	Possession 	of 	a 	bachelor's 	degree 	from 	an
accredited 	four-year 	college 	or 	university,
documented 	participation 	in 	a 	minimum of
three 	abatement 	projects 	inside 	an 	asbestos
containment 	area, 	successful 	completion 	of 	a
project 	monitor 	initial 	training 	course, 	and
any 	associated 	annual 	refresher 	courses
accredited 	by 	the 	department;
(2) 	Possession 	of 	two 	years 	of 	full-time 	college
education 	from 	an 	accredited 	college 	or
university, 	one 	year 	of 	experience 	in
engineering 	or 	industrial 	hygiene, 	documented
participation 	in 	a 	minimum of 	three 	abatement
projects 	inside 	an 	asbestos 	containment 	area,
successful 	completion 	of 	a 	project 	monitor
initial 	training 	course, 	and 	any 	associated
annual 	refresher 	courses 	accredited 	by 	the
department; 	or
(3) 	Possession 	of 	a 	high 	school 	diploma 	or
General 	Equivalency Diploma, 	three 	years 	of
experience 	in 	engineering 	or 	industrial
hygiene, 	documented participation 	in 	a
minimum of 	three 	abatement 	projects 	inside 	an
asbestos 	containment 	area, 	successful
504-25
§11-504-36
completion 	of 	a 	project 	monitor 	initial
training 	course, 	and 	any 	associated 	annual
refresher 	course 	accredited 	by 	the
department. 	[Ef f 	FEB 	} 5 2001 	] 	(Auth:
HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763,
Appendix 	C(l) (B) (6))
§11-504-37 	Reserved
§11-504-38 	Reserved
§11-504-39 	Reserved
§11-504-40 	Reserved
SUBCHAPTER 	4
Accreditation 	of 	Training 	Courses
§11-504-41 	General 	requirements. 	All 	training
courses 	which 	are 	used 	to 	fulfill 	certification
requirements 	must 	be 	accredited by 	the 	department. 	One
day 	of 	training 	equals 	eight 	hours, 	including 	breaks
and 	lunch. 	Any 	applicant 	seeking 	accreditation 	of 	an
asbestos 	training 	course 	shall 	comply with 	the
requirements 	of 	this 	subchapter 	and 	shall 	apply 	to 	the
department 	as 	required 	by 	chapter 	11-504-43 	before
accreditation 	may be 	granted by 	the 	department.
[Eff 	FEB 15 	2001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C(3))
§11-504-42 	Interim accreditation. 	(a) 	Training
courses 	which 	are 	accredited, 	licensed, 	certified,
permitted 	or 	approved 	by a 	state 	other 	than 	Hawaii
which 	has 	EPA 	approval 	on 	the 	effective 	date 	of 	these
rules 	shall 	be 	accredited on 	an 	interim basis,
504-26
§11-504-43
according 	to 	the 	following 	guidelines, 	for 	a 	period 	of
six months 	or 	until 	their 	current 	accreditation
expires, 	whichever 	is 	sooner, 	at 	which 	time 	they 	shall
meet 	all 	current 	requirements. 	Complete 	accreditation
shall 	be 	granted 	following 	an 	audit 	of 	the 	course(s)
and 	if 	they 	are 	found 	to 	be 	in 	compliance 	with 	this
subchapter.
(b) 	New 	applicants 	shall 	be 	granted 	interim
accreditation upon 	submission 	of 	all 	required materials
for 	a 	period 	of 	six months, 	during 	which 	the 	department
shall 	audit 	their 	training 	course(s) 	and 	determine
whether 	the 	course(sj 	meets 	the 	requirement 	of 	this
subchapter. 	[Eff 	~EB 15 	2001] 	(Auth: 	HRS 	§342P-
41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C(3))
§11-504-43 	Application 	for 	training 	course
accreditation. 	(a) 	The 	applicant 	for 	accreditation of
an 	asbestos 	training 	course 	must 	submit 	the 	following
information 	in 	writing 	to 	the 	department 	in 	compliance
with 	the 	instructions 	on 	the 	application 	form:
(1) 	The 	name, 	address, 	and 	phone 	number 	of 	the
firm 	or 	person 	to 	be 	presenting 	the 	course;
(2) 	The 	type 	of 	course 	or 	courses 	for 	which
accreditation 	is 	being 	requested;
(3) 	A detailed 	outline 	of 	the 	course 	curriculum
including 	the 	amount 	of 	time 	allotted 	to 	each
topic;
(4) 	The 	name 	and 	qualifications 	of 	the 	person
developing 	the 	instruction program 	for 	each
topic 	or 	a 	statement 	that 	the 	training
materials 	have 	been purchased 	from 	the 	EPA
and 	have 	been updated 	to 	meet 	current
requirements;
(5) 	The 	names 	of 	the 	course 	instructors 	and
documentation 	to 	demonstrate 	that 	they 	are
adequately 	qualified 	and 	experienced 	in 	the
areas 	they 	are 	to 	teach;
(6) 	A description 	of 	the 	instruction program 	for
each 	topic, 	including 	teaching 	methods 	to 	be
used 	and 	copies 	of 	written 	materials 	to 	be
distributed;
504-27
§11-504-43
(7) 	A description 	of 	the 	type 	of 	equipment 	to 	be
used 	for 	demonstrations 	and 	"hands-on"
practice 	exercises, 	such 	as 	respirators,
negative 	air 	units, 	water 	spray 	devices,
protective 	clothing, 	and 	construction
materials;
(8) 	The 	instructor-to-student 	ratio 	for 	"hands-
on" 	practice 	exercises 	and 	demonstrations;
(9) 	Documentation 	that 	the 	number 	of 	instructors,
the 	amount 	of 	equipment, 	and 	the 	facilities
are 	adequate 	to 	provide 	the 	students 	with
proper 	training;
(10) 	Documentation 	that 	the 	training 	course 	shall
give 	a 	written, 	multiple 	choice 	examination
at 	the 	conclusion 	of 	the 	course;
(11) 	Documentation 	that 	the 	minimum grade 	of
seventy per 	cent 	correct 	must 	be 	obtained 	for
a 	student 	to 	successfully 	complete 	the
course;
(12) 	Documentation 	that 	students 	who 	attend 	and
successfully complete 	the 	course 	shall 	be
issued 	numbered 	certificates 	indicating 	the
name 	of 	the 	training 	provider, 	student, 	and
the 	course 	completed, 	the 	dates 	of 	the 	course
and 	the 	examination, 	and 	a 	statement
indicating 	that 	the 	student 	passed 	the
written 	exam;
(13) 	Documentation 	that 	the 	department 	shall 	be
provided, 	in 	writing, 	the 	names 	and
examination 	scores 	of 	all 	course 	participants
at 	the 	completion 	of 	the 	course; 	and
(14) 	An 	agreement 	to 	inform 	the 	department 	in
writing 	at 	least 	thirty days 	in 	advance 	of
the 	start 	of 	any 	asbestos 	training 	course 	to
be 	conducted by 	the 	applicant, 	and permission
for 	representatives 	of 	the 	department 	to
attend 	any 	asbestos 	training 	course 	and 	take
the 	examination without 	advance 	notice 	or
cost 	to 	the 	department.
(b) 	Within 	thirty working 	days 	after 	receiving 	an
application, 	the 	department 	shall 	acknowledge 	receipt
of 	the 	application 	and 	notify 	the 	applicant 	of 	any
504-28
§11-504-45
deficiency 	in 	the 	application. 	Within 	thirty working
days 	after 	receiving 	the 	amended 	application 	that
includes 	any 	additional 	information 	requested 	by 	the
department, 	the 	department 	shall 	approve 	or 	deny 	the
application. 	If 	the 	department 	requests 	further
information 	from 	an 	applicant, 	and 	does 	not 	receive
that 	information within 	thirty 	days, 	the 	application
shall 	be 	considered 	abandoned 	and 	certification 	shall
be 	denied. 	[Eff 	FEB J 5 2001 . 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appehtiix 	C(3))
§11-504-44 	Denial 	of 	application. 	The 	department
may 	deny an 	application 	for 	accreditation 	of 	any
training 	course 	that 	fails 	to 	meet 	the 	standards
established by 	these 	rules, 	including, 	but 	not 	limited
to:
(1) 	Failure 	to 	demonstrate 	the 	ability 	of 	the
training 	course 	to 	comply 	fully 	with
applicable 	requirements, 	procedures, 	and
standards 	set 	forth 	in 	these 	rules;
(2) 	Past 	history 	of 	incompetence 	or 	negligence 	in
providing 	training 	courses 	on 	the 	part 	of 	the
responsible 	person, 	employees, 	or 	agents;
(3) 	Submission 	of 	false 	information 	on 	an
application 	or 	issuance 	of 	false
documentation;
(4) 	Failure 	to 	demonstrate 	the 	ability of 	the
training 	course 	to 	effectively 	train 	course
participants; 	or
(5) 	Past 	history 	of 	noncompliance 	with 	federal 	or
state 	asbestos 	re$ulations.
[Eff 	FEB 1 5 2001 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-45 	Complete 	accreditation. 	(a) 	Final
accreditation 	shall 	be 	granted 	for 	a 	period 	of 	two
years 	after 	the 	department 	has 	determined 	that 	the
applicant's 	asbestos 	training 	course 	meets 	the
requirements 	of 	these 	rules. 	Accreditation may 	involve
an 	audit 	conducted by 	the 	department, 	which 	can 	include
504-29
§11-504-45
attending 	the 	training 	course 	and/or 	reviewing 	records
kept 	by 	the 	training 	provider.
