Specialty Minerals, Inc. v. Dunbar Mechanical, Inc.

04-4376; 04-4377United States Court Of Appeals For The 6th Circuit6 dic 2005

Testo completo

NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
File Name: 05a0954n.06
Filed: December 6, 2005
Nos. 04-4376/4377
UNITED STATES COURT OF APPEALS
FOR THE SIXTH CIRCUIT
Specialty Minerals, Inc., et al.,
Plaintiff-Appellee / Cross-Appellant,
v.
Dunbar Mechanical, Inc.,
Defendant-Appellant / Cross-Appellee.
)
)
)
)
)
)
)
)
)
ON APPEAL FROM THE
UNITED STATES DISTRICT
C O U R T F O R T H E
NORTHERN DISTRICT OF
OHIO
O P I N I O N
BEFORE: MERRITT, MARTIN, and COLE, Circuit Judges
R. GUY COLE, JR., Circuit Judge. Defendant-Appellant and Cross-Appellee Dunbar
Mechanical, Inc. (“Dunbar”) appeals the district court’s decision declaring invalid two affidavits
Dunbar filed in support of mechanic’s liens, the court’s dismissal of Dunbar’s counterclaim for
judgment on bonds substituted for the liens per Ohio law, and the court’s denial of Dunbar’s motion
to bifurcate the proceedings. Plaintiff-Appellee and Cross-Appellant Specialty Minerals, Inc.
(“SMI”) appeals the district court’s dismissal of its claim for slander of title against Dunbar. For
the reasons that follow, we AFFIRM the decisions of the district court.
I.
This case arises from the implementation of a two-stage process to manufacture polymers,
developed by SMI, whereby material is pelletized and heated.

-- 1 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 2 -
SMI contracted with Triad Construction Services, Inc. (“Triad”) to install a pelletizing
system in its Ohio plant (“contract 1"). Triad subcontracted with Dunbar (“subcontract 1A”) to
perform this service. SMI entered into a second contract with LB&W Engineering, Inc. (“LB&W”)
to install a kiln system (“contract 2”). LB&W subcontracted with Triad (“subcontract 2A”) who
subcontracted again with Dunbar (“subcontract 2B”).
On December 14, 2000, SMI tested the pelletizing and kiln systems. Because of flaws in
the SMI design, both systems had to be modified. SMI and LB&W bypassed a financially imperiled
Triad and contracted directly with Dunbar to modify the two systems (“contracts 3 and 4”). SMI and
LB&W paid Triad for the work on contracts 1 and 2. SMI and LB&W also substantially paid
Dunbar for the work on contracts 3 and 4. Triad filed for bankruptcy, however, and failed to pay
Dunbar a collective $240,904 on subcontracts 1A and 2B.
On March 22, 2001, Dunbar filed a pair of affidavits, thereby establishing two mechanic’s
liens against SMI’s Ohio plant. SMI posted monetary bonds to remove the liens, pursuant to Ohio
law. See O.R.C. § 1311.11(C). SMI brought this action requesting a declaratory judgment that
Dunbar’s affidavits were not filed within 75 days of the last day of work performed on the site, as
required by O.R.C. § 1311.06(B)(3). Moreover, SMI brought a claim for slander of title to property.
Dunbar moved to bifurcate the proceedings and filed a counterclaim requesting summary judgment
on the bonds posted by SMI in lieu of the liens. Following a bench trial, the district court held on
summary judgment that the affidavits were untimely; the court held against the moving party on
each other claim. This appeal and cross-appeal followed.

