UNITED STATES COURT OF APPEALS
FOR THE NINTH CIRCUIT
COKER EQUIPMENT CO., INC.,
Plaintiff - Appellant,
v.
BERNIE WITTIG; et al.,
Defendants - Appellees.
No. 08-16359
D.C. No. 2:06-CV-00516-RCJ-
RJJ
MEMORANDUM *
COKER EQUIPMENT CO., INC.,
Plaintiff - Appellee,
v.
CITIWEST STRUCTURES
(CALIFORNIA), INC.,
Defendant - Appellant,
and
BERNIE WITTIG; et al.,
No. 08-16362
D.C. No. 2:06-CV-00516-RCJ-
RJJ
FILED
FEB 16 2010
MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
-- 1 of 10 --
** The Honorable Barbara M.G. Lynn, U.S. District Judge for the
Northern District of Texas, sitting by designation.
2
Defendants.
Appeal from the United States District Court
for the District of Nevada
Robert C. Jones, District Judge, Presiding
Argued and Submitted December 9, 2009
San Francisco, California
Before: SCHROEDER and CALLAHAN, Circuit Judges, and LYNN, ** District
Judge.
Coker Equipment Co., Inc. appeals the district court’s judgment, following
partial summary judgment and a bench trial in favor of Citiwest Structures
(California), Inc. Citiwest cross-appeals on the amount of its attorney fees and
costs awarded. This court has jurisdiction under 28 U.S.C. § 1291. We affirm in
part, and reverse and remand in part for further proceedings.
I.
The district court did not err by granting Citiwest summary judgment on
Coker’s breach of contract claim. We review the district court’s grant of summary
judgment de novo. See Northrop Grumman Corp. v. Factory Mut. Ins. Co., 563
-- 2 of 10 --
3
F.3d 777, 783 (9th Cir. 2009).
Coker leased a crane to Citiwest, with an option to purchase, for use on the
Pinnacle Museum Tower project. At issue is whether the district court correctly
interpreted the contract as providing for specified crane usage over the life of the
lease term, rather than per month, and whether Citiwest exceeded its allotted usage.
Coker contends that the contract unambiguously limits Citiwest’s basic usage to
250 hours monthly.
It is reasonable to interpret the contract to mean that 250 hours per month is
the basis for the rental rate, not a monthly limit. See Caldwell v. Consol. Realty &
Mgmt. Co., 668 P.2d 284, 287 (Nev. 1983) (requiring the Court to seek a
reasonable interpretation for an ambiguous contract). Because there is more than
one reasonable interpretation of the contract, the contract is ambiguous, and the
district court properly considered parol evidence. See Glenbrook Homeowners v.
Glenbrook Co., 901 P.2d 132, 137 (Nev. 1995). Ambiguity is construed against
the drafter, Coker. See Williams v. Waldman, 836 P.2d 614, 619 (Nev. 1992). The
contract did not provide for objectively timing crane usage. Coker did not provide
a meter to track monthly usage and there was evidence that Coker represented to
Citiwest that usage hours would be considered in the aggregate. Parol evidence
supports Citiwest’s interpretation, and we agree with the district court’s
-- 3 of 10 --
4
interpretation that the contract provided Citiwest with 4,875 hours of usage
aggregated over the 19.5 months it leased the crane.
Citiwest did not exceed its 4,875 hours of allotted crane usage. The operator
logs show 4,420 hours of usage. Once the payroll logs are corrected to exclude the
time when the operator was at work but not using the crane, they show 4,305 hours
of use. Because Citiwest did not exceed its allotted usage, the district court
correctly granted Citiwest’s motion for summary judgment.
II.
The district court correctly found after a bench trial that Coker breached the
contract, because Citiwest had reasonable grounds for insecurity and Coker failed
to provide to Citiwest an adequate assurance of due performance. We review for
clear error the district court’s factual findings in a bench trial. See Saltarelli v. Bob
Baker Group Med. Trust, 35 F.3d 382, 384 (9th Cir. 1994).
In August 2004, Citiwest notified Coker that it intended to exercise the
option and pay Coker $109,924.76 to purchase the crane in September 2004.
Citiwest became insecure as to whether the crane was encumbered and sought
adequate assurance from Coker. See Nev. Rev. Stat. §§ 104.2312, 104.2609.
Coker argues that Citiwest did not have a reasonable basis for insecurity, since
Coker provided Citiwest with a UCC-1 filing from G.E. Capital, showing that its
-- 4 of 10 --
2 Cal/OSHA is the state of California’s occupational safety and health plan.
5
security interest in the crane had been released. The district court did not commit
clear error in finding that Citiwest was reasonably insecure, despite the release,
based on events that occurred during the parties’ relationship. The crane was not
Cal/OSHA certified when delivered to the job site and was consequently
inoperable for three weeks.1 Further, Coker breached its contractual obligation to
provide monthly maintenance on the crane. In January 2004, the crane’s hoist
motor, the motor by which items are raised and lowered, seized up and ceased
functioning. In May 2004, the swing motor, which powers the turning of the
crane, ceased functioning. Although Citiwest had completed many projects
requiring tower cranes, it had never had a hoist or swing motor blow on any other
crane during a lease. Viewing Coker’s repeated delinquencies as cumulative, the
district court correctly determined that Citiwest had reasonable grounds for
insecurity. See Nev. Rev. Stat. § 104.2609, Comment 4.
