CourtListener 10800257•Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange
Dewayne Blaha d/b/a Blaha Roofing, LLC v. Larry Strange
CourtListener 10800257Iowactapp25 feb 2026
Testo completo
IN THE COURT OF APPEALS OF IOWA
_______________
No. 24-1865
Filed February 25, 2026
_______________
Dewayne Blaha d/b/a Blaha Roofing, LLC,
Plaintiff–Appellant,
v.
Larry Strange,
Defendant–Appellee.
_______________
Appeal from the Iowa District Court for Mills County,
The Honorable Amy Zacharias, Judge.
_______________
AFFIRMED AS MODIFIED
_______________
J. Joseph Narmi, Council Bluffs, attorney for appellant.
Wyatt D. Suhr of Peters Law Firm, P.C., Council Bluffs, attorney for
appellee.
_______________
Considered without oral argument
by Ahlers, P.J., and Chicchelly and Sandy, JJ.
Opinion by Ahlers, P.J.
1
AHLERS, Presiding Judge.
Larry Strange hired Dewayne Blaha’s construction business, Blaha
Roofing, LLC, to install a new roof, siding, and gutters on Strange’s house
and an outbuilding. Dissatisfied with the work after Blaha completed the
project, Strange did not pay the outstanding balance on the contract. Blaha
sued to recover the balance. Strange filed a counterclaim seeking damages
for the cost needed to remedy the claimed defects in the work. Following a
bench trial, the district court denied Blaha’s claim and entered judgment in
Strange’s favor on his counterclaim for $50,066.93.
Blaha appeals. He contends (1) the district court’s ruling denying his
breach-of-contract claim is not supported by the evidence and (2) the
damages awarded to Strange results in unjust enrichment.
We find the district court’s ruling is supported by substantial evidence,
but we find that its damage calculation failed to properly account for the
outstanding balance owed on the underlying contract. We affirm as modified.
I. Factual and Procedural Background
Strange and Blaha contracted for Strange to pay Blaha $36,427.02 to
replace the roof, siding, and gutters on Strange’s house and a nearby shed to
repair storm damage. Strange paid $15,000.00 to Blaha for materials, and
Blaha began work on the project with the use of a subcontractor.
During the siding replacement phase of the job, another storm hit.
The subcontractor and his crew had removed the siding near one of the
windows on the home and were not able to replace it before the storm rolled
through. Rain from the storm leaked through this window and caused
damage to Strange’s floor.
2
After the project was completed, Strange paid $6,000.00 directly to
the subcontractor because he was worried Blaha would not pay the
subcontractor. Strange testified that he was dissatisfied with the quality of
the work, and he notified Blaha of the problems so they could be fixed. Blaha
claims he was not informed of the issues until after the job was complete and
Strange declined a final walkthrough after the job was complete. Strange
testified that he never declined a walkthrough or access to the property to
remedy the defective work. Strange’s issues with the job were not corrected,
so he did not pay the remaining $15,427.02 due under the contract. Blaha
sued to recover the unpaid balance, and Strange counterclaimed for an
amount equal to the cost to fix the damage caused by Blaha’s work and to
complete the project in a workmanlike manner.
During the bench trial, the court heard testimony from both parties
and two contractors Strange called. The court noted some credibility issues
with one of the contractors but ruled in Strange’s favor in part because the
pictures and video evidence corroborated the testimony of Strange and his
witnesses. The court found Blaha’s claim that Strange denied Blaha the
opportunity to do a final walkthrough and fix the problems lacked credibility.
The court denied Blaha’s claim for the unpaid contract balance and entered
judgment in favor of Strange on his counterclaim in the amount of
$50,066.93—the cost of electrical repairs, flooring repairs, and replacement
siding needed to repair the defective work and complete the project.
II. Standard of Review
We review breach-of-contract claims for correction of errors at law.
