IN THE UNITED STATES DISTRICT COURT
FOR THE MIDDLE DISTRICT OF TENNESSEE
AT NASHVILLE
BLUSKY RESTORATION 	)
CONTRACTORS, LLC 	) 	Case No. 3:23-cv-01084
) 	Judge Trauger
v. 	) 	Magistrate Judge Holmes
)
BRMO, LLC 	)
To: The Honorable Aleta A. Trauger, United States District Judge
REPORT & RECOMMENDATION
Pending before the Court is the Plaintiff Blusky Restoration Contractors, LLC’s “Motion
for Entry of Judgment for Damages Pursuant to F.R.C.P. 55(b)(2)” (Docket No. 26), to which
Defendant BRMO, LLC has failed to respond. This motion was referred to the undersigned
Magistrate Judge “for the preparation of a report and recommendation as to an award of damages
in this case.” (Docket No. 27.) Plaintiff then filed a memorandum in support of its motion (Docket
No. 35) in compliance with the Court’s order. For the reasons stated below, the undersigned finds
that this matter can be resolved without hearing and respectfully recommends that Plaintiff’s
motion for default judgment (Docket No. 26) be GRANTED IN PART.
I. 	FACTUAL BACKGROUND AND PROCEDURAL HISTORY
Plaintiff, a general contracting company, filed its complaint against Defendant, BRMO,
LLC, a subcontractor, on October 18, 2023. (Docket No. 1.) Plaintiff alleges that the two entered
into three separate contracts wherein Defendant, a subcontractor, would perform “certain exterior
and interior capital improvements (removal and replacement/remodel)” of apartments located in
Davidson County, Tennessee. (Id. at ¶ 8.) Plaintiff refers to these three contracts as “Exterior
Subcontract,” “Interior Subcontract,” and “Upgrades Subcontract.” (Docket Nos. 1-1, 1-2, 1-3.)
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 1 of 10 PageID #: <pageID>
2
Plaintiff asserts, however, that Defendant failed to perform or complete the contracted
services; sub-subcontracted some of those services without permission or authority; and failed to
properly hire, train, manage, or supervise its employees. (Docket No. 1 at ¶¶ 10–17.) Plaintiff
alleges that it paid Defendant for services that were not properly performed or completed, and that
it was forced to hire additional subcontractors to complete the work. (Id. at ¶¶ 18–19.) Accordingly,
Plaintiff initiated this lawsuit and asserted the following claims against Defendant: (1) breach of
subcontracts; (2) indemnity; (3) negligence; (4) contribution; and (5) unjust enrichment or monies
had and received. (Id. at ¶¶ 20–59.)
On January 23, 2024, Plaintiff filed a motion for entry of default as to Defendant (Docket
No. 11), which the Clerk of Court granted on April 1, 2024 (Docket No. 14). Four months later,
on August 9, 2024, Plaintiff filed a one page “Motion for Entry of Judgment for Damages,” which
was accompanied by two affidavits. (Docket Nos. 20, 20-1 to 20-2.) Plaintiff did not specify
whether the motion was filed pursuant to Rule 55(b)(1) of the Federal Rules of Civil Procedure,
which allows the Clerk of Court to enter a default judgment if the claim is for a sum certain, or
pursuant to Rule 55(b)(2), which allows the Court to enter a judgment in all other cases.1 However,
on September 13, 2024, the Clerk of Court entered an order denying the motion without prejudice.
(Docket No. 21.) In the order, the Clerk of Court explained that she construed the motion as one
made pursuant to Rule 55(b)(1) but was required to deny the motion because Plaintiff requested
attorney’s fees, which are not sum certain damages, and because the information submitted in
support of the motion was insufficient to enable the Clerk to determine whether Plaintiff’s damages
were for a sum certain.