Coker breached the contract by failing to provide an adequate assurance of
due performance. Citiwest requested that Coker provide it with the paperwork
needed to transfer title, including title documents and a bill of sale. Coker never
provided a bill of sale and never informed Citiwest that title documents do not
normally accompany the sale of cranes. Citiwest’s counsel discovered several
-- 5 of 10 --
6
UCC filings listing Coker as the debtor, as well as a California tax lien filed against
Coker, which Citiwest reasonably believed encumbered the crane. Coker asserts
on appeal that the UCC filings and tax lien did not encumber the crane, but did not
communicate that position to Citiwest before the expiration of the option. Citiwest
had reason for concern, because it understood a California tax lien to encumber “all
personal and real property in the county” and believed that its knowledge of UCC
filings against Coker would prevent Citiwest from being a buyer in the ordinary
course of business. See Cal. Rev. & Tax. Code § 2191.4; Cal Com. Code § 9320,
Comment 3. Even if Citiwest’s belief that the crane was encumbered was incorrect
(which is unclear), it was not unreasonable, arbitrary, or capricious. The district
court did not err by finding that Citiwest had reasonable grounds for insecurity and
that Coker breached the contract by failing to provide an adequate assurance of due
performance.
III.
The district court correctly determined that Coker abused process and was
liable for punitive damages. Under Nevada law, the two elements of abuse of
process are “(1) an ulterior purpose by the defendant[] other than resolving a legal
dispute, and (2) a willful act in the use of the legal process not proper in the regular
conduct of the proceeding.” LaMantia v. Redisi, 38 P.3d 877, 879 (Nev. 2002).
-- 6 of 10 --
7
After the expiration of the option, Coker began billing Citiwest for “double
shifting” of the crane, asserting that Citiwest had been using the crane for sixteen
hours per day. Coker admitted at trial that it had no proof of double shifting and
that it billed Citiwest those amounts “[o]ut of frustration.” When Citiwest refused
to pay the double shifting bills, Coker recorded a lien on the Pinnacle project. At
trial, Coker acknowledged it had a prior judgment against it for filing an
inappropriate lien. Further, Coker sued Citiwest’s president and a crane operator
personally, though neither was a signatory to the contract. The above facts amply
support the district court’s finding that Coker abused process. Because there was
substantial evidence of oppression, fraud, or malice, the district court properly
awarded punitive damages. See Bongiovi v. Sullivan, 138 P.3d 433, 450 (Nev.
2006).
Coker argues that the district court violated its due process rights by
awarding punitive damages when it did not award compensatory damages for
abuse of process, but instead awarded only attorney fees and costs. There was no
due process violation because attorney fees and costs can constitute compensatory
damages for abuse of process. See Horgan v. Felton, 170 P.3d 982, 989 (Nev.
2007) (Maupin, C.J. concurring); see also Sternberg v. Johnson, 582 F.3d 1114,
1122 (9th Cir. 2009) (recognizing that attorney fees can be damages in abuse of
-- 7 of 10 --
8
process suits). Because the district court awarded $50,000 in attorney fees and
$5,000 in costs as compensatory damages, and $20,000 in punitive damages, the
ratio of punitive damages to compensatory damages was not excessive. See
generally Bongiovi, 138 P.3d at 451-52. Moreover, the district court satisfied Nev.
Rev. Stat. § 42.005(3) by providing a separate hearing before awarding punitive
damages.
IV.
Citiwest’s cross-appeal asserts that the district court abused its discretion by
awarding it $50,000 in attorney fees and $5,000 in costs, rather than its requested
fees of $91,692 and costs of $6,079.32. Under Nevada law, a lower court has great
discretion in awarding fees, to be “tempered only by reason and fairness.” Albios
v. Horizon Communities, Inc., 132 P.3d 1022, 1034 (Nev. 2006). However, the
trial court must conduct its analysis in light of the factors identified in Brunzell v.
Golden Gate National Bank, 455 P.2d 31, 33 (Nev. 1969), namely the “advocate’s
professional qualities, the nature of the litigation, the work performed, and the
result.” Albios, 132 P.3d at 1034. We review the district court’s award for abuse
of discretion. Id.
The district court found in its May 14, 2008 order that Citiwest was entitled
to reasonable attorney fees and costs, but found that Citiwest “has already been
-- 8 of 10 --
9
made substantially whole by the grant of summary judgment against Coker, the
findings at trial in favor of Citiwest, and the award of $20,000 in punitive
damages.” The court ruled that “an award of $50,000.00 in attorney fees and
$5,000.00 in costs to Citiwest for its claims of $91,692.00 in attorney fees and
$6,079.32 in costs is reasonable.” The district court seemingly held Citiwest’s
victory against it when it reduced its fees and costs, without referencing the
Brunzell factors. Brunzell requires the district court to consider Citiwest’s “total
win” in awarding its fees, not as a basis for reducing them. The district court’s
award of attorney fees is reversed and remanded for reconsideration of fees in light
of the Brunzell factors.
Under Nev. Rev. Stat. § 18.020, the prevailing party in an action alleging
more than $2,500.00 in damages is entitled to recover all costs as a matter of right.
“[T]he determination of which expenses are allowable as costs is within the sound
discretion of the trial court.” Albios, 132 P.3d at 1037. However, because the
district court did not consider whether certain costs were allowable, but rather
reduced costs seemingly indiscriminately in light of Citiwest’s prevailing overall,
the district court’s award of costs is reversed and remanded for reconsideration and
explanation of why particular costs sought are not awarded. Each party shall bear
its own costs on appeal.
-- 9 of 10 --
10
AFFIRMED IN PART; REVERSED AND REMANDED IN PART.