CourtListener 10793930•Queens Land Builder v. Cal Garden CA2/7
Testo completo
Filed 2/13/26 Queens Land Builder v. Cal Garden CA2/7
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions
not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has
not been certified for publication or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
SECOND APPELLATE DISTRICT
DIVISION SEVEN
QUEENS LAND BUILDER, INC., B330797
Plaintiff and Respondent, (Los Angeles County
Super. Ct. No. 20GDCV00072)
v.
CAL GARDEN, LLC et al.,
Defendants and Appellants.
APPEAL from a judgment of the Superior Court of
Los Angeles County, Maurice A. Leiter, Judge. Affirmed.
Zarmi Law and David Zarmi for Defendants and
Appellants.
Law Office of Steven P. Scandura, Steven P. Scandura; and
Howard C. Posner for Plaintiff and Respondent.
________________________
INTRODUCTION
Cal Garden, LLC and Ming Gu (together, Cal Garden)
appeal from a $1,678,371.79 judgment in favor of Queens Land
Builder, Inc. In 2016, Cal Garden contracted with Queens Land
to build a 20-unit condominium complex in the City of Arcadia.
The project was completed in 2019, after substantial delays. The
parties sued one another, primarily alleging breach of contract
claims. After a bench trial, the court found in favor of Queens
Land. On appeal, Cal Garden characterizes the trial court’s
findings as legal in nature and based on undisputed evidence.
But Cal Garden essentially challenges the trial court’s factual
findings and invites us to reweigh the evidence. On appeal, we
do not reweigh the evidence or make credibility determinations.
Accordingly, we affirm.
FACTUAL AND PROCEDURAL BACKGROUND
A. The Contracts
Gu is the majority shareholder of Cal Garden. Cal Garden
purchased a lot in the City of Arcadia, which abutted two
neighboring properties with concrete block walls on both sides.
Queens Land is a construction company owned by Tie Gao.
On February 26, 2016, Cal Garden hired Queens Land to
build 20 condominiums with subterranean parking for
$5.75 million (February 26 contract). The February 26 contract
specified Queens Land was responsible for the “[m]ain structure,
all water, electricity, gas, heat and landscaping facilities” and
that it “will be responsible for [these items] till they are fit for
move-in.” Queens Land promised to deliver the completed
2
property by May 1, 2017, which is 420 calendar days from the
March 1, 2016 start date. The contract provided for a $1,000
bonus “for each day that the project is completed ahead of
schedule” and a penalty of $1,000 for each day the project was
delayed. The February 26 contract was written in both English
and Mandarin because Gu’s primary language is Mandarin.
Cal Garden provided the architectural plans, the engineering
plans, and the building plans to Queens Land. Gao testified
Queens Land had no input on the plans.
On March 31, 2016, the parties signed another contract
that specified a price of $6.9 million for the project (March 31
contract). Unlike the February 26 contract, this contract was not
translated into Mandarin. Gao testified at trial that the
March 31 contract provided for higher quality finishing work, and
that the initial February 26 contract included “very simple, very
common” finishes.
Gu testified the parties generated the March 31 contract
“for the purpose of getting a bigger line of credit with the bank.”
Gu stated the parties intended the loan to be divided into a
$5.75 million portion to pay Queens Land and the remaining
$1.15 million would be split between Cal Garden and
Queens Land to pay for expenses such as city fees, design fees,
and staff expenses. The financing company approved the loan
and paid out funds based upon Queens Land’s periodic requests
and Cal Garden’s approval.
The parties subsequently agreed to change the construction
start date from March 1, 2016, to April 5, 2016, but retained the
construction period of 420 days. Thus, the parties intended
construction to finish in 2017. Shortly after construction began,
Queens Land discovered the soils engineering report provided to
3
it by Cal Garden, which stated there was “no caving” of the soil
upon excavation, was incorrect. Gao testified the soil at the lot
was commonly known as “sugar sand” because it would flow back
into any hole that was drilled.1 The condition of the soil required
a different type of shoring system. The parties were therefore
required to revise the engineering plans, resubmit the plans to
the city for approval, and hire a different drilling company.
