UNITED STATES DISTRICT COURT
EASTERN DISTRICT OF LOUISIANA
ORDER & REASONS
Before the Court is a motion for summary judgment filed by defendant Wright National
Flood Insurance Company (“Wright”).1 Plaintiff Justin Armstrong responds in opposition,2 and
Wright replies in further support of its motion.3 Having considered the parties’ memoranda, the
record, and the applicable law, the Court grants the motion because Armstrong’s lawsuit was
untimely filed.
I. 	BACKGROUND
This case concerns an insurance coverage dispute in the wake of Hurricane Ida, which hit
the Louisiana coast on August 29, 2021. Armstrong alleges that Wright issued a Standard Flood
Insurance Policy (“SFIP”) covering the property located at 402 Madie Lane in Slidell, Louisiana
(the “property”).4 	Wright provided flood insurance as a “Write-Your-Own” program carrier
participating in the National Flood Insurance Program (“NFIP”) pursuant to the National Flood
Insurance Act of 1968, as amended.5 	The NFIP is administered by the Federal Emergency
Management Agency (“FEMA”).6 The policy provided building damage coverage in the amount
1 R. Doc. 23.
2 R. Doc. 24.
3 R. Doc. 26.
4 R. Doc. 1 at 1.
5 R. Docs. 1 at 2; 23 at 1.
6 R. Doc. 23-1 at 4.
JUSTIN ARMSTRONG
VERSUS
WRIGHT NATIONAL FLOOD
INSURANCE COMPANY
CIVIL ACTION
NO. 23-4306
SECTION M (4)
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 1 of 9
2
of $250,000, subject to a $1,250 deductible, and contents coverage in the amount of $100,000, also
subject to a $1,250 deductible.7
On September 6, 2021, Armstrong notified Wright that the property sustained flood
damage as a result of Hurricane Ida.8 	Wright assigned the claim to an independent adjustor,
Colonial Claims Corporation (“Colonial”), which dispatched an NFIP authorized independent
adjustor to the property.9 	On September 8, 2021, the adjustor inspected and photographed the
property, determining that “a general condition of flooding, as defined by the SFIP, existed at the
[p]roperty on August 29, 2021.” 10 The adjustor prepared an estimate for building damages in the
amount of $64,175.87, after applying the $1,250 deductible and non-recoverable depreciation, and
an estimate for contents damages in the amount of $4,893.23, after applying the $1,250 deductible
and depreciation.11 	The adjustor also prepared a proof of loss reflecting these amounts, which
Armstrong signed on October 1, 2021.12 Wright issued payments to Armstrong for the amounts
stated in the October 1, 2021 proof of loss.13
On November 8, 2021, Wright issued to Armstrong a letter denying a portion of his claim.14
Specifically, Wright denied the claim as to “2 rugs and the Mariah Collection in the living room,”
because “there was no physical damage to these items caused by the flood water.”15
On April 29, 2022, Wright issued another denial letter to Armstrong.16 This time, Wright
stated that the engineer’s “inspection concluded [that] the house has not been structurally damaged