-- 2 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 3 -
SMI is a Delaware corporation that conducts business principally in New York. LB&W is
a Pennsylvania corporation that conducts business principally in that state. Dunbar is an Ohio
corporation that conducts business exclusively in Ohio; its owner is an Ohio resident. Thus, the
district court had jurisdiction in this diversity case pursuant to 28 U.S.C. § 1332. 28 U.S.C. § 1291
in turn grants us jurisdiction to hear this timely set of appeals.
II.
A. Dunbar’s Motion to Bifurcate the Proceedings
Federal Rule of Civil Procedure 42(b) states: “The court, in furtherance of expedition and
economy, may order a separate trial of any claim.” In addition to speed and economy, the
convenience of the parties and the avoidance of prejudice are important factors. See In re Beverly
Hill Fire Litig., 695 F.2d 207, 216 (6th Cir. 1982). We review the denial of a motion to bifurcate
for abuse of discretion, Yung v. Raymark Industries, Inc., 789 F.2d 397, 400 (6th Cir. 1986), which
exists only upon a “definite and firm conviction that the court below committed a clear error of
judgment in the conclusion it reached upon a weighing of the relevant factors.” Taylor v. U.S.
Parole Comm'n, 734 F.2d 1152, 1155 (6th Cir. 1984).
The district court did not abuse its discretion. Contracts 1 and 2 involve the same parties and
arise out of the same project. The two mechanic’s liens at issue attach to the same property. The
court found that bifurcating the proceedings would not serve judicial economy, would have little
effect on the convenience of the parties in such a short trial, and was unnecessary to avoid prejudice
because there was no jury to confuse. In short, the court reasonably weighed the relevant factors.
Accordingly, we affirm the district court’s denial of Dunbar’s motion to bifurcate.

-- 3 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 4 -
B. The Timeliness of Dunbar’s Affidavits
Upon appeal from a bench trial, we review the district court’s findings of fact for clear error
and its findings of law de novo. Pressman v. Franklin Nat'l Bank, 384 F.3d 182, 185 (6th Cir. 2004).
Although we give substantial deference to the district court’s assessments of witness credibility,
FED . R. CIV . P. 52(a), we review a district court’s application of state law—which governs this
diversity case—de novo. Leavitt v. Jane L., 518 U.S. 137 (1996); International Ins. Co. v. Stonewall
Ins. Co., 86 F.3d 601, 604 (6th Cir. 1996).
Under Ohio law, a contractor must file mechanic’s lien affidavits within 75 days of the last
day of work it performed on the contract at issue. O.R.C. § 1311.06(B)(3); King, Gilbert & Warner
v. Ship Bldg. Co., 34 N.E. 436, 439 (Ohio 1893). The last day of performance cannot be extended
by “tacking together” labor performed on subsequent contracts. King, 34 N.E. at 439; Talco Capital
Corp. v. State Underground Parking Comm., 324 N.E.2d 762, 769 (Ohio Ct. App. 1974).
Furthermore, unnecessary and unsolicited tinkering and repair do not extend the last day of
performance. Walter v. Brothers, 181 N.E. 554, 555 (Ohio Ct. App. 1932); Bohunek v. Smith, 172
N.E. 852, 854 (Ohio Ct. App. 1930). “The true test is whether the alleged repairs are a necessary
part of the proper completion and performance of the work which the lien claimant undertook to do.”
Walter, 181 N.E. at 553.
Dunbar filed its mechanic’s lien affidavits on March 22, 2001, claiming to have performed
meaningful work on contracts 1 and 2 as late as January of 2001. The district court determined that
“any work performed after December 14, 2000, under contracts #1 and #2 was voluntary, gratuitous
and without Plaintiff’s knowledge.” The court characterized the work Dunbar performed in

-- 4 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 5 -
connection with contracts 1 and 2 in January of 2001 to be “trivial,” i.e., unnecessary to the
completion of the project.
The district court’s factual findings are supported by the record. The district court credited
the testimony of a Dunbar employee that the work conducted by Dunbar in January of 2001 was
“odds and ends” and “not required to be complete to test the plant.” Various witnesses also testified
that Dunbar was not asked to perform additional work after December 31, 2000 and that most of
work performed by Dunbar in January of 2001 related to contracts 3 and 4.
Dunbar argues that the district court’s findings are incompatible with uncontested facts.
Dunbar points to its request to work during the 2000 Christmas holiday season, which took place
before contracts 3 and 4 were signed. Dunbar argues that this request, denied by SMI, is evidence
that work remained on contracts 1 and 2. However, Dunbar’s request to work over the holidays is
wholly compatible with the district court’s findings. The district court found that some work did
remain on the first set of contracts: trivial odds and ends. Furthermore, the record reflects that
although contracts 3 and 4 had not been signed, informal “punch lists” had been authored detailing
the relevant work. Thus, the work Dunbar sought to perform over the holidays could have related
to contracts 3 and 4, consistent with the district court’s findings.
In short, the district court correctly identified and applied Ohio law. Accordingly, we affirm
the district court’s invalidation of Dunbar’s affidavits as untimely; we correspondingly affirm the
district court’s summary judgment in favor of SMI, denying to Dunbar a judgment on the bonds.

