REM Construction v. Wheatland Union High School Dist. CA3

CourtListener 10814269Calctapp24 mar 2026

Testo completo

Filed 3/24/26 REM Construction v. Wheatland Union High School Dist. CA3
NOT TO BE PUBLISHED
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
THIRD APPELLATE DISTRICT
(Yuba)
----

REM CONSTRUCTION, INC., C100232

Plaintiff and Respondent, (Super. Ct. No. CVCV21-
00847)
v.

WHEATLAND UNION HIGH SCHOOL DISTRICT,

Defendant and Appellant.

REM Construction, Inc. (REM), sued Wheatland Union High School District (the
District) for breach of a public works contract to modernize a high school. REM alleged
it performed all work required under the contract, but the District failed to pay it the full
contract price. Following a week-long bench trial, the trial court entered judgment in
favor of REM. The District appeals, arguing that REM’s lawsuit is barred because it
failed to comply with all steps of the contract’s claim resolution process, and compliance
with that process is a condition precedent to litigation. In particular, the District argues
(1) REM’s claim was untimely, and (2) even if it was timely, REM did not complete the

1
final step of the claim resolution process, namely, mediation. The trial court rejected the
District’s arguments, finding the claim was timely and that any failure to mediate was the
District’s fault. We agree and thus affirm.
THE RELEVANT CONTRACT PROVISIONS
Because it is the focus of this appeal, we begin with a description of the relevant
contract provisions—specifically, section 25 of the contract governing “Claims.”1 A
“Claim” is defined as a “separate demand by Contractor . . . for one or more of the
following”: (1) “A time extension, including . . . for relief from damages or penalties for
delay assessed by District under this Agreement”; (2) “Payment by the District of money
. . . arising from work done by . . . Contractor pursuant to the Agreement and payment for

1 Many of the relevant contract provisions are identical to provisions in Public
Contract Code section 9204, which creates a claim resolution process for public works
projects in order to ensure that contractors are “paid in full and in a timely manner” for
work “that is complete and not in dispute.” (Pub. Contract Code, § 9204, subd. (a).)
Section 9204 provides “a public entity may prescribe reasonable . . . claim[] and dispute
resolution procedures and requirements in addition to the provisions of this section, so
long as the contractual provisions do not conflict with or otherwise impair the timeframes
and procedures set forth in this section.” (Id., subd. (f).) As potentially relevant here,
sections 25.4, 25.7.2, and 25.9 of the parties’ contract contain “procedures and
requirements in addition to the provisions of” Public Contract Code section 9204. The
District cites section 9204 but fails to demonstrate that it affects any of our conclusions in
this case. We note that whether we are interpreting the parties’ contract or the identical
provisions of section 9204, our review is de novo. (See Filtzer v. Ernst (2022)
79 Cal.App.5th 579, 583 [“de novo standard of review” applies where no extrinsic
evidence was admitted concerning the contract’s meaning]; Michaels v. State Personnel
Bd. (2022) 76 Cal.App.5th 560, 567 [“questions of statutory interpretation are subject to
the de novo standard of review”].) We also note the District drafted the contract, and any
contract provisions that do not appear in section 9204 are subject to the “ ‘ “well
established rule of construction” that any ambiguities must be construed against’ the
drafter, where the uncertainty cannot be resolved by other rules of contract
interpretation.” (Breathe Southern California v. American Lung Assn. (2023)
88 Cal.App.5th 1172, 1182.)

2
which is not otherwise expressly provided or to which the claimant is not otherwise
entitled”; and (3) “Payment of an amount that is disputed by the District.”
The contract provides, “Compliance with . . . the claim submission procedures
described in this Claims section is an express condition precedent to Contractor’s right to
commence litigation . . . . The Contractor cannot . . . assert or bring any Claim in any . . .
subsequent legal action until that Claim has gone through the Claims Resolution Process
herein.” It also provides, “The procedures and provisions of this Claims section shall not
apply to [¶] . . . District’s determination of . . . whether the Work complies with the
Contract Documents for purposes of accepting the Work.”
The claim resolution process begins with the contractor’s submission or
presentation of a written claim, which must be done “within ten (10) calendar days from
the date Contractor discovers or reasonably should discover, that an act, error, or
omission of District, its agents or employees, or action, condition or other situation has
occurred that may entitle Contractor to file a Claim.” Upon receipt of a claim, the
District shall review it and provide a written response within 45 days (or longer in certain
circumstances) identifying what portion of the claim is disputed and what portion is
undisputed, and it shall pay any undisputed portion of the claim within 60 days.
If the contactor disputes the District’s response to the claim, it “may demand in
writing an informal conference to meet and confer for settlement of the issues in dispute.”
Upon receipt of such a demand, the District “shall schedule a meet and confer conference
within 30 days for settlement of the dispute.” “Within 10 business days following the
conclusion of the meet and confer conference, if the Claim or any portion of the Claim
remains in dispute, the District shall provide the Contractor a written statement
identifying the portion of the Claim that remains in dispute and the portion that is
undisputed. Any payment due on an undisputed portion of the Claim shall be processed
and made within 60 days after the District issues its written statement.”