7 R. Doc. 23-7 at 1.
8 R. Doc. 23-6 at 2.
9 Id.
10 Id.
11 Id. at 2-3.
12 Id. at 3 (citing R. Doc. 23-8).
13 Id.
14 Id. at 5 (citing R. Doc. 23-14).
15 R. Doc. 23-14 at 1.
16 R. Doc. 23-6 at 5 (citing R. Doc. 23-15).
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 2 of 9
3
by hydrodynamic, hydrostatic, buoyant, or frictional forces floodwaters.”17 	The letter further
recited Wright’s conclusion that a leaning post and sloped ceiling beam were the “result of either
inadequate installation and/or remediation of the members,” not “flood-induced settlement or from
the floodwaters.”18 And the letter stated that “[t]he pier at the northeast corner of the front porch
is leaning as a result of long term, historical differential settlement,” but “[t]he pier at the northwest
corner of the front porch has sunk as a result of flood-induced differential settlement.” 19 Lastly,
Wright stated that “the cracks in the brick veneer below the French doors on the east side of the
house are the result of a tree impact and are not related to the floodwaters.”20
Sometime thereafter, Wright and Colonial received additional information regarding the
damage to the property.21 	As a result, another NFIP authorized independent adjustor affiliated
with Colonial prepared a revised estimate for covered flood damage to the building in the total
amount of $66,204.37, after considering application of the deductible and non-recoverable
depreciation.22 The adjustor prepared a revised proof of loss consistent with the revised building
damage estimate, for an additional payment amount of $2,028.50, which Armstrong signed on
August 30, 2022.23 Because the August 30, 2022 proof of loss was signed after the proof-of-loss
deadline,24 Wright obtained from FEMA a limited waiver of the proof-of-loss requirement for the
additional undisputed amounts contained in the untimely August 30, 2022 proof of loss.25 Wright
issued the additional payment.26
17 R. Doc. 23-15 at 2.
18 Id.
19 Id.
20 Id.
21 R. Doc. 23-6 at 3.
22 Id.
23 Id. (citing R. Doc. 23-9).
24 FEMA extended the typical 60-day proof-of-loss deadline to 180 days for Hurricane Ida flood damage
claims, making the proof-of-loss deadline on February 25, 2022. Id. at 5.
25 Id. at 3.
26 Id.
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 3 of 9
4
Colonial again received further information, and the adjustor prepared another revised
building damage estimate and proof of loss, this time in the amount of $69,807.35, after
considering application of the deductible and non-recoverable depreciation.27 On October 6, 2022,
Armstrong signed the proof of loss for the additional $3,602.98 in building damages.28 Wright did
not make any additional payment at that time.29
Subsequently, Colonial prepared a third revised building damage estimate and proof of
loss, this time in the amount of $72,672.37, after considering application of the deductible and
non-recoverable depreciation.30 This figure included increased pricing for the additional damages
contained in the second revised building damage estimate.31 On November 17, 2022, Armstrong
signed the proof of loss for the additional $6,468.00 (over the $66,204.37 already paid) in building
damages.32 	Wright issued payments to Armstrong in the total amount of $6,468.00 for the
additional building damages.33
In sum, Wright issued payments to Armstrong in the total amount of $72,672.37 for
building damages, and $4,893.23 for lost contents, as reflected in the third proof of loss.34 Wright
has no additional signed, sworn proof-of-loss documents in its file relating to Armstrong’s claim.35
27 Id. at 4.
28 Id. (citing R. Doc. 23-11).
29 Id.
30 Id.
31 Id.
32 Id. (citing R. Doc. 23-12).
33 Id.
34 Id. (citing R. Doc. 23-12).
35 Id. at 5.
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 4 of 9
5
Armstrong filed this suit against Wright on August 25, 2023, alleging that Wright breached
the insurance policy by failing to pay an adequate amount to cover his losses.36 Wright now moves
for summary judgment, arguing that Armstrong’s lawsuit was untimely filed. 37
II. 	LAW & ANALYSIS
A. Summary Judgment Standard
Summary judgment is proper if the pleadings, depositions, answers to interrogatories, and
admissions on file, together with the affidavits, if any, show that there is no genuine issue as to
any material fact and that the moving party is entitled to a judgment as a matter of law. Celotex
Corp. v. Catrett, 477 U.S. 317, 322 (1986); Fed. R. Civ. P. 56. “Rule 56(c) mandates the entry of
summary judgment, after adequate time for discovery and upon motion, against a party who fails
to make a showing sufficient to establish the existence of an element essential to that party’s case,
and on which that party will bear the burden of proof at trial.” Celotex, 477 U.S. at 322. A party
moving for summary judgment bears the initial burden of demonstrating the basis for summary
judgment and identifying those portions of the record, discovery, and any affidavits supporting the
conclusion that there is no genuine issue of material fact. Id. at 323. If the moving party meets
that burden, then the nonmoving party must use evidence cognizable under Rule 56 to demonstrate
the existence of a genuine issue of material fact. Id. at 324.