(b) 	Any 	significant 	change 	in 	an 	accredited
course 	must 	be 	reported 	to 	and 	approved 	by 	the
department 	prior 	to 	presenting 	the 	changed 	course.
Course 	changes 	must 	be 	received by 	the 	director 	thirty
days 	prior 	to 	the 	changed 	course 	being 	offered.
(c) 	The 	department 	maintains 	the 	right 	to 	attend
any 	training 	course, 	regardless 	of 	accreditation
status, 	without 	advance 	notice.
(d) 	Failure 	by 	the 	department 	to 	act 	on 	an
application 	for 	complete 	accreditation 	shall 	be 	deemed
an 	approval 	of 	the 	application. 	[Eff 	FEB } 5 200 	]
(Auth: 	HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix
C ( 3) )
§11-504-46 	Suspension, 	revocation, 	and
modification 	of 	accreditation. 	(a) 	The 	department 	may
suspend, 	revoke, 	or 	modify any 	training 	course
accreditation 	after 	a 	hearing 	in 	accordance 	with
chapter 	91, 	HRS, 	for:
(1) 	Failure 	to 	comply with 	the 	applicable
requirements, 	procedures, 	and 	standards;
(2) 	Misrepresentation 	of 	the 	extent 	of 	a 	training
course's 	approval 	by 	a 	state 	or 	the 	EPA;
(3) 	Failure 	to 	submit 	required 	information 	or
notifications 	in 	a 	timely manner;
(4) 	Failure 	to 	maintain 	requisite 	records;
(5) 	Falsifications 	of 	accreditation 	records,
instructor 	qualifications, 	or 	other
accreditation 	information; 	or
(6) 	Failure 	to 	adhere 	to 	the 	training 	standards
and 	requirements 	of 	the 	EPA 	or 	chapter 	504.
(b) 	The 	department 	may 	also 	suspend 	or 	withdraw
training 	course 	accreditation 	if 	an 	accredited 	training
course 	instructor 	or 	other person with 	supervisory
authority 	over 	the 	delivery of 	training 	has 	been 	found
in 	violation 	of 	other 	asbestos 	rules 	administered by
the 	department. 	A finding 	of 	violation, 	or 	execution 	of
a 	consent 	agreement 	and 	order 	constitute 	evidence 	of 	a
failure 	to 	comply with 	relevant 	statutes, 	rules, 	and
504-30
§11-504-49
regulations. 	[Eff 	FEB 15 	2001 	(Auth: 	HRS 	§342P-
41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C(4))
§11-504-47 	Letters 	of 	accreditation. 	After
accreditation has 	been granted, 	a 	certificate 	of
accreditation 	shall 	be 	issued 	to 	the 	applicant 	and
shall 	contain 	the 	following:
(1) 	The 	date 	of 	issuance;
(2) 	The 	date 	of 	expiration;
(3) 	The 	name 	and 	address 	of 	the 	training 	agency,
institution, 	firm, 	or 	person, 	and 	the 	name 	of
the 	training 	course;
(4) 	A statement 	as 	to 	whether 	the 	accreditation
is 	complete 	or 	interim; 	and
(5) 	The 	name, 	address, 	and phone 	number 	of 	the
state 	certifying 	authority.
[Ef f 	F[B 	} 5 200 j 	] 	(Auth: 	HRS 	§342P-4 l)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-48 	Expiration 	of 	accreditation. 	(a)
Interim accreditation 	shall 	expire 	six months 	from 	the
first 	day 	of 	the 	month 	stated on 	the 	letter 	of 	interim
accreditation.
(b) 	Complete 	accreditation 	shall 	expire 	two 	years
from 	the 	first 	day 	of 	the 	month 	statec;l-pA 	J;.~ 	01
certificate 	of 	accreditation. 	[Eff 	t t.D 1;:)
(Auth: 	HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix
C)
§11-504-49 	Renewal 	of 	accreditation. 	(a) 	To
renew 	an 	accreditation 	of 	an 	asbestos 	training 	course,
the 	applicant 	shall 	resubmit 	the 	information 	required
in 	section 	11-504-43 	without 	reference 	to 	any
previously 	submitted material. 	A visitation 	is 	not
required 	to 	renew 	accreditation.
(b) 	In 	any 	case 	in which 	the 	responsible 	person
of 	a 	training 	course 	with 	complete
accreditation has 	filed 	an 	application 	in
proper 	form 	for 	renewal, 	not 	less 	than 	sixty
504-31
§11-504-49
days 	prior 	to 	expiration 	of 	its 	existing
complete 	accreditation, 	such 	existing
complete 	accreditation 	shall 	not 	expire 	until
final 	action on 	the 	application 	has 	been
taken 	b.Y the 	department.
[Eff 	f tB 15 	2001 	] 	(Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C)
§11-504-50 	Reciprocity. 	(a) 	Each 	applicant 	for
accreditation 	of 	an 	asbestos 	training 	course 	which 	is
accredited, 	licensed, 	certified, 	permitted, 	or 	approved
by a 	state 	other 	than Hawaii 	which 	has 	EPA 	approval 	may
petition 	the 	director 	to 	grant 	complete 	accreditation
without 	a 	visitation 	of 	the 	in-progress 	training 	course
by 	the 	department. 	The 	department 	shall 	evaluate 	the
requirements 	for 	accreditation, 	approval, 	permitting,
certification, 	or 	licensure 	of 	the 	approving 	authority
and 	shall 	grant 	accreditation 	without 	a 	visitation 	if
the 	department 	determines 	that 	the 	requirements 	of 	the
authority 	are 	equal 	to 	or 	greater 	than 	the 	requirements
for 	accreditation 	in 	the 	State.
(b) 	If 	the 	asbestos 	training 	course 	seeking
complete 	accreditation 	is 	not 	accredited, 	licensed,
certified, 	permitted, 	or 	approved 	by 	another 	state 	or
by 	a 	federal 	agency, 	then 	an 	audit 	of 	the 	course 	by 	a
department 	representative 	during 	the 	interim
accreqi~~tion ~eriod will 	be 	performed.
[Eff 	t tfJ 15 	L001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C(l) (H))
§11-504-51 	Retroactive 	accreditation. 	Training
courses 	that 	have 	taken place 	prior 	to 	accreditation 	by
the 	department 	may 	be 	accredited 	retroactively 	by 	the
department, 	provided 	that 	all 	accreditation
requirements, 	except 	the 	visitation, 	are 	met 	by 	the
course 	and 	the 	candidate 	instructor.
[Eff 	FEB 15 	2001 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix C)
504-32
§11-504-52
§11-504-52 	Initial 	course 	contents 	and
requirements. 	(a) 	The 	initial 	training 	course 	for
abatement 	workers 	shall 	consist 	of 	a 	four-day 	course
that 	shall 	include 	lectures, 	demonstrations, 	fourteen
hours 	of 	hands-on 	training, 	individual 	respirator 	fit
testing, 	course 	review, 	and 	one 	or 	more 	written
examinations. 	The 	fourteen 	hours 	of 	hands-on 	training
shall 	permit 	students 	to 	have 	actual 	experience
performing 	tasks 	associated 	with 	asbestos 	abatement.
