CourtListener 2802797•L J Sutter Partners v. Odysseus Farms CA3
Testo completo
Filed 5/21/15 L J Sutter Partners v. Odysseus Farms CA3
NOT TO BE PUBLISHED
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
THIRD APPELLATE DISTRICT
(Sutter)
----
L J SUTTER PARTNERS, L.P.,
Plaintiff and Appellant, C074082
v. (Super. Ct. No. CVCS081016)
ODYSSEUS FARMS et al.,
Defendants and Respondents.
This is the third appeal in the continuing saga of litigation over real property
owned by Odysseus Farms (Odysseus)1 in South Sutter County. (See South Sutter, LLC
v. LJ Sutter Partners, L.P. (South Sutter I) [(C057843) dismissed after the parties notified
us of a settlement]; S. Sutter, LLC v. LJ Sutter Partners, L.P. (2011) 193 Cal.App.4th
1 LJ Sutter’s second amended complaint was filed against Odysseus Farms,
a California general partnership, Elysian Farms, Inc., and Robert Leal, as trustee
of the Leal Family Trust. We refer to defendants and respondents collectively as
Odysseus.
1
634, 640 (South Sutter II).) This appeal concerns an option held by LJ Sutter Partners
L.P. (LJ Sutter) to buy “mitigation” property from Odysseus. Mitigation property refers
to real property that developers must acquire and set aside when proceeding to build
residential and industrial developments. When the deadline loomed for LJ Sutter to make
a large payment to preserve its option, it asked Odysseus for a loan and extension of time
to make the option payment. When Odysseus refused, LJ Sutter engaged in a ruse by
purporting to exercise the option but while imposing an impossible-to-fulfill condition.
Odysseus eventually balked, and LJ Sutter sued for causes of action that included breach
of contract, fraudulent inducement, fraudulent concealment, and intentional interference
with prospective economic advantage. A trial was conducted by a referee and culminated
in a judgment for Odysseus.
On appeal, LJ Sutter contends (1) the referee erred by finding LJ Sutter impliedly
repudiated the option agreement by imposing the unreasonable condition that Odysseus
provide assurances it could convey the mitigation property and (2) any implied
repudiation was nullified by Odysseus’s failure to treat the demand for assurances as a
breach of contract. LJ Sutter’s arguments focus exclusively on the referee’s implied
repudiation ground for rejecting the breach of contract claim.
We reject LJ Sutter’s arguments for lack of prejudice. LJ Sutter has not addressed
a second ground on which the referee based his decision, namely that LJ Sutter was
equitably estopped from demanding assurances when it had argued in the collateral
litigation that Odysseus unquestionably had clear title to the mitigation property.
Moreover, LJ Sutter fails to discuss a third ground given by the referee for rejecting the
breach of contract claim, namely abrogation of the contract by mutual intent of the
parties. Thus, even if the contract had not been unilaterally repudiated by LJ Sutter, there
are two other grounds for affirming the judgment for Odysseus: (1) LJ Sutter was
2
equitably estopped from demanding reassurances from Odysseus; and (2) the option
agreement was mutually abrogated by the parties. Accordingly, we affirm.
BACKGROUND
We recount the factual and procedural history only to the extent pertinent to the
resolution of the repudiation of contract arguments raised on appeal by LJ Sutter.
An Expensive Option Becomes a Problem for LJ Sutter
In 2004, South Sutter County was the focus of numerous developers who wanted
to build residential and industrial projects. Part of Odysseus’s property appeared to be
valuable as mitigation property. In 2005, Odysseus sold a long-term option for
acquisition of its mitigation property to LJ Sutter Partners.
A crisis loomed for LJ Sutter when a payment of $1,750,000 to renew the option
was coming due in January 2008. With the severe downturn in the real estate market, LJ
Sutter had run into financial difficulties, lawsuits, and roadblocks in its attempts to
develop property in Sutter County. As the referee found, “by the end of 2006, it had
become clear that LJ Sutter would not be able to realize the substantial profits
contemplated when it entered into the O[ption] A[greement] with Odysseus in January,
2005. . . . [¶] Similarly, the only apparently available means to turn a profit from a
different deal –- either with [the owners of the Sacramento] Kings or with Lynch
[Developments, Inc.] –- also vanished with time. Thus, by the end of 2006, LJ Sutter was
holding rights to acquire property for development with no real prospect of realizing
profit on the deal.”