3
Finally, “Any disputed portion of the Claim, as identified by the contractor in
writing, shall be submitted to nonbinding mediation . . . . If mediation is unsuccessful,
the parts of the Claim remaining in dispute shall be subject to applicable procedures
outside this section.” The District acknowledges that “applicable procedures outside this
section” includes litigation.
The contract also provides, “Failure by the District to . . . meet the time
requirements” of the claim resolution process “shall result in the Claim being deemed
rejected in its entirety.”
FACTUAL AND PROCEDURAL BACKGROUND
As the sole issue on appeal is whether REM’s lawsuit is barred by its failure to
comply with the contract’s claim resolution process, our description of the factual and
procedural background focuses on things that are relevant to that issue.2 Additional facts
and evidence are described in the relevant discussion section, below.
Background Relevant to the District’s Arguments on Appeal
REM entered into a written contract with the District to modernize 40 classrooms
at a high school for a total price of approximately $2.98 million. REM completed the
bulk of the work during the summer of 2019, and the District took possession of the
classrooms in August and classes began as scheduled. However, REM continued to work
on “punch list” items for several months. A punch list is a list of items that remain to be
completed or corrected, and it is prepared by the project’s architect as the project nears
completion. As found by the trial court, “The contractor fixes items on the punch list,
there is re-inspection, possibly a new punch list, more fixing and so on until the District
determines all items are complete.”

2 Following the bench trial, the court issued a written statement of decision on the
merits that contains numerous findings of fact. Neither party challenges those findings
and we thus rely on them in our description of the underlying facts.

4
A dispute arose between the parties, and the District ultimately refused to pay
REM approximately $220,600 of the contract price. The parties’ dispute centered
primarily on two issues. The first related to the punch list. The District contended REM
either failed to complete some of the contract work or completed it deficiently, as
identified on the punch list, and the District threatened to self-perform that work and
deduct its costs from the contract price. REM, in contrast, contended it satisfactorily
completed all items on the punch list that were within the scope of its work. The second
issue involved the District’s contention that REM had overbilled for work it had done
pursuant to previously approved change orders (we occasionally refer to this as the
“overbilling issue”). Although the District had already paid for this work, it threatened to
withhold or recoup those amounts from any remaining payments due on the contract. In
addition to the punch list and overbilling issues, the parties also disputed whether the
District should approve four additional proposed change orders totaling approximately
$20,000,3 and the District was threatening to impose damages on REM for delays in
completing the project (it would apparently impose those damages by subtracting them
from any remaining amounts due under the contract).
In October, November, and December, the parties were working through the punch
list. On December 23 or 24, REM sent the District an updated punch list showing that,
with a few minor exceptions, all items were either completed or were not within the
scope of its work. As to the minor exceptions, REM gave an estimate of when the work
would be completed.

3 These proposed change orders are different than the previously approved change
orders that gave rise to the overbilling issue. We note the trial court ultimately found that
REM was not entitled to payment on the proposed change orders because “they were
never mentioned in the claim and, thus, despite the apparent merit of three of them,
cannot be the basis of any recovery.” (Italics added.) In other words, the trial court
found the portion of REM’s claim that concerned the proposed change orders was barred
because REM failed to comply with the claim resolution process as to that portion.

5
On December 26, the District asked REM to send it any pending proposed change
orders so that it could “evaluate them.”
On December 27, the District sent REM a letter stating: (1) it was in the process
of auditing all previously approved change orders and had uncovered “substantial”
overbilling and would provide “further communications” on this issue “soon”; (2) it
would “self-perform the remaining floor wax work” and would withhold $13,000 from
the contract price as a result;4 and (3) it rejected all proposed change orders as untimely.
The District also stated it would be willing to limit its imposition of delay damages to
$10,000 if, among other things, REM would “make good faith efforts to achieve a just
resolution and efficient close-out of this project.”
On January 3, the District sent REM a letter stating its “initial review” of
previously approved change orders had identified approximately $23,000 in overbilling
and that the full amount of overbilling was not readily ascertainable because REM had
provided inadequate documentation, and it demanded REM promptly provide certain
documentation. The District also stated it could currently “defensibly retain” almost
$90,000 from the contract price, consisting of (1) approximately $51,000 in delay
damages, (2) $13,000 to complete the floor wax work, and (3) approximately $25,000 in
overbilling.
On January 9, the District sent REM a letter stating, “numerous items on the
Project that were supposedly completed have not, in fact, been completed,” and it
enclosed a spreadsheet (or updated punch list) identifying 11 such items and estimating it
would cost $88,465.56 to complete those items itself. The District’s letter concluded,

4 The trial court ultimately found the District was not justified in withholding any
amount from the contract price due to the floor wax issue, and the District does not
challenge this finding.