The 	instructor-to-student 	ratio 	shall 	be 	no 	less 	than 	1
to 	25 	during 	the 	hands-on portion 	of 	the 	course. 	The
department 	recommends 	the 	use 	of 	audiovisual 	materials
to 	complement 	lectures 	where 	appropriate. 	The 	training
course 	shall 	adequately 	address 	the 	following 	topics:
(1) 	Physical 	characteristics 	of 	asbestos
including 	the 	identification of 	asbestos 	and
its 	aerodynamic 	characteristics, 	typical
uses, 	physical 	appearance, 	and 	a 	summary of
abatement 	control 	options;
(2) 	Potential 	health 	effects 	related 	to 	asbestos
exposure 	including 	the 	nature 	of 	asbestos-
related 	diseases, 	routes 	of 	exposure, 	dose-
response 	relationships 	and 	the 	lack 	of 	a 	safe
exposure 	level, 	the 	synergistic 	effect
between 	cigarette 	smoking 	and 	asbestos
exposure, 	the 	latency period 	for 	asbestos-
related 	diseases, 	and 	a 	discussion 	of 	the
relationship 	of 	asbestos 	exposure 	to
asbestosis, 	lung 	cancer, 	mesothelioma, 	and
cancers 	of 	other 	organs;
(3) 	Employee 	personal 	protective 	equipment
including 	the 	classes 	and 	characteristics 	of
respirator 	types; 	limitations 	of 	respirators
and 	their 	proper 	selection, 	inspection,
donning, 	use, 	maintenance, 	and 	storage
procedures; 	methods 	for 	field 	testing 	of 	the
facepiece-to-face 	seal 	(positive 	and 	negative
pressure 	fit 	checks); 	qualitative 	and
quantitative 	fit 	testing 	procedures;
variability between 	field 	and 	laboratory
protection 	factors 	that 	alter 	the 	fit 	of 	the
respirator 	(e.g., 	facial 	hair); 	components 	of
504-33
§11-504-52
a 	proper 	respiratory protection program;
selection 	and 	use 	of 	personal 	protective
clothing; 	use, 	storage, 	and 	handling 	of 	non-
disposable 	clothing; 	and 	regulations 	covering
personal 	protective 	equipment;
(4) 	State-of-the-art 	work practices 	including
proper 	work practices 	for 	abatement
activities 	with 	descriptions 	of 	proper
construction, 	maintenance 	of 	barriers 	and
decontamination 	enclosure 	systems;
positioning 	of 	warning 	signs; 	electrical 	and
ventilation 	system 	lockout; 	proper working
techniques 	for 	minimizing 	fiber 	release; 	use
of 	wet 	methods; 	use 	of 	negative 	pressure
exhaust 	ventilation 	equipment; 	use 	of 	high
efficiency particulate 	air 	(HEPA) 	vacuums;
proper 	clean up 	and 	disposal 	procedures; 	work
practices 	for 	removal, 	encapsulation,
enclosure, 	and 	repair 	of 	ACM; 	emergency
procedures 	for 	sudden 	releases; 	potential
exposure 	situations; 	transport 	and 	disposal
procedures; 	and 	recommended 	and 	prohibited
work 	practices;
(5) 	Personal 	hygiene 	including 	entry 	and 	exit
procedures 	for 	the 	work 	area; 	use 	of 	showers;
avoidance 	of 	eating, 	drinking, 	smoking, 	and
chewing 	in 	the 	work 	area; 	and 	potential
exposure, 	such 	as 	family 	exposure;
(6) 	Additional 	safety hazards 	that 	may 	be
encountered during 	the 	abatement 	activities
and how 	to 	deal 	with 	them, 	including
electrical 	hazards, 	heat 	stress, 	air
contaminants 	other 	than 	asbestos, 	fire 	and
explosion hazards, 	scaffold 	and 	ladder
hazards, 	slips, 	trips 	and 	falls, 	and 	confined
spaces;
(7) 	Medical 	monitoring 	including 	OSHA 	and 	EPA
Worker 	Protection 	Rule 	requirements 	for
physical 	examinations, 	including pulmonary
function 	tests, 	chest 	x-rays, 	medical 	history
for 	each 	employee, 	and 	any 	other 	tests
specified by 	the 	physician;
504-34
§11-504-52
(8) 	Air 	monitoring 	including 	procedures 	to
determine 	airborne 	concentrations 	of 	asbestos
fibers, 	focusing 	on how 	personal 	air
sampling 	is 	performed 	and 	the 	reasons 	for 	it;
(9) 	Relevant 	federal, 	state 	and 	local 	regulatory
requirements, 	procedures, 	and 	standards 	with
particular 	attention directed 	at 	relevant
EPA, 	OSHA, 	and 	state 	rules 	concerning
abatement 	workers;
(10) 	Establishment 	of 	respiratory protection
programs; 	and
(11) 	A review 	of 	key 	aspects 	of 	the 	training
course.
(b) 	The 	initial 	training 	course 	for
contractors/Supervisors 	shall 	consist 	of 	a 	five-day
course 	that 	shall 	include 	lectures, 	demonstrations, 	at
least 	fourteen 	hours 	of 	hands-on 	training, 	individual
respirator 	fit 	testing, 	course 	review, 	and 	one 	or more
written 	examinations. 	The 	fourteen 	hours 	of 	hands-on
training 	shall 	permit 	students 	to 	have 	actual
experience 	performing 	tasks 	associated 	with 	asbestos
abatement. 	The 	instructor-to-student 	ratio 	shall 	be 	no
less 	than 	1 	to 	25 	during 	the 	hands-on 	portion of 	the
course. 	The 	department 	recommends 	the 	use 	of
audiovisual 	materials 	to 	complement 	lectures, 	where
appropriate. 	The 	program 	shall 	adequately 	address 	the
following 	topics:
(1) 	The 	physical 	characteristics 	of 	asbestos 	and
asbestos-containing 	materials 	including 	the
identification of 	asbestos 	and 	its
aerodynamic 	characteristics, 	typical 	uses,
physical 	appearance, 	a 	review 	of 	hazard
assessment 	considerations, 	and 	a 	summary 	of
abatement 	control 	options;
(2) 	Potential 	health 	effects 	related 	to 	asbestos
exposure 	including 	the 	nature 	of 	asbestos-
related 	diseases, 	routes 	of 	exposure, 	dose-
response 	relationships 	and 	the 	lack 	of 	a 	safe
exposure 	level, 	synergism between 	cigarette
smoking 	and 	asbestos 	exposure, 	the 	latency
period 	for 	diseases, 	and 	a 	discussion of 	the
relationship 	of 	asbestos 	exposure 	to
504-35
§11-504-52
asbestosis, 	lung 	cancer, 	mesothelioma, 	and
cancers 	of 	other 	organs;
(3) 	Employee 	personal 	protective 	equipment
including 	the 	classes 	and 	characteristics 	of
respirator 	types; 	limitations 	of 	respirators
and 	their 	proper 	selection, 	inspection,
donning, 	use, 	maintenance, 	and 	storage
procedures; 	methods 	for 	field 	testing 	of 	the
facepiece-to-face 	seal 	(positive 	and 	negative
pressure 	fit 	checks); 	qualitative 	and
quantitative 	fit 	testing 	procedures;
variability between 	field 	and 	laboratory
protection 	factors 	that 	alter 	the 	fit 	of 	the
respirator 	(e.g., 	facial 	hair); 	components 	of
a 	proper 	respiratory protection program;
selection and use 	of 	personal 	protective
clothing; 	use, 	storage, 	and 	handling 	of 	non-
disposable 	clothing; 	and 	rules 	covering
personal 	protective 	equipment;
(4) 	State-of-the-art 	work 	practices 	including
proper 	work practices 	for 	abatement
activities 	with 	descriptions 	of 	proper
construction and maintenance 	of 	barriers 	and
decontamination 	enclosure 	systems;
positioning 	of 	warning 	signs; 	electrical 	and
ventilation 	system 	lockout; 	proper 	working
techniques 	for 	minimizing 	fiber 	release; 	use
of 	wet 	methods; 	use 	of 	negative 	pressure
exhaust 	ventilation 	equipment; 	use 	of 	high
efficiency particulate 	air 	(HEPA) 	vacuums;
proper 	clean up 	and 	disposal 	procedures; 	work
practices 	for 	removal, 	encapsulation,
enclosure, 	and 	repair 	of 	ACM; 	emergency
procedures 	for 	unplanned 	releases; 	potential
exposure 	situations; 	transport 	and 	disposal
procedures; 	and 	recommended 	and 	prohibited
work 	practices. 	Discussion 	of 	new 	abatement-
related 	techniques 	and 	methodologies 	may 	be
included;
(5) 	Personal 	hygiene 	including 	entry 	and 	exit
procedures 	for 	the 	work 	area; 	use 	of 	showers;
avoidance 	of 	eating, 	drinking, 	smoking, 	and
504-36
§11-504-52
chewing 	in 	the 	work 	area; 	and potential
exposures, 	such 	as 	family 	exposure;
(6) 	Additional 	safety hazards 	that 	may be
encountered during 	the 	abatement 	activities
and 	how 	to 	deal 	with 	them 	including
electrical 	hazards, 	heat 	stress, 	air
contaminants 	other 	than 	asbestos, 	fire 	and
explosion hazards, 	scaffold and 	ladder
hazards, 	slips, 	trips, 	and 	falls, 	and
confined 	spaces;
(7) 	Medical 	monitoring 	including 	HIOSH
requirements 	for 	a 	pulmonary 	function 	test,
chest 	X-rays 	and 	a 	medical 	history 	for 	each
employee;
(8) 	Air 	monitoring 	including 	procedures 	to
determine 	airborne 	concentrations 	of 	asbestos
fibers, 	including 	descriptions 	of 	aggressive
air 	sampling, 	sampling 	equipment 	and 	methods,
reasons 	for 	air 	monitoring, 	types 	of 	samples,
and 	interpretation 	of 	results, 	specifically
from 	analyses 	performed by 	polarized 	light,
phase-contrast, 	and 	electron microscopy
analysis;
(9) 	Relevant 	federal, 	state, 	and 	local 	regulatory
requirements 	including 	the 	following
procedures 	and 	standards:
(A) 	Requirements 	of 	TSCA 	Title 	II;
(B) 	40 	CFR 	Part 	61, 	National 	Emission
Standards 	for 	Hazardous 	Air 	Pollutants
(NESHAP), 	Subparts 	A 	(General
Provisions) 	and M (National 	Emission
Standards 	for 	Asbestos);
(C) 	HIOSH Asbestos 	Construction, 	General
Industry 	and 	respiratory 	protection
Standards 	(chapter 	12-145 	and 	12-206);
(D) 	Chapters 	501 	and 	502;
(E) 	40 	CFR, 	Part 	763, 	Asbestos 	Hazard
Emergency Response 	Act 	(AHERA);
(F) 	Applicable 	state 	and 	local 	rules, 	and
differences 	between 	federal 	and 	state
requirements, 	where 	they 	apply, 	and 	the
504-37
§11-504-52
effects 	on 	public 	and 	non-public 	schools
or 	public 	or 	commercial 	buildings;
(10) 	Respiratory protection programs 	and medical
monitoring 	programs;
(11) 	Insurance 	and 	liability 	issues 	including
worker's 	compensation 	coverage 	and
exclusions, 	third-party 	liabilities 	and
defenses, 	insurance 	coverage 	and 	exclusions;
(12) 	Record 	keeping 	for 	asbestos 	abatement
projects 	including 	records 	required by
federal, 	state, 	and 	local 	rules, 	and 	records
recommended 	for 	legal 	and 	insurance 	purposes;
(13) 	Supervisory 	techniques 	for 	asbestos 	abatement
activities, 	including 	supervisory practices
to 	enforce 	and 	reinforce 	the 	required 	work
practices 	and 	discourage 	unsafe 	work
practices;
(14) 	Contract 	specifications 	including 	discussion
of 	key 	elements 	that 	are 	included 	in 	contract
specifications; 	and
(15) 	A review 	of 	key 	aspects 	of 	the 	training
course.