Iowa Mortg. Ctr., L.L.C. v. Baccam, 841 N.W.2d 107, 110 (Iowa 2013). The
district court’s factual findings are binding if they are supported by
substantial evidence, but its conclusions of law and application of legal
3
principles are not binding on us. Id. Substantial evidence exists when a
“reasonable mind would accept it as adequate to reach a conclusion.”
EnviroGas, L.P. v. Cedar Rapids/Linn Cnty. Solid Waste Agency, 641 N.W.2d
776, 781 (Iowa 2002) (quoting Land O’Lakes, Inc. v. Hanig, 610 N.W.2d 518,
522 (Iowa 2000)). We also view the evidence in the light most favorable to
the district court’s judgment. Id. And we do not reweigh the evidence or
assess the credibility of witnesses. Id. at 785.
III. Breach of Contract
Blaha contends the district court’s decision denying his claim that
Strange breached the contract is not supported by the evidence. He argues
that the evidence, including Strange’s $6,000.00 payment to the
subcontractor, only supports a finding that Strange breached the contract by
not paying the remaining balance when the work was complete.
To be successful on a breach-of-contract claim, a party must prove:
(1) the existence of a contract; (2) the terms and conditions of the contract;
(3) that it has performed all the terms and conditions required under the
contract; (4) the defendant’s breach of the contract in some particular way;
and (5) that plaintiff has suffered damages as a result of the breach.
Iowa Mortg. Ctr., 841 N.W.2d at 110–11 (quoting Molo Oil Co. v. River City Ford
Truck Sales, Inc., 578 N.W.2d 222, 224 (Iowa 1998)). Construction contracts
contain an implied warranty that the contract work will be done “in a
reasonably good and workmanlike manner.” Fry v. Blauvelt, 818 N.W.2d
123, 134 (Iowa 2012) (citation omitted).
The bulk of Blaha’s argument on this issue is devoted to pointing out
why he believes the court should have believed his evidence over the
competing evidence presented by Strange. But his argument disregards our
standard of review. Weighing evidence and assessing credibility of witnesses
4
is the task of the factfinder at trial, not the appellate court. EnviroGas, 641
N.W.2d at 785. Here, the district court was the factfinder, and it took great
care in explaining its weighing of the evidence and credibility determinations.
In doing so, it noted credibility issues with one of the contractor witnesses
called by Strange due to the witness’s criminal history. Despite this, the
court found his testimony and the video and photo evidence presented by
Strange were sufficient to conclude that Blaha did not complete the job in a
workmanlike manner. Given the deference we afford district courts in
assessing witness credibility, the court’s careful credibility assessment, and
the photo and video evidence, a reasonable person could conclude Blaha
failed to complete the project in a workmanlike manner. Thus, there is
substantial evidence supporting the court’s determination that Blaha
breached the contract and Strange did not.
We are also not persuaded by Blaha’s claim that Strange’s partial
payment to the subcontractor constitutes acceptance of the work. The only
authority Blaha cites in support of his contention that payment to a
subcontractor can be considered acceptance of work is Higdon v. Rana.
No. 23-1107, 2024 WL 4370048 (Iowa Ct. App. Oct. 2, 2024). But Higdon
only addressed payment as evidence that a contract existed—a disputed issue
in that case. Id. at *6. Here, there is no dispute that a contract existed. The
fight is over whether Blaha or Strange breached it. Higdon does not proclaim
the legal principle claimed by Blaha that partial payment constitutes
acceptance of the work. Id. at *6. As Blaha cites no relevant authority, he
forfeits his claim that Strange accepted Blaha’s work by making partial
payment to the subcontractor. See State v. Jackson, 4 N.W.3d 298, 311 (Iowa
2024) (“A party forfeits an issue on appeal when the party fails to cite any
authority in support of the issue.”); Iowa R. App. P. 6.903(2)(a)(8)(3).