6
“Hopefully . . . the Parties can work cooperatively to resolve these issues in a timely
manner.”
On January 14, the District sent REM a letter stating it still had not received the
documentation it had demanded regarding the previously approved change orders and
asking that REM do so by January 17.
On January 15, the parties exchanged e-mails regarding work REM was
performing that afternoon (including painting, replacing lights, and installing “the base
on the science cabinets skirts”), and the status of some of the remaining punch list items.
That evening, REM sent an e-mail stating it “will provide a work plan that lists the work
it plans on performing and the projected dates for each item” by the end of the week, and
the District confirmed it would “permit [REM] to furnish the work plan . . . for the
District’s consideration and sufficient time for its review and implementation if it is
indeed acceptable to the District. Of course, this leaves the overbilling and delay
damages issue live, and this action would be in reliance on what I understand to be your
representation that work on the project has not ceased because the punch list is in
progress.”
On January 17, REM sent the District an e-mail stating the work plan would take a
few more days to prepare, and the District responded, “Ok.”
On January 27, the District sent REM a letter noting it still had not provided the
work plan and asking when it would provide the documentation regarding the previously
approved change orders. The District also enclosed a “current punch list reflecting the
work the District will be self-performing and the estimated cost of self-performance.”
The “current punch list” enclosed with the January 27 letter is similar to the spreadsheet
enclosed with the January 9 letter, but some of the items on it changed and the estimated
cost to perform those items was now $69,960.51, rather than $88,465.56.
On January 30, REM sent the District a letter stating it had performed all items on
the punch list that were within the scope of its work except some painting that it was

7
“ready, willing and able to complete.” REM also noted the District “provide[d] no details
to support [its] contention the punch list work performed in January is deficient” and it
asked the District to “identify with particularity what work is deficient and why it is
deficient.” It also stated it was “willing to provide a credit to the District in the amount
of $8,000 . . . to strip and re-seal the floor.” Finally, it stated it would provide the
requested documentation to the District on February 14.
On January 31, REM sent the District a letter disputing its contention it was
entitled either (1) to be “repaid a portion of the amount it paid REM for certain work
performed” pursuant to the previously approved change orders, or (2) to any damages for
delay. The letter concluded, “REM is committed to closing out the project and resolving
the issues without the need to resort to litigation.”
On February 5, the District hand delivered a letter to REM (the letter was dated
February 4), and it is the District’s position that this letter triggered the claim submission
deadline provided in the contract. The letter enclosed a resolution adopted by the
District’s board on February 3. The resolution stated the project was complete and it
directed the superintendent to “disburse any remaining portion of the Contract Price
under the Agreement . . . minus any amounts not otherwise due to Contractor including
by way of illustration and not by limitation”: (1) $30,708.01 “in readily identifiable
change order charges . . . that were erroneously issued on the basis of inflated proposed
change orders submitted by Contractor”;5 (2) $69,960.51 “as a reduction in the Contract
Price to reflect the anticipated reasonable cost for the District to self-perform all
remaining work for the project”; and (3) $2,599.20 “as a reduction to the Contract Price
reflecting additional costs incurred by the District” because it had to perform additional

5 This appears to refer to the overbilling issue. We note the trial court found there
was no evidence introduced at trial regarding inflated change orders or overbilling, and
the District does not challenge this finding.