(c) 	The 	initial 	training 	course 	for 	inspectors
shall 	consist 	of 	a 	three-day 	course 	that 	shall 	include
lectures, 	demonstrations, 	four 	hours 	of 	hands-on
training, 	individual 	respirator 	fit 	testing, 	course
review, 	and 	a 	written 	examination. 	The 	four 	hours 	of
hands-on 	training 	shall 	permit 	students 	to 	have 	actual
experience 	performing 	tasks 	associated 	with 	asbestos
inspection. 	The 	instructor-to-student 	ratio 	shall 	be
no 	less 	than 	1 	to 	25 	during 	the 	hands-on portion 	of 	the
course. 	The 	department 	recommends 	the 	use 	of
audiovisual 	materials 	to 	complement 	lectures, 	where
appropriate. 	The 	inspector 	training 	course 	shall
adequately 	address 	the 	following 	topics:
(1) 	Background 	information 	on 	asbestos 	including
the 	identification of 	asbestos, 	with 	examples
and 	discussion 	of 	the 	uses 	and 	locations 	of
asbestos 	in 	buildings; 	and 	the 	physical
appearance 	of 	asbestos;
(2) 	Potential 	health 	effects 	related 	to 	asbestos
exposure 	including 	the 	nature 	of 	asbestos-
504-38
§11-504-52
related 	diseases; 	routes 	of 	exposure; 	dose-
response 	relationships 	and 	the 	lack 	of 	a 	safe
exposure 	level; 	the 	synergistic 	effect
between 	cigarette 	smoking 	and 	asbestos
exposure; 	the 	latency period 	for 	asbestos-
related 	diseases; 	a 	discussion 	of 	the
relationship 	of 	asbestos 	exposure 	to
asbestosis, 	lung 	cancer, 	mesothelioma, 	and
cancers 	of 	other 	organs;
(3) 	Functions, 	qualifications, 	and 	role 	of
inspectors 	and 	management 	planners, 	including
discussions 	of 	prior 	experience; 	discussions
of 	the 	functions 	of 	a 	certified 	asbestos
inspector 	as 	compared 	to 	those 	of 	a 	certified
management 	planner; 	discussion 	of 	inspection
process 	including 	inventory 	of ACM 	and
physical 	assessment;
(4) 	Legal 	liabilities 	and 	defenses 	including
responsibilities 	of 	the 	inspector 	and
management 	planner; 	a 	discussion 	of
comprehensive 	general 	liability policies,
claims-made, 	and 	occurrence 	policies,
environmental 	and 	pollution 	liability policy
clauses; 	state 	liability 	insurance
requirements; 	bonding 	and 	the 	relationship 	of
insurance 	availability 	to 	bond 	availability;
(5) 	Understanding 	building 	systems 	including 	the
interrelationship 	between 	building 	systems,
with 	an 	overview 	of 	common 	building 	physical
plan 	layouts; 	heat, 	ventilation, 	and 	air
conditioning 	system types, 	physical
organization, 	and 	where 	asbestos 	is 	found 	on
heat, 	ventilation, 	and 	air 	conditioning
components; 	building mechanical 	systems,
their 	types 	and 	organization, 	and 	where 	to
look 	for 	asbestos 	on 	such 	systems; 	inspecting
electrical 	systems, 	including 	appropriate
safety precautions; 	and 	reading 	blueprints
and 	as-built 	drawings;
(6) 	Public, 	employee, 	and building 	occupant
relations, 	including 	notifying 	employee
organizations 	about 	the 	inspection; 	signs 	to
504-39
§11-504-52
warn 	building 	occupants; 	tact 	in 	dealing 	with
occupants 	and 	the 	press; 	scheduling 	of
inspections 	to 	minimize 	disruption; 	and
education 	of 	building 	occupants 	about 	actions
being 	taken;
(7) 	Pre-inspection planning 	and 	review 	of
previous 	inspection 	records 	including
scheduling 	the 	inspection 	and 	obtaining
access; 	building 	record 	review;
identification of 	probable 	homogeneous 	areas
from 	blueprints 	or 	as-built 	drawings;
consultation with maintenance 	or 	building
personnel; 	review 	of 	previous 	inspection,
sampling, 	and 	abatement 	records 	of 	a
building; 	and 	the 	role 	of 	the 	inspector 	in
exclusions 	for 	previously performed
inspections;
(8) 	Inspecting 	for 	friable 	and 	non-friable
asbestos-containing 	material 	and 	assessing
the 	condition 	of 	friable 	asbestos-containing
material 	including 	procedures 	to 	follow 	in
conducting visual 	inspections 	for 	friable 	and
non-friable 	asbestos-containing 	material;
types 	of 	building 	materials 	that 	may 	contain
asbestos; 	touching 	materials 	to 	determine
friability; 	open 	return 	air 	plenums 	and 	their
importance 	in 	heat, 	ventilation, 	and 	air
conditioning 	systems; 	assessing 	damage,
significant 	damage, 	potential 	damage, 	and
potential 	significant 	damage; 	amount 	of
suspected 	asbestos-containing 	material, 	both
in 	total 	quantity 	and 	as 	a 	percentage 	of 	the
total 	area; 	type 	of 	damage; 	accessibility;
asbestos-containing 	material's 	potential 	for
disturbance; 	known 	or 	suspected 	causes 	of
damage 	or 	significant 	damage; 	and
deterioration 	as 	assessment 	factors;
(9) 	Bulk 	sampling 	and 	documentation 	of 	asbestos
in 	schools 	including 	detailed 	discussion 	of
the 	"Simplified 	Sampling 	Scheme 	for 	Friable
Surfacing Materials" 	(EPA 	560/5-85-030a
October 	1985); 	techniques 	to 	ensure 	sampling
504-40
§11-504-52
in 	a 	randomly 	distributed manner 	for 	other
than 	friable 	surfacing 	materials; 	sampling 	of
non-friable 	materials; 	techniques 	for 	bulk
sampling; 	sampling 	equipment 	the 	inspector
should 	use; 	patching 	or 	repair 	of 	damage 	done
in 	sampling; 	an 	inspector's 	repair 	kit;
discussion 	of 	polarized 	light 	microscopy;
choosing 	an 	accredited 	laboratory 	to 	analyze
bulk 	samples; 	and 	quality 	control 	and 	quality
assurance 	procedures;
(10) 	Inspectors' 	respiratory protection 	and
personal 	protective 	equipment 	including 	the
classes 	and 	characteristics 	of 	respirator
types; 	limitations 	of 	respirators; 	proper
selection, 	inspection, 	donning, 	use,
maintenance, 	and 	storage 	procedures 	for
respirators; 	methods 	for 	field 	testing 	of 	the
facepiece-to-face 	seal 	(positive 	and 	negative
pressure 	fit 	checks); 	qualitative 	and
quantitative 	fit 	testing 	procedures;
variability between 	field 	and 	laboratory
protection 	factors 	that 	alter 	respirator 	fit
(e.g., 	facial 	hair); 	components 	of 	a 	proper
respiratory protection program; 	selection 	and
use 	of 	personal 	protective 	clothing; 	and use,
storage, 	and 	handling 	of 	non-disposable
clothing;
(11) 	Record 	keeping 	and writing 	the 	inspection
report 	including 	labeling 	of 	samples 	and
keying 	sample 	identification 	to 	sampling
location; 	recommendations 	on 	sample 	labeling;
detailing 	of 	asbestos-containing 	material
inventory; 	photographs 	of 	selected 	sampling
areas 	and 	examples 	of 	asbestos-containing
material 	condition; 	information 	required 	for
inclusion 	in 	the 	management 	plan 	by TSCA
Title 	II 	section 	203 (i) (1);
(12) 	Regulatory 	review 	including:
(A) 	Requirements 	of 	TSCA 	title 	II;
(B) 	40 	CFR 	Part 	61, 	National 	Emission
Standards 	for 	Hazardous 	Air 	Pollutants
(NESHAP), 	Subparts A 	(General
504-41
§11-504-52
Provisions) 	and M (National 	Emission
Standards 	for 	Asbestos);
(C) 	HIOSH Asbestos 	Construction, 	General
Industry 	and 	respiratory protection
Standards 	(chapters 	12-145 	and 	12-206);
(D) 	Chapter 	501 	(Asbestos 	Emission
Standards)and 	502 	(Asbestos-Containing
Materials 	in 	Schools)of 	Title 	11;
(E) 	Asbestos 	Hazard 	Emergency Response 	Act
(AHERA) 	40 	CFR 	Part 	763; 	and
(F) 	Applicable 	state 	and 	local 	rules, 	and
differences 	between 	federal 	and 	state
requirements, 	where 	they 	apply, 	and 	the
effects 	on public 	and 	non-public 	schools
or 	public 	or 	commercial 	buildings;
(13) 	A field 	trip 	including 	a 	walk-through
inspection; 	on-site 	discussion 	about
information 	gathering 	and 	the 	determination
of 	sampling 	locations; 	on-site 	practice 	in
physical 	assessment; 	and 	classroom 	discussion
of 	field 	exercise; 	and
(14) 	A review 	of 	key 	aspects 	of 	the 	training
course.