LJ Sutter sought a loan from Odysseus and to have Odysseus extend the deadline
for the option payment. When Odysseus refused, LJ Sutter purported to exercise the
option and demanded assurances Odysseus could deliver title to 63 acres of mitigation
property. At the time, the 63 acres were still part of litigation in South Sutter II that
would not be resolved within the short option exercise window. Both LJ Sutter and
3
Odysseus went through the motions on the option purchase –- by opening escrow and
even surveying the property –- even though neither side actually intended to follow
through on the option purchase. In January 2007, Odysseus declared LJ Sutter to be in
breach of the option agreement. Soon thereafter, LJ Sutter sued Odysseus for breach of
contract and various other related causes of action. A 13-day trial before a referee
resulted in a judgment in favor of Odysseus.
The Referee’s Statement of Decision
After trial, the referee issued a 43-page statement of decision. The referee found
three bases for rejecting LJ Sutter’s claim that Odysseus breached the option agreement.
1. Implied Repudiation
First, the referee found that “[t]he preponderance of the evidence establishes that
the ‘assurances’ demanded by LJ Sutter at the time of the purported exercise of the option
to purchase the 63 acres were not reasonable under the circumstances and constituted a
repudiation of the Option Agreement by LJ Sutter.” As the referee explained, “the means
by which LJ Sutter communicated the exercise of the option on the 63 acres appears to
have been an attempt to ‘have their cake and eat it, too’ –- i.e., exercise the option while
trying to engineer a breach by Odysseus in order to have a basis to seek return of their
investment –- the option payments. Put in other words, LJ Sutter’s declaration that
Odysseus was in breach of its obligations under the O[ption] A[greement] by virtue of the
continuing litigation with South Sutter and its demands for ‘assurances’ that [Odysseus]
could deliver title as required by the O[ption] A[greement] was, itself, a repudiation of
the O[ption] A[greement].”
2. Equitable Estoppel
Second, the referee found that “when South Sutter filed Sutter I and Sutter II, LJ
Sutter vigorously defended the litigation, asserting the very opposite of the position
underlying the request for assurances.” Thus, “as a separate ground of decision on this
4
issue, the Referee finds that, even if otherwise warranted on the facts, [LJ Sutter] is
equitably estopped to assert the question of inability to deliver the property free of [LJ
Sutter]’s claims as a basis for assurances.” (Italics added.) As the referee explained, “LJ
Sutter uniquely knew what its view of South Sutter’s purported rights were and whether
they had a true concern about those possible rights in connection with their own land
acquisition from Odysseus. It is clear from LJ Sutter’s conduct, starting with the events
surrounding the Brennan Tract exchange in 2005, that LJ Sutter adamantly refuted the
existence of those rights and that it intended Odysseus to act in concert with it in
challenging those claims. Based on LJ Sutter’s conduct, Odysseus was fully justified in
concluding for several years that there was nothing to be concerned about in connection
with the LJ Sutter-Odysseus agreement as a result of the South Sutter claims.”
3. Abrogation of the Contract by Mutual Intent
Third, the referee found that “[t]he evidence also establishes that at the time
Odysseus received the purported exercise of the option including the request for
assurances, it had determined not to further honor the terms of the Option Agreement.”
The referee further found that “[t]he conduct of the parties from and after December 27,
2007, notwithstanding evidence that they ostensibly continued to perform certain aspects
of the Option Agreement, constitutes their implied mutual abrogation of the Option
Agreement.” “Odysseus’ response, particularly in light of [Odysseus manager] Leal’s
acknowledgements that he did not intend that Odysseus close on the 63 acres, was a
response in kind –- we want out also. The net effect of this conduct is that it evidenced
mutual intent of both parties to abandon the Option Agreement.” Thus, “[a]s of January
18, 2008, then, both parties had, by their conduct, repudiated the contract.” The referee
added, “Like in Jones v. Noble (1934) 3 Cal.App.2d 316, 322, ‘[t]he facts in this case
more nearly describe a case of an abandonment of the contract by one party, followed by
the alleged acquiescence of the other.”
5
On these grounds, the referee concluded, “there was no actionable breach of
contract by Odysseus” with respect to the option agreement. Judgment was entered in
favor of Odysseus.