1 Unless otherwise noted, all references to rules are to the Federal Rules of Civil Procedure.
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 2 of 10 PageID #: <pageID>
3
On December 19, 2024, Plaintiff filed a “Supplemental Motion for Entry of Judgment for
Damages,” which was accompanied by thirty exhibits. (Docket Nos. 22, 22-1 to 22-30.) Once
again, Plaintiff did not specify whether the motion was filed pursuant to Rule 55(b)(1) or 55(b)(2).
Accordingly, on April 23, 2025, the Clerk of Court entered another order construing the motion as
being made under Rule 55(b)(1) and denied it without prejudice for the same reasons, namely that
the motion was not one for sum-certain damages. (Docket No. 24.)
In the instant motion, Plaintiff seeks “a money judgment against Defendant in the amount
of $760,200.00, plus pre- and postjudgment interest” under Rule 55(b)(2). (Docket No. 26.)
Plaintiff did not originally file a memorandum in support of its motion or provide the Court with
any substantive argument as to why a default judgment should be entered in its favor and against
Defendant. Instead, Plaintiff asked the Court to schedule a hearing “so that it may present witness
testimony on the issue of damages and interest.” (Id. at 2.) Accordingly, the Court ordered Plaintiff
to file a supplemental memorandum in support of its motion that would provide the Court with
detail about: (1) how Plaintiff has calculated its requested damages figure of $760,200.00, as well
as its request for “pre- and postjudgment interest,” and (2) under which legal claim or claims
Plaintiff believes it may recover its requested damages figure.
Plaintiff filed its supplemental memorandum, but now requests a different and higher
amount of damages totaling $1,358,719.71 as well as prejudgment interest at a rate of 10%.
(Docket No. 35.) In other words, Plaintiff no longer requests postjudgment interest and does not
make any request related to attorney’s fees and costs. Plaintiff filed four exhibits to its
memorandum, which include an affidavit from Robby Webb dated August 6, 2024 and its three
contracts with BMO. (Docket Nos. 35-1, 35-2, 35-3, 35-4.) Along with its memorandum, Plaintiff
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 3 of 10 PageID #: <pageID>
4
filed a more recent affidavit from Robby Webb dated October 26, 2025 and two supporting
exhibits. (Docket Nos. 34, 34-1, 34-2.)
II. 	LEGAL STANDARDS AND ANALYSIS
A. 	Default Judgment
As the Court set forth in its prior order, due to Defendant’s default, the Court is entitled to
accept as true the well-pleaded factual allegations of the complaint. (Docket No. 28 at 3 (citing I
Love Juice Bar Franchising, LLC v. ILJB Charlotte Juice, LLC, No. 3:19-cv-00981, 2020 WL
4735031, at *3 (M.D. Tenn. Aug. 14, 2020); Vesligaj v. Peterson, 331 F. App’x 351, 355 (6th Cir.
2009)). However, default is not considered an admission of damages. Vesligaj, 331 F. App’x at
355 (“Where damages are unliquidated a default admits only [the defaulting party’s] liability and
the amount of damages must be proved.”).
To determine damages, the trial court can, but is not required to, hold an evidentiary
hearing. “[A] hearing is not necessarily required if the moving party submits uncontested, sworn
affidavits sufficient to establish the amount of damages.” Broad. Music, Inc. v. Marler, No. 1:09-
cv-193, 2009 WL 3785878, at *5 (E.D. Tenn. Nov. 12, 2009). See also Fed. R. Civ. P. 55(b)(2)(A)
(district court “may conduct hearings . . . when, to enter or effectuate judgment, it needs to: (A)
conduct an accounting; (B) determine the amount of damages; (C) establish the truth of any
allegation by evidence; or (D) investigate any other matter”); Vesligaj, 331 F. App’x at 354.
In its supporting memorandum, Plaintiff seeks a default judgment against Defendant;
monetary damages in the amount of $1,358,719.71; and prejudgment interest at a rate of 10%.
(Docket No. 35.) Plaintiff no longer seeks postjudgment interest or attorney’s fees and expenses.