(d) 	The 	initial 	training 	course 	for 	management
planners 	shall 	consist 	of 	the 	three-day 	inspector
training 	course 	outlined 	in paragraph 	(c) 	and 	a 	two-day
management 	planner 	training 	course. 	Successful
completion of 	an 	accredited 	inspector 	course 	shall 	be 	a
prerequisite 	for 	admission 	to 	the 	management 	planner
training 	course. 	The 	two-day 	training 	program 	shall
include 	lectures, 	demonstrations, 	course 	review, 	and
one 	or 	more 	written 	examinations. 	The 	department
recommends 	the 	use 	of 	audiovisual 	materials 	to
complement 	lectures, 	where 	appropriate. 	The 	asbestos
management 	planner 	training 	course 	shall 	adequately
address 	the 	following 	topics:
(1) 	Course 	overview 	including 	the 	role 	and
responsibilities 	of 	a 	management 	planner;
operations 	and 	maintenance 	programs; 	setting
work 	priorities; 	and protection 	of 	building
occupants;
504-42
§11-504-52
(2) 	Evaluation 	and 	interpretation 	of 	survey
results 	including 	review 	of 	TSCA Title 	II
requirements 	for 	inspection 	and 	management
plans 	for 	school 	building 	as 	given 	in 	section
203(i) (1) 	of 	TSCA Title 	II; 	interpretation 	of
field 	data 	and 	laboratory 	results; 	and 	a
comparison 	between 	field 	inspectors' 	data
sheet 	with 	laboratory 	results 	and 	site
survey;
(3) 	Hazard 	assessment 	including 	amplification 	of
the 	difference 	between physical 	assessment
and 	hazard 	assessment; 	the 	role 	of 	the
management 	planner 	in 	hazard 	assessment; 	an
explanation 	of 	significant 	damage, 	damage,
potential 	damage, 	and potential 	significant
damage; 	the 	use 	of 	a 	description 	code 	or
decision 	tree 	for 	assessment 	of 	asbestos-
containing 	material; 	assessment 	of 	friable
asbestos-containing 	material; 	the
relationship 	of 	accessibility, 	vibration
sources, 	use 	of 	adjoining 	space, 	and 	air
plenums 	and 	other 	factors 	to 	hazard
assessment;
(4) 	Legal 	implications 	including 	liability;
insurance 	issues 	specific 	to 	planners;
liabilities 	associated 	with 	interim 	control
measures, 	in-house 	maintenance, 	repair, 	and
removal; 	use 	of 	results 	from 	previously
performed 	inspections;
(5) 	Evaluation 	and 	selection of 	control 	options
including 	an 	overview of 	encapsulation,
enclosure, 	interim operations 	and
maintenance, 	and 	removal; 	advantages 	and
disadvantages 	of 	each method; 	response
actions 	described via 	a 	decision 	tree 	or
other 	appropriate 	method; 	work practices 	for
each 	response 	action; 	staging 	and
prioritizing 	of 	work 	in 	both vacant 	and
occupied 	buildings; 	and 	the 	need 	for
containment 	barriers 	and 	decontamination 	in
response 	actions;
504-43
§11-504-52
(6) 	Role 	of 	other 	professionals 	including 	the 	use
of 	industrial 	hygienists, 	engineers, 	and
architects 	in 	developing 	technical
specifications 	for 	response 	actions; 	any
requirements 	that 	may 	exist 	for 	architect
sign-off 	of 	plans; 	and 	the 	team 	approach 	to
design 	of 	high-quality 	job 	specifications;
(7) 	Developing 	an 	operations 	and 	maintenance 	plan
including 	the 	purpose 	of 	the 	plan; 	a
discussion 	of 	applicable 	EPA guidance
documents; 	what 	actions 	should be 	taken by
custodial 	staff; 	proper 	cleaning 	procedures;
steam cleaning 	and 	HEPA vacuuming; 	reducing
disturbance 	of 	asbestos-containing 	materials;
scheduling 	operation and maintenance 	for 	off-
hours; 	rescheduling 	or 	canceling 	renovation
in 	areas 	with 	asbestos-containing 	material;
boiler 	room maintenance; 	disposal 	of
asbestos-containing 	material; 	in-house
procedures 	for 	asbestos-containing 	materials-
bridging 	and penetrating 	encapsulants; 	pipe
fittings; 	metal 	sleeves; 	polyvinyl 	chloride,
canvas, 	and 	wet 	wraps; 	muslin 	with 	straps;
fiber 	mesh 	cloth; 	mineral 	wool, 	and
insulating 	cement; 	discussion 	of 	employee
protection programs 	and 	staff 	training; 	and 	a
case 	study 	in 	developing 	an 	operation 	and
maintenance 	plan 	including 	the 	development,
implementation process, 	and problems 	that
have 	been 	experienced;
(8) 	Regulatory 	review 	including:
(A) 	Requirements 	of 	TSCA 	title 	II;
(B) 	40 	CFR 	Part 	61, 	National 	Emission
Standards 	for 	Hazardous 	Air 	Pollutants
(NESHAP), 	Subparts A 	(General
Provisions) 	and M (National 	Emission
Standards 	for 	Asbestos);
(C) 	HIOSH Asbestos 	Construction, 	General
Industry 	and 	respiratory protection
Standards 	(chapters 	12-145 	and 	12-206);
504-44
§11-504-52
(D) 	Chapter 	501 	(Asbestos 	Emission
Standards)and 	502 	(Asbestos-Containing
Materials 	in 	Schools) 	of 	Title 	11;
(E) 	Asbestos 	Hazard 	Emergency Response 	Act
(AHERA) 	40 	CFR 	Part 	763; 	and
(F) 	Applicable 	state 	and 	local 	rules, 	and
differences 	between 	federal 	and 	state
requirements, 	where 	they 	apply, 	and 	the
effects 	on 	public 	and 	non-public 	schools
or 	public 	or 	commercial 	buildings;
(9) 	Record-keeping 	for 	the 	management 	planner
including 	the 	use 	of 	a 	field 	inspector's 	data
sheet 	along 	with 	laboratory 	results; 	ongoing
record-keeping 	as 	a 	means 	to 	track 	asbestos
disturbance; 	and 	procedures 	for 	record-
keeping;
(10) 	Assembling 	and 	submitting 	the 	management 	plan
including 	plan 	requirements 	in 	TSCA 	Title 	II
section 	203(i) (1); 	and 	the 	management 	plan 	as
a 	planning 	tool;
(11) 	Financing 	abatement 	actions 	including
economic 	analysis 	and 	cost 	estimates;
development 	of 	cost 	estimates; 	present 	costs
of 	abatement 	versus 	future 	operations 	and
maintenance 	costs; 	and Asbestos 	School 	Hazard
Abatement 	Act 	grants 	and 	loans; 	and
(12) 	A review 	of 	key 	aspects 	of 	the 	training
course.