The new engineering plan required I-beams to be pounded
into the ground rather than inserted into a hole that had been
dug. The pounding of the I-beams caused vibrations to spread to
the neighboring properties, resulting in their concrete block walls
sinking and other property damage. The neighbors complained
to the city and sued. The project was delayed while the parties
attempted to fix the problem.
In June 2017, the parties signed a third contract entitled
“Supplemental Contract on Construction of Cal Garden”
(supplemental contract) with a $6.1 million contract price “[i]n
consideration of the serious delay of the construction progress
and over budget of the construction cost[s] . . . .” Under the
supplemental contract, the parties agreed “to have the completion
date specified under the original contract extended to
October 31st, 2017, and [Cal Garden] will not claim the daily
penalty fee of USD one thousand for the period from June 30,
2017 through October 31st, 2017 if [Queens Land] completes and
turns over all items in this project before October 31st, 2017. In
1 Cal Gardens obtained a later soils report dated
February 29, 2016, that indicated “boring found caving at
4 to 10 feet.” Gao testified he did not receive the new report prior
to construction and was not told about the caving prior to
excavation.
4
the meantime, [Cal Garden] agrees to raise construction cost
from USD 5.75 million which is specified under the original
contract to USD 6.1 million (which will include the additional
cost of materials and labor for the work on drift sand in
basements submitted by [Queens Land]).” The supplemental
contract also provided for a $100,000 bonus to Queens Land if it
completed the project before October 31, 2017. The supplemental
contract specified that the terms of the February 26 contract
remained in effect and that the supplemental contract overrode
the February 26 contract to the extent there were any
inconsistencies between the two. Gao testified the supplemental
contract also provided that Cal Garden would be responsible for
paying any higher costs for certain materials, such as tile, wood
flooring, carpet, bathtubs, exterior walls, painting, and railing, if
these costs exceeded the budget under the February 26 contract.
The funds from the financing company ran out in
November 2017, and the subcontractors stopped work because
they were not paid. Gao and his wife made personal loans to Gu
to ensure the subcontractors were paid and the project completed.
Cal Garden does not dispute these loans were unpaid and their
amounts. In 2018, the city “red tagged” the project twice and
lifted the stop work order on July 17, 2018. Cal Garden hired
Kevin Chang in May 2019 to oversee construction.
A certificate of occupancy was issued by the city in
September 2019. Cal Garden sold three units but was prevented
from selling any others because Queens Land recorded a lien on
the property, which forced Cal Garden to rent out the remaining
units.
5
B. The Litigation Proceedings
On January 17, 2020, Queens Land sued Cal Garden for
breach of contract, enforcement of the mechanics lien, an
accounting, and intentional interference with contractual
relations. Queens Land alleged the March 31 contract for
$6.9 million was the operative contract between the parties.
Queens Land further alleged Cal Garden paid $4.3 million of that
amount, leaving a balance of more than $2.5 million plus other
charges for change orders, soft costs, engineering, and “other
incidental charges.” Queens Land asserted it completed its final
work on the project on August 30, 2019, and delivered the project
to Cal Garden under the March 31 contract.
Cal Garden filed a cross-complaint against Queens Land,
Gao, his wife, and the qualifying license holders for Queens Land,
alleging claims for breach of contract, misappropriation of
construction funds, and quiet title. Cal Garden set out the
circumstances leading to the three contracts between the parties,
as set out above. Cal Garden alleged the parties intended the
February 26 contract and the supplemental contract to be the
binding contracts. Cal Garden explained the supplemental
contract incorporated the terms of the February 26 contract but
allowed for a $100,000 bonus to Queens Land if it completed the
project by October 31, 2017, and called for liquidated damages of
$1,000 per day if the project was not completed by that date.
Cal Garden further alleged it paid over $1 million to various
contractors, subcontractors, engineers, and others to get the
project to completion. Cal Garden claimed it was entitled to
reimbursement of “at least $600,000” for the amount it overpaid
Queens Land to complete the project. Cal Garden additionally
6
alleged a Queens Land representative signed an unconditional
waiver and release on May 20, 2019, confirming the completion of
the project and full payment by Cal Garden.