Because the damages in this case – contract damages – are certain and supported by a sworn
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 4 of 10 PageID #: <pageID>
5
declaration (Docket No. 34), the Court concludes that an evidentiary hearing is unnecessary. Fed.
R. Civ. P. 55(b).
B. 	Defendant’s Liability
In its supporting memorandum, Plaintiff focuses on what it believes it is entitled to recover
pursuant to Defendant’s alleged breach of subcontracts. Plaintiff does not address any of its other
claims against Defendant, including for indemnity, negligence, contribution, or unjust enrichment
or monies had and received. Accordingly, the Court will only analyze whether Defendant is liable
under a breach of subcontracts theory.
To establish a claim for breach of contract under Tennessee law, a plaintiff must show: (1)
the existence of an enforceable contract; (2) non-performance amounting to a breach of that
contract; and (3) damages caused by the breach. C & W Asset Acquisition, LLC v. Oggs, 230
S.W.3d 671, 676–77 (Tenn. Ct. App. 2007) (citing citation omitted). “To be enforceable under
Tennessee law, a contract must result from a meeting of the minds of the parties in mutual assent
to the terms, must be based upon a sufficient consideration, free from fraud or undue influence,
not against public policy and sufficiently definite to be enforced.” Starnes Family Office, LLC v.
McCullar, 765 F.Supp.2d 1036, 1050 (W.D. Tenn. 2011) (quoting Doe v. HCA Health Svcs. of
Tenn., Inc., 46 S.W.3d 191, 196 (Tenn. 2001)) (cleaned up).
Although a contract may be written or oral, it “must be of sufficient explicitness so that a
court can perceive what are the respective obligations of the parties.” HCA Health Servs. of Tenn.,
46 S.W.3d at 196 (quoting Higgins v. Oil, Chem. & Atomic Workers Int’l Union, Local # 3-677,
811 S.W.2d 875, 879 (Tenn. 1991)). A contract’s terms are “sufficiently definite if they provide a
basis for determining whether a breach has occurred and for giving an appropriate remedy.” Jones
v. LeMoyne–Owen Coll., 308 S.W.3d 894, 904 (Tenn. Ct. App. 2009).
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 5 of 10 PageID #: <pageID>
6
To state a valid claim for breach of contract, a plaintiff is not required to identify all the
terms of an enforceable agreement, but the complaint must “raise a right to relief above the
speculative level.” Bishop v. Lucent Techs., Inc., 520 F.3d 516, 519 (6th Cir. 2008) (quoting Bell
Atlantic Corp. v. Twombly, 550 U.S. 544, 545 (2007)). Direct recitals of the elements are
unnecessary if the complaint contains “either direct or inferential allegations respecting all material
elements.” Id.
The Court finds that Plaintiff has sufficiently alleged all elements of a breach of contract
claim against Defendant. Plaintiff asserts that it entered into three subcontracts with Defendant;
that Defendant failed to perform under those subcontracts; and that Plaintiff suffered damages
because of that failure to perform. (Docket No. 1 at ¶¶ 20–35.) For these reasons, the Court finds
that Plaintiff is entitled to default judgment with respect to its breach of subcontracts claim.
C. 	Plaintiff’s Damages
Plaintiff seeks damages for it breach of subcontracts claim in the total amount of
$1,358,719.71, which is comprised of: (1) $990,517.71 that Plaintiff paid to Defendant for the
work that is the subject of the subcontracts, and (2) $368,202.00 as “backcharge” that was paid to
third parties to complete the work that Defendant failed to complete. (Docket No. 35 at 4.) To
support its request for damages, Plaintiff submitted the affidavit of Robby Webb, its Senior
National Project Director. (Docket No. 34.) In his affidavit, Mr. Webb references records that
reflect what Plaintiff paid to Defendant for its work, and what Plaintiff paid to a third-party to
complete Defendant’s work. (Id. at ¶¶ 8–10, 14–15.)