(d) 	The 	initial 	training 	course 	for 	abatement
project 	designers 	shall 	consist 	of 	a 	three-day 	course
that 	shall 	include 	lectures, 	demonstrations, 	course
review, 	and 	one 	or 	more 	written 	examinations. 	The
department 	recommends 	the 	use 	of 	audiovisual 	material
to 	complement 	lectures 	where 	appropriate. 	The 	three-
day 	abatement 	project 	designer 	training 	course 	shall
adequately 	address 	the 	following 	topics:
(1) 	Background 	information on 	asbestos 	including
identification of 	asbestos; 	examples 	and
discussion 	of 	the 	uses 	and 	locations 	of
asbestos 	in 	buildings; 	and 	the 	physical
appearance 	of 	asbestos;
504-45
§11-504-52
(2) 	Potential 	health 	effects 	related 	to 	asbestos
exposure 	including 	the 	nature 	of 	asbestos-
related 	diseases; 	routes 	of 	exposure; 	dose-
response 	relationships 	and 	the 	lack 	of 	a 	safe
exposure 	level; 	the 	synergistic 	effect
between 	cigarette 	smoking 	and 	asbestos
exposure; 	the 	latency period 	of 	asbestos-
related 	diseases; 	and 	a 	discussion 	of 	the
relationship 	between 	asbestos 	exposure 	and
asbestosis, 	lung 	cancer, 	mesothelioma, 	and
cancers 	of 	other 	organs;
(3) 	An 	overview 	of 	abatement 	construction
projects 	including 	use 	of 	abatement 	as 	a
portion 	of 	a 	renovation project; 	and OSHA
requirements 	for 	notification 	of 	other
abatement 	entities 	on 	a 	multi-employer 	site,
pursuant 	to 	chapter 	12-145;
(4) 	Safety 	system design 	specifications 	including
design, 	construction and maintenance 	of
containment 	barriers 	and 	decontamination
enclosure 	systems; 	positioning 	of 	warning
signs; 	electrical 	and ventilation 	system 	lock
out; 	proper 	working 	techniques 	for 	minimizing
fiber 	release; 	entry 	and 	exit 	procedures 	for
the 	work 	area; 	use 	of 	wet 	methods; 	proper
techniques 	for 	initial 	cleaning; 	use 	of
negative 	pressure 	exhaust 	ventilation
equipment; 	use 	of 	HEPA vacuums; 	proper 	clean-
up 	and 	disposal 	of 	asbestos; 	work practices
as 	they 	apply 	to 	encapsulation, 	enclosure,
and 	repair; 	and 	use 	of 	glove 	bags 	and 	a
demonstration 	of 	glove 	bag 	use;
(5) 	Visit 	to 	an 	abatement 	site 	or 	other 	suitable
building 	site, 	including 	on-site 	discussions
of 	abatement 	design 	and 	building 	walk-through
inspection. 	The 	visit 	shall 	include 	a
discussion 	of 	the 	rationale 	for 	the 	concept
of 	functional 	spaces 	during 	the 	walk-through;
(6) 	Employee 	personal 	protective 	equipment
including 	the 	classes 	and 	characteristics 	of
respirator 	types; 	limitations 	of 	respirators;
proper 	selection, 	inspection, 	donning, 	use,
504-46
§11-504-52
maintenance, 	and 	storage 	procedures; 	methods
for 	field 	testing 	of 	the 	facepiece-to-face
seal 	(positive 	and 	negative 	pressure 	fit
checks); 	qualitative 	and 	quantitative 	fit
testing 	procedures; 	variability between 	field
and 	laboratory protection 	factors 	that 	alter
the 	fit 	of 	the 	respirator 	(e.g., 	facial
hair); 	components 	of 	a 	proper 	respiratory
protection program; 	selection 	and 	use 	of
personal 	protective 	clothing; 	use, 	storage,
and 	handling 	of 	non-disposable 	clothing; 	and
rules 	covering 	personal 	protective 	equipment;
(7) 	Additional 	safety hazards 	including 	those
encountered 	during 	abatement 	activities 	and
how 	to 	deal 	with 	them, 	especially 	electrical
hazards, 	heat 	stress, 	air 	contaminants 	other
than 	asbestos, 	fire, 	and 	explosion 	hazards;
(8) 	Fiber 	aerodynamics 	and 	control 	including
aerodynamic 	characteristics 	of 	asbestos
fibers; 	the 	importance 	of 	proper 	containment
barriers; 	the 	settling 	time 	for 	asbestos
fibers; 	wet 	methods 	in 	abatement; 	aggressive
air 	monitoring 	following 	abatement; 	and
aggressive 	air movement 	and 	negative 	pressure
exhaust 	ventilation 	as 	a 	clean 	up 	method;
(9) 	Designing 	abatement 	solutions 	including
discussions 	of 	removal, 	enclosure, 	and
encapsulation methods; 	and 	asbestos 	waste
disposal;
(10) 	Final 	clearance 	process 	including 	a
discussion 	of 	the 	need 	for 	a 	written 	sampling
rationale 	for 	aggressive 	final 	air 	clearance;
requirements 	of 	a 	complete 	visual 	inspection;
and 	the 	relationship 	of 	the 	visual 	inspection
to 	final 	air 	clearance;
(11) 	Budgeting 	and 	cost 	estimation 	including 	the
development 	of 	a 	cost 	estimate; 	present 	costs
of 	abatement 	versus 	future 	costs, 	including
periodic 	surveillance 	and 	operations 	and
maintenance; 	and 	setting 	priorities 	for
abatement 	jobs 	to 	reduce 	cost;
504-47
§11-504-52
(12) 	Writing 	abatement 	specifications 	including
preparation 	of 	and 	need 	for 	a 	written 	project
design; 	means 	and 	methods 	specifications
versus 	performance 	specifications; 	the 	design
of 	abatement 	in 	occupied 	buildings;
modification 	of 	guide 	specifications 	to 	a
particular 	building; 	worker 	and 	building
occupant 	health 	and medical 	considerations;
replacement 	of 	asbestos-containing 	materials
with 	non-asbestos 	substitutes; 	clearance 	of
work 	area 	after 	abatement; 	and 	air 	monitoring
for 	clearance, 	if 	required;
(13) 	Preparing 	abatement 	drawings 	including 	the
significance 	and 	need 	for 	as-built 	drawings;
the 	use 	of 	as-built 	drawings 	as 	base
drawings; 	the 	use 	of 	inspection photographs
and 	on-site 	reports; 	methods 	of 	preparing
abatement 	drawings; 	diagramming 	containment
barriers; 	relationship 	of 	drawings 	to 	design
specifications; 	and particular 	problems
related 	to 	abatement 	drawings;
(14) 	Contract 	preparation 	and 	administration;
(15) 	Legal 	liabilities 	and 	defenses 	including
insurance 	considerations; 	bonding; 	hold-
harmless 	clauses; 	use 	of 	abatement 	entities'
liability 	insurance; 	and 	claims-made 	versus
occurrence 	policies;
(16) 	Replacement 	of 	asbestos 	with 	asbestos-free
substitutes;
(17) 	The 	role 	of 	other 	consultants 	including 	the
development 	of 	technical 	specification
sections 	by 	industrial 	hygienists 	or
engineers; 	and 	the 	multi-disciplinary 	team
approach 	to 	abatement 	design;
(18) 	Occupied 	buildings 	including 	special 	design
procedures 	required 	in occupied 	buildings;
education 	of 	occupants; 	extra 	monitoring
recommendations; 	staging 	of 	work 	to 	minimize
occupant 	exposure; 	and 	scheduling 	of
renovation 	to 	minimize 	exposure;
504-48
§11-504-52
(19) 	Relevant 	federal, 	state, 	and 	local 	regulatory
requirements, 	procedures, 	and 	standards,
including:
(A) 	Requirements 	of 	TSCA 	title 	II;
(B) 	40 	CFR 	Part 	61, 	National 	Emission
Standards 	for 	Hazardous 	Air 	Pollutants
(NESHAP), 	Subparts A 	(General
Provisions) 	and M (National 	Emission
Standards 	for 	Asbestos);
(C) 	Chapters 	12-145 	and 	12-206, 	HIOSH
Asbestos 	Construction, 	General 	Industry
and 	Respiratory 	Protection 	Standards;
(D) 	Chapter 	501 	(Asbestos 	Emission
Standards) 	and 	502 	(Asbestos-Containing
Materials 	in 	Schools) 	of 	Title 	11;
(E) 	40 	CFR, 	Part 	763, 	Asbestos 	Hazard
Emergency Response 	Act 	(AHERA); 	and
(F) 	Applicable 	state 	and 	local 	rules, 	and
differences 	between 	federal 	and 	state
requirements, 	where 	they 	apply, 	and 	the
effects 	on public 	and 	non-public 	schools
or 	public 	or 	commercial 	buildings; 	and
(20) 	A review 	of 	key 	aspects 	of 	the 	training
course.
(f) 	The 	initial 	training 	course 	for 	project
monitors 	shall 	consist 	of 	a 	five-day 	or 	two-day
training 	course 	that 	shall 	include 	lectures,
demonstrations, 	at 	least 	six hours 	of 	hands-on
training, 	course 	review, 	and 	at 	least 	one 	written,
multiple 	choice 	examination. 	The 	instructor-to-student
ratio 	shall 	be 	no 	less 	than 	1 	to 	25 	during 	the 	hands-on
portion 	of 	the 	course. 	The 	department 	recommends 	the
use 	of 	audiovisual 	materials 	to 	complement 	lectures,
where 	appropriate. 	The 	two-day 	course 	shall 	only be
taken 	by persons 	who 	hold 	current 	management 	planner 	or
contractor/supervisor 	certification, 	and 	shall 	address
topics 	that 	are 	not 	presented 	in 	the 	inspector,
management 	planner 	or 	contractor/supervisor 	courses.