The trial court conducted a six-day bench trial in
early 2023. It issued a final statement of decision on April 18,
2023. The court found Queens Land proved its breach of contract
claim, but that the operative contract was not the March 31
contract advanced by Queens Land because the parties did not
intend the March 31 contract to be binding between them.2 It
instead found that the February 26 contract and the
supplemental contract were valid and binding on the parties.
The court further found the supplemental contract provided for a
$350,000 incentive to the original price of $5.75 million, added a
$100,000 bonus if Queens Land completed the project by
October 31, 2017, and imposed a $1,000 liquidated damages
penalty for each delayed day beyond October 31, 2017.
The court stated Cal Garden’s recovery under the
liquidated damages provision depended on whether Queens Land
breached the contract or whether the delay in completing the
project was excused. The court found Cal Garden failed to
demonstrate Queens Land breached the contract. The multiple
delays were attributed to problems with the soils engineering, the
depletion of the construction loan, and multiple change orders,
none of which were attributable to Queens Land. Queens Land
2 The court determined the evidence did not establish the
parties “intended to artificially inflate the putative cost of the
contract to secure a larger construction loan,” but also found
Queens Land did not prove the March 31 contract was “a valid,
binding agreement.”
7
was thus entitled to the February 26 contract price of
$5.75 million because it substantially completed the project, but
not the $350,000 incentive or the $100,000 bonus under the
supplemental contract because it did not complete the project by
October 31, 2017.
The court rejected Cal Garden’s purported unconditional
waiver and release as “not authentic.” The court also rejected the
parties’ remaining arguments regarding offsets or amounts they
were owed, stating it based its decisions on the documentary
evidence and credibility determinations.
The court entered judgment against Gu and Cal Garden in
the amount of $1,678,371.79 in favor of Queens Land. The court
found Cal Garden failed to prove any of its causes of action in the
cross-complaint. Cal Garden timely appealed.
DISCUSSION
A. Standard of Review
Cal Garden asserts the trial court abused its discretion
when it made unsupported factual findings and that it
misinterpreted the parties’ contracts. We, however, review a trial
court’s factual findings for substantial evidence and generally
review the interpretation of a contract under a de novo standard.
“When a civil appeal challenges findings of fact, the
appellate court’s power begins and ends with a determination of
whether there is any substantial evidence—contradicted or
uncontradicted—to support the trial court findings.” (Schmidt v.
Superior Court (2020) 44 Cal.App.5th 570, 582; see Gray v. Don
Miller & Associates, Inc. (1984) 35 Cal.3d 498, 503.) “ ‘In general,
in reviewing a judgment based upon a statement of decision
8
following a bench trial, “any conflict in the evidence or reasonable
inferences to be drawn from the facts will be resolved in support
of the determination of the trial court decision. [Citations.]”
[Citation.] In a substantial evidence challenge to a judgment, the
appellate court will “consider all of the evidence in the light most
favorable to the prevailing party, giving it the benefit of every
reasonable inference, and resolving conflicts in support of the
[findings]. [Citations.]” [Citation.] We may not reweigh the
evidence and are bound by the trial court’s credibility
determinations. [Citations.] Moreover, findings of fact are
liberally construed to support the judgment.’ ” (In re Marriage of
Ciprari (2019) 32 Cal.App.5th 83, 94.)
“ ‘The substantial evidence standard applies to both express
and implied findings of fact made by the superior court in its
statement of decision rendered after a nonjury trial.’ [Citation.]
‘The court’s statement of decision is sufficient if it fairly discloses
the court's determination as to the ultimate facts and material
issues in the case.’ [Citation.] ‘ “Where [a] statement of decision
sets forth the factual and legal basis for the decision, any conflict
in the evidence or reasonable inferences to be drawn from the
facts will be resolved in support of the determination of the trial
court decision.” ’ ” (In re Marriage of Ciprari, supra,
32 Cal.App.5th at p. 94.)
By contrast, the abuse of discretion standard measures
whether, given the established evidence, the lower court’s action
“ ‘ “ ‘falls within the permissible range of options set by the legal
criteria.’ ” ’ ” (Robbins v. Alibrandi (2005) 127 Cal.App.4th 438,
452; Dorman v. DWLC Corp. (1995) 35 Cal.App.4th 1808, 1815.)