In its complaint, Plaintiff alleges that Defendant defaulted in its performance of the three
subcontracts into which the parties entered by, among other things, hiring or using sub-
subcontractors without Plaintiff’s authorization and failing to complete the services required under
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 6 of 10 PageID #: <pageID>
7
the subcontracts. (Id.) Plaintiff points to two provisions in the subcontracts that it contends allow
it to recover monetary damages from Defendant for its breaches. First, under the subcontracts,
Defendant agreed that, if it assigned or delegated its duties under the contract to another contractor,
Defendant would pay to Plaintiff all sums paid by Plaintiff to Defendant pursuant to the
subcontracts. (Docket No. 1-1 at 4; Docket No. 1-2 at 4; Docket No. 1-3 at 4.) Second, under the
subcontracts, Defendant agreed that, if it failed to cure any delay or defect, Plaintiff could
“backcharge” Defendant for costs to remedy those delays or defects, which could include costs for
additional workmen, materials, equipment, etc. (Docket No. 1-1 at 4; Docket No. 1-2 at 4; Docket
No. 1-3 at 4.)
In his affidavit, Mr. Webb states that Plaintiff paid Defendant $990,517.71 for work done
at the subject property. (Docket No. 34 at ¶ 7.) He refers to three summaries showing that Plaintiff
paid Defendant a total of $508,723.41 for roof work (Docket No. 34-1 at 1); $274,752.00 for
repairs (id. at 2); and $207,042.30 for code upgrades (id. at 3). Mr. Webb also states that Plaintiff
paid other third-party contractors $368.202.00 to complete or repair Defendant’s work. (Docket
No. 34 at ¶ 13.) He refers to two summaries showing that Plaintiff paid third-party Premier
Industrial Solutions $297,500.00 and $70,702.00 to complete or fix Defendant’s work. (Docket
No. 34-2.)
Based on Mr. Webb’s affidavit and the accompanying exhibits, the Court finds that an
award of damages of $1,358,719.71 is appropriate, which includes $990,517.71 that Plaintiff paid
to Defendant for the work that is the subject of the subcontracts and $368,202.00 as “backcharge.”
Separately, Plaintiff asks the Court to award it prejudgment interest at a rate of 10% per
annum from October 31, 2021, the latest date on which Defendant breached the subcontracts, to
the date on which the Court enters its final order. (Docket No. 35 at 6.) In diversity cases in the
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 7 of 10 PageID #: <pageID>
8
Sixth Circuit, “state law governs awards of prejudgment interest.” Estate of Riddle ex rel. Riddle
v. S. Farm Bureau Life Ins. Co., 421 F.3d 400, 409 (6th Cir. 2005) (quoting F.D.I.C. v. First
Heights Bank, FSB, 229 F.3d 528, 542 (6th Cir. 2000)). “Under Tennessee law, pre-judgment
interest ‘may be awarded . . . in accordance with the principles of equity at any rate not in excess
of a maximum effective rate of ten percent (10%) per annum.’” Kova Bristol Tenn 1894, LLC v.
Bristol Preservation, LLC, No. , 2020 WL 1344313, at *2 (E.D. Tenn. Oct. 5, 2020) (quoting Tenn.
Code Ann. § 47-14-123). “An award of prejudgment interest is within the sound discretion of the
trial court,” but “a court must keep in mind that the purpose of awarding the interest is to fully
compensate a plaintiff for the loss of the use of funds to which he or she was legally entitled, not
to penalize a defendant for wrongdoing.” Myint v. Allstate Ins. Co., 970 S.W.2d 920, 927 (Tenn.