-- 5 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 6 -
C. SMI’s Claim of Slander of Title
The district court held that, although the supporting affidavits were untimely, Dunbar’s
mechanic’s liens did not constitute slander of title under Ohio law because they were not filed
maliciously. As aforementioned, we defer to the district court’s assessment of credibility but review
its interpretations of state law de novo. Malice, moreover, typically presents a question of law. See
Bose Corp. v. Consumers Union of U.S., Inc., 466 U.S. 485, 492 (1984).
To prove slander of title in Ohio, a plaintiff must show that the defendant (1) made a
defamatory statement against the property of another, (2) which was false and malicious, and (3)
caused actual or special damages. Green v. Lamarr, 744 N.E.2d 212, 224 (Ohio App. Ct. 2000).
A statement is malicious if made with “reckless or wanton disregard of the rights of another.”
Childers v. Commerce Mortgage Invs., 579 N.E.2d 219, 221 (Ohio App. Ct. 1989).
SMI asserts that a letter from Dunbar employee Skip Galbraith evidences Dunbar’s malice.
In this letter, dated February 5, 2001, Galbraith states that Dunbar is “within three (3) weeks of
instituting our legal rights under the Ohio Lien laws.” Galbraith testified that he was familiar with
O.R.C. § 1311.06(B)(3)’s time requirements. Furthermore, SMI points out that three weeks from
February 5, 2001, is almost exactly 75 days from the day SMI tested the system. According to SMI,
this letter shows that Dunbar knew its affidavits, filed in March, were untimely.
Nevertheless, the district court did not find “reckless or wanton disregard” in Dunbar’s act
of filing the affidavits on March 22, 2001. The court credited Galbraith’s explanation of his letter
at trial, namely, that Dunbar was within three weeks of giving up its collection efforts and exercising

-- 6 of 7 --

Nos. 04-4376/4377
Specialty Minerals v. Dunbar Mechanical
- 7 -
its option under Ohio law to file a mechanic’s lien. That the date coincided with SMI’s test of the
system was, according to the district court, a coincidence.
We affirm the district court for two reasons. First, we owe substantial deference to the
credibility determination of the lower courts; the plaintiff is not entitled to a redetermination of
credibility. NLRB v. S. E. Nichols of Ohio, Inc., 472 F.2d 1228, 1229 (6th Cir. 1972) (per curiam)
(“This court does not sit to retry disputed issues of fact or to redetermine issues of credibility of
witnesses.”). Thus, although our examination is de novo, we read Galbraith’s letter with the
assumption that his trial testimony is true.
Second, the facts do not easily support a claim for slander of title. “Generally, the claim
arises because the presence of the affidavit or other filed documents prevents the titled owner from
completing a proposed sale.” Green, 744 N.E.2d at 224. Ohio’s rule allowing property holders to
post bonds in lieu of mechanic’s liens, see O.R.C. § 1311.11(C), provides an easy mechanism to
remove the cloud to title. Thus, the subject affidavits do not constitute “instrument[s] that cast doubt
on the property’s title and [do] not stand in the way of a record owner’s ‘full and free exercise of
ownership.” Green, 744 N.E.2d at 224 (quoting Catawba West, Inc. v. Domo, 598 N.E.2d 883, 885
(Ohio App. 1991).
III.
For the reasons articulated above, we AFFIRM the judgment of the district court in all
respects.

-- 7 of 7 --

Continua la tua ricerca in ChatGPT o Claude

Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.