Reviewing courts “ ‘defer to the trial court’s factual findings so
long as they are supported by substantial evidence, and
9
determine whether, under those facts, the court abused its
discretion. If there is no evidence to support the court’s findings,
then an abuse of discretion has occurred.’ ” (Doe v. Software One,
Inc. (2022) 85 Cal.App.5th 98, 109.)
We review de novo the interpretation of a contract or other
written instrument where no conflicting extrinsic evidence was
introduced. (See Parsons v. Bristol Development Co. (1965)
62 Cal.2d 861, 865-866; see also In re Martinez (2012)
210 Cal.App.4th 800, 815.) “To the extent there is conflicting
extrinsic evidence requiring credibility determinations by the
finder of fact regarding a meaning of which the contract is
reasonably susceptible, we will uphold the trial court’s
determination if supported by substantial evidence.” (Hewlett-
Packard Co. v. Oracle Corp. (2021) 65 Cal.App.5th 506, 531-532.)
B. Substantial Evidence Supports the Trial Court’s Finding
that Queens Land Substantially Performed Under the
Parties’ Operative Contract
Cal Garden argues Queens Land failed to deliver the
“move-in” ready building it promised in the February 26 contract.
According to Cal Garden, a certificate of occupancy was issued
only after it was forced to hire Chang in May 2019 to oversee
completion of the project. Cal Garden alternatively argues the
trial court should have allowed it to recoup its costs to mitigate
its damages and for defects in the construction even if
Queens Land substantially performed on the project.
1. Governing Law
The California Supreme Court set out the doctrine of
substantial performance in a construction case in Thomas
10
Haverty Co. v. Jones (1921) 185 Cal. 285, 289 (Thomas Haverty).
There, the high court held that a contractor’s substantial
performance entitles him to recover the amount of the contract
price less the amount allowed as damages for his failure to
strictly comply with the contract specifications. (Ibid.) Thomas
Haverty explained, “there is a substantial performance where the
variance from the specifications of the contract does not impair
the building or structure as a whole, and where after it is erected
the building is actually used for the intended purpose, or where
the defects can be remedied without great expenditure and
without material damage to other parts of the structure, but that
the defects must not run through the whole work so that the
object of the owner in having the work done in a particular way is
not accomplished, or be such that a new contract is not
substituted for the original one, nor be so substantial as not to be
capable of a remedy and the allowance out of the contract price
will not give the owner essentially what he contracted for.” (Id.
at p. 291; see Murray’s Iron Works, Inc. v. Boyce (2008)
158 Cal.App.4th 1279, 1292 (Murray’s Iron Works); see also Lowy
v. United Pacific Ins. Co. (1967) 67 Cal.2d 87, 92-93.) “Several
courts in California have denied contractors the right to recover
pursuant to the doctrine of substantial performance where their
performance was not found to meet a reasonable standard.”
(Murray’s Iron Works, at p. 1292.)
2. The Trial Court’s Substantial Performance Finding Is
Supported by Substantial Evidence
Here, substantial evidence supports the trial court’s finding
that Queens Land substantially performed on the contract by
giving Cal Garden “essentially what [it] contracted for.” (Thomas
11
Haverty, supra, 185 Cal. at p. 291.) Gao testified Queens Land
ultimately completed the construction of the units. The court
admitted into evidence the approved inspection reports and
photographs showing the completed buildings and underground
parking. Additionally, Cal Garden recorded a Notice of
Completion verifying that “[a] work of improvement on the
property hereinafter described was COMPLETED on April 12,
2019” and “[t]he work of improvement completed is described as
follows: New Constructions-20 Unit Condominium.” Gu testified
a certificate of occupancy was issued on September 30, 2019.
This is substantial evidence of Queens Land’s substantial
performance of the parties’ construction contract.