1998) (citations omitted). See also Am.’s Collectibles Network, Inc. v. Sterling Commerce (Am.),
Inc., 819 F. App’x 397, 400 (6th Cir. 2020). “Equitable factors relevant to a court’s decision
include the following: (1) promptness in the commencement of a claim, (2) unreasonable delay of
the proceedings by either party, (3) abusive litigation practices by either party, (4) the certainty of
the existence of an underlying obligation, (4) the certainty of the amount in dispute, and (5) prior
compensation for the lost time value of the plaintiff’s money.” Poole v. Union Planters Bank, N.A.,
337 S.W.3d 771, 791 (Tenn. Ct. App. 2010) (collecting cases).
“Tennessee courts have established the following guiding principles to assist courts in the
decision of whether to award pre-judgment interest: (1) whether such an award is fair; (2) whether
the ‘amount of the obligation is certain, or can be ascertained by a proper accounting’; and (3)
whether the amount is ‘disputed on reasonable grounds.’” Kova Bristol Tenn 1894, LLC, 2020 WL
13443413, at *2 (quoting Myint, 970 S.W.2d at 927).
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 8 of 10 PageID #: <pageID>
9
Here, each of these three factors weighs in favor of an award of prejudgment interest. The
amount owed to Plaintiff under the subcontracts is certain, as is Defendant’s obligation to pay
those amounts, based on the facts alleged in the Complaint and Mr. Webb’s affidavit. However,
Plaintiff does not explain why the maximum rate of 10% should apply. Further, Plaintiff alleges
that Defendant’s last breach occurred on October 31, 2021, but it did not file its complaint until
nearly two years later on October 18, 2023.
Nevertheless, based on the totality of the circumstances, including that Defendant did not
attempt to assert a defense, the Court finds that Plaintiff should be awarded its requested rate of
prejudgment interest of 10%. However, in accordance with the principles of equity, the Court will
only calculate prejudgment interest from October 18, 2022 (one year before the date the complaint
was filed) to September 13, 2024 (the date of the Court’s initial order regarding default judgment)
because the Court finds that Plaintiff was delayed in filing its complaint. See Advanced Workzone
Servs., LLC v. R.R. Consultants, PLLC, No. 3:23-CV-00947, 2024 WL 4652210, at *2 (M.D. Tenn.
Nov. 1, 2024). The Court calculates this amount as $259,087.37. To come up with this amount,
the Court: (1) took 10% of $1,358,719.71, which is approximately $135,871.97; (2) divided that
number by 365 days, which is approximately $372.25; and (3) multiplied that number by 696 (the
number of days between October 18, 2022 and September 14, 2024), which is $259,087.37. See
id.
In its supporting memorandum, Plaintiff does not seek an award of any other form of
damages, including postjudgment interest or attorney’s fees and costs. Accordingly, the Court will
not award any other amounts of damages to Plaintiff.
Case 3:23-cv-01084 Document 37 Filed 11/19/25 Page 9 of 10 PageID #: <pageID>
10
III. 	CONCLUSION
Based on the foregoing, it is respectfully RECOMMENDED that:
1. 	Plaintiff’s unopposed “Motion for Entry of Judgment for Damages Pursuant to
F.R.C.P. 55(b)(2)” (Docket No. 26) be GRANTED IN PART.
2. 	Judgment be entered against Defendant in favor of Plaintiff for:
a. 	compensatory damages in the amount of $1,358,719.71; and
b. 	prejudgment interest from October 18, 2022 to September 14, 2024 in the
amount of $259,087.37.
3. 	A final judgment be entered in this action in accordance with Federal Rule of Civil
Procedure 58.
ANY OBJECTIONS to this Report and Recommendation must be filed with the Clerk of
Court within fourteen (14) days of service of this Report and Recommendation and must state with
particularity the specific portions of this Report and Recommendation to which objection is made.
See Fed. R. of Civ. P. 72(b)(2), Local R. 72.02(b). Failure to file written objections within the
specified time can be deemed a waiver of the right to appeal the District Court’s Order regarding
the Report and Recommendation. See Thomas v. Arn, 474 U.S. 140 (1985); United States v.
Walters, 638 F.2d 947 (6th Cir. 1981). Any response to the objections must be filed within fourteen
(14) days after service of objections. See Fed. R. Civ. P. 72(b)(2), Local R. 72.02(b).
Respectfully submitted,
Signed By:
J. Gregory Wehrman
United States Magistrate Judge