DISCUSSION
We begin by noting a few cardinal principles of appellate review. We start with
the presumption the judgment is correct. (In re Marriage of Arceneaux (1990) 51 Cal.3d
1130, 1133.) An appellant has the burden to demonstrate error. (Denham v. Superior
Court (1970) 2 Cal.3d 557, 564.) And issues not raised in an appellant’s opening brief
are deemed abandoned. (Reyes v. Kosha (1998) 65 Cal.App.4th 451, 466.) Moreover,
mere assertion of error does not suffice. “To demonstrate error, appellant must present
meaningful legal analysis supported by citations to authority and citations to facts in the
record that support the claim of error. (City of Lincoln v. Barringer (2002) 102
Cal.App.4th 1211, 1239, fn. 16; In re Marriage of Nichols (1994) 27 Cal.App.4th 661,
672-673, fn. 3.) When a point is asserted without argument and authority for the
proposition, ‘it is deemed to be without foundation and requires no discussion by the
reviewing court.’ (Atchley v. City of Fresno [(1984)] 151 Cal.App.3d [635,] 647; accord,
Berger v. Godden [(1985)] 163 Cal.App.3d [1113,] 1117 [‘failure of appellant to advance
any pertinent or intelligible legal argument . . . constitute[s] an abandonment of the
[claim of error’].)” (In re S.C. (2006) 138 Cal.App.4th 396, 408.)
LJ Sutter contends the judgment should be reversed for two reasons: (1) the
implied repudiation finding of the referee was not supported by the facts or law, and (2)
any implied repudiation was nullified by the fact Odysseus did not immediately declare
LJ Sutter to be in breach of contract. In so arguing, LJ Sutter’s opening brief does not
mention the separate basis for finding repudiation of the contract –- namely that LJ Sutter
was equitably estopped from demanding assurances from Odysseus in direct
contravention to LJ Sutter’s arguments in Sutter I and Sutter II. LJ Sutter’s reply brief
6
even states that “estoppel is not the issue before the Court in this appeal.” Thus, even if
the referee erred that the demand for assurances constituted an implied repudiation, we
would nonetheless affirm on the unchallenged equitable estoppel ground articulated by
the referee.
Moreover, LJ Sutter presents no argument that the option agreement was
abrogated by mutual intent of the parties. Abrogation by mutual intent, however, was a
third basis on which the referee based his decision. LJ Sutter’s opening brief refers only
twice to this ground. First, LJ Sutter asserts: “Despite the Referee’s finding that there
was a ‘mutual intent of both parties to abandon the Option Agreement’ [citation], there
was never a threat by statement or the conduct by either party that evidenced an intent to
abandon this contract!” However, this assertion is made without the benefit of any legal
authority regarding abrogation of contract by mutual intent. Instead, the assertion is
made within the argument that focused on “California’s existing doctrine of anticipatory
breach by repudiation . . . .” This stray assertion does not constitute a developed
argument that properly challenges the abrogation of contract finding of the referee. (In re
S.C., supra, 138 Cal.App.4th at p. 408.)
LJ Sutter’s second reference to abrogation of contract is found in the conclusion of
the opening brief, where it states: “The Referee disregarded the law when he determined
that the parties mutually abrogated the agreement.” This is a conclusion, not an
argument. It does not properly raise the issue of abrogation of contract. (Atchley v. City
of Fresno, supra, 151 Cal.App.3d at p. 647.) Consequently, the abrogation of contract
ground has not been properly argued and constitutes a separate reason, apart from implied
repudiation and equitable estoppel, for affirming the judgment. A single valid basis for
the trial court’s decision suffices to affirm the denial of a motion for new trial. (Salazar
v. Southern Cal. Gas Co. (1997) 54 Cal.App.4th 1370, 1376; Waller v. TJD, Inc. (1993)
12 Cal.App.4th 830, 833.)
7
Based on the second and third grounds for the judgment, we reject LJ Sutter’s
arguments about implied repudiation for lack of prejudice.
DISPOSITION
The judgment is affirmed. Respondents Odysseus Farms, Elysian Farms, Inc., and
Robert Leal shall recover their costs on appeal. (Cal. Rules of Court, rule 8.278(a)(1)
& (2).)
HOCH , J.
We concur:
BLEASE , Acting P. J.
NICHOLSON , J.
8
Ti chiedi come si applica questo testo alla tua situazione?
Consulenza gratuita, senza impegno
Descrivi la tua situazione. Il nostro team ti ricontatterà via e-mail per la tua consulenza.
Continua la tua ricerca in ChatGPT o Claude
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.