Cal Garden does not dispute Queens Land built
20 condominiums and a subterranean garage. It instead argues
the project was not “move-in ready” because it was unable to get
a certificate of occupancy in May 2019. Cal Garden relies on
Chang’s testimony that the elevator, sump pump, and garage
ventilation were “not done” by then, and there remained “a lot of
loose end[s] for [the] interior.” It also contends the landscaping
was not done. Cal Garden asserts it had to hire Chang in
May 2019 to oversee and coordinate the completion of the project
over the final few months of construction. It further cites its
payment of $1,220,770 to mitigate its damages as evidence of how
far from “move-in” condition the project was in May 2019.
Even accepting Cal Garden’s assertion that Queens Land
stopped work at the site in May 2019 and the property was not in
move-in ready condition, as the finder of fact, the trial court
nevertheless was entitled to find that Queens Land substantially
performed under the parties’ contract. The court could
reasonably find the amount of work remaining was easily
12
remedied or compensated. “What constitutes substantial
performance is a question of fact, but it is essential that there be
no wilful departure from the terms of the contract, and that the
defects be such as may be easily remedied or compensated, so
that the promisee may get practically what the contract calls for.”
(Posner v. Grunwald-Marx, Inc. (1961) 56 Cal.2d 169, 187; see
Murray’s Iron Works, supra, 158 Cal.App.4th at p. 1293
[substantial performance on construction contract was shown
where the jury could reasonably have concluded that the amount
of work remaining could be easily fixed].)
Cal Garden fails to cite any authority that allows us to
ignore the substantial performance doctrine in favor of strict
compliance with the move-in ready provision of the contract.
Thus, Cal Garden’s assertion that Queens Land failed to deliver a
move-in ready property, even if true, does not override the
substantial evidence that Queens Land built a 20-unit
condominium complex and underground parking under the
contract.
3. The Trial Court Properly Found Cal Garden Failed
To Prove It Was Entitled to an Offset for Damages It
Incurred
Cal Garden argues in the alternative that, even if the trial
court’s finding of substantial performance was supported by the
evidence, the court should have allowed Cal Garden to recover
$1,220,770.26 for costs it paid to correct construction defects and
mitigate its damages. Cal Garden argues it paid $1,220,770.26
for subcontractor work and for HVAC units, water heaters, gas
meters, and landscaping that should have been borne by
Queens Land under the contract. As stated, the doctrine of
13
substantial performance entitles a property owner to recover the
amount of the contract price less the amount allowed as damages
for the contractor’s failure to strictly adhere to the parties’
contract. (See Thomas Haverty, supra, 185 Cal. at p. 289.)
According to Cal Garden, the court “gave no reasons why
Cal Garden’s costs in correcting those defects and mitigating
damages generally would not be recoverable.” The statement of
decision belies this assertion. The trial court found Cal Garden
“did not prove that the $1,220,770.26 they claimed to have spent
to pay subcontractors and for materials and other costs were
mitigation of damages for a supposed breach by Queens Land.”
The court specifically found the depletion of the construction loan
resulted in the failure to pay the subcontractors, but that the
construction loan issue was not attributable to Queens Land.
Cal Garden fails to demonstrate the court erred when it
found Cal Garden did not prove an offset. In its appellate
briefing, Cal Garden cites, among other evidence, trial
exhibit 522 and Gu’s testimony regarding the purported defects.
Trial exhibit 522 is a spreadsheet listing the date, the check
number, the payee, and the amounts of payments made by
Cal Garden to various vendors from 2018 to 2019. The exhibit
also includes copies of checks written by Cal Garden to those
vendors. The spreadsheet has a column labeled “description,” but
the descriptions are written in Chinese, and there does not
appear to be a certified translation in the record. (See Evid.
Code, § 753, subd. (a) [“When the written characters in a writing
offered in evidence are incapable of being deciphered or
understood directly, a translator who can decipher the characters
or understand the language shall be sworn to decipher or
translate the writing.”]; cf. Cal. Rules of Court, rule 3.1110(g)
14
[“Exhibits written in a foreign language must be accompanied by
an English translation, certified under oath by a qualified
interpreter”].) Cal Garden provides no explanation regarding
how to read this spreadsheet or why these payments are
recoverable as damages for Queens Land’s purported deficient
performance under the parties’ contract.