36 R. Doc. 1. Armstrong also alleged claims under Louisiana’s bad-faith penalty statutes, La. R.S. 22:1892
and 22:1973. Id. Those claims were dismissed with prejudice on Wright’s consent motion to dismiss. R. Doc. 14
(citing R. Doc. 13).
37 R. Doc. 23. Wright also argues that Armstrong did not submit a timely, signed, and sworn proof of loss
for additional amounts he now claims are owed. R. Doc. 23-1 at 12-18. In response, Armstrong contends that Wright,
with FEMA’s approval, waived the proof-of-loss requirement. R. Doc. 24 at 3-4, 7-8 (citing R. Doc. 24-2, an email
attaching a proof-of-loss waiver). Wright counters that the waiver was limited only to the August 20, 2022 proof of
loss and that Armstrong did not dispute that part of Wright’s statement of uncontested facts. R. Doc. 26 at 2-6.
Because Armstrong filed only the email and not the actual waiver into the record, the Court is unable to determine
whether the waiver was limited, as Wright contends, or global, as Armstrong says. Nevertheless, the Court need not
reach the proof-of-loss issue because it holds that Armstrong’s lawsuit was untimely filed.
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 5 of 9
6
A genuine issue of material fact exists if a reasonable jury could return a verdict for the
nonmoving party. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986). The substantive
law identifies which facts are material. 	Id. 	Material facts are not genuinely disputed when a
rational trier of fact could not find for the nonmoving party upon a review of the record taken as a
whole. See Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587 (1986); EEOC
v. Simbaki, Ltd., 767 F.3d 475, 481 (5th Cir. 2014). 	Unsubstantiated assertions, conclusory
allegations, and merely colorable factual bases are insufficient to defeat a motion for summary
judgment. See Anderson, 477 U.S. at 249-50; Little v. Liquid Air Corp., 37 F.3d 1069, 1075 (5th
Cir. 1994); Hopper v. Frank, 16 F.3d 92, 97 (5th Cir. 1994). In ruling on a summary-judgment
motion, a court may not resolve credibility issues or weigh evidence. See Delta & Pine Land Co.
v. Nationwide Agribusiness Ins. Co., 530 F.3d 395, 398-99 (5th Cir. 2008). Furthermore, a court
must assess the evidence, review the facts, and draw any appropriate inferences based on the
evidence in the light most favorable to the party opposing summary judgment. See Tolan v. Cotton,
572 U.S. 650, 656-57 (2014); Daniels v. City of Arlington, 246 F.3d 500, 502 (5th Cir. 2001). Yet,
a court only draws reasonable inferences in favor of the nonmovant “when there is an actual
controversy, that is, when both parties have submitted evidence of contradictory facts.” Little, 37
F.3d at 1075 (citing Lujan v. Nat’l Wildlife Fed’n, 497 U.S. 871, 888 (1990)).
After the movant demonstrates the absence of a genuine issue of material fact, the
nonmovant must articulate specific facts showing a genuine issue and point to supporting,
competent evidence that may be presented in a form admissible at trial. See Lynch Props., Inc. v.
Potomac Ins. Co., 140 F.3d 622, 625 (5th Cir. 1998); Fed. R. Civ. P. 56(c)(1)(A), (c)(2). Such
facts must create more than “some metaphysical doubt as to the material facts.” Matsushita, 475
U.S. at 586. When the nonmovant will bear the burden of proof at trial on the dispositive issue,
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 6 of 9
7
the moving party may simply point to insufficient admissible evidence to establish an essential
element of the nonmovant’s claim in order to satisfy its summary-judgment burden. See Celotex,
477 U.S. at 322-25; Fed. R. Civ. P. 56(c)(1)(B). Unless there is a genuine issue for trial that could
support a judgment in favor of the nonmovant, summary judgment must be granted. See Little, 37
F.3d at 1075-76.