8
inspections due to “Contractor’s false representation that the Project was complete and
ready for final inspection.” In its letter, the District stated, “If REM has a proposal as to
how it intends to resolve this dispute, it can communication that proposal . . . in
writing. . . . The District clearly is interested in a cooperative close-out of the Project, but
if REM is unwilling to cooperate, the District can continue to close-out the Project
unilaterally.”
On February 6 and 7, the parties again exchanged e-mails. REM asked the District
to “confirm that [it] refuses to allow REM to perform the painting work as proposed in
my letter to you of January 30,” and the District responded, “at present, yes,” but it would
provide a more detailed response after it received the substantiating documentation
regarding previously approved change orders that REM had stated it would provide by
February 14.
On February 13, REM submitted an invoice to the District. The invoice identified
a “current payment due” of $71,580.60, and a retention of $149,019.54, for a total
amount still due of approximately $220,600 (i.e., the amount sought in this lawsuit).
On February 14, REM provided the District with the requested documentation
regarding the previously approved change orders.
On February 26, the District sent a letter to REM, and REM contends (and the trial
court found) it was this letter that triggered the claim submission deadline. The District
stated it had reviewed the documentation regarding previously approved change orders
and identified approximately $154,000 in overbilling, and it intended to withhold that
amount from any remaining payment due, but REM “may be able to reduce this
withholding” by “immediately” providing certain additional documentation. The District
also stated it “will be withholding” an additional $80,257.94 “to self-perform the
remainder of the Project,” consisting of the $69,960.51 identified in the board resolution
and $10,297.43 in “additional work . . . that has been recently identified.”

9
On March 6, REM submitted a claim disputing the District’s contentions it had
(1) overbilled, or (2) failed to satisfactorily perform all required work. REM demanded
the District immediately pay it the remaining contract price.
On April 10, the District sent REM a letter denying the claim on numerous
grounds, including that it was untimely.
A little over a year later, on June 1, 2021, REM sent the District a “written demand
for the informal meet and confer process.” It appears the District never responded to this
demand.
REM filed the present lawsuit in August 2021. It alleged it completed all work
required by the contract, and the District breached the contract by failing to pay it the
total amount due. It also alleged it submitted a claim and “requested the meeting” as
required by the contract, but the District failed to comply with its duties and declined to
meet. This breach of contract cause of action is the focus of this appeal.6 The District
filed an answer and, as an affirmative defense, alleged REM “failed to timely comply
with all applicable contractually required claims procedures,” and the lawsuit was barred
as a result.
In late 2022, in response to an e-mail from REM’s counsel regarding mediation,
the District’s counsel stated, “As for mediation, the District has always said no, but I’ll
talk to them again this week.”
The District’s Motion for Judgment and the Trial Court’s Ruling Thereon
The matter proceeded to a bench trial. After REM finished presenting its
evidence, the District filed a motion for judgment pursuant to Code of Civil Procedure

6 REM also asserted a cause of action for violation of prompt payment statutes and a
cause of action alleging the District breached a separate contract involving the
construction of bleachers on the high school campus. Like the parties, we do not discuss
these causes of action because they are not at issue in this appeal.

10
section 631.8.7 The District argued REM (1) failed to timely file a claim, and (2) failed
to complete all steps of the claim resolution process, including mediation, and its lawsuit
was thus barred by section 25.4 of the contract, which, as noted, provides, “Compliance
with . . . the claim submission procedures described in this Claims section is an express
condition precedent to Contractor’s right to commence litigation . . . . The Contractor
cannot . . . assert or bring any Claim . . . or subsequent legal action until that Claim has
gone through the Claims Resolution Process herein.”
REM opposed the motion, arguing, among other things: (1) its claim was timely;
(2) section 25.9.1 of the contract exempted the breach of contract claim at issue in the
lawsuit from the claim resolution process; and (3) it was the District that refused to
complete all steps of the claim resolution process because it never responded to REM’s
request for the informal meet and confer conference and it rejected REM’s requests to
mediate.8
The trial court denied the District’s motion. In doing so it found the claim was
timely and that mediation was not required because the District did not respond to the
meet and confer conference demand.
With regards to the timeliness of the claim, the trial court noted the various letters
and e-mails between the parties showed “both sides [were] trying to work this out,” and
the District “was holding open the possibility” that “if you do this, this, and this” it would

7 Code of Civil Procedure section 631.8 provides, “After a party has completed his
presentation of evidence in a trial by the court, the other party . . . may move for a
judgment. The court as trier of the facts shall weigh the evidence and may render a
judgment in favor of the moving party.” Such a motion is similar to a motion for nonsuit
in a jury trial. (Roth v. Parker (1997) 57 Cal.App.4th 542, 549.)
8 In light of our conclusion that REM’s claim was timely and not subject to
mediation, we need not address whether the claim was exempt from the claim resolution
process under section 25.9.1 of the contract.