Additionally, Gu’s testimony does not support Cal Garden’s
argument that the entire amount it paid was recoverable. At
trial, Gu gave a “rough estimat[e]” that $200,000 to $300,000 of
Cal Garden’s payments were made to correct construction defects.
As set out below, Cal Garden expressly waived and released
Queens Land from “any and all negligence and construction
defect claims” and agreed that Cal Garden “will be precluded
from asserting same, or any payment made pursuant to this
Agreement, as a setoff or defense . . . .”
C. Substantial Evidence Supports the Trial Court’s Finding
that Cal Garden Breached the Contract
Next, Cal Garden argues the trial court erred when it found
Queens Land proved its breach of contract claim against
Cal Garden because the evidence showed that Cal Garden paid
more than it owed on the contract. According to Cal Garden,
Queens Land’s own calculations established Cal Garden paid
$5,786,728 to it on a contract valued at $5,750,000. Cal Garden
fails to explain how or why the extra $36,728 it paid to
Queens Land proves it did not breach the operative contracts.
Cal Garden provides no legal authority or evidentiary support for
the proposition that it only had to pay $5,750,000 and nothing
more. Indeed, both the February 26 contract and the
supplemental contract contemplated Cal Garden would pay
15
Queens Land additional monies for change orders, upgrades, and
other expenses. Cal Garden has failed to meet its burden to
demonstrate error on appeal. (See Jameson v. Desta (2018)
5 Cal.5th 594, 608-609.)
D. Substantial Evidence Supports the Trial Court’s Change
Order Findings
Cal Garden also challenges the trial court’s finding that
change order nos. 4 (handicap railing), 8 (stucco), and 10 (patio
roof) were valid and payable. In making its findings regarding
the 26 change orders submitted by Queens Land, the trial court
“reviewed the evidence concerning each change order and made
credibility determinations concerning the relevant testimony; the
Court [did] not fully adopt either side’s arguments concerning
how each one should be categorized.” The court then determined
that 11 change orders were valid and payable by Cal Garden.
Although Cal Garden argues we should review these
determinations de novo as matters of contract interpretation, in
essence, Cal Garden challenges the court’s factual findings, and
substantial evidence supports the court’s findings.
1. Change Order No. 4
At trial, Gao testified Queens Land submitted change order
no. 4 because the city required installation of a railing on a
handicap ramp to comply with the Americans with Disabilities
Act (ADA). Gao explained Cal Garden provided all the
architectural, building, and engineering plans necessary for the
construction of the project without any input from Queens Land.
Gao stated the plan design for the railing was inconsistent with
16
the city’s requirements. Gao denied he was “responsible for
engineering mistakes or mistakes made by architects.”
Trial exhibit 26, which set out all the change orders for
which Queens Land sought to recover, explained that change
order no. 4 represented an additional $20,503.03 cost for “[l]abor
charges for extra front yard concrete work, side gate, and extra
driveway concrete work. This was extra work not addressed in
the plans or within the $25,000 construction budget.” The
supplemental contract specified that labor charges for “railings”
must be approved by Cal Garden and that any costs exceeding
the original budget were to be borne by Cal Garden. Substantial
evidence supports the trial court’s finding that change order no. 4
was valid and payable.
Cal Garden attempts to overcome this substantial evidence
by arguing that the court should have accepted its version of
conflicting facts. It contends the plans for the project required
that “[a]ll work shall conform to all applicable federal, state and
local codes and ordinances. Nothing shown in these drawings
shall be constructed [sic] as permission to violate any [of the]
above codes.” Cal Garden argues Gao’s review of these plans
before bidding on the contract, plus the language found in these
plans, meant that the parties agreed Queens Land would be
responsible for building the railing in conformance with the ADA
without regard to whether the plans conformed to ADA
requirements. Cal Garden provides no legal or factual basis for
the proposition that Queens Land was responsible for correcting
any defects or mistakes in the plans provided to it by Cal Garden.