B. Time Bar
Wright, citing 42 U.S.C. § 4072 and the “Suits Against Us” section of the SFIP, argues that
Armstrong’s breach-of-contract claim is time-barred because he failed to file suit within one year
of the mailing of the November 8, 2021 partial-denial letter.38 In opposition, Armstrong argues
that Wright should be estopped from invoking the statutory one-year limitations period because
Wright continued to adjust the claim after November 8, 2021.39 Wright replies, arguing that its
continued consideration of Armstrong’s claims after issuance of the November 8, 2021 partial-
denial letter does not equate to a waiver of the limitations period, which is mandated by federal
law. 40 Wright’s position is correct.
Section 4072 provides that:
In the event the program is carried out as provided in section 4071 of this title, the
Administrator shall be authorized to adjust and make payment of any claims for
proved and approved losses covered by flood insurance, and upon the disallowance
by the Administrator of any such claim, or upon the refusal of the claimant to
accept the amount allowed upon any such claim, the claimant, within one year
after the date of mailing of notice of disallowance or partial disallowance by the
Administrator, may institute an action against the Administrator on such claim in
the United States district court for the district in which the insured property or the
major part thereof shall have been situated, and original exclusive jurisdiction is
hereby conferred upon such court to hear and determine such action without regard
to the amount in the controversy.
38 R. Doc. 23-1 at 18-23.
39 R. Doc. 24 at 4-7.
40 R. Doc. 26 at 6-9.
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 7 of 9
8
42 U.S.C. § 4072 (emphasis added). 	The “Suits Against Us” section of the SFIP essentially
incorporates § 4072 into the policy and provides:
You may not sue us to recover money under this policy unless you have complied
with all the requirements of the policy. If you do sue, you must start the suit within
1 year after the date of the written denial of all or part of the claim, and you must
file the suit in the United States District Court of the district in which the covered
property was located at the time of loss. This requirement applies to any claim that
you may have under this policy and to any dispute that you may have arising out of
the handling of any claim under the policy.41
Under both § 4072 and the SFIP, the November 8, 2021 partial-denial letter triggered the
one-year statute of limitations for Armstrong to file suit against Wright. 	In fact, that letter
explicitly informed Armstrong that “Federal law permits you to file suit in the Federal District
Court where the damage occurred within one year of when your insurer first denied all or part of
your claim.”42 It also stated that Armstrong could file an appeal, but that “[f]iling an appeal does
not extend the one-year timeframe to file suit against your insurer.”43 	In Cohen v. Allstate
Insurance Company, the Fifth Circuit recognized that the SFIP’s limitations period, which is also
stated in § 4072, must be strictly construed, and a disallowance of all or part of a claim always
starts the clock. 924 F.3d 776, 780 (5th Cir. 2019). Indeed, in Cohen, as here, the insurer continued
to adjust the claim after issuance of the partial denial. See Cohen v. Allstate Ins. Co., 2018 WL
1144761, at *7 (S.D. Tex. Mar. 2, 2018), aff’d, 924 F.3d 776. 	Nevertheless, the Fifth Circuit,
strictly construing the applicable law, held that the limitations period began to run from the
issuance of the partial-denial letter. Cohen, 924 F.3d at 780-82. Accordingly, Armstrong’s breach-
of-contract claim, which was filed more than a year after issuance of the first partial-denial letter,
is time-barred.
41 R. Doc. 23-5 at 21-22.
42 R. Doc. 23-14 at 4.
43 Id.
Case 2:23-cv-04306-BWA-KWR Document 27 Filed 10/30/25 Page 8 of 9
9
III. 	CONCLUSION
Accordingly, for the foregoing reasons,
IT IS ORDERED that Wright’s motion for summary judgment (R. Doc. 23) is GRANTED,
and Armstrong’s claims are DISMISSED WITH PREJUDICE.
New Orleans, Louisiana, this 30 th day of October, 2025.
________________________________
BARRY W. ASHE
UNITED STATES DISTRICT JUDGE