11
“release the amounts . . . owing” to REM. It found it did not become clear the District
was not going to pay REM any additional monies until it sent the February 26 letter, and
REM’s claim, which was filed on March 6 (or nine days thereafter) was thus timely.
Prior to the February 26 letter, there was “an ongoing discussing, an ongoing luring,
basically, leading the contractor to believe, look, you can rely on our good faith here. We
are going to—this is a matter that hasn’t proceeded to the point where we are basically
saying no, . . . we are not going to pay you. [¶] That moment didn’t occur until that
letter.”
Finally, the trial court found, “There were requests for mediation, a request for that
meet-and-confer conference that were ignored” by the District. It also found the meet
and confer conference was not mandatory because the contract provides the contractor
“may” request such a conference, and “the happening of the meet-and-confer conference
is a condition precedent” to mediation. “And so mediation—the next step in the process,
from an unsuccessful meet-and-confer conference, could have been nonbinding
mediation. [¶] It never got to that because the district failed to respond . . . so the whole
process is derailed.”
The Conclusion of Trial and the Trial Court’s Statement of Decision
After the trial court denied the District’s motion for judgment, the trial continued
and the trial court ultimately issued a statement of decision finding in favor of REM on
the merits, at least in part. In particular, it found REM did substantially all the things
required under the contract and the District breached the contract by failing to pay it all
required amounts. It calculated the “proper amount due under the contract” as the unpaid
balance of the contract price (i.e., $220,600.15) minus $30,940.80 for items it found
REM did not adequately complete, for a total of $189,659.35. It also awarded statutory
penalties, interest, and costs and attorney fees, bringing the total amount awarded to

12
$465,252.13.9 In its statement of decision, the trial court noted, “The District reasserts
. . . that REM’s claim was untimely. The court denied these arguments at the time of the
District’s motion for judgment during the trial. The court continues to find the argument
that REM’s claim was untimely or not in compliance with the contract documents or
claims statutes without merit.”
Judgement was entered accordingly, and this appeal followed.
DISCUSSION
The sole issue on appeal is whether the trial court erred in finding REM’s lawsuit
was not barred by its failure to comply with the claim resolution process. The District
does not claim the judgment is otherwise in error. Instead, the District argues only that
the trial court should have found REM’s lawsuit was barred because (1) its claim was not
timely, and (2) even if it was timely, it never completed the final step of the claim
resolution process (i.e., mediation).
A. Standard of Review
In reviewing a judgment following a bench trial, we review questions of law de
novo, and we review the trial court’s findings of fact for substantial evidence. (Pearce v.
Briggs (2021) 68 Cal.App.5th 466, 473.) Some of the issues raised in the appeal involve
the interpretation of the parties’ contract, which we review de novo. (Filtzer v. Ernst,
supra, 79 Cal.App.5th at p. 583 [we “apply a de novo standard of review to interpret a
contract” where no extrinsic evidence was admitted concerning the contract’s meaning].)
However, the question of whether REM’s claim was timely is analogous to a statute of
limitations issue, and “[r]esolution of a statute of limitations issue is normally a question
of fact. [Citation.] ‘The trial court’s finding on the accrual of a cause of action for statute
of limitations is upheld on appeal if supported by substantial evidence.’ ” (Pearce, at

9 The District does not challenge this portion of the judgment other than to note the
fee award must be reversed if the underlying judgment is reversed.

13
p. 474; see also Brewer v. Remington (2020) 46 Cal.App.5th 14, 28 [“ ‘[t]here are no hard
and fast rules for determining what facts or circumstances will compel inquiry by the
injured party and render him chargeable with knowledge. [Citation.] It is a question for
the trier of fact’ ”]; Pedro v. City of Los Angeles (2014) 229 Cal.App.4th 87, 106 [“The
date that a person in the exercise of reasonable diligence should have discovered the facts
is a question of fact. [Citations.] We review the trial court’s finding [on this issue] under
the substantial evidence test”].) “Under the deferential substantial evidence standard of
review, findings of fact are liberally construed to support the judgment or order and we
consider the evidence in the light most favorable to the prevailing party, drawing all
reasonable inferences in support of the findings. [Citation.] ‘A single witness’s
testimony may constitute substantial evidence to support a finding. [Citation.] It is not
our role as a reviewing court to reweigh the evidence or to assess witness credibility.
[Citation.] “A judgment or order of a lower court is presumed to be correct on appeal,
and all intendments and presumptions are indulged in favor of its correctness.” ’ ”
(Powell v. Tagami (2018) 26 Cal.App.5th 219, 231.)
B. The Lawsuit Asserts a “Claim” as Defined by the Contract
The first issue we address is whether the breach of contract claim asserted in this
lawsuit is a “claim” as that term is defined by the contract. To the extent the trial found it
was not, we disagree. As noted, the contract defines a claim as a demand by the
contractor for: (1) “A time extension”; (2) “Payment by the District of money . . . arising
from work done by, or on behalf of, Contractor pursuant to the Agreement and payment
for which is not otherwise expressly provided or to which the claimant is not otherwise
entitled”; or (3) “Payment of an amount that is disputed by the District.” The trial court
found REM was not demanding a time extension and the first definition thus did not
apply, and neither party suggests otherwise. The trial court also found the second
definition did not apply because REM was demanding payment of the full contract price,
which was something the contract expressly provided it was entitled to. The trial court