5
IV. Damages
For his final challenge on appeal, Blaha’s brief presents a mixed bag
blending several legal concepts. Because of the blended nature of the
briefing, the scope of Blaha’s challenge is not entirely clear. As we discern it,
Blaha is claiming that the district court’s calculation of damages is incorrect
because it awarded Strange the full amount he claimed as damages without
accounting for the fact that Strange did not pay the remaining balance owed
to Blaha.1 On this point, we find merit in Blaha’s claim.
Lewis Electric Co. v. Miller drives the outcome here. 791 N.W.2d 691
(Iowa 2010). In Lewis, like here: (1) the owners claimed defective work by a
contractor, so the owners refused to pay; (2) the contractor sued the owners
to recover the unpaid balance on the contract; and (3) the owners asserted
that they owed no money to the contractor and counterclaimed seeking
recovery for the cost of repairing the defective work. Id. at 693.
1
To the extent Blaha was attempting to raise a mitigation-of-damages issue, we
reject the challenge because it is based on Blaha’s disagreement with the district court’s
factual findings. As noted previously, the court made specific factual findings, including
credibility findings, adverse to Blaha. Those findings included rejecting Blaha’s evidence
that Strange denied Blaha the opportunity for a final inspection and the opportunity to fix
the defective work because the court found such evidence unbelievable. See EnviroGas,
641 N.W.2d at 785 (tasking the factfinder with weighing the evidence and making
credibility determinations). The court’s findings are supported by substantial evidence,
and we do not disturb them on appeal. Those findings negate any failure-to-mitigate-
damages argument Blaha makes on appeal.
If Blaha was attempting to raise any issue other than that which we’ve discerned,
we find that Blaha has forfeited the issue by failing to clearly identify it, make more than a
perfunctory argument in support of it, or cite any authority in support of it. See Jackson,
4 N.W.3d at 311 (finding forfeiture of an issue based on any of the above-described failings).
6
In Lewis, the supreme court determined that, as a matter of law, the
contractor did not substantially perform the contract due to defective
performance. Id. at 694–96. In doing so, the supreme court spelled out the
formula for calculating damages in this situation as “the unpaid contract
price minus the cost of completing any unfinished work and remedying any
defective work, plus any other damages suffered by the owner, not to exceed
the benefit actually received by the owner.” Id. at 695 (cleaned up). If use of
that formula reveals that the owner’s damages exceed the remaining contract
price, the owner will be entitled to judgment in the amount of that excess. Id.
To illustrate calculation of damages under the formula, the court used this
example:
A contracts to build a house for B for $100,000 but repudiates the contract
after doing part of the work and having been paid $40,000. Other builders
will charge B $80,000 to finish the house. B’s damages include the
$80,000 cost to complete the work less the $60,000 cost avoided or
$20,000, together with damages for any loss caused by delay.
Id. at 695 n.6 (citation omitted). This example is akin to the one present in
this case.
Here, the district court found that it would cost Strange $50,066.93 to
complete the project and remedy any defective work. That finding is
supported by substantial evidence, so we affirm that figure. However, the
$50,066.93 cost-to-finish-and-repair figure needs to be reduced by the unpaid
contract price to avoid a windfall to Strange resulting from him not having to
pay the remaining balance on the contract. It is undisputed that the
remaining balance owed on the contract between Strange and Blaha is
$15,427.02. Applying the formula spelled out in Lewis, Strange’s damages
are $34,639.91 ($50,066.93 less $15,427.02). As that damage figure is the
only one supported by substantial evidence, we affirm the district court’s
award of damages but modify it to $34,639.91.
7
V. Conclusion
We reject Blaha’s challenge to the district court’s ruling finding that
Blaha breached the contract and Strange did not, as the ruling is supported
by substantial evidence. We modify the district court’s entry of judgment in
favor of Strange to a damage figure of $34,639.91. In all other respects, we
affirm the district court.
AFFIRMED AS MODIFIED.
8
Continua la tua ricerca in ChatGPT o Claude
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.