The trial court was entitled to reject Cal Garden’s theory of
liability. (See Gomez v. Smith (2020) 54 Cal.App.5th 1016, 1028-
17
1029 (Gomez) [the trial court is entitled to resolve factual
conflicts in the evidence].)
2. Change Order No. 8
Substantial evidence also supports the trial court’s finding
that change order no. 8 was valid and payable. At trial,
Queens Land presented evidence that change order no. 8 arose
from Cal Garden’s request in 2018 to upgrade the stucco on the
buildings. The February 26 contract specified, “Plaster/Stucco
(LA HABRA or Santa Barbara).” Gao testified La Habra and
Santa Barbara are companies that manufacture stucco. He
explained the original contract provided for the cheapest stucco
finish, which was sprayed on, and that a smooth finish required
more labor and took more time. As a result, the new stucco
required the scaffolding to remain up for a longer time.
Cal Garden disputed Gao’s testimony. It argued it
contracted for a smooth finish, relying on its construction expert’s
testimony that La Habra is a manufacturer that has a smooth
finish named Santa Barbara. The trial court was entitled to
make a credibility determination regarding the conflicting
testimony between Gao and Cal Garden’s expert. Whether the
parties intended for a smooth or rough finish in their initial
contract was a factual finding properly decided by the trial court.
(See Gomez, supra, 54 Cal.App.5th at pp. 1028-1029.)
3. Change Order No. 10
Substantial evidence also supports the trial court’s finding
that change order no. 10 was valid and payable. Gao testified at
trial that change order no. 10 arose from Cal Garden’s request for
an upgrade to the patio roof design by adding “rough carpentry”
18
and “plastering stucco.” Cal Garden argues that Gao later
testified: “at the time when the exterior wall stucco was
discussed the portion below the patio roof was open we used the
wrong cabinetry work and we fill in that area and afterwards we
used the same stucco for that area as the ones on the exterior
wall and those stucco were finished on the same level or same
quality.”
Cal Garden focuses on the word “wrong” to argue that Gao
admitted he made a mistake that needed to be corrected. In
Cal Garden’s view, any cost to correct the “wrong cabinetry work”
should be allocated to Queens Land. Gao’s testimony on this
point was vague and ambiguous, and as the fact finder the trial
court was entitled to interpret it as supporting his prior
testimony that change order no. 10 was an upgrade to the patio
roof. “It is for the trier of fact to consider internal inconsistencies
in testimony, to resolve them if this is possible, and to determine
what weight should be given to such testimony.” (Clemmer v.
Hartford Ins. Co. (1978) 22 Cal.3d 865, 878, overruled on another
ground by Ryan v. Rosenfeld (2017) 3 Cal.5th 124, 135; see
Regalado v. Callaghan (2016) 3 Cal.App.5th 582, 595-596 [“It is
not our task to weigh conflicts and disputes in the evidence; that
is the province of the trier of fact”].)
E. Cal Garden Fails To Demonstrate the Trial Court Erred by
Failing To Credit It $132,295
Cal Garden argues this court should modify the judgment
so it is credited for $132,295 that Queens Land purportedly
“admitted Cal Garden had spent on parts of the project that were
[Queens Land’s] obligation under the contract.” Cal Garden
asserts the trial court miscalculated and failed to credit
19
Cal Garden for certain amounts it paid for “the basic stucco
($13,000), fire sprinkler ($81,865), and HVAC ($37,430) [that]
should have been included” in the contract. In support of its
claim that Queens Land “admitted” it was obligated to provide
these items under the contract, Cal Garden cites the parties’
contracts, trial exhibit no. 26 (a spreadsheet that sets out
Queens Land’s damages), trial exhibit no. 10 (a disbursement
request to the financing company), and trial exhibit no. 11 (a
spreadsheet that shows disbursements from the financing
company). These documents are not admissions of liability by
Queens Land. Nor do they demonstrate on their face, in the
absence of any explanation of their contents, Queens Land’s
liability. Indeed, Cal Garden does not provide any reasoned
argument why or how it was entitled to a credit, or why the
stucco, fire sprinkler and HVAC costs noted above were costs that
fell under the parties’ contract. Accordingly, “[w]e may [and do]
disregard conclusory arguments that are not supported by
pertinent legal authority or fail to disclose the reasoning by
which the appellant reached the conclusions he wants us to
adopt.” (City of Santa Maria v. Adam (2012)
211 Cal.App.4th 266, 287; In re Marriage of Falcone & Fyke
(2008) 164 Cal.App.4th 814, 830 [“We are not bound to develop
appellants’ arguments for them”].)