14
found the second definition encompassed claims for “payment outside of the contract,”10
which “would imply, if it’s outside the contract, then payment of the contract amount is
something that is not the subject of a claim.” The trial court then went on, “So if that’s
true, then the third [definition] . . . cannot mean, when it says, ‘Payment of an amount
that is disputed by the district,’ it cannot mean amounts due under the contract. That
would be internally inconsistent. It can’t mean that.” We disagree with the trial court’s
conclusion that the second definition of a claim somehow means the third definition
cannot mean what it says. A claim includes a demand for “[p]ayment of an amount that is
disputed by the District.” REM contends the District owes it the full contract price,
including the remaining $220,600, and the District disputes that it owes REM this
amount. Simply put, that is a claim.
C. Timeliness
The contract provides a claim must be submitted “within ten (10) calendar days
from the date Contractor discovers or reasonably should discover, that an act, error or
omission of District, its agents or employees, or action, condition, or other situation has
occurred that may entitle Contractor to file a Claim.” The District’s position is that its
February 4 letter to REM, which was delivered on February 5, triggered the 10-day
deadline because it “conclusively established” REM “had actual knowledge of an act or
action of the [D]istrict . . . that entitled REM to present a claim.” The District thus
contends REM had until February 15 to file a claim, and its claim, which was filed on
March 6, was untimely. REM’s position is that, assuming it had to file a claim, it was the
District’s February 26 letter that triggered the 10-day deadline. The trial court agreed

10 An example might be a demand by a contractor to approve a proposed change
order for extra work the District asked it to do. (See, e.g., Weeshoff Constr. Co. v. Los
Angeles County Flood Control Dist. (1979) 88 Cal.App.3d 579, 588-589.)

15
with REM, and found “the claim was timely filed, March 6th.” We conclude this finding
is supported by substantial evidence.
David Schell, REM’s senior project manager, testified on behalf of REM. He
testified that, until he received the District’s February 26 letter, he did not know or have
reason to know the District was not going to pay him the remainder of the contract price.
It was only when he received the February 26 letter that he determined REM “probably
should file a claim.” Until that time, Schell was committed to completing all punch list
items and he thought the District would pay the remainder of the contract price once he
did so. He testified it was “very common” for there to be “multiple punch lists” on a
project, and “[n]ormally if . . . they give you the punch list, you have time to complete the
punch list, procure materials, and get the subcontractors lined up, and you keep working
on the punch list until it’s complete.” He also testified, “My commitment to the district
was, I was going to complete this project, and complete all punch list items, and I did not
understand until all the way until the very end and we got the letter on February 26th that
they weren’t going to pay me.” Until that time, his understanding was “if I complete the
items, then in my mind these items that they alleged that we didn’t complete that aren’t
on our plans and specs, someone will get to whoever they need to get to and say, hey,
look this isn’t even in their scope of work. Why are you back-charging someone for
items that aren’t in their scope of work? [¶] So I believed that we were going to . . .
work out our disagreements, and then we would go our separate ways, I would have the
project done, and the close-out documents documented. [¶] That’s what I believed in my
heart the whole way through this project.” Schell also testified REM submitted its last
invoice to the District on February 13 and it usually takes 25 to 30 days for an invoice to
be paid. After submitting the invoice, “I’m waiting for [it] to be processed, thinking that
everything is fine, and they are going to do that, because that would be normal, and that
never happened.” Instead, approximately two weeks later “this February . . . 26th letter
came that said, hey, we are not going to pay you, and at that point I realized we weren’t