The 	project 	monitor 	training 	course 	shall 	adequately
address 	the 	following 	topics:
(1) 	Roles 	and 	responsibilities 	of 	the 	project
monitor 	including 	definition 	and
504-49
§11-504-52
responsibilities 	of 	the 	project 	monitor;
regulatory 	and 	specification 	compliance
monitoring; 	air 	monitoring; 	conducting visual
inspections; 	and 	final 	clearance 	monitoring;
(2) 	Characteristics 	of 	asbestos 	and 	asbestos-
containing materials 	including 	the 	typical
uses 	of 	asbestos; 	physical 	appearance 	of
asbestos; 	review 	of 	asbestos 	abatement 	and
control 	techniques; 	presentation 	of 	the
health 	effects 	of 	asbestos 	exposure,
including 	routes 	of 	exposure, 	dose-response
relationships 	and 	latency 	periods 	for
asbestos-related 	diseases; 	and 	a 	discussion
of 	the 	relationship 	of 	asbestos 	exposure 	to
asbestosis, 	lung 	cancer, 	mesothelioma, 	and
cancers 	of 	other 	organs;
(3) 	Federal 	and 	state 	asbestos 	requirements
including:
(A) 	Requirements 	of 	TSCA 	title 	II;
(B) 	40 	CFR 	Part 	61, 	National 	Emission
Standards 	for 	Hazardous 	Air 	Pollutants
(NESHAP), 	Subparts A 	(General
Provisions) 	and M (National 	Emission
Standards 	for 	Asbestos);
(C) 	Chapters 	12-145 	and 	12-206, 	HIOSH
Asbestos 	Construction, 	General 	Industry
and 	Respiratory 	Protection 	Standards;
(D) 	Chapters 	501 	and 	502;
(E) 	40 	CFR 	Part 	763, 	Asbestos 	Hazard
Emergency Response 	Act 	(AHERA); 	and
(F) 	Applicable 	state 	and 	local 	rules, 	and
differences 	between 	federal 	and 	state
requirements, 	where 	they 	apply, 	and 	the
effects 	on public 	and 	non-public 	schools
or 	public 	or 	commercial 	buildings;
(4) 	Understanding 	building 	construction 	and
building 	systems 	including 	building
construction basics; 	building 	physical 	plan
layout; 	building 	systems 	(heat, 	ventilation,
and 	air 	conditioning 	system, 	electrical,
etc.); 	layout 	and 	organization, 	where
asbestos 	is 	likely 	to 	be 	found 	on 	building
504-50
§11 	504-52
systems; 	and 	renovations 	and 	the 	effect 	of
asbestos 	abatement 	on 	building 	systems;
(5) 	Asbestos 	abatement 	contracts, 	specifications,
and 	drawings 	including 	basic 	provisions 	of
the 	contract; 	relationships 	between principal
parties; 	establishing 	chain 	of 	command; 	types
of 	specifications, 	including means 	and
methods, 	performance, 	and proprietary and
nonproprietary; 	reading 	and 	interpreting
records 	and 	abatement 	drawings; 	discussion 	of
change 	orders; 	and 	common 	enforcement
responsibilities 	and 	authority 	of 	a 	project
monitor;
(6) 	Response 	actions 	and 	abatement 	practices
including 	pre-work 	inspections; 	pre-work
considerations 	such 	as 	pre-cleaning 	of 	the
work 	area, 	removal 	of 	furniture, 	fixtures,
and 	equipment; 	shutdown 	and modification 	of
building 	systems; 	construction 	and
maintenance 	of 	containment 	barriers; 	proper
demarcation of 	work 	areas; 	work 	area 	entry
and 	exit, 	hygiene 	practices; 	determining 	the
effectiveness 	of 	air 	filtration 	equipment;
techniques 	for 	minimizing 	fiber 	release 	such
as 	wet 	methods 	and 	continuous 	cleaning;
abatement 	methods 	other 	than 	removal;
abatement 	area 	clean up 	procedures; 	waste
transport 	and 	disposal 	procedures; 	and
contingency planning 	for 	emergency 	response;
(7) 	Asbestos 	abatement 	equipment 	including
typical 	equipment 	found 	on 	an 	abatement
project 	such 	as 	air 	filtration 	devices,
vacuum 	systems, 	and 	negative 	pressure
differential 	monitoring; 	HEPA 	filtration
units, 	theory 	of 	filtration, 	design 	and
construction 	of 	HEPA 	filtration 	units,
qualitative 	and 	quantitative 	performance 	of
HEPA 	filtration 	units, 	sizing 	the 	ventilation
requirements, 	location of 	HEPA 	filtration
units, 	qualitative 	and 	quantitative 	tests 	of
containment 	barrier 	integrity; 	best 	available
technology;
504-51
§11-504-52
(8) 	Personal 	protective 	equipment 	including
proper 	selection of 	respiratory protection;
classes 	and 	characteristics 	of 	respirator
types, 	limitations 	of 	respirators; 	proper use
of 	other 	safety 	equipment, 	protective
clothing 	selection, 	use, 	and proper 	handling,
hard 	and 	bump 	hats, 	safety 	shoes; 	breathing
air 	systems, 	high 	pressure 	versus 	low
pressure, 	testing 	for 	Grade 	Dair,
determining 	proper 	backup 	air 	volumes;
(9) 	Air 	monitoring 	strategies 	including 	sampling
equipment, 	sampling pumps 	(low versus 	high
volume), 	flow 	regulating 	devices 	(critical
and 	limiting 	orifices), 	use 	of 	fibrous
aerosol 	monitors 	on 	abatement 	projects;
sampling 	media, 	types 	of 	filters, 	types 	of
cassettes, 	filter 	orientation, 	storage 	and
shipment 	of 	filters; 	calibration 	techniques,
primary 	calibration 	standards, 	secondary
calibration 	standards, 	temperature 	and
pressure 	effects, 	frequency 	of 	calibration,
record-keeping 	and 	field 	work 	documentation,
calculations; 	air 	sample 	analysis, 	techniques
available 	and 	limitations 	of 	AHERA 	on 	their
use, 	transmission 	electron microscopy
(background 	to 	sample 	preparation 	and
analysis, 	air 	sample 	conditions 	which
prohibit 	analysis, 	EPA's 	recommended
technique 	for 	analysis 	of 	final 	air 	clearance
samples), 	phase 	contrast 	microscopy
(background 	to 	sample 	preparation, 	and 	the
AHERA 	limits 	on 	the 	use 	of 	phase 	contrast
microscopy), 	what 	each 	technique 	measures;
analytical 	methodologies, 	AHERA TEM protocol,
NIOSH 	7400, 	OSHA 	reference 	method 	(non
clearance), 	EPA 	recommendation 	for 	clearance
(TEM); 	sampling 	strategies 	for 	clearance
monitoring, 	types 	of 	air 	samples 	(personal
breathing 	zone 	versus 	fixed-station 	area)
sampling 	location 	and 	objectives 	(pre-
abatement, 	during 	abatement, 	and 	clearance
monitoring), 	number 	of 	samples 	to 	be
504-52
§11-504-52
collected, 	minimum and maximum air 	volumes,
clearance 	monitoring 	(post-visual 	inspection)
(number 	of 	samples 	required, 	selection of
sampling 	locations, 	period 	of 	sampling,
aggressive 	sampling, 	interpretations 	of
sampling 	results, 	calculations), 	quality
assurance; 	and 	special 	sampling 	problems,
crawl 	spaces, 	acceptable 	samples 	for
laboratory analysis, 	sampling 	in 	occupied
buildings 	(barrier monitoring);
(10) 	Safety 	and 	health 	issues 	other 	than 	asbestos
including 	confined-space 	entry, 	electrical
hazards, 	fire 	and 	explosion 	concerns, 	ladders
and 	scaffolding, 	heat 	stress, 	air
contaminants 	other 	than 	asbestos, 	fall
hazards, 	and 	hazardous 	materials 	on 	abatement
projects;
(11) 	Conducting visual 	inspections 	including
inspections 	during 	abatement, 	visual
inspections 	using 	the 	ASTM E1368 	document;
conducting 	inspections 	for 	completeness 	of
removal; 	discussion 	of 	"how 	clean 	is 	clean?";
(12) 	Legal 	responsibilities 	and 	liabilities 	of
project 	monitors 	including 	specification
enforcement 	capabilities; 	regulatory
enforcement; 	licensing; 	powers 	delegated 	to
project 	monitors 	through 	contract 	documents;
(13) 	Record-keeping 	and 	report 	writing 	including
developing 	project 	logs 	and 	daily 	logs 	(what
should be 	included, 	who 	sees 	them); 	final
report 	preparation; 	record-keeping 	under
federal 	regulations; 	and
(14) 	Workshops 	(six 	hours 	spread 	over 	three 	days)
including 	contracts, 	specifications, 	and
drawings. 	The 	workshop 	requirement 	may be
fulfilled 	by 	the 	issuance 	of 	a 	set 	of
contracts, 	specifications, 	and 	drawings 	and
then 	being 	asked 	to 	answer 	questions 	and make
recommendations 	to 	a 	project 	architect,
engineer, 	or 	to 	the 	building 	owner 	based 	on
given 	conditions 	and 	these 	documents; 	Air
monitoring 	strategies 	and 	asbestos 	abatement
504-53
§11-504-52
equipment: 	This 	workshop 	could 	consist 	of
simulated 	abatement 	sites 	for 	which 	sampling
strategies 'would have 	to 	be 	developed 	(i.e.,
occupied 	buildings, 	industrial 	situations).
Through 	demonstrations 	and 	exhibition, 	the
project 	monitor may 	also 	be 	able 	to 	gain 	a
better 	understanding 	of 	the 	function 	of
various 	pieces 	of 	equipment 	used 	on 	abatement
projects 	(air 	filtration 	units 	water
filtration 	units, 	negative 	pressure
monitoring 	devices, 	sampling 	pump 	calibration
devices, 	etc.); 	Conducting visual
inspections: 	This 	workshop 	could 	consist,
ideally, 	of 	an 	interactive 	video 	in which 	a
participant 	is 	"taken 	through" 	a 	work 	area
and 	asked 	to 	make 	notes 	of 	what 	is 	seen. 	A
series 	of 	questions 	will 	be 	asked 	which 	are
designed 	to 	stimulate 	a 	person's 	recall 	of
the 	area. 	This 	workshop 	could 	consist 	of 	a
series 	of 	two 	or 	three 	videos 	with 	different
site 	conditions 	and 	different 	degrees 	of
cleanliness. 	[Eff FEB 15 	20 	] 	(Auth:
HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763,
Appendix 	C(l) (B))
§11-504-53 	Refresher 	course 	contents 	and
requirements. 	(a) 	Refresher 	training 	courses 	shall 	be
specific 	to 	each 	discipline 	and 	each 	shall 	be 	not 	less
than 	eight 	hours 	in 	length 	with 	the 	exception 	of 	the
training 	course 	for 	inspectors. 	Refresher 	courses 	for
inspectors 	shall 	be 	not 	less 	than 	four 	hours 	in 	length.
Management 	planners 	shall 	attend 	the 	inspector
refresher 	course, 	plus 	an 	additional 	four-hour 	course
for 	management 	planners.
(b) 	For 	each 	discipline, 	the 	refresher 	training
course 	shall 	review 	and 	discuss 	changes 	in 	federal 	and
state 	rules, 	developments 	in 	state-of-the-art
procedures, 	a 	review 	of 	key 	aspects 	of 	the 	initial
training 	course 	including 	the 	health 	effects 	of
asbestos 	exposure, 	and 	a 	written, 	multiple 	choice
examination.