F. Cal Garden Fails To Demonstrate the Trial Court Erred by
Not Crediting a $50,000 Loan It Made to Queens Land
Cal Garden next argues this court should modify the
judgment so it is credited $50,000 for a loan it made to
Queens Land. Queens Land does not dispute Cal Garden loaned
it $50,000, but asserts the parties agreed the $50,000 would be
20
used by Queens Land to pay expenses that were Cal Garden’s
responsibility under the contract. Gao testified at trial that
“there were other expenses that occurred for the project, which
[were] supposed to be paid by the developer, but we ended up
paying—paid for it, so the developer told us that we could use
those remaining money, the 50,000, to pay those expenses.”
Cal Garden does not dispute the parties agreed to this allocation
of the $50,000 loan. It instead argues that the $50,000 loan
“should either be an offset or a recognition that [Cal Garden] paid
over the $5,750,000 contract price and no breach occurred on
their part.” The trial court was entitled to credit Gao’s testimony
and decline to offset the damages amount, and Cal Garden has
not demonstrated any persuasive reason why we should modify
the judgment. (See Conservatorship of O.B. (2020) 9 Cal.5th 989,
1008; Lenk v. Total-Western, Inc. (2001) 89 Cal.App.4th 959, 968
[“we defer to the trier of fact on issues of credibility”].)
G. Cal Garden Fails To Demonstrate the Trial Court Erred
When It Awarded Queens Land $64,112 in Engineering
Costs
Cal Garden argues the trial court erred when it
awarded $64,112 in “excluded engineering costs,” and that this
court should modify the judgment because the parties agreed to
release one another from claims for engineering costs associated
with the neighboring properties’ subsidence problems. The
record belies this argument.
As stated, during construction the neighbors’ walls began to
sink, and other damage occurred as a result of the pounding of
the I-beams into the ground for the underground parking
structure. The neighboring homeowners’ associations sued
21
Cal Garden, Queens Land, and certain subcontractors. In 2022,
Cal Garden and Queens Land, among others, settled with the
homeowners’ associations. Under the settlement agreement,
Cal Garden paid $500,000, and Queens Land (through its
insurer) paid $675,000 to the homeowners’ associations.
The settlement agreement also specified that there existed
additional lawsuits between Cal Garden and Queens Land, i.e.,
this case, deemed the “mechanic’s lien action”; Cal Garden’s
cross-complaint in this action, deemed the “contract dispute
action”; and a construction defect action filed by Cal Garden
against Queens Land and its subcontractors under Los Angeles
County Superior Court Case No. 20STCV16589. Although
Cal Garden released Queens Land from certain construction
defect claims as part of the parties’ settlement with the
neighboring homeowners’ associations, Queens Land expressly
retained “all of their claims asserted in the Mechanic’s Lien
Action.” Under these facts, the trial court properly found
Cal Garden is liable for $64,112 in excluded engineering costs
because Queens Land did not release these claims in the
settlement of the homeowners’ association cases. (See Regalado
v. Callaghan, supra, 3 Cal.App.5th at pp. 595-596.)
22
DISPOSITION
The judgment is affirmed. Queens Land may recover its
costs on appeal.
MARTINEZ, P. J.
We concur:
STONE, J. GIZA, J.*
* Judge of the Los Angeles County Superior Court, assigned
by the Chief Justice pursuant to article VI, section 6 of the
California Constitution.
23
Ti chiedi come si applica questo testo alla tua situazione?
Consulenza gratuita, senza impegno
Descrivi la tua situazione. Il nostro team ti ricontatterà via e-mail per la tua consulenza.
Continua la tua ricerca in ChatGPT o Claude
Collega Omnilex per cercare nel corpus legale dal tuo assistente IA.