16
going to get paid, so that’s why I filed a claim.” Given the communications between the
parties, we cannot say Schell’s belief was unreasonable.
Those communications show the parties were still working together on the punch
list in January and REM was continuing to cross items off that list. On January 15, for
example, the parties exchanged e-mails about work REM was performing that day. That
evening, REM stated it would provide a “work plan” listing additional punch list items it
planned on completing and projected dates for each item. The District grumbled, but
stated it would allow REM to submit a work plan for its consideration, and it
acknowledged it “has a good faith and fair dealing obligation.” When REM then notified
the District the work plan would be a few days late, it responded, “Ok.”
As another example, on January 9 and again on January 27, the District sent REM
a spreadsheet or “current punch list” of items that still needed to be completed. The
January 9 letter stated, “Hopefully . . . the Parties can work cooperatively to resolve these
issues in a timely manner,” which supports a finding the parties were still working
cooperatively on the punch list. Moreover, a comparison of the two punch lists
demonstrates REM had satisfactorily completed at least some of the items on the earlier
list, which also supports a finding the parties were still working cooperatively to resolve
the punch list issues. For example, the January 9 punch list estimated the cost to the
District to self-perform all items thereon was approximately $88,000, while the
January 27 list estimated the cost would be approximately $69,000. In other words,
between January 9 and January 27, REM continued to work on the punch list and
completed approximately $20,000 worth of work. As another example, the January 9
punch list identifies 38 doors to paint, while the January 27 punch list identifies just 12
doors. The January 9 list also states REM still has to “[a]dd floor base at science
casework skirts” and “[a]ddress hot water connection at Science Lab,” while these two
items do not appear on the January 27 punch list. Again, this demonstrates REM was
continuing to correct punch list items to the District’s satisfaction.

17
On January 30 and January 31, REM sent letters to the District regarding the
District’s contention that “the punch list work performed in January is deficient” and it
asked the District to identify what work was deficient and why it was deficient. It also
argued the District could not recoup monies it had previously paid pursuant to approved
change orders. This supports a finding that the parties were still working on both the
punch list and the overbilling issue at that time.
Despite the progress the parties continued to make on these issues in January, the
District’s position is that its February 4 letter triggered the claim presentation requirement
because it enclosed the board resolution directing the superintendent to “disburse any
remaining portion of the Contract Price . . . minus any amounts not otherwise due the
Contractor including by way of illustration and not by limitation”: (1) $30,708.01 for
overbilling, (2) $69,960.51 for remaining unperformed or deficiently performed work,
and (3) $2,599.20 for additional inspection fees. The District contends this resolution
made it clear it was not going to pay the entire balance of the contract price, which
provided REM with all the information it needed to trigger the claim presentation
requirement. As the trial court implicitly found, however, the District’s letter
demonstrates the parties were still trying to resolve their disputes. For example, the letter
opens by acknowledging receipt of REM’s January 30 and 31 letters and stating it
“intends to defer responding to that correspondence until after it received the promised
documentation substantiating . . . the . . . proposed change orders submitted by REM.” It
is reasonable to assume that, until the District’s deferred response was forthcoming, the
parties were still trying to resolve the overbilling issue.
The letter also states, “your correspondence of January 30 . . . indicates that you
object to the adequacy of the District’s existing documentation [regarding the work REM
allegedly neglected to perform] and that further inspection and documentation of the
same is necessary. The District is more than happy to oblige this demand in this instance
but notes that it will be at REM’s expense.” Again, it is reasonable to assume this

18
signified that further documentation and/or inspection could demonstrate REM’s work
was satisfactory.
The letter also states, “If REM has a proposal as to how it intends to resolve this
dispute, it can communication that proposal to our office in writing,” and, “The District
clearly is interested in a cooperative close-out of the Project.” Again, this supports a
finding the parties were still trying to cooperatively resolve their disputes.
This understanding is reiterated by an e-mail exchange between the parties a few
days after the February 4 letter. REM asked the District to “confirm that [it] refuses to
allow REM to perform the painting work as proposed in my letter to you of January 30,
2020. Please provide a yes or no answer.” The District responded, “The answer to your
question is, at present, yes.” “[T]he project is now complete . . . . [REM] submitted a
proposal . . . to perform one fifth (1/5) of the remaining work for the project, and the
District told you that it would respond to the letters in which that proposal was contained
in more detail after it had a chance to review the substantiating documentation for REM’s
change orders . . . which [REM] has promised to provide next week. Unless and until
that proposal is accepted and reduced to an agreement to the contrary, REM is not to
perform the painting work it proposed. Again, the District intends to respond in more
detail to your January 30 and 31 correspondence after it receives the substantiating
documentation you have promised to provide next week.” This e-mail supports a finding
the District was still open to allowing REM to finish some of the remaining punch list
work after it had a chance to review the substantiating documentation regarding the
overbilling issue. It also supports a finding the parties were still working on the
overbilling issue, and that the substantiating documentation might convince the District
there was no overbilling. In other words, the District was waiting for the substantiating
documentation before it decided how to proceed. REM submitted the substantiating
documentation on February 14; the February 26 letter followed shortly thereafter; and
REM filed a claim nine days later.

19
Viewed in its totality, we conclude the evidence discussed above is sufficient to
support the trial court’s finding REM’s claim was timely.
D. Mediation
Even if the claim was timely filed, the District argues there is a second bar to this
lawsuit: REM failed to complete the last step of claim resolution process, namely,
mediation. The claim resolution process effectively has three successive steps: (1) claim
initiation or presentation; (2) a meet and confer conference; and (3) mediation. It is
undisputed the parties never completed the third step of the process (or the second step
for that matter), and the District contends that REM’s breach of contract claim is thus
barred. As noted above, the trial court rejected the District’s argument, finding “[t]here
were requests for mediation” and “for that meet-and-confer conference that were
ignored” by the District. These findings are supported by the evidence.
On June 1, 2021, REM sent the District a written “demand for the informal meet
and confer process,” the record contains no evidence the District ever responded to that
demand, and the District’s counsel acknowledged at the hearing on the motion for
judgment that REM “made that demand, and at that point we remained silent.” The trial
court’s finding that the District ignored REM’s demand for the meet and confer
conference is thus supported by the evidence. The District suggests the demand was
untimely because it was submitted over one year after REM submitted its claim. We
disagree because the contract contains no deadline for demanding an informal
conference, even though it contains deadlines for almost every other step of the claim
resolution process.
The trial court also cited an e-mail from the District’s counsel to REM’s counsel
that stated, “As for mediation, the District has always said no.” (Italics added.) The trial
court noted, “ ‘Always’ means . . . going all the way back to the beginning.” Given
counsel’s acknowledgement that the District had “always said no” to mediation, the

20
District cannot now be heard to argue that REM’s lawsuit is barred because it failed to
complete mediation.
The District challenges the trial court’s conclusion that mediation was not required
under these facts. Its position is that mediation is a condition precedent to litigation, and
because mediation never occurred, REM’s lawsuit is barred. The trial court, however,
found that “[t]he happening of the meet-and-confer conference is . . a condition
precedent to then setting up the mediation.” We agree.
“A condition precedent is an act which must be performed . . . before the
promisor’s duty of performance arises.” (Sosin v. Richardson (1962) 210 Cal.App.2d
258, 264.) “Under the law of contracts, parties may expressly agree that a right or duty is
conditional upon the occurrence or nonoccurrence of an act or event. [Citations.] Thus, a
condition precedent is . . . an act of a party that must be performed . . . before the
contractual right accrues or the contractual duty arises.” (Platt Pacific, Inc. v. Andelson
(1993) 6 Cal.4th 307, 313.) “Where one party’s obligation is dependent on the prior
proper performance of the other party, and that other party does not perform, the
obligation is excused.” (Alki Partners, LP v. DB Fund Services, LLC (2016)
4 Cal.App.5th 574, 592.) The failure of one party to perform a condition precedent thus
excuses the other party’s performance which was dependent on it. (See Mainieri v.
Magnuson (1954) 126 Cal.App.2d 426, 429.)
The contract in this case provides, “the District shall schedule a meet and confer
conference within 30 days” of receipt of a demand by the contractor. (Italics added.) It
goes on to provide, “Within 10 business days following the conclusion of the meet and
confer conference . . . the District shall provide the Contractor a written statement
identifying the portion of the claim that remains in dispute . . . . Any disputed portion of
the Claim, as identified by the contractor in writing, shall be submitted to nonbinding
mediation.” (Italics added.) “[T]he term ‘shall’ has long been considered mandatory
under California’s contract interpretation rules.” (Segal v. Silberstein (2007)

21
156 Cal.App.4th 627, 634.) By its use of the word “shall,” the contract thus effectively
creates three successive obligations or duties. First, the District has an obligation to
schedule a meet and confer conference upon demand by REM. Second, the District has
an obligation to provide REM with a written statement identifying that portion of the
claim that remains in dispute following the conclusion of the conference. And third,
REM has an obligation to submit any disputed portion of the claim to mediation. Where
the parties have agreed the District has an obligation to schedule the conference and to
provide REM with the written statement, those acts must be performed before REM’s
obligation to submit its claim to mediation arises. (See, e.g., Platt Pacific, Inc. v.
Andelson, supra, 6 Cal.4th at pp. 313-314.) Because the evidence showed the District
failed to comply with either of its obligations, REM’s obligation to submit its claim to
mediation never arose.
Because we affirm the judgment, we need not address the District’s argument
regarding attorney fees.
DISPOSITION
The judgment is affirmed and REM shall recover its costs on appeal. (Cal. Rules
of Court, rule 8.278(a)(1), (2).)

/s/
EARL, P. J.

We concur:

/s/
HULL, J.

/s/
FEINBERG, J.

22