504-54
§11-504-54
(c) 	Successful 	completion 	of 	a 	refresher 	training
course, 	and 	application 	to 	the 	department 	extends
certification 	for 	one 	year 	from 	the 	date.
(d) 	Individuals 	whose 	certifications 	have 	expired
within 	the 	previous 	twelve 	month period may 	attend 	a
refresher 	course 	rather 	than 	retake 	the 	initial 	course.
This 	grace 	period 	extends 	twelve 	months 	from 	the 	date
of 	expiration 	of 	the 	certification, 	but 	the 	person with
the 	expired 	certification 	shall 	not 	perform work within
that 	discipline 	during 	the 	grace 	period.
[Eff 	FEB 15 	2001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C(l) (D))
§11-504-54 	Examinations. 	(a) 	All 	persons 	who
enroll 	in 	a 	training 	course 	shall 	be 	required 	to 	pass 	a
closed 	book 	examination 	in written, 	multiple 	choice
form 	with 	a 	minimum grade 	of 	seventy per 	cent 	correct
in 	order 	to 	successfully 	complete 	the 	course. 	The
examination 	shall 	be 	administered 	by 	the 	training
provider. 	Each 	examination 	shall 	adequately 	cover 	the
topics 	included 	in 	the 	training 	course 	for 	that
discipline. 	Persons 	who 	pass 	the 	examination 	shall
receive 	a 	document 	indicating 	that 	they 	have 	completed
the 	course 	and 	passed 	the 	written 	exam 	in 	that 	specific
discipline. 	A person 	receiving 	less 	than 	seventy
percent 	correct 	on 	an 	exam may 	take 	not 	more 	than 	two
similar written, 	multiple 	choice 	exams 	without 	retaking
the 	course.
(b) 	The 	following 	are 	the 	requirements 	of
examinations 	in 	each 	course:
(1) 	Abatement 	workers 	- 	fifty 	multiple 	choice
questions.
(2) 	Contractors/supervisors 	- 	one 	hundred
multiple 	choice 	questions;
(3) 	Inspectors 	- 	fifty 	multiple 	choice 	questions;
(4) 	Management 	planners 	- 	fifty 	multiple 	choice
questions;
(5) 	Project 	designers 	- 	one 	hundred 	multiple
choice 	questions; 	and
(6) 	Project 	monitors 	- 	one 	hundred 	multiple
choice 	questions.
504-55
§11-504-54
(c) 	Not 	withstanding 	subsections 	(a) 	and 	(b),
instructors 	may make 	the 	following 	accommodations 	for
students 	in 	a 	worker 	training 	course 	only who 	have 	a
language 	barrier 	or 	other problem taking 	the
examination. 	The 	instructor may give 	the 	exam on 	a
one-on-one 	basis, 	away 	from 	other 	students. 	The
instructor 	may 	read 	the 	questions 	to 	the 	student, 	and
then 	read 	each 	of 	the 	multiple 	choice 	answers. 	After
the 	student 	chooses 	a 	response, 	the 	instructor may
point 	to 	the 	choice 	that 	the 	student 	picked. 	At 	no
time 	shall 	the 	instructor 	indicate 	the 	correct 	answer,
coach 	or 	attempt 	to 	influence 	the 	student's 	choice.
The 	training 	provider 	shall 	notify 	the 	department
whenever 	they will 	be 	providing 	this 	service, 	to 	allow
a 	representative 	of 	the 	department 	the 	chance 	to
observe 	the 	exam. 	[Eff FEB 15 	2001 	] 	(Auth: 	HRS
§342P-41) 	(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C (1) (C))
§11-504-55 	Course 	Certificates. 	The 	training
provider 	shall 	issue 	certificates 	to 	students 	who
successfully pass 	the 	examination 	at 	the 	end 	of 	an
initial 	or 	refresher 	training 	course. 	The 	certificate
shall 	include 	the 	following 	information:
(1) 	A unique, 	identifying 	number 	for 	each
student;
( 2) 	The 	name, 	address, 	and 	phone 	number 	of
training 	provider;
( 3) 	The 	student's 	name 	and 	social 	security
number;
( 4) 	The 	name 	of 	the 	course 	for 	which 	that
has 	received 	certification;
( 5) 	The 	date ( s) 	of 	the 	course 	and 	the
examination;
the
student
(6) 	The 	expiration 	date 	of 	the 	certificate,
limited 	to 	one 	year 	from 	the 	date 	of 	the
examination; 	and
(7) 	A statement 	specifying 	that 	the 	training
course 	meets 	all 	requirements 	of 	the 	Asbestos
504-56
§11-504-56
Model 	Accreditation 	Plan 	and 	that 	the
training 	provider 	is 	accredited 	to 	provide
training 	within 	the 	State 	of 	Hawaii.
[Eff 	FEB 15 	2001 	] (Auth: 	HRS 	§342P-41)
(Imp: 	40 	CFR 	Part 	763, 	Appendix 	C(l) (C))
§11-504-56 	Record-keeping 	requirements 	for
training 	providers. 	(a) 	All 	providers 	of 	accredited
asbestos 	training 	courses 	must 	comply with 	the
following 	minimum 	record-keeping 	requirements:
(1) 	A training 	provider must 	retain 	copies 	of 	all
instructional 	materials 	used 	in 	the 	delivery
of 	the 	classroom 	training 	such 	as 	student
manuals, 	instructor 	notebooks, 	and 	handouts;
(2) 	A training 	provider must 	retain 	copies 	of 	all
instructors 1 	resumes, 	and 	the 	documents
approving 	each 	instructor 	issued 	by 	the
department. 	Records 	must 	accurately 	identify
the 	instructors 	that 	taught 	each 	particular
course 	for 	each 	date 	that 	a 	course 	is
offered;
(3) 	A training 	provider must 	document 	that 	each
person who 	receives 	a 	certificate 	for 	an
initial 	or 	refresher 	training 	course 	has
achieved 	a 	passing 	score 	on 	the 	examination.
These 	records 	must 	clearly 	indicate 	the 	date
upon 	which 	the 	exam was 	administered, 	the
training 	course 	and 	discipline 	for 	which 	the
exam was 	given, 	the 	name 	of 	the 	person who
proctored 	the 	exam, 	a 	copy 	of 	the 	exam, 	and
the 	name 	and 	test 	score 	of 	each 	person 	taking
the 	exam;
(4) 	The 	training 	provider 	shall 	maintain 	records
that 	document 	the 	names 	of 	all 	persons 	who
have 	been 	awarded 	certificates, 	their
certificate 	numbers, 	the 	disciplines 	for
which 	certification was 	conferred, 	training
and 	expiration 	dates, 	and 	the 	training
location. 	Records 	will 	be 	kept 	in 	a 	manner
that 	allows 	verification by 	telephone 	of 	the
required 	information;
504-57
§11-504-56
(5) 	Training 	providers 	must 	verify 	current
certification of 	the 	students 	in 	a 	refresher
course, 	or 	expiration 	of 	their 	certification
within 	the 	last 	twelve 	month 	period. 	Students
should 	present 	their 	valid 	or 	expired
certificate 	from 	the 	training 	provider, 	or
the 	department-issued 	certification.
Training 	providers 	offering 	the 	initial
management 	planner 	training 	course 	must
verify 	that 	the 	student 	holds 	a 	valid
inspector 	certification 	at 	the 	time 	of 	course
admission; 	and
(6) 	(A) 	The 	training 	provider 	shall 	maintain 	all
required 	records 	for 	a 	minimum of 	three
years; 	and
(B) 	The 	training 	provider 	shall 	allow
reasonable 	access 	to 	all 	of 	the 	records
required 	by 	the 	Model 	Accreditation
Plan, 	and any 	other 	records 	required 	by
the 	department 	for 	the 	accreditation 	of
asbestos 	training 	providers 	and 	courses,
to 	both 	EPA 	and 	the 	department, 	on
request.
(b) 	If 	a 	training 	provider 	ceases 	to 	conduct
training, 	the 	training 	provider 	shall 	notify 	the
department 	and 	allow 	the 	department 	to 	make 	copies 	of
the 	training 	providers 	asbestos 	training 	records.
[Eff 	F£8 J5 2001 	] 	(Auth: 	HRS 	§342P-41) 	(Imp: 	40
CFR 	Part 	763, 	Appendix 	C(l) (F))
§11-504-57 	Instructor 	qualifications 	for 	training
courses. 	(a) 	Each 	training 	course 	shall 	be 	taught 	by
a 	department-approved 	instructor. 	Approval 	shall 	be
based upon 	a 	review 	of 	the 	instructors 	academic
credentials 	and/or 	field 	experience 	in 	asbestos
abatement. 	The 	training 	provider 	must 	notify 	the
department 	in 	advance 	whenever 	it 	changes 	course
instructors.
(b) 	At 	a 	minimum, 	the 	instructor 	shall:
(1) 	Have 	one 	year 	of 	experience 	performing 	the
functions 	for 	the 	class 	being 	taught, 	and
504-58
hold 	current 	certification 	in 	that
discipline; 	or
§11-504-57
(2) 	Have 	six months 	of 	teaching 	experience 	and
have 	held 	certification 	in 	the 	discipline
being 	taught. 	[Eff 	FEB 15 	2001 	] 	(Auth:
HRS 	§342P-41) 	(Imp: 	40 	CFR 	Part 	763,
Appendix 	C(l